Exhibit F _ Project Cost Matrix.xlsx
XLSX spreadsheet 25 KB Posted
- Attached to
- CLSU J-475-DB Campus Infrastructure Phase III
- Solicitation number
- PE-47200-RFQ-2027-000000153
- Issued by
- Clayton County, Georgia
About this file
This is a Cost Proposal Matrix for Design-Build Services related to Project No. J-475-DB, Campus Infrastructure Phase III at Clayton State University in Morrow, Georgia. The matrix serves as a guide for bidders to prepare their cost proposals by indicating where the Owner wishes to allocate costs across three primary cost categories: Construction Fee, General Conditions, and Cost of Work By Others. The document outlines cost allocation requirements across seven major cost sections: Site Supervision & Management, Site Office Expense, Safety & Security, Cleaning, General Equipment, Bonds & Insurance, and Miscellaneous expenses. Key line items include senior project management positions, site office setup and operations, safety equipment and personnel, temporary facilities and utilities, construction equipment, insurance requirements, and various project-related miscellaneous costs. The matrix indicates a projected fee of $1,231,000 based on a $46 million Guaranteed Maximum Price (GMP).
The cost proposal structure requires bidders to allocate expenses to appropriate categories marked with "X," with certain items marked as "NA" (not applicable), "Incl." (included in other line items), or assigned specific dollar values. Safety Engineer costs are specified at $30,000 in General Conditions. Bidders must follow this allocation framework when submitting their cost proposals to ensure consistency with the Owner's budgeting requirements. The matrix does not specify response deadlines, award dates, or contract terms within the document itself, as it functions primarily as a cost breakdown template for the design-build project delivery method.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit C _ DB Fee Proposal.docx | DOCX document | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet | |
| Egnyte Upload Instructions.pdf | ||
| _CLSU J_475 DB RFQ_RFP.pdf | ||
| Exhibit D _ Precon Cost and Expenses.xlsx | XLSX spreadsheet | |
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cost Proposal Matrix
| PROJECT COST MATRIX | ||||||||
| The spaces marked with an "X" below indicate where the Owner wishes to allocate costs for the project. Please follow this as a guide in preparing your cost proposal for the project. | ||||||||
| Project No. J-475, Campus Infrastructure Phase III | ||||||||
| Clayton State University, Morrow, Georgia | ||||||||
| I. Site Supervision & Management: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Project Executive | X | |||||||
| Corporate Executives | X | |||||||
| Legal Services | X | |||||||
| Senior Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Asst. Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Area Supt. | X | NA | ||||||
| Secretary | X | $0 | $0 | 0 | $0 | |||
| Project Engineer | X | $0 | $0 | 0 | $0 | |||
| Engineer or Eng. Company | X | $0 | $0 | |||||
| Cost Control | X | $0 | $0 | |||||
| Safety Engineer | X | 0 | $30,000 | |||||
| Scheduling | X | $0 | $0 | 0 | $0 | |||
| Purchasing | X | 0 | $0 | |||||
| Project Accountant | X | Incl. | ||||||
| Rodman | X | Incl. | ||||||
| $0 | $0 | 0 | $0 |
| II. Site Office Expense: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Job Office Trailer Rent | X | NA | ||||||
| Office Jobsite Build Out | X | $0 | $0 | 0 | $0 | |||
| Office Jobsite Set-up | X | $0 | $0 | 0 | $0 | |||
| Temp. Const. Trailer/Storage | X | NA | ||||||
| Office Furniture | X | Incl. Below | ||||||
| Office Machines/Equip. | X | $0 | $0 | 0 | $0 | |||
| Copy Machines/Maintenance | X | Incl. Above | ||||||
| Office Supplies | X | $0 | $0 | 0 | $0 | |||
| Janitor/San. Supplies | X | $0 | $0 | |||||
| Postage & Shipping | X | $0 | $0 | 0 | $0 | |||
| First Aid/Med. Treat. | X | $0 | $0 | |||||
| Telephone System | X | $0 | $0 | 0 | $0 | |||
| Phone Installation | X | 0 | $0 | |||||
| Phone Charges | X | 0 | $0 | |||||
| Phone Charges-Long Dist. | X | By Arch. | ||||||
| Radio Communications | X | $0 | $0 | 0 | $0 | |||
| Radio Maintenance | X | Incl. | ||||||
| Computer-PCS | X | $0 | $0 | 0 | $0 | |||
