This document is a payment request form and monthly submittal checklist for a construction contract with the Department of Veterans Affairs. The payment request form requires the contractor to provide the original and current contract amounts, amounts completed to date and recommended for payment, retainage and previous payments amounts, and certification that payments to subcontractors have been made. The monthly submittal checklist requires the contractor to submit items on a recurring basis for payment request approval, including daily production reports, safety inspection reports, quality control reports, an updated schedule, waste manifests, as-built drawings updates, certified payrolls, and warranty information. The contracting officer, contracting officer's representative, and project manager must initial each item upon submission.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--VISN 1 Construction MATOC, newest first.
File Type Posted
WD MA20230001 Effective 12082023.pdf PDF
523-19-602 Rev 1 AD100 AS101 AS102.pdf PDF
Amendment 0017 RFIs.pdf PDF
523 19 602 Project Manual Part 1 A0016.pdf PDF
523 19 602 Drawings Pages 19 to 23 A0016.pdf PDF
Seed Project Original Site Visit Sign In Sheet August 9 2023 A0016.pdf PDF
523-19-602 Seed ICRA JP Police Office A0016.pdf PDF
SPECIAL MATOC REQUIREMENTS A0016.pdf PDF
Exhibit F Price Schedule Sheet A0016.pdf PDF
Exhibit E Base Offer Cost Breakdown A0016.xlsx XLSX spreadsheet
523 19 602 Drawings Pages 10 to 18 A0016.pdf PDF
523 19 602 Drawings Pages 1 to 9 A0016.pdf PDF
523 19 602 Project Manual Part 2 A0016.pdf PDF
36C24123R0073 0016.pdf PDF
Exhibit G VA PAY FORM w Monthly checklist A0016.pdf PDF
523-19-602 Seed Project Notice of Task Order Request for Proposal A0016.pdf PDF
Seed Project Parking Map A0016.PNG PNG image
Amendment 0016 RFIs.pdf PDF
36C24123R0073 0015.pdf PDF
36C24123R0073 0014.pdf PDF
MATOC RFIs Amendment 10.pdf PDF
523-19-602 Revised Specs.pdf PDF
SSJ Lock Systems.pdf PDF
SSJ DDC BMS.pdf PDF
Seed RFIs Amendment 10.pdf PDF
36C24123R0073 0008.pdf PDF
S06 36C24123R0073 0006.pdf PDF
36C24123R0073 0005.docx DOCX document
Amendment 5 Seed RFIs.pdf PDF
Updated Exhibit B Past Performance Questionnaire.pdf PDF
GENERAL CONTRACT REQUIREMENT SECTIONS 01000 01001 01300 01451 01700.pdf PDF
Seed Project RFIs.pdf PDF
36C24123R0073 0004.pdf PDF
WD MA20230001 Effective 08112023.pdf PDF
36C24123R0073 0004.docx DOCX document
36C24123R0073 0001.pdf PDF
36C24123R0073 Solicitation.pdf PDF
523 19 602 Drawings Pages 31 to 68.pdf PDF
523 19 602 Specifications.pdf PDF
Exhibit E Base Offer Cost Breakdown.xlsx XLSX spreadsheet
Exhibit D Proposal Inquiry Form.pdf PDF
523 19 602 Project Manual Part 2.pdf PDF
Exhibit C Safety Questionnaire.pdf PDF
Exhibit B Past Performance Questionnaire.pdf PDF
523 19 602 Drawings Pages 10 to 18.pdf PDF
523 19 602 Drawings Pages 1 to 9.pdf PDF
523 19 602 Task Order RFP.pdf PDF
Exhibit F Price Schedule Sheet.pdf PDF
SPECIAL MATOC REQUIREMENTS.pdf PDF
GENERAL CONTRACT REQUIREMENTS SECTIONS 01000 01001 01300 01451 01700.pdf PDF
Show all 50

Z2DA--VISN 1 Construction MATOC has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Pay Form

Contractor: ____________________________ Contract No.: ________________________

_____________________________ Project No.: ________________________

______________________________ Period Ending: ________________________

Request No.: _________________________

Date of Request: __________________________

Project Title: ______________________________________________________ ___________________

PROGRESS PAYMENT

Original Contract Amount: $________________________

Increases Authorized: $________________________

Decreases Authorized: $________________________

Current Contract Amount: $________________________

Activities Completed to Date: $________________________

Less Retainage: $________________________

Less Previous Payments: $________________________

Amount Recommended for Payment: $________________________

Contract Balance: $________________________

CERTIFICATION

I hereby certify, to the best of my knowledge and belief, that-

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor’s performance.

NAME – SIGNATURE TITLE DATE

I have reviewed this payment request and agree that the Contractor is entitled to payment in the amount shown above.

Construction Representative Date

Contracting Officer’s Representative Date

Contracting Officer Date

Monthly Submittal Checklist Submittals required prior to pay request approval

Item

Date Submitted

PM

Initial

COR /CO

Initial

Daily Production Reports 852.236-79

Daily Safety Inspection Reports 01 35 26 1.9A

Certified Safety Professional (CSP) Monthly Site Safety Inspection 01 35 26 1.9B

Exposure Hours – 01 35 26 1.10.C

Quality Control Reports 01 45 00 3.9A

Updated Schedule – 013216.15 para 1.4.A

Waste Manifests – 017419 para 1.5.D

Monthly As-built Update – 01 00 00 1.14B, 01 00 00 1.15B

Weekly Certified Payrolls – FAR 52.222-8

Warranty Information – 010000 para 1.16.A

Sustainable Construction Progress Reports – 018113 para 1.5.F

COR/CO and PM may agree that a submittal is not applicable to the project or to the current month.