Exhibit_A_-_Scope_of_Services.pdf
PDF 157 KB Posted
- Attached to
- Fire Training Complex (Project No. 22209-218)
- Solicitation number
- RFP- 26 - 299
- Issued by
- Pinellas County, Florida
About this file
This Scope of Services document outlines the construction management requirements for the City of St. Petersburg, Florida's Fire Training and K-9 Compound project located at 22nd Street South. The project encompasses the relocation of the existing K-9 Training Facility and construction of a new Fire Training Facility. The construction management firm selected will be responsible for providing comprehensive oversight and coordination throughout the project delivery process, ensuring compliance with all applicable codes, standards, and regulatory requirements. The scope of services includes pre-construction planning, cost and schedule management, quality assurance and control, safety oversight, and coordination among all project stakeholders including city departments, contractors, and design professionals.
The construction manager will serve as the city's representative on-site and will be responsible for monitoring contractor performance, managing project documentation, processing contractor payment requests, maintaining project schedules, and ensuring adherence to the approved budget. The firm must demonstrate experience in similar public sector construction projects and possess expertise in both fire training facility design standards and K-9 facility requirements. The construction manager will coordinate with the City of St. Petersburg's departments and maintain regular communication with project stakeholders throughout the duration of the project, which will extend from pre-construction through final closeout and substantial completion of all work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Fire_Training_Complex_(Project_No._22209-218).pdf | ||
| Attachment_-_Fee_Proposal_Form.xlsx | XLSX spreadsheet | |
| Attachment_-_Experience_Table.xlsx | XLSX spreadsheet | |
| Draft_Agreement_AIA_A201-2017.DOCX | DOCX document | |
| Draft_General_Conditions_AIA_A133-2019.DOCX | DOCX document | |
| Exhibit_B_-_Bond_and_Insurance.pdf | ||
| Exhibit_C_-_Proposal_Requirements.pdf | ||
| Exhibit_E_-_Owner_Direct_Purchase_Policy.pdf | ||
| Attachment_-_Proposal_Format.pdf | ||
| Attachment_-_Subcontractor_Utilization_Plan.docx | DOCX document | |
| Performance_&_Payment_Bond_.DOCX | DOCX document | |
| Solicitation_Development_Form_-_INTERNAL_USE_ONLY.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rev: 02/15/24cm Page 1 of 4
Exhibit A - Scope Of Services Construction Manager at Risk
Fire Training Complex City of St. Petersburg, Florida
Project No. 22209-218
INTENT
The City of St. Petersburg, Florida (“City”) is seeking the services of a qualified construction management (“CM”) firm interested in providing CM services for Fire Training and K-9 Compound
– Lake Maggiore Programming and Site Analysis project, located at 22nd Street South, St.
Petersburg, Florida, 33712. The Scope of Services sets forth the services, activities and responsibilities that will be performed by the Construction Manager and the Deliverables that will be provided by the CM pursuant to an Agreement.
BACKGROUND
The existing Public Safety Training Facilities, constructed in the 1980s, are located on approximately two acres within the City’s Public Works compound on the western shore of Lake Maggiore. St. Petersburg Fire & Rescue (SPFR) utilizes the facility for approximately 90,000 hours of training annually, supporting both personnel and apparatus training activities. The facility has exceeded its useful service life and requires replacement.
A programming study was conducted to evaluate whether a new Public Safety Training Facility could be accommodated within the existing Public Works compound. The study concluded that, with the relocation of the existing K-9 Training Facility, a new Fire Training Facility can be constructed on-site while maintaining ongoing operations. The final site configuration will be determined during conceptual design.
The Fire Training Facility will include but not limited to a Logistics Building with the following components:
• Offices
• Break Room
• Classrooms
• Decontamination classroom,
• Conference Room
• Weight Room
• Locker Rooms, including restrooms and showers
• Laundry Room
• Gear Storage
The SPFR Drill Grounds will include but not limited to:
• Truck Bay
• Commercial Burn/Training Tower
• Covered Car Fire Training Area
• Exterior Training Areas and Support Facilities
The project site spans multiple parcels and will require replatting. The site is located within the Lake Maggiore/ Salt Creek Swamp Watershed. Portions of the project area are located within the
Rev: 02/15/24cm Page 2 of 4
100-year Pinellas County floodplain and will require floodplain compensation. Site development will also require placement of fill in certain areas.
The project, or portions thereof, will be designed and constructed to function as a designated Emergency Operations Center (EOC) to include a backup generator.
The project will be designed and constructed to achieve LEED Gold certification.
SCOPE OF SERVICES
TASK 1 DESIGN DEVELOPMENT PHASE
1.1 Kickoff Meeting between Designers, Construction Manager, City of St. Pete Contracting, and End-User Groups to review the project scope, list of required items, list of desired items, timeframes, understand existing traffic patterns, soil characteristics from a structural and environmental perspective and discuss the overall site/facility master plan.
