This document contains exhibits supporting a Request for Quotation (RFQ) issued by the Eugene Water & Electric Board (EWEB), a municipal utility serving the Eugene, Oregon area. The exhibits provide comprehensive information about EWEB's construction project portfolio, categorized by department and work type, spanning electric generation, water operations, substations, water treatment facilities, and recreational improvements. The document outlines representative projects completed since 2022, including major undertakings such as the E. 40th Avenue Storage Tanks ($19.2 million), Hillyard Transmission Main Replacement ($9.37 million), Carmen-Smith Turbine Generator Rehabilitation ($24.6 million), and Currin Substation Rebuild ($7 million). EWEB's construction work encompasses water storage tank installation, transmission line work, hydroelectric equipment refurbishment, substations rebuilds, civil earthwork, site improvements, building construction and repair, concrete work, and specialty equipment operations. The exhibits detail specific technical requirements and capabilities needed across multiple project categories, including underwater welding and diving services, electrical transmission work, water treatment plant construction, and environmental improvements related to fish passage and habitat restoration.
The document serves as a reference guide for contractors interested in bidding on EWEB projects and demonstrates the breadth of construction services required across the utility's operations. Pricing for individual projects ranges from $33,500 to $24.6 million, with anticipated future projects including the Willamette Water Treatment Plant (estimated 2027–2028) and continued substation rebuilds as part of a ten-year reliability program. EWEB indicates it performs some construction work in-house, particularly within the electrical distribution department, but contracts specialized services as needed. The exhibits emphasize the geographic scope of projects, with water department work concentrated within Eugene and Springfield, while generation department projects occur at Carmen-Smith and Leaburg/Walterville dam facilities located 1.5 to 2 hours from Eugene. No specific contract award dates, bid due dates, or renewal terms are provided in these exhibits, which function primarily as project examples and capability descriptions for prospective contractors.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT A
EXAMPLES OF SELECT EWEB PROJECTS (2022 ONWARD)
WATER DEPARTMENT
22-021-PW E. 40th Ave Storage Tanks – Tank Construc�on $19.2M Descrip�on: EWEB requires construc�on services to facilitate the construc�on of two 7.5-milliongallon (MG) round par�ally buried AWWA D110 prestressed concrete storage tanks at EWEB’s E. 40th Ave Storage Tank site. The project will require staking, site prepara�on, underdrain infrastructure, tank construc�on, yard piping, sediment and erosion control, and backfilling.
23-011-PW Hillyard Transmission Main Replacement $9.37M Descrip�on: EWEB requires bids from qualified contractors interested in providing construc�on services for the Hillyard St 36-inch transmission main and 24-inch storm drain replacement.
23-049-PW Shasta 975 Storage Tanks $2.9M Descrip�on: EWEB requires construc�on services to facilitate the construc�on of two 0.5 million gallon (MG) glass-fused-to-steel water storage tanks at EWEB’s Shasta 975 Storage Tank Site. The project also requires site prepara�on, yard piping, and sediment / erosion control.
22-140-PW Lorrane, Chambers, Crest Drive Main Replacement $947K Construc�on and installa�on of app. 4225’ of 8” polyvinyl chloride water main pipe in Lorane Highway.
23-236-PW Amazon Park Well Improvement – Site Work $250K Descrip�on: The Eugene Water & Electric Board (EWEB) requests bids for construc�on services to improve an exis�ng well, install new piping and treatment system equipment, and complete all required site work at the Amazon Park Well Site. EWEB has partnered with the YMCA and the City of Eugene Parks Department to complete the project on their property.
23-100/101 Customer Side Plumbing Repairs $125K On-call residen�al and commercial plumbing services including plumbing repairs, installa�ons, reloca�ons, and maintenance.
GENERATION / DAM SAFETY / CARMEN-SMITH LICENSING
013-2017 Carmen-Smith Turbine Generator Rehabilita�on $24.6M Design-Build services for rehabilita�on of two Carmen-Smith powerhouse turbine generators
002-2011 CMGC Services for Carmen-Smith Relicensing Projects $15.3M For the implementa�on of environmental improvements to the Carmen-Smith Hydroelectric Project on the upper McKenzie River, OR.
