Exhibit F _ Project Cost Matrix.xlsx
XLSX spreadsheet 31 KB Posted
- Solicitation number
- PE-54300-RFQC-2025-000000054
- Issued by
- Cobb County, Georgia
About this file
This is a Project Cost Matrix (Exhibit F) for an unnamed construction project in Georgia, detailing the allocation of costs across three categories: Construction Fee, General Conditions, and Cost of Work By Others. The matrix comprehensively breaks down project costs into seven major sections: Site Supervision & Management, Site Office Expense, Safety & Security, Cleaning, General Equipment, Bonds & Insurance, and Miscellaneous expenses.
The document indicates a projected fee based on a $46 million Guaranteed Maximum Price (GMP) and includes specific allocations for key personnel such as Project Executive, Senior Project Manager, Project Superintendent, and support staff. Notable cost allocations include $30,000 for Safety Engineer under General Conditions, and $1,231,000 for Builders Risk Insurance. The matrix uses "X" marks to indicate the owner's preferred cost allocation category for each line item, providing a clear framework for contractors to prepare their cost proposals.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1.docx | DOCX document | |
| Exhibit E _ Contractor Affidavit.docx | DOCX document | |
| Exhibit G _ Proposers Disclosure Statement.doc | DOC document | |
| Addendum 3.docx | DOCX document | |
| 777_25_125 KSU Campus Alta Survey_SUE and GIS.docx | DOCX document | |
| Exhibit A _ Certification Form.docx | DOCX document | |
| Exhibit B _ Certificate of Insurance and Mino.docx | DOCX document | |
| Exhibit D _ Consultant Fee Proposal Sample.docx | DOCX document | |
| Addendum 5.docx | DOCX document | |
| Addendum 2.docx | DOCX document | |
| Addendum 4.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cost Proposal Matrix
| EXHIBIT F - PROJECT COST MATRIX | ||||||||
| The spaces marked with an "X" below indicate where the Owner wishes to allocate costs for the project. Please follow this as a guide in preparing your cost proposal for the project. | ||||||||
| Project No., Project Name | ||||||||
| Institution, City, Georgia | ||||||||
| I. Site Supervision & Management: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Project Executive | X | |||||||
| Corporate Executives | X | |||||||
| Legal Services | X | |||||||
| Senior Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Mgr. | X | $0 | $0 | 0 | $0 | |||
| Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Asst. Project Supt. | X | $0 | $0 | 0 | $0 | |||
| Area Supt. | X | NA | ||||||
| Secretary | X | $0 | $0 | 0 | $0 | |||
| Project Engineer | X | $0 | $0 | 0 | $0 | |||
| Engineer or Eng. Company | X | $0 | $0 | |||||
| Cost Control | X | $0 | $0 | |||||
| Safety Engineer | X | 0 | $30,000 | |||||
| Scheduling | X | $0 | $0 | 0 | $0 | |||
| Purchasing | X | 0 | $0 | |||||
| Project Accountant | X | Incl. | ||||||
| Rodman | X | Incl. | ||||||
| $0 | $0 | 0 | $0 |
| II. Site Office Expense: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Job Office Trailer Rent | X | NA | ||||||
| Office Jobsite Build Out | X | $0 | $0 | 0 | $0 | |||
| Office Jobsite Set-up | X | $0 | $0 | 0 | $0 | |||
| Temp. Const. Trailer/Storage | X | NA | ||||||
| Office Furniture | X | Incl. Below | ||||||
| Office Machines/Equip. | X | $0 | $0 | 0 | $0 | |||
| Copy Machines/Maintenance | X | Incl. Above | ||||||
| Office Supplies | X | $0 | $0 | 0 | $0 | |||
| Janitor/San. Supplies | X | $0 | $0 | |||||
| Postage & Shipping | X | $0 | $0 | 0 | $0 | |||
| First Aid/Med. Treat. | X | $0 | $0 | |||||
| Telephone System | X | $0 | $0 | 0 | $0 | |||
| Phone Installation | X | 0 | $0 | |||||
| Phone Charges | X | 0 | $0 | |||||
| Phone Charges-Long Dist. | X | By Arch. | ||||||
| Radio Communications | X | $0 | $0 | 0 | $0 | |||
| Radio Maintenance | X | Incl. | ||||||
| Computer-PCS | X | $0 | $0 | 0 | $0 | |||
| Computers | X | Incl. | ||||||
| Software | X | $0 | $0 | 0 | $0 | |||
| MIS Charges | X | 0 | $0 | |||||
| Temp. Electric-Office | X | |||||||
| Security-Office | X | |||||||
| Water - Field Office | X |