| Computers | X | Incl. | ||||||
| Software | X | $0 | $0 | 0 | $0 | |||
| MIS Charges | X | 0 | $0 | |||||
| Temp. Electric-Office | X | |||||||
| Security-Office | X | |||||||
| Water - Field Office | X |
| 0 | $0 | |||||||
| III. Safety & Security: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Safety Incentives | X | NA | ||||||
| Watchman/Guard Ser. | X | 0 | $0 | |||||
| Traffic Control | X | $0 | $0 | 0 | $0 | |||
| Safety Equipment | X | $0 | $0 | 0 | $0 | |||
| Rainwear/Hardhats, etc. | X | 0 | $0 | |||||
| Drug Testing | X | $0 | $0 | 0 | $0 | |||
| Fences & Gates | X | 0 | $0 | |||||
| Fire Protection, Extinquishers, Barrels | X | 0 | $0 | |||||
| Covered Walkways | X | 0 | $0 | |||||
| Roadway Maintenance | X | $0 | $0 | |||||
| Sidewalk Barricades | X | $0 | $0 | |||||
| Safety Railings | X | $0 | $0 | |||||
| Opening Closures | X | |||||||
| Weather Protection | X | |||||||
| Ladders & Stailrs | X |
| IV. Cleaning: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Trash Bin Rent/Haul | X | Incl. | ||||||
| Trash Chutes/Hoppers | X | $0 | $0 | 0 | $0 | |||
| Dump Fees/Hauling | X | $0 | 0 | $0 | ||||
| Dust Barricades | X | 0 | $0 | |||||
| Daily Cleaning | X | |||||||
| Final Cleanup-Building | X | |||||||
| Window/Skylight Cleaning | X |
| $0 | 0 | $0 | ||||||
| V. General Equipment: | Construction Fee | General Conditions | Cost of Work | By Others | $0 | 0 | $0 | |
| Small Tools/Expendables | X | $0 | $0 | 0 | $0 | |||
| Survey Equipment | X | Incl. | ||||||
| Hoist/Operator | X | 0 | $0 | |||||
| Hoist Service | X | $0 | $0 | 0 | $0 | |||
| Erect/Dismantle Hoist | X | 0 | $0 | |||||
| Temp. Elev. & Operator | X | $0 | 0 | $0 | ||||
| Rapair Cab/Temp. Elev. | X | $0 | 0 | $0 | ||||
| Protect Perm. Elevator | X | |||||||
| Fuel/Oil/Grease | X | |||||||
| Forklift Rental | X | |||||||
| Contractor Equipment License | X | |||||||
| Contractor Equipment Permits | X | |||||||
| Tower Crane Service | X | |||||||
| Erect/Dismantle Crane | X | |||||||
| Crane Rental/Operator | X | |||||||
| Construction Equipment | X |
| VI. Bonds & Insurance: | Construction Fee | General Conditions | Cost of Work | By Others | |
| Perform. & Payment Bonds | X | ||||
| Workers Comp. Insurance | X | ||||
| Liability Insurance | X | ||||
| Fed. & State Unemployment | X | ||||
| FICA | X | ||||
| Builders Risk Insurance | X | ||||
| $1,231,000 |
| Projected Fee (Based on $46 Million GMP) | ERROR:#REF! | |
| Builders Risk Insurance | X |
| VII. Miscellaneous: | Construction Fee | General Conditions | Cost of Work | By Others | ||
| CM General Overhead Cost | X | |||||
| CM Profit Margin | X | |||||
| Costs Over GMP | X | |||||
| Project Staff Living Expenses | X | |||||
| Executive Travel | X | |||||
| Air Fare | X | |||||
| Car Rental | X | |||||
| Hotel | X | |||||
| Meals | X | |||||
| Project Staff Moving Expenses | X | |||||
| Warranty Work | X | |||||
| Off-Site Parking | X | |||||
| Ceremony Expense | X | |||||
| Vehicle for On-Site Project Manager | X | |||||
| Vehicle for On-Site Superintendent | X | |||||
| Vehicle Repairs/Maintenance | X | |||||
| Water - Coolers | X | |||||
| Water Barrels | X | |||||
| Ice Machine | X | |||||
| Ice and/or Cups | X | |||||
| Temporary Toilets Install | X | |||||
| Temporary Toilets | X | |||||
| Cold Weather Protection | X | |||||
| Temp. Heat for Bldg. | X | |||||
| Job Signs | X | |||||
| Progress Photos | X | |||||
| Extra Plans & Specs. | X | |||||
| Blueprint/Photostat. | X | |||||
| Temp. Electric -Building | X | |||||
| Building Permit | X | |||||
| Plan Check Fees | X | |||||
| Temporary Roads | X | |||||
| Project Taxes | X | |||||
| Moving Coordination & Costs for Project | X | |||||
| Materials Incorporated Into the Building | X | |||||
| Corrective Work | X | |||||
| Punchlist Work | X | |||||
| Advertising for Bids | X | |||||
| Soils Testing & Investigation | X | |||||
| Construction Materials Testing | X | 0 | $0 | |||
| Special Inspections | X | |||||
| Water Connection Fees | X | |||||
| Sanitary Connection Fees | X | |||||
| Storm Connection Fees | X | |||||
| Gas Service Fees | X | |||||
| Power Service Fees | X | |||||
| Impact Fee | X |
&"Arial,Bold"&16&UAttachment A
&D &T &P
Sheet2
Sheet3
File details come from the government source that posted it. Updated .