23-130-PW Carmen-Smith Campus Improvements $2.36M Descrip�on: EWEB requires professional construc�on services for a new access road, to provide trenching, conduit etc. for power and communica�ons, provide founda�onal prep work, provide a new garage, provide demoli�on of exis�ng heavy equipment building and provide a new replacement, and more.
23-009-PW Temporary Trap and Haul (Task Order under Wildish CMGC Contract) $1.4M Installa�on of temporary trap & haul device for fish passage at Carmen-Smith hydro project.
22-069-PW Stone Creek Pole Replacement Installa�on $772K Remove and replace damaged power poles at EWEB’s Oak Grove to Lake Harriet 115 kV transmission line in Clackamas County.
23-255-PW Carmen Bridge Seismic Retrofit and Rehabilita�on $560K Description: EWEB requires construc�on services at EWEB’s Carmen-Smith Hydroelectric Project for the furnishing of labor, materials, and equipment for the seismic retrofit and repair of ODOT Bridge No.
18750 in Linn County, OR.
23-200-PW Leaburg Powerhouse Generator Turbine Runner Removal $298.9K Descrip�on: EWEB requires the furnishing of the labor, materials, and equipment for the removal of the Leaburg powerhouse genera�on Unit 1 turbine runner.
23-067-PW Carmen-Smith Tree Removal & Blanket Repair $125K Descrip�on: EWEB requires professional construc�on services for tree removal and impervious blanket repair at the Carmen Diversion and Trail Bridge reservoirs.
23-051-PW Leaburg Homes Roof Replacement $108.2K Descrip�on: EWEB requires roof replacement services for the EWEB Leaburg residences.
23-034-PW Carmen-Smith Transmission Line Culvert Improvements $99.1K Descrip�on: The Eugene Water & Electric Board (EWEB) requests bids for professional construc�on services for culvert improvements at three separate loca�ons along EWEB’s Carmen-Smith transmission line, including CMP and fish passage pipe arch installa�on. There are several restric�ons on the construc�on window that must be considered, but generally the work is expected to occur in June, July, or August.
23-099-PW Walterville Penstock Repair $35K Perform joint and crack repairs. Contractor will use chemical grout materials, pumps, and various other equipment items to repair the joints and cracks at loca�ons listed below and shown in the photos following.
23-070-PW Campground Work at Ice Cap Campground $33.5K Work of the project includes but is not limited to providing materials and labor to perform demoli�on and construc�on of the following: Fire ring restora�on, relocate picnic table and place on and atach to pier blocks, construct gravel paving near well, construct UA trails, grade and level accessible site, construct UA tent pad, install campsite posts and signs, install bollards.
SYSTEMS ENGINEERING
(ELECTRIC TRANSMISSION AND SUBSTATIONS)
22-181-PW Currin Substa�on Rebuild $7M Rebuild of Currin substa�on featuring an 8-terminal breaker-and-a-half AIS configura�on and 8 posi�on medium-voltage metal clad switchgear.
23-143-PW Substa�on Pain�ng – Energized and De-Energized EWEB has a need for Substa�on energized and de-energized pain�ng services on an “as-needed” basis.
EWEB has historically painted and/or cleaned one substa�on per year; however, under this contract there will be no minimum or maximum number of substa�ons serviced each year. Timing of services are in July or August. The majority of substa�ons are located within the Eugene/Springfield city limits. The Contractor shall provide all labor, travel, material and equipment to perform the work. EWEB will contact Contractor when services are required.
23-143-PW Pain�ng of Energized and De-Energized Substa�ons $100K The majority of substa�ons are located within the Eugene/Springfield city limits. Es�mated at 1 to 2 substa�ons per year.
ELECTRIC DISTRIBUTION (Most work self-performed)
23-150-PW Belknap & Smith Ridge Tower Batery Installa�on and Recycling $26.4K Replacement of the site batery banks.
