This document contains an exhibit for a performance relevancy questionnaire and details for a construction MATOC solicitation. The questionnaire exhibit requests information on up to five past general construction projects to demonstrate relevancy, including description of work, subcontractor details, references, and safety history. The MATOC solicitation is for $40 million in construction services over five years in support of the Arkansas National Guard. Awards will be made to at least four small businesses. Task orders may be set aside for socioeconomic programs. Bid bonds are required over $150,000.

View the file

Other files for this federal contract opportunity

Other files attached to Construction - Multiple Award Task Order Contract (MATOC) Arkansas National Guard, newest first.
File Type Posted
EXHIBIT_D_Proposal_Form_30DEC2022.docx DOCX document
W912JF23R0001-0002.pdf PDF
QandA_Doc_W912JF23R0001_30DEC2022.pdf PDF
AMENDMENT W912JF23R0001 0001.pdf PDF
EXHIBIT D - Proposal Form.docx DOCX document
Attachment 01 PROTOTYPICAL PROJECT PLANS_ARKANSAS ANG MATOC_05MAY2022.pdf PDF
Attachment 01 - SPECIAL CONTRACT REQUIREMENTS.docx DOCX document
W912JF23R0001 MATOC SOLICITATION.pdf PDF
Attachment 01 PROTOTYPICAL PROJECT SPECIFICATIONS_ARKANSAS ANG MATOC_05MAY2022.pdf PDF
EXHIBIT B - Subcontractor Information and Consent Form.docx DOCX document
EXHIBIT C - Reference Questionnaire Package.docx DOCX document
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IDIQ MATOC RFP W912JF-23-R-0001

EXHIBIT A - PERFORMANCE RELEVANCY QUESTIONNAIRE

PART 1: Prepare not more than five (5) Part 1 forms for general construction.

Provide the following information requested in this format for each of the projects/contracts being described. Projects may be on going and cannot have been completed any earlier than 5 years prior to the solicitation issue date. Provide frank, concise comments regarding YOUR PERFORMANCE on the contracts you identify. Use as much space as required.

A. Offeror (Your) Name (Company/Division): ______________________________________________

B. Project/Contract Title: _______________________________________________________________

C. Contract Specifics:

1. Description of Effort as ___________Prime Contractor or _________Subcontractor

2. Contract Number__________________________________________________________

3. Original Contract $ Value _____________ Current/Final Contract $ Value ____________

4. If amounts in 3 above are different, provide a brief description of the reason:

5. Completion Date:

i. Original Date: ________________________________________________________

ii. Current Scheduled Completion Date( if ongoing): ___________________________

iii. Estimate/Final Completion Date:_________________________________________

iv. Primary cause for Contract Modifications__________________________________

v. If IDIQ Number of Task Orders issued:____________________________________

**If reference is for an IDIQ Contract provide items 1-3 above, contract completion date and number of task/delivery orders issued. The Basic Contract will not count as one of 5 contracts/projects. The basic contract alone will not be considered for relevancy. The proposal must discuss relevant task order(s ) complete to 90%. Count each TO discussed as a single project/contract.**

Task Order Number: _____________________________________________________ Title: __________________________________________________________________ Original TO $ Value: _____________ Current/Final $ Value: _____________________ If amounts above are different, provide a brief description of the reason:

Task Order Completion Date:

1. Original Date: _____________________________________________

2. Current Schedule if ongoing _________________________________

3. Estimate/Final Completion Date:_______________________________

4. Primary cause for Contract Modifications________________________

D. Provide detailed description of the work performed under the contract and describe why you believe the work is very relevant, relevant or semi-relevant to this solicited project. Also discuss similarity of the client type, United States Green Building Council (USGBC) (LEED®) or similar sustainability requirements. Use as much space below as necessary to provide this description.

Exhibit A Part I continues on Next Page… Additionally, please address the following items:

1.Describe the specific elements of the work performed by your firm.
2.Indicate what elements of work were performed by your major subcontractors and indicate if those same subcontractors will be used on MATOC projects.
3.Address any technical areas about this project you consider uniquely relevant to this solicitation.
4.Point of Contact for Owner/Government agency Contracting Officer and or inspector; include a current phone number and facsimile number. Email address is also desired.

End of Part 1- Questionnaire Requirements – Prepare and send Exhibit C Package to the reference(s) for each of the five (5) General Construction projects.

EXHIBIT A - PERFORMANCE RELEVANCY QUESTIONNAIRE

PART 2: Provide the following information one time.

Additional offeror information required, but not project specific. This information need only be provided once in your submission package.

2A. Applicable to all offerors - Describe your Compliance with the requirements of FAR clause 52.219-8, Utilization of Small Business Concerns (Oct 2014). Describe below the methods you have used to comply with this policy on prior federal contracts. Include any evidence, or a point of contact to verify this information, if available.

Even if you are a Small or Small Disadvantaged Business, this clause in Federal Contracts applies. It is the policy of the United States that small business concerns, veteran-owned small business concerns, service-disabled veteran-owned small business concerns, HUBZone small business concerns, small disadvantaged business concerns, and women-owned small business concerns shall have the maximum practicable opportunity to participate in performing contracts let by any Federal agency, including contracts and subcontracts for subsystems, assemblies, components, and related services for major systems.) It is also policy to establish procedures to ensure the timely payment of amounts due pursuant to the terms of their subcontracts.

2B. Name subcontractors and/or Teaming Partners to be utilized on this contract. Multiple subcontractors may be named for the same discipline, but are limited to a maximum of three (3) subcontractors per discipline. As a minimum, provide the name(s) of subcontractors to be utilized in the following areas:

Electrical:

Mechanical:

Roofing:

Horizontal disciplines: (include paving and civil site work)

Each major subcontractor and/or Teaming Partner must also complete an Exhibit B, “Subcontractor Information and Consent Form” to be considered. Offerors shall have major subcontractors identify on the Exhibit B three references, owners (if they were the Prime) or other Prime contractors they have worked for. References for subcontractors from the proposing offeror are not acceptable. See Exhibit “B” format for information to be provided. Written references for subcontractors may be included and are encouraged. However, subcontractors do not need to send out Exhibit C questionnaires.

2C. Discuss assessment of liquidated damages on any contracts within the last five years. (frequency, circumstances, severity of problem, etc.)

2D. Offerors are strongly encouraged to include with their proposals information on problems encountered on relevant projects and the specific corrective actions taken to remedy the problems.

2E. Adequacy of implementation of safety plan; acceptable safety history; and the Experience Modification Rate (EMR).

File details come from the government source that posted it. Updated .