1.2 Evaluate the owner’s schedule and construction budget and provide feedback as to validity, challenges and opportunities.
1.3 Review geotechnical report, hazardous material surveys and other site environmental reports that may be required.
1.4 Attend meetings with the Owners, End Users, and Designers during the design period to discuss option Analysis.
1.5 Develop preliminary staging, access and phasing plan.
1.6 Develop preliminary procurement and construction schedule.
1.7 Provide list of alternatives based on their added value or life cycle cost analysis versus first cost to the project.
1.8 Assemble and present bound deliverable including narrative, schedule of values, detailed cost breakdowns, list of alternates, allowances, unit prices, clarifications, project schedule, list of documents and other exhibits necessary. Attend in-person meetings as necessary.
A minimum of two (2) meetings are included, the first is an on-site meeting to review site conditions and site logistics, the second of which is to present the deliverable to the project team at the completion of the Design Development Phase.
1.9 Develop Safety Plan and delineate costs and procedures. Develop Quality Control Plan.
1.10 Develop project specific SBE / WMBE Opportunity Program by conducting workshops with potential vendors to understand the market capabilities so that scope of work can be delineated to allow for maximum participation.
1.11 Perform interdisciplinary plan review and provide written report of findings including suggestions to the Design team for alternative building techniques or products that can add value to the project.
1.12 Assist Design team with any data or means and methods descriptions that are required to be submitted with the Environmental permits. (FDEP, SWFWMD, EPC) participate in conference calls with design team and/or City during the Design Development phase.
Rev: 02/15/24cm Page 3 of 4
TASK 2 90% CONSTRUCTION DOCUMENT PHASE
2.1 Update quantity surveys based on completed structural drawings, completed civil drawings, partial architectural and MEP drawings.
2.2 Update staging, access and phasing plan. Update construction schedule.
2.3 Develop safety plan and delineate costs and procedures. Develop quality control plan.
2.4 Advertise project on social media, local publications, and state publications to maximize
SBE and MBE awareness and participation. Assist SBE / MBE subcontractors with project scope review in preparation for subcontractor bidding phase. Host information meetings as needed.
2.5 Update cost estimate, clarifications and other exhibits.
2.6 Perform interdisciplinary plan review and provide written report of findings including suggestions to the design team for alternative building techniques or products that can add value to the project.
2.7 Assist design team with any data or means and methods descriptions that are required to be submitted with the environmental permits. (FDEP, SWFWMD, EPC).
2.8 Participate in meetings with design team and/or city during the 90% phase.
2.9 Attend one interim meeting and one meeting at the completion of the 90% phase to present an updated deliverable.
2.10 GMP 100% construction documents, permitting & subcontractor procurement phase finalize quantity surveys for buildings and site improvements.
2.11 Verify that design team has incorporated all required scope items, comments from interdisciplinary review and properly delineated alternates.
2.12 Finalize staging, access, phasing plans. Finalize construction schedule.
2.13 Finalize safety and quality control plans.
2.14 Finalize subcontractor/vendor proposal packages including scopes of work to comply with SBE / WMBE opportunity plan.
2.15 Update cost estimate, clarifications, list of documents and other exhibits for deliverable.
2.16 Attend one meeting to review deliverable with the project team and one meeting to review the final GMP with the city prior to submitting to city commission for approval.
2.17 Apply for building permits and other required utility connections requests.
2.18 Assist design team if needed for response to comments by authorities having jurisdiction until permits are approved.
2.19 Produce request for proposal from local subcontractors and vendors for the scopes of work delineated on the project.
Rev: 02/15/24cm Page 4 of 4
2.20 Conduct pre-proposal meetings and communicate with potential awardees to explain the project approach, timeline and specific requirements for administration and performance of the work.
2.21 Review proposals, tabulate results and make recommendations for award to the city.
Provide reports of buyout versus GMP and utilization of SBE / WMBE firms.
2.22 Attend one meeting upon completion of the preconstruction services and transition into the construction phase of the project.
TASK 3 KEY DELIVERABLES
3.1 Design Development Phae Construction Budget
3.2 90% Construction Document Phase Construction Budget
3.3 90% Construction Document Phase Drawing and Specification Document Review
(Provide red-marked PDF set of plans and specifications)
3.4 Construction Schedule
3.5 Construction Site Utilization Plans
TASK 4 GRANT MANAGEMENT
The CM shall provide grant management support services to assist the City with administration, documentation, compliance, and reporting requirements associated with applicable federal, state, regional, or local funding sources. Services may include coordination with the City, funding agencies, project stakeholders, design professionals, and other consultants as necessary to support grant compliance and project delivery.
The CMAR shall provide all services necessary for the successful delivery of the project, including the program elements described herein and all associated, related, and incidental work required to provide a complete, operational, and functional facility.