This is a Statement of Work (SOW) for the Geostationary Littoral Imaging and Monitoring Radiometer (GLIMR) Access to Space (ATS) contract with NASA, covering Life Cycle Implementation Phases D through F. The contract is organized into three Contract Line Items (CLINs): CLIN 1 covers baseline ATS services including spacecraft design, ground segment integration, payload integration, observatory testing, launch, and 12 months of on-orbit operations; CLIN 2 provides an optional 12-month extended mission operations period; and CLIN 3 provides a second optional 12-month extended operations period.

The Contractor must furnish all personnel, engineering disciplines, materials, services, equipment, facilities, and software necessary to perform work including: planning and designing the GLIMR Observatory and Launch Segment; designing and integrating the Ground Segment (GMOC and communication infrastructure); integrating the Government-provided GLIMR Payload onto the GLIMR Spacecraft; performing environmental and interface testing; launching the Observatory to geostationary orbit; conducting in-orbit checkout; and providing 12 months of baseline mission operations with weekly coordination meetings and monthly status reports. Key deliverables include Interface Control Documents, thermal and structural analyses, coupled loads analysis, contamination control plans, verification reports, and software integration test plans. The contractor must maintain AS9100 quality compliance, provide facility access for up to two Government representatives beginning three months before payload receipt through one month after on-orbit checkout, conduct multiple formal reviews (ATSRR, ATSIR, ATSTRR, ATSORR, ATSPLAR), and track and resolve any discrepancies related to payload, spacecraft, or ground segment performance. Milestone payments are structured across review gates and operational periods, with 5% due at Kick-Off, 15% at ATS Requirements Review, 10% at Pre-Ship Review, 10% at Integration Review, 10% at Test Readiness Review, 10% at Operations Readiness Review, 30% at Post-Launch Assessment, and 10% distributed monthly during the 12-month baseline operations period.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract No. XXXXXXXXX Exhibit A – Statement of Work (SOW) (Version 0.1)

XXXXXXXXXX

EXHIBIT A

Statement of Work (SOW)

For

Geostationary Littoral Imaging and Monitoring Radiometer (GLIMR)

Access to Space (ATS) Version 0.1

January 15, 2026

Document Change Record

Revision Date Description of Change

0.1 1/15/2026 Initial version.

Table of Contents

1. Introduction and Definitions

1.1. Introduction

1.2. Definitions

2. Scope of Work

3. Reference Documents and Contract Data Requirements List

3.1. Reference Documents

3.2. Contract Data Requirements List

4. Management

4.1. Schedule

4.2. Reviews and Meetings

4.2.1. Formal Contractor Reviews

4.2.2. Support for Formal Government Led Key Decision Points (KDPs) and GLIMR Mission Reviews

4.2.3. Technical Interchange Meetings (TIM)

4.2.4. Monthly Progress Briefings

4.3. On-Site Representatives

5. Configuration Control/Management, Quality Control, and Safety and Mission Assurance

6. ATS and Mission Operations

6.1. Plan and Design GLIMR Observatory and Launch Segment [CLIN 1]

6.1.1. GLIMR Observatory and Launch Segment Services Design, Planning, and Analyses [CLIN 1]

6.2. Plan GLIMR Spacecraft to GLIMR Payload Integration [CLIN 1]

6.3. Design, Integrate, and Test the GLIMR Ground Segment [CLIN 1]

6.3.1. GLIMR Ground Segment Design, Analysis, and Integration [CLIN 1]

6.3.1.1. GLIMR Payload Operations [CLIN 1]

6.3.2. GLIMR Ground Segment Testing and Readiness [CLIN 1]

6.3.3. GLIMR Spacecraft and Ground Segment Simulators [CLIN 1]

6.4. Perform GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]

6.4.1. GLIMR Payload Delivery, Receipt, Inspection, and Handling [CLIN 1]

6.4.2. GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]

6.5. Perform GLIMR Observatory Testing, and Pre-Launch Processing [CLIN 1]

6.5.1. Flight System Readiness, Pre-Ship, Launch Site Preparations [CLIN 1]

6.6. Launch and Perform GLIMR Observatory In-Orbit Checkout [CLIN 1]

6.7. Perform GLIMR Mission On-Orbit Operations [CLIN 1]

6.8. Extended Operations [CLINs 2 and 3]

7. Milestone Payments

This Statement of Work (SOW) details the work to be performed by the Geostationary Littoral Imaging and Monitory Radiometer (GLIMR) Access to Space (ATS) Contractor (Contractor) and its team members for the National Aeronautics and Space Administration (NASA) Life Cycle Implementation Phases D through F.