23-095-PW River road Substa�on Roof $15.6k Replacement of roof for EWEB’s Leaburg dam residen�al campus. Retrofit of a new mechanically fastened heat-welded 80mil TPO membrane roofing system.
HAYDEN BRIDGE WATER TREATMENT PLANT
23-129-PW HB Water Filtra�on Plant Canopy Replacement $146.3K Construc�on services for the Hayden Bridge Filtra�on Plant Canopy Replacement.
FACILITIES
23-135-PW Pain�ng at Roosevelt Opera�ons Center Exterior pain�ng of the EWEB Roosevelt Opera�ons Center Building.
23-051-PW Leaburg Homes Roof Replacement $108.2K
24-003-PW Roosevelt Opera�ons Center Expansion/Bertelsen Annex Construc�on of a new exterior, uncovered storage lay-down yard with access road, security fencing, site prep, grading, landscaping and associated u�lity work.
EXHIBIT B
CONSTRUCTION WORK BY TYPE AND DEPARTMENT
ELECTRICAL DISTRIBUTION
Generally low voltage of 600 volts or less. Most construc�on work in this department is self-performed but contracted occasionally.
o Electrical Contractor (Installa�on, demoli�on, wiring in industrial se�ngs)
SUBSTATIONS / ELECTRICAL TRANSMISSION SYSTEMS
10 Substa�ons in 10 years Rebuild Project Electric Reliability and Resiliency Projects | EWEB Example of 1 of the 10 projects: Currin Substa�on Rebuild | EWEB o Installa�on of large steel substa�on equipment and structures o Demoli�on o Concrete founda�on o Electrical conduit o Installa�on of electrical equipment
ELECTRIC GENERATION - DAMS
Loca�ons: Carmen-Smith dams and power plants, Leaburg Diversion Dam and Canal, Walterville Canal and power plant, steam turbine generator at the Springfield Interna�onal Paper facility, Stone Creek Diversion Dam and power plant
The Carmen-Smith Project is app. 1.5 to 2 hours from Eugene and 35 minutes from Leaburg/Walterville.
Refurbishment/Repair/Installa�on of Large Hydro-Equipment o Installing trash racks, debris booms, fish screens, fish passage facili�es o Tunnel repair and maintenance o Steel gate structures and mechanical hoists, associated electrical and control systems o Concrete spillway inspec�on, repair, and expansion o Welding, grinding, metal fabrica�on o Underwater diving to repair concrete or steel components, including welding, drilling, cu�ng, torquing (Examples: Stop log guides, temporary water conveyance systems, bulkhead guides) o Underwater debris removal and repairs/ improvements.
o Underwater inspec�ons to determine condi�on of welds, concrete, wire rope, embedded steel o Millwright work for pump and equipment repair/installa�on o Removal & applica�on of sealants, coa�ngs, and films o Pipe fi�ng and cleaning (8” or smaller) o Work involving barges/small boats
Refurbishment/Repair/Installa�on of Hydro-Related Electric Equipment o Installa�on or repair of hydroelectric genera�on equipment (Examples: turbine generators, turbine shut-off valves, pumps, motors, governors, exciters within powerhouse of 15 KV or less) o Electrical conduit installa�on, both rigid and flex conduit o Substa�on Rebuilds; Carmen in 2017 and Load Bank star�ng in 2024 https://www.eweb.org/electricreliability https://www.eweb.org/projects/electric-reliability-projects/currin-substation-rebuild o Powerhouse structural improvements o Process water and cooling systems
Control Systems:
o Low voltage system projects:
Installing, wiring, and calibra�ng process instrumenta�on (temperature, level, flow, pressure) o Medium voltage system projects:
Working within medium voltage switchgear (13KV) Working with MV poten�al transformers and current transformers o Process control system projects:
Allen-Bradley Control Logix PLC hardware Programming new I/O modules and new communica�on modules in an Allen-Bradley control system Installing and programming process control network hardware and so�ware
Environmental Improvements o Building fish-safe underwater structures. Larger upcoming projects include:
Trap and haul facility below Trail Bridge Trail Bridge spillway modifica�ons Spillway gate replacement Smith spillway modifica�ons o Some shotcrete and anchoring associated with the spillway approach o Aqua�c habitat installa�on
Decommissioning of the Leaburg Canal
Examples of Poten�al Projects:
Johnson Creek Ou�all: EWEB will modify the canal embankment for an ou�all structure below Johnson Creek. The new ou�all will provide an addi�onal outlet for stormwater from the canal.
