Exhibit C _ DB Fee Proposal.docx
DOCX document 25 KB Posted
- Solicitation number
- PE-47200-RFQ-2026-000000120
- Issued by
- Fulton County, Georgia
About this file
This is a Design Builder (DB) Fee Proposal document for the Peachtree Center Parking Deck and Retail project at Georgia State University (Project No. BR-50-2603). The proposal establishes the compensation structure for design-build services, which includes basic design services, construction administration services, pre-construction consulting services, and construction services. The document requires breakdown of fees and costs across three primary categories: Design Consultants Fee, Pre-Construction Fee, and Construction Fee, with all services to be completed within contract-specified time limits.
The fee structure consists of three fixed-fee components: a Design Consultants Fee for basic design and construction administration, a Pre-Construction Fee representing gross profit for pre-construction consulting services, and a Construction Fee representing gross profit for construction services. Additionally, the Design Builder must provide maximum amounts for Pre-Construction Costs and Expenses and Construction Overhead Costs, with both categories inclusive of all direct and incidental expenses. The document requires the Design Builder to complete Attachments A and B to detail pre-construction and construction overhead costs respectively, excluding the associated fees from these overhead cost calculations. The proposal requires signature authorization from a designated DB officer and must include the firm name and officer title.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit G _ Proposer_s Disclosure Statement.doc | DOC document | |
| _GSU BR_50_2603 DB RFQ_RFP.pdf | ||
| Exhibit F _ Project Cost Matrix.xlsx | XLSX spreadsheet | |
| Egnyte Upload Instructions.pdf | ||
| Exhibit D _ Precon Cost and Expenses.xlsx | XLSX spreadsheet | |
| Exhibit E _ General Conditions Breakdown.xlsx | XLSX spreadsheet | |
| Exhibit B _ Contractor Affidavit.docx | DOCX document | |
| Exhibit A _ Certification Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
15 of Exhibit C
Project No. BR-50-2603, Peachtree Center Parking Deck and Retail Georgia State University
DESIGN BUILDER (DB) FEE PROPOSAL
1. DB’S FEE:
Basis of Fee. The DB’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the DB as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the DB performs all the requirements of the Contract Documents within the time limits established. (See Article 4.1.1 of the General Requirements.) If applicable, the fees and costs should be broken down by each site within a multi-site project.
A. DESIGN CONSULTANTS FEE:
Design Consultants Fee. Representing the fee amount for basic design services and construction administration services provided by DB. Owner shall pay to DB a Design Consultants Fee:
TOTAL
Design Fee (fixed fee)
B. PRECONSTRUCTION FEE:
Pre-Construction Fee. Representing the gross profit for the pre-construction consulting services provided by DB as set forth in Section 2, Parts 1 and 2 of the General Requirements, and as described in Paragraph 4.1.1.1(a), Owner shall pay to DB a Preconstruction Fee:
TOTAL
Pre-Construction Fee (fixed fee)
C. CONSTRUCTION FEE:
Construction Fee. Representing the gross profit for the construction services provided by DB as set forth in Section 3, Part 1 of the General Requirements, and as described in Paragraph 4.1.1.1(b) Owner shall pay to DB a Construction Fee.
TOTAL
Construction Fee (fixed fee)
2. DB’S PRECONSTRUCTION & CONSTRUCTION OVERHEAD COSTS and EXPENSES:
The DB’s Overhead Costs. The maximum amount for the DB’s Pre-Construction Costs and Expenses and Construction Overhead Costs are inclusive of all direct and incidental expenses are as described in Paragraph 4.1.1.2 .
AMOUNT
A. Maximum Pre-construction Costs & Expenses (From Attachment A. Do not include the Pre-Construction Fee in this amount)
B. Maximum Construction Overhead Costs (From Attachment B. Do not include the Construction Fee in this amount)
Total Maximum Overhead Cost (Sum of A & B)
DB Firm Name
By:__________________________________________________________ Signature of DB Officer
Title of DB Officer
File details come from the government source that posted it. Updated .