GLIMR is a hyperspectral ocean color sensor which targets the Gulf of America and other coastal and ocean waters of North and South America. With its vantage point from geostationary orbit, GLIMR will be the first hyperspectral ocean color sensor in the Western Hemisphere to study ocean processes at the diurnal timescales required to observe the dynamic ecological, biogeochemical, and physical processes typical of coastal and ocean waters. GLIMR is uniquely designed to capture the spatiotemporal evolution of phytoplankton blooms, which grow and dissipate on scales of hours to days, monitor phytoplankton physiology, growth rates and shifts in community composition, resolve coastal features, fronts, eddies, and upwelling features, and monitor biogeochemical fluxes and land-ocean exchanges at sub-diurnal to multi-day scales. GLIMR will improve quantification of primary productivity, biomass, and carbon fluxes within coastal aquatic ecosystems and across the land-sea interface and contribute observations that will aid development and evaluation of models that project future changes in carbon cycling and marine ecosystems for use in ecological forecasting and as inputs for improved climate change predictions. The two main science goals of GLIMR are (1) to understand the processes contributing to rapid changes in phytoplankton growth rate and community composition, and (2) quantify how high frequency fluxes of sediments, organic matter, and other materials between and within coastal ecosystems regulate the productivity and health of coastal ecosystems. The science application objectives aim to study the formation, magnitude, and trajectories of harmful algal blooms, oil spills, and Sargassum accumulation events.

Figure 1. GLIMR Mission

1. Introduction and Definitions

1.1. Introduction

Access to Space (ATS)

Contractor services required to integrate the GLIMR Payload onto the GLIMR spacecraft and place the Observatory into the specified GEO orbit and that will allow the Government to acquire the necessary scientific measurements (including transmission of this data to the GSDS) to assess rapidly evolving processes such as phytoplankton physiology and bloom evolution, episodic/seasonal river discharge, dissolved and particulate carbon transformations, and coastal storm damage.

Distributed Active Archive Center (DAAC)

The Government-assigned location(s) where GLIMR data and data products will be delivered by the GLIMR GSDS for public access and permanent archive.

GLIMR Ground Segment Provides the GLIMR Observatory command, control, and communication uplink and downlink, and data transfers from the GLIMR GMOC to the GLIMR GSDS.

GLIMR Ground Station Provides the GLIMR GMOC communications to and from the GLIMR Observatory.

GLIMR Mission

The entire GLIMR science mission performed by the Government and the Contractor. Includes the GLIMR Payload and Access to Space, data product generation, science results, and PI-led science community.

GLIMR Mission Operations Center

(GMOC)

Control center for uploading GLIMR Spacecraft and GLIMR Payload commands to the GLIMR Spacecraft and receiving GLIMR Spacecraft, GLIMR Payload, GLIMR science and housekeeping data from the GLIMR Spacecraft.

GLIMR Observatory The combination of the GLIMR Payload to the GLIMR Spacecraft.

GLIMR Payload

The Government-provided hardware that will be integrated into the GLIMR Spacecraft. The GLIMR Payload is a geostationary hyperspectral ocean color sensor capable of repeat coverage designed for the primary mission focus on ecosystem processes in the Gulf of America Includes all GLIMR Payload intra-connected cables and harnesses between the GLIMR Payload’s subsystems.

Does not include the Contractor-provided cables such as power, data, and communications to the GLIMR Payload-to-GLIMR Spacecraft interface.

GLIMR Science Data Segment

(GSDS)

The facility operated by the Government, located at NASA Goddard Space Flight Center, that receives GLIMR mission raw data (L0) from the GMOC to generate science products and deliver them to the GLIMR DAAC.

GLIMR Spacecraft

The vehicle with mechanical, electrical, and thermal interface for the GLIMR Payload to achieve the GLIMR mission. For the purposes of this effort, the GLIMR Payload may be hosted on a dedicated spacecraft or share the spacecraft with other payloads.

Interface Control Document (ICD)

Defines the interface between two systems (e.g., GLIMR Payload-to-GLIMR Spacecraft Mechanical and Thermal ICD; GLIMR Payload-to-GLIMR Spacecraft Electrical ICD; GLIMR GSDS-to-

GMOC ICD).

Launch Segment A rocket system including all necessary operations for launch to insert GLIMR Observatory from Earth’s surface into orbit.

Shall Means the imperative. Compliance and formal traceability and verification by the Contractor is mandatory. Any deviations from these contractually imposed mandatory requirements require a

1.2. Definitions

formal change implemented through a written contract modification.

Will Designates the intent of NASA or the Government.

May Terms "may" or "can" denote discretionary privilege or permission.