Cogswell Creek Canal Plugs: EWEB may construct canal plugs to isolate deficient por�ons of the canal. The plugs will allow stormwater from Cogswell Creek to flow away from problem areas to the wasteway gate at the Luffman spillway.
Modifica�on and/or repair of the concrete liner and/or exis�ng spillway at the Walterville forebay. (An�cipated in app. 3 years)
Seal cracks and joints in the Walterville penstock and spillway during the 2024 outage.
Transmission Line Work o Examples include 2018 Deer Cr realignment and ~2025 Load Bank T-line extension o Large tree removal o Pole replacement
Recrea�onal Improvements o Forest Service trail building o Campground development o Day use areas o Fishing nodes o Building and installing boat ramps
Streambed Work:
o Streambed restora�on and/or construc�on In-water works Stream bypass systems / de-watering o Hydro-seeding, plan�ngs, erosion mi�ga�on
Bridge Maintenance:
o Occasional seismic upgrades Welding, anchorage, micro-piling o Joint repair o Decking and miscellaneous concrete repair HPC concrete Slurry seal PPC or MPC concrete o Coa�ngs o Guardrail repair and upgrades o Occasional pile scour mi�ga�on o In-water works, de-watering
ELECTRIC GENERATION / WATER DEPARTMENT
Genera�on Department : Carmen-Smith and Leaburg / Walterville dam projects Water Department: Work performed within the city of Eugene, OR
Site Improvements / Civil Construc�on o Site U�li�es:
Water distribu�on systems Electrical and communica�ons conduit installa�ons Stormwater drainage and culvert installa�on (usually to include pipes and junc�on boxes) Underground conduit installa�on Sep�c and sanitary sewer systems (not as commonly contracted as above) o Civil Earthwork
Erosion Control Rock fall protec�on (Genera�on Dept) Well drilling Excava�on Rock anchors Site grading Access roads Trenching and backfill o Soil Stabiliza�on and Geotechnical Construc�on Methods
Gabion or rip-rap armoring Hilfiker, gabion-basket or similar earthen retainage systems Keystone or ultra-block systems
Tie-back and/or soldier pile systems Micro pile installa�on o Building construc�on and repair
Roofing Mechanical and pump buildings Reinforced concrete walls and miscellaneous structural concrete Wood and steel buildings Industrial Pain�ng Industrial Fencing Tilt-up concrete (Water Dept) Masonry and FRP (Water Dept) o Installa�on of Prefabricated concrete structures
U�lity vaults Water management structures Shops Storage Restrooms Mechanical structures o Road construc�on, rehabilita�on, repair
Access Road Construc�on and Site Works Clearing and grubbing Embanked engineered fill and/or cut Subgrade prepara�on Rock placement, grading and compac�on Asphalt concrete placement on occasion Traffic control and flagging Striping
For exis�ng structures, may include mechanical piping and electrical equipment
Concrete saw-cu�ng, Steel removal via cu�ng or mechanical means o Concrete, Masonry, and Asphalt work
Repairing exis�ng or pouring new founda�ons, pedestals, slabs Concrete Joint Repair Installa�on of or construc�ng culvert, cofferdams, water bypass systems Culvert lining methods Concrete placement, finishing, flat work Paving Founda�on and slab-on-grade construc�on o Specialty Equipment Needs:
Vac-excava�on Long-reach excava�on equipment CAD Trucking Crane and heavy li�
WATER OPERATIONS
Note: EWEB generally works inside City limits and under permits issued by the City of Eugene or Lane County.
Please see the sec�on above for project work common to both this department and Electric Genera�on.
