Exhibit_C___CM_GC_Fee_Proposal.docx

DOCX document 15 KB Posted

Attached to
Renovations to Interdisciplinary Research Building
Solicitation number
PE-51200-RFQC-2026-000000031
Issued by
Richmond County, Georgia

About this file

This file is a CM/GC Fee Proposal exhibit for a construction management/general contractor engagement with an institution in Georgia, specifically related to renovations at the Interdisciplinary Research Building at Augusta University. The proposal establishes the fee structure for pre-construction and construction services, with fees divided into two primary categories: pre-construction consulting services and construction services. The CM/GC will provide services as outlined in the General Requirements contract documents, with specific performance requirements and established time limits.

The fee structure consists of a fixed Pre-Construction Fee and a fixed Construction Fee, both to be specified by the contracting parties. Additionally, the CM/GC's Pre-Construction Costs and Expenses and Construction Overhead Costs are subject to maximum amounts detailed in attachments, with these overhead costs inclusive of all direct and incidental project expenses. The proposal requires the CM/GC to itemize maximum pre-construction costs and expenses separately from the pre-construction fee, and construction overhead costs separately from the construction fee, ensuring clear delineation between gross profit compensation and reimbursable expenses. The document requires signature authorization from a CM/GC officer with title designation, establishing binding commitment to the proposed fee structure.

View the file

Other files

File Type Posted
SIGN IN SHEET.pdf PDF
Exhibit_A___Certification_Form_1 (1).docx DOCX document
J_430 CM RFQ_RFP_.pdf PDF
Exhibit_B___Contractor_Affidavit (2).docx DOCX document
Exhibit_E___General_Conditions_Breakdown.xlsx XLSX spreadsheet
Exhibit_F___Project_Cost_Matrix.xlsx XLSX spreadsheet
Addendum 1.doc DOC document
Exhibit_G___Proposer_s_Disclosure_Statement.doc DOC document
NOIA.docx DOCX document
Addendum 2.doc DOC document
Addendum 3.doc DOC document
Score Sheets.pdf PDF
Exhibit_D___Preconstruction_Cost___Expenses_B.xlsx XLSX spreadsheet
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT C

Project #, Project Name, Institution, City, Georgia

CM/GC FEE PROPOSAL

1. CM/GC’S FEE:

Basis of Fee. The CM/GC’s fee is the amount, established by and agreed to by both parties, which is the full amount of compensation due to the CM/GC as gross profit, and for any and all expenses of the Project not included and identified as a Cost of the Work, provided that the CM/GC performs all the requirements of the Contract Documents within the time limits established. (See Article 4.1.1 of the General Requirements.) If applicable, the fees and costs should be broken down by each site within a multi-site project.

A. PRECONSTRUCTION FEE:

Pre-Construction Fee. Representing the gross profit for the pre-construction consulting services provided by CM/GC as set forth in Section 2, Parts 1 and 2 of the General Requirements, and as described in Paragraph 4.1.1.1(a), Owner shall pay to CM/GC a Preconstruction Fee:

TOTAL

Pre-Construction Fee (fixed fee)

B. CONSTRUCTION FEE:

Construction Fee. Representing the gross profit for the construction services provided by CM/GC as set forth in Section 3, Part 1 of the General Requirements, and as described in Paragraph 4.1.1.1(b) Owner shall pay to CM/GC a Construction Fee.

TOTAL

Construction Fee (fixed fee)

2. CM/GC’S PRECONSTRUCTION COSTS AND CONSTRUCTION OVERHEAD COSTS:

The CM/GC’s Overhead Costs. The maximum amount for the CM/GC’s Pre-Construction Costs and Expenses and Construction Overhead Costs are inclusive of all direct and incidental expenses are as described in Paragraph 4.1.1.2 .

AMOUNT

A. Maximum Pre-construction Costs & Expenses (From Attachment A. Do not include the Pre-Construction Fee in this amount)

B. Maximum Construction Overhead Costs (From Attachment B. Do not include the Construction Fee in this amount)

Total Maximum Overhead Cost (Sum of A & B)

CM/GC Name

By:_________________________________________________________ Signature of CM/GC Officer

Title of CM/GC Officer

File details come from the government source that posted it. Updated .