Exhibit B 2025.docx

DOCX document 60 KB Posted

Attached to
SDFM Water Treatment Chemicals bid RFP solicitation.
Solicitation number
RFP IHHA 2026000244 3
Issued by
Pueblo County, Colorado

About this file

Exhibit B is a price worksheet for the SDFM Water Treatment Chemicals bid RFP solicitation issued by the State of Colorado. The document establishes the cost structure for water treatment services encompassing boiler plant and cooling tower operations. Bidders must provide itemized monthly costs for system checks, monitoring, and required testing; equipment usage; and materials and chemical costs for both boiler plant and cooling tower requirements. Additional line items include training with health and safety components, disposal fees if applicable, and miscellaneous cleaning and maintenance services.

The pricing structure requires bidders to submit monthly costs for each service category, a one-time mobilization cost, and any additional fees. Bidders must also provide a transition fee covering equipment setup, fine-tuning to meet site requirements, and coordination of existing equipment transition to the chosen vendor's equipment. The total cost for the first year, including all one-time fees, must be clearly identified. This comprehensive pricing approach allows the State of Colorado to evaluate the full financial impact of each bid proposal for water treatment chemical services and related operational support.

View the file

Other files

File Type Posted
Addendum 2.docx DOCX document
Final Water Treatment Chemicals SDFM RFP .docx DOCX document
Exhibit D Contract Template, Terms & Conditions v 4.13 Final Locked.docx.pdf PDF
Walkthrough.pdf PDF
Addendum 1 (1) (2).docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT B

Price Work Sheet

EXHIBIT B, TABLE 1 – COST TABLE

In the following table list the cost of each item and what it will cost per month:

Bid Item
Per month Cost

Boiler Plant Requirements: System Checks, Monitoring and Required Testing

Boiler Plant Equipment Usage Cost

Boiler Plant Material/Chemical cost

Cooling Towers Requirements: System Checks, Monitoring and Required Tests

Cooling Tower Equipment Usage Cost

Cooling Tower Materials/Chemical Cost

Training including Health and Safety

Disposal Fees, if applicable

Misc. Cleaning and Maintenance

TOTAL

One time Mobilization Cost: $_______________________________________________________________________________ Additional Fees: $_____________________________________________________________________________________________ Transition fee, setting and fine tuning all equipment to meet site requirements, coordinating the transition of existing equipment to chosen vendors equipment.

Total Cost (First year with one-time fees): $ ______________________________________________________________

Exhibit B, Rev 7/2025 Page 1 of 2