Exhibit C _ CM_GC_Fee_Proposal_Form.docx
DOCX document 18 KB Posted
- Solicitation number
- PE-50300-RFP-2025-000000226
- Issued by
- Fulton County, Georgia
About this file
This document is a CM/GC Fee Proposal Form for the Bobby Dodd Stadium Fan Experience Renovation project at the Georgia Institute of Technology. The form outlines the comprehensive fee structure and cost breakdown for a Construction Manager/General Contractor (CM/GC) engagement, detailing the financial components for preconstruction and construction phase services.
The proposal requires the CM/GC to submit detailed fee breakdowns across multiple categories, including a fixed preconstruction services fee, construction phase services fee (percentage-based), construction overhead costs, and fees for potential changes in the work. Additional cost components include reimbursement rates for builder's risk insurance, contractor's general liability insurance, and performance & payment bonds. The document provides a standardized template for the contractor to specify their pricing structure, with spaces to list fixed fees, percentage rates, and total cost summaries, which will be submitted in a sealed envelope during the interview process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit G _ Proposer_Disclosure_Statement.doc | DOC document | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit H _ A105 GTFI_CM Insurance Requiremen.pdf | ||
| Exhibit A _ Certification_Form.docx | DOCX document | |
| Exhibit E _ General_Conditions_Breakdown.xlsx | XLSX spreadsheet | |
| Exhibit I _ Sample Form of A133_2019_Owner_CM.pdf | ||
| Exhibit D _ Preconstruction_CostExpenses_Brea.xlsx | XLSX spreadsheet | |
| Exhibit J _ Preliminary Schedule.pdf | ||
| 0481_2025 CM RFQ_RFP_final 06_30_2025.pdf | ||
| Exhibit F _ Project_Cost_Matrix.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT C
CM/GC FEE PROPOSAL
(Submit In a Sealed Envelope with Exhibit D and E at Interview)
Bobby Dodd Stadium Fan Experience Renovation Georgia Institute of Technology
1. CM/GC’S FEE:
Basis of Fee. The CM/GC’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the CM/GC as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the CM/GC performs all the requirements of the Contract Documents within the time limits established. If applicable, the fees and costs should be broken down by each site within a multi-site project.
A. PRECONSTRUCTION PHASE SERVICES FEE:
Pre-Construction Phase Services Fee. (See Section 4.1.2 of AIA A133-2009) Attach to this CM/GC PROPOSAL form a completed copy of Exhibit D – Preconstruction Costs and Expenses Breakdown.
Amount
Pre-Construction Services Phase Fee (fixed fee)
B. CONSTRUCTION PHASE SERVICES FEE:
Construction Phase Services Fee. (See Section 5.1.1 of AIA A133-2009)
Amount
Construction Phase Services Fee (expressed as a percentage of the Cost of the Work)
2. CM/GC’S CONSTRUCTION OVERHEAD COSTS:
Attach to this CM/GC PROPOSAL form a completed copy of Exhibit E – Construction Overhead Costs Breakdown.
3. CM/GC’S FEE FOR CHANGES IN THE COST OF THE WORK:
Changes Fee. (See Section 5.1.2 of AIA A133-2009).
Amount
CM/GC Fee for changes in the Cost of the Work (expressed as a percentage of the net change in the Cost of the Work due to a Modification)
4. REIMBURSEMENT FOR BUILDER’S RISK, CONTRACTOR’S GENERAL LIABILITY INSURANCE, AND BONDS.
See Section 5.3.6 of AIA A133-2009.
TOTAL
Reimbursement for Builder’s Risk (expressed as a fixed rate per $1000 of the net change in the Cost of the Work due to a Change Order)
| Reimbursement for Contractor’s General Liability insurance (expressed as a fixed percentage of the net change in the Cost of the Work due to a Change Order) |
| % |
| Reimbursement for Performance & Payment Bonds (expresses as a fixed percentage of the net change in the Cost of the Work due to a Change Order) |
| % |
5. SUMMARY
TOTAL
Pre-Construction Services Fee (fixed fee)
General Conditions/Overhead Costs – Exhibit E
General Conditions
Months
CM/GC Construction Phase Services Fee (expressed as a percentage of the Cost of the Work)
CM/GC Fee for changes in the Cost of the Work (expressed as a percentage of the net change in the Cost of the Work due to a Modification)
CM/GC Name
By:_________________________________________________________ Signature of CM/GC Officer
Title of CM/GC Officer
File details come from the government source that posted it. Updated .