Work specific to Water opera�ons:
o Major construc�on of large water storage tanks Water Storage Improvements | EWEB o Construc�on of pipeline systems Water Pipeline Projects | EWEB o Demoli�on of exis�ng facili�es, pipes and concrete.
o Build or refurbish aggregate driveways leading to reservoirs and/or pump sta�ons o Piping and plumbing installa�on, reconnec�on, and improvements o Installa�on of potable water mains from 2” to 24” and occasionally larger o Installa�on of water services and meters from 5/8” to 6” and occasionally larger o Installa�on of fire hydrants and fire lines.
WATER TREATMENT
At the Hayden Bridge facility, work is usually self-performed but general construc�on is contracted from �me to �me.
Major Project Planned: A General Contractor with extensive project experience in construc�ng water treatment plants will be needed to build the future second source water treatment facility in Springfield, OR, some�me in year 2027 or 2028 (best es�mate at present.) Willamete Water Treatment Plant |
EWEB
Construc�on Work Contracted at the Hayden Bridge Facility:
o Civil Earthwork Stormwater drainage Underground conduit installa�on Asphalt concrete placement on occasion Erosion Control Excava�on Rock anchors o Road Construc�on and Site Works Clearing and grubbing for pond site prepara�on/maintenance Subgrade prepara�on Rock placement, grading and compac�on o Building construc�on and repair
Roofing Mechanical and pump buildings Reinforced concrete walls and miscellaneous structural concrete Industrial Pain�ng https://www.eweb.org/projects/water-storage-improvements https://www.eweb.org/projects/water-reliability-projects/pipeline-projects https://www.eweb.org/projects/willamette-water-treatment-plant
Industrial Fencing
Concrete saw-cu�ng, Steel removal via cu�ng or mechanical means o Concrete, Masonry, and Asphalt work
Culvert installa�on related to drying beds and ponds Construc�ng or installing cofferdams and water bypass systems Repairing exis�ng or pouring new founda�ons, pedestals, slabs Concrete Joint Repair o Prefabricated concrete structures
U�lity vaults Water management structures Shops Storage Restrooms Mechanical structures o Specialty Equipment Needs:
Vac-excava�on Long-reach excava�on equipment CAD Trucking Crane and heavy li�
EXHIBIT C
EXAMPLES OF PROJECTS – PAST, PRESENT, FUTURE
SUBSTATIONS / ELECTRICAL TRANSMISSION SYSTEMS
10 SUBSTATIONS IN 10 YEARS
Electric Reliability and Resiliency Projects | EWEB
CURRIN SUBSTATION REBUILD PROJECT
Currin Substa�on Rebuild | EWEB
EWEB plans to address this aging bubble of infrastructure with 10 major substa�on rebuilds in the next 10 years that will increase load capacity to ensure we meet future needs and improve reliability by avoiding outages due to equipment failure. We're beginning this year with the rebuild of Currin Substa�on.
https://www.eweb.org/electricreliability https://www.eweb.org/projects/electric-reliability-projects/currin-substation-rebuild
ELECTRIC GENERATION - DAMS
CARMEN-SMITH RELICENSING PROJECT
BACKGROUND
The Carmen-Smith Hydropower Project is a network of three dams, three reservoirs, and two power-genera�ng plants, located just a few miles downstream from the headwaters of the McKenzie River. For more than 50 years, Carmen-Smith has reliably served our customers with low-cost hydropower. The plant remains valuable as a carbon-free genera�on resource that can ramp up and down to meet customers' peak energy needs. In other words, Carmen-Smith operates as a system to store water overnight and produces power during high usage �mes when we would otherwise be buying power on the wholesale market during those more expensive hours.
POWER HOUSE PROJECT WORK
Electric and controls improvements at the Trail Bridge powerhouse
TURBINE GENERATOR REHABILITATION
Design-Build services for rehabilita�on of two Carmen-Smith powerhouse turbine generators
POWER TUNNEL WORK
Performed joint and crack repairs. Contractor used chemical grout materials, pumps, and various other equipment items to repair the joints and cracks.