| 0 | $0 | |||||||
| III. Safety & Security: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Safety Incentives | X | NA | ||||||
| Watchman/Guard Ser. | X | 0 | $0 | |||||
| Traffic Control | X | $0 | $0 | 0 | $0 | |||
| Safety Equipment | X | $0 | $0 | 0 | $0 | |||
| Rainwear/Hardhats, etc. | X | 0 | $0 | |||||
| Drug Testing | X | $0 | $0 | 0 | $0 | |||
| Fences & Gates | X | 0 | $0 | |||||
| Fire Protection, Extinquishers, Barrels | X | 0 | $0 | |||||
| Covered Walkways | X | 0 | $0 | |||||
| Roadway Maintenance | X | $0 | $0 | |||||
| Sidewalk Barricades | X | $0 | $0 | |||||
| Safety Railings | X | $0 | $0 | |||||
| Opening Closures | X | |||||||
| Weather Protection | X | |||||||
| Ladders & Stailrs | X |
| IV. Cleaning: | Construction Fee | General Conditions | Cost of Work | By Others | ||||
| Trash Bin Rent/Haul | X | Incl. | ||||||
| Trash Chutes/Hoppers | X | $0 | $0 | 0 | $0 | |||
| Dump Fees/Hauling | X | $0 | 0 | $0 | ||||
| Dust Barricades | X | 0 | $0 | |||||
| Daily Cleaning | X | |||||||
| Final Cleanup-Building | X | |||||||
| Window/Skylight Cleaning | X |
| $0 | 0 | $0 | ||||||
| V. General Equipment: | Construction Fee | General Conditions | Cost of Work | By Others | $0 | 0 | $0 | |
| Small Tools/Expendables | X | $0 | $0 | 0 | $0 | |||
| Survey Equipment | X | Incl. | ||||||
| Hoist/Operator | X | 0 | $0 | |||||
| Hoist Service | X | $0 | $0 | 0 | $0 | |||
| Erect/Dismantle Hoist | X | 0 | $0 | |||||
| Temp. Elev. & Operator | X | $0 | 0 | $0 | ||||
| Rapair Cab/Temp. Elev. | X | $0 | 0 | $0 | ||||
| Protect Perm. Elevator | X | |||||||
| Fuel/Oil/Grease | X | |||||||
| Forklift Rental | X | |||||||
| Contractor Equipment License | X | |||||||
| Contractor Equipment Permits | X | |||||||
| Tower Crane Service | X | |||||||
| Erect/Dismantle Crane | X | |||||||
| Crane Rental/Operator | X | |||||||
| Construction Equipment | X |
| VI. Bonds & Insurance: | Construction Fee | General Conditions | Cost of Work | By Others | |
| Perform. & Payment Bonds | X | ||||
| Workers Comp. Insurance | X | ||||
| Liability Insurance | X | ||||
| Fed. & State Unemployment | X | ||||
| FICA | X | ||||
| Builders Risk Insurance | X | ||||
| $1,231,000 |
| Projected Fee (Based on $46 Million GMP) | ERROR:#REF! | |
| Builders Risk Insurance | X |
| VII. Miscellaneous: | Construction Fee | General Conditions | Cost of Work | By Others | ||
| CM General Overhead Cost | X | |||||
| CM Profit Margin | X | |||||
| Costs Over GMP | X | |||||
| Project Staff Living Expenses | X | |||||
| Executive Travel | X | |||||
| Air Fare | X | |||||
| Car Rental | X | |||||
| Hotel | X | |||||
| Meals | X | |||||
| Project Staff Moving Expenses | X | |||||
| Warranty Work | X | |||||
| Off-Site Parking | X | |||||
| Ceremony Expense | X | |||||
| Vehicle for On-Site Project Manager | X | |||||
| Vehicle for On-Site Superintendent | X | |||||
| Vehicle Repairs/Maintenance | X | |||||
| Water - Coolers | X | |||||
| Water Barrels | X | |||||
| Ice Machine | X | |||||
| Ice and/or Cups | X | |||||
| Temporary Toilets Install | X | |||||
| Temporary Toilets | X | |||||
| Cold Weather Protection | X | |||||
| Temp. Heat for Bldg. | X | |||||
| Job Signs | X | |||||
| Progress Photos | X | |||||
| Extra Plans & Specs. | X | |||||
| Blueprint/Photostat. | X | |||||
| Temp. Electric -Building | X | |||||
| Building Permit | X | |||||
| Plan Check Fees | X | |||||
| Temporary Roads | X | |||||
| Project Taxes | X | |||||
| Moving Coordination & Costs for Project | X | |||||
| Materials Incorporated Into the Building | X | |||||
| Corrective Work | X | |||||
| Punchlist Work | X | |||||
| Advertising for Bids | X | |||||
| Soils Testing & Investigation | X | |||||
| Construction Materials Testing | X | 0 | $0 | |||
| Special Inspections | X | |||||
| Water Connection Fees | X | |||||
| Sanitary Connection Fees | X | |||||
| Storm Connection Fees | X | |||||
| Gas Service Fees | X | |||||
| Power Service Fees | X | |||||
| Impact Fee | X |
&"Arial,Bold"&16&UAttachment A
&D &T &P
Sheet2
Sheet3
File details come from the government source that posted it. Updated .