Exhibit J _ Preliminary Schedule.pdf

PDF 185 KB Posted

Attached to
2001-26 RFQP-CM/GC GTFI Bobby Dodd Stadium Fan Experience Renovation
Solicitation number
PE-50300-RFP-2025-000000226
Issued by
Fulton County, Georgia

About this file

This document is a preliminary project schedule for the Bobby Dodd Stadium Fan Experience Renovation, associated with Georgia Tech's Infrastructure and Sustainability department. The comprehensive 640-day project timeline spans from June 16, 2025, to November 26, 2027, and includes multiple key phases: contracting (55 days), design (39 weeks), bid and award (13 weeks), and construction and closeout (260 days). The schedule specifically outlines detailed milestones including design team and construction team selection, schematic design, design development, construction documents, permitting, procurement, and construction, with careful consideration of football seasons in 2025, 2026, and 2027.

The project schedule demonstrates a phased approach with strategic timing to minimize disruption to football operations, with construction activities carefully planned around seasonal constraints. The timeline indicates concurrent and sequential work streams, with specific durations allocated for each project stage, suggesting a methodical and structured renovation approach. Notable elements include an 8-week schematic design period, 21-week construction document production, 13-week bid and award process, and a 39-week construction period, all designed to culminate in a comprehensive stadium fan experience renovation without significantly impacting athletic program continuity.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task Name Duration Start Finish

1 Bobby Dodd Stadium Fan Experience Renovation 640 days? Mon 6/16/25 Fri 11/26/27

2 Contracting 55 days Mon 6/16/25 Fri 8/29/25

3 Design Team Selection 50 days Mon 6/16/25 Fri 8/22/25

4 Construction Team Selection 50 days Mon 6/23/25 Fri 8/29/25

5 Design 39 wks Mon 9/1/25 Fri 5/29/26

6 Schematic Design 8 wks Mon 9/1/25 Fri 10/24/25

7 Design Team Released into DD's 8 wks Mon 9/1/25 Fri 10/24/25

8 Design Development 8 wks Mon 10/27/25 Fri 12/19/25

9 Design Team Released into CD's 8 wks Mon 10/27/25 Fri 12/19/25

10 Construction Documents 21 wks Mon 1/5/26 Fri 5/29/26

11 Team Production Time 21 wks Mon 1/5/26 Fri 5/29/26

12 Bid & Award 13 wks Mon 6/1/26 Fri 8/28/26

13 Permitting 4 wks Mon 6/1/26 Fri 6/26/26

14 Bid & Award 13 wks Mon 6/1/26 Fri 8/28/26

15 Construction & Closeout 260 days Mon 8/31/26 Fri 8/27/27

16 Procurement 13 wks Mon 8/31/26 Fri 11/27/26

17 Construction 39 wks Mon 11/30/26 Fri 8/27/27

18 Football Season 2025 60 days? Mon 9/8/25 Fri 11/28/25

19 Season 2025 60 days? Mon 9/8/25 Fri 11/28/25

20 Football Season 2026 60 days? Mon 9/7/26 Fri 11/27/26

21 Season 2026 60 days? Mon 9/7/26 Fri 11/27/26

22 Football Season 2027 60 days? Mon 9/6/27 Fri 11/26/27

23 Season 2027 60 days? Mon 9/6/27 Fri 11/26/27

Design Team Selection

Construction Team Selection

Design Team Released into DD's

Design Team Released into CD's

Team Production Time

Permitting

Bid & Award

Procurement

Construction

Season 2025

Season 2026

Season 2027

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026 Qtr 4, 2026 Qtr 1, 2027 Qtr 2, 2027 Qtr 3, 2027 Qtr 4, 2027 Qtr 1, 2028

Bobby Dodd Stadium Fan Experience Renovation - Preliminary Schedule 06.12.2025

Exhibit J - Preliminary Schedule