HEAVY EQUIPMENT MAINTENANCE AND REPLACEMENT
Divers removing debris from the trash rack at Trail Bridge
Replacement of turbine shut-off valves at main powerhouse
NATURAL RESOURCE PROJECTS
• Crea�ng fish passage past Trail Bridge dam, which will give federally threatened salmon and trout access to historic spawning areas upstream of the dam.
• Enhancing biodiversity across more than 300 acres of terrestrial wildlife habitat by encouraging na�ve plant species, preserving mature trees and enhancing understory development, and providing dead wood habitat.
• Monitoring and respec�ng sites around the project that are culturally significant to the Confederated Tribes of
Grand Ronde, Confederated Tribes of Siletz, and Confederated Tribes of Warm Springs (and other indigenous tribes and bands).
• Rebuilding Trail Bridge Campground and shoreline trail, including universally accessible opportuni�es and signs about the history and ecology of the area.
• Monitoring rare, na�ve plants and removing invasive species.
RECREATION IMPROVEMENTS - CARMEN CAMPGROUND AREA
TEMPORARY FISH TRAP AND HAUL
Installa�on of temporary trap & haul device for fish passage at Carmen-Smith Hydro Project
DECOMMISSIONING OF LEABURG DAM
Decommissioning the Leaburg Hydroelectric Project | EWEB
To decommission the Leaburg Hydroelectric Project, EWEB will:
• Remove Leaburg Dam and restore Leaburg Lake to river form.
• Cooperate with transporta�on authori�es to develop access to Leaburg Dam Road on the south side of the river.
• Repair the Leaburg Canal so it can convey tributary flows to the river.
• Work with neighbors who get water from the Leaburg Canal to find alternate solu�ons, with par�cular focus on the Leaburg and McKenzie fish hatcheries.
• Perform a similar assessment of the Walterville Power Plant by 2030.
https://www.eweb.org/projects/mckenzie-river-hydro-projects/decommissioning-the-leaburg-hydroelectric-project
WATER DEPARTMENT – Work is generally performed within Eugene / Springfield, OR
EAST 40TH WATER STORAGE PROJECT
Two new 7.5-million-gallon earthquake-proof tanks on an undeveloped 10-acre site.
E. 40th Project | EWEB https://www.eweb.org/projects/water-storage-improvements/e-40th
EAST 40TH WATER STORAGE PROJECT (con�nued)
COLLEGE HILL PROJECT
College Hill Reservoir Replacement Project | EWEB
EWEB will dismantle the leaky and an�quated reservoir and replace it in the next few years with new, modern drinking water storage tanks built to withstand major earthquakes.
https://www.eweb.org/collegehill
WATER OPERATIONS
Water Outages | EWEB https://www.eweb.org/outages-and-safety/water-outages
WATER TREATMENT
HAYDEN BRIDGE WATER TREATMENT PLANT (SOURCE: MCKENZIE RIVER)
FUTURE SECOND SOURCE WATER TREATMENT FACILITY (SOURCE: WILLAMETTE RIVER)
Willamete Water Treatment Plant | EWEB
For nearly 90 years, the community of Eugene has relied on the McKenzie River as our only source of drinking water. Some other ci�es in the valley get their drinking water from the Willamete River. A�er years of careful planning for the future, EWEB will join Corvallis, Wilsonville, Hillsboro, Beaverton and other communi�es by tapping into this high-quality water source.
Of the 20 largest ci�es in the Northwest, Eugene is the only one with a single source of drinking water. While the McKenzie River will con�nue to be Eugene's primary water source, EWEB is in the early stages of developing an addi�onal water supply on the Willamete River.
EWEB has made numerous atempts to build a second water treatment plant over the last several decades. In 2017, Commissioners directed staff to postpone planning and funding for the project, and instead focus short-term efforts on developing Emergency Water Sta�ons. Since then, EWEB has worked with community partners to construct five emergency water distribution sites throughout the community.
Accessing the Willamete River as a redundant source is an important next step to ensure we can provide drinking water to our customers in case an emergency impacts the Hayden Bridge Filtra�on Plant or McKenzie River supply.
https://www.eweb.org/projects/emergency-water-stations