The Contractor shall, except as otherwise specified furnish all necessary personnel, engineering disciplines, expertise, materials, services, equipment, facilities, institutional systems and software, and technical and management processes to perform the GLIMR ATS requirements as follows:

A. Plan and design the GLIMR Observatory and Launch Segment;

B. Plan GLIMR Spacecraft to GLIMR Payload integration ;

C. Design, integrate, and test the GLIMR Ground Segment;

D. Perform GLIMR Payload to GLIMR Spacecraft integration;

E. Perform GLIMR Observatory testing, and Pre-Launch processing;

F. Launch and perform GLIMR Mission In-Orbit checkout;

G. Perform On-Orbit operations; and H. Perform extended operations, if required.

The SOW and scope of work is organized with the following Contract Line-Item Number (CLIN) structure:

CLIN Description

GLIMR ATS Services and Integration Planning; GLIMR Spacecraft Design, Testing, and Readiness; GLIMR Ground Segment Design, Integration, Testing, and Readiness; GLIMR Payload Integration onto GLIMR Spacecraft; GLIMR Observatory Testing, and Pre-Launch Processing; GLIMR Observatory integration onto Launch Vehicle, and Readiness; Launch; GLIMR Observatory In-Orbit Checkout and Baseline On-Orbit Operations.

2 Extended GLIMR Mission On-Orbit Operations Option Period 1 (12 Months following Baseline Operations).

3 Extended GLIMR Mission On-Orbit Operations Option Period 2 (12 Months following Extended Mission Operations Option Period 1).

The Government will support the following minimum activities during the performance of this contract:

A. Support the development of any accommodation, if necessary, for the GLIMR Payload, GLIMR

Payload Operations, and GLIMR Ground Segment;

B. Complete all necessary GLIMR Payload pre-ship activities, ship the GLIMR Payload to the Contractor, and conduct post-ship inspection and checkout;

C. Support post-ship activities, including Integration and Test (I&T) of the GLIMR Payload with the

GLIMR spacecraft and subsequent GLIMR observatory, and GLIMR Ground Segment testing activities;

D. Provide technical support to the Contractor during prelaunch activities, launch, In-Orbit checkout, and On-Orbit operations;

E. Operate and maintain the GSDS during On-Orbit operations; and F. Support GLIMR Payload end-of-life operations and decommissioning.

All SOW sections herein, unless specifically defined by CLIN, apply to all CLINs.

2. Scope of Work

The following documents are for reference only. The requirements of the contract and this SOW establish the contractual obligations of the parties.

Document Number Document Title

GLIMR AM-04 GLIMR Reduced-Order Structural Model GLIMR AM-07 GLIMR Reduced-Order Thermal Model GLIMR SE-04 GLIMR Mission Concept of Operations (CONOPS) GLIMR-06-002 GLIMR Payload to Host Interface Definition Document (IDD) GLIMR SW-08 GLIMR Flight Software User’s Guide D4957031-500 GLIMR Instrument Installation Control Drawing (IICD) NPR 8621.1C NASA Procedural Requirements for Mishap and Close Call

Reporting, Investigating, and Recordkeeping

When apparent conflicts exist between this contract and these reference documents, the Contractor shall notify the Contracting Officer that there is such a conflict and request direction from the Contracting Officer as to how to proceed.

The Contractor shall develop, deliver, and maintain all documentation required by contract Exhibit B, Data Requirements List (DRL)/Data Requirements Description (DRD), even if not otherwise referenced within this SOW. In accordance with RFO/FAR 52.227-16, Additional, Data Requirements, the Contractor shall preserve, for a period of three (3) years after the end of the GLIMR Mission On-Orbit Operations (including any extended On-Orbit Operations), all appropriate documentation required to maintain a traceable record of engineering and programmatic decisions and hardware characteristics and performance, whether formal or informal. The Government reserves the right to review this documentation upon written request by the Contracting Officer.

3. Reference Documents and Contract Data Requirements List

3.1. Reference Documents

3.2. Contract Data Requirements List

The Contractor shall manage the functions necessary to perform the contract tasks outlined herein, to include the planning, organizing, staffing, directing, configuration and risk management, and controlling of all contract activities so that the requirements can be achieved in the most efficient manner.

The Contractor shall generate and provide an ATS status schedule with the Monthly Project Status Report (MPSR) (DRL/DRD PM-01), to include critical milestones, schedule reserve tracking, and an assessment of schedule risk.

The Contractor shall include and highlight the top three critical path(s) in the ATS schedule.

The Contractor shall lead, conduct, participate in, and/or support a variety of formal and informal reviews and meetings as set forth below.

The Government will establish a review team to attend each of the formal reviews and will coordinate the review agenda with the Contractor prior to each review and approve the terms of reference (ToR) per the process in the applicable DRL/DRD.

For each of the below reviews, the Contractor shall:

A. Prepare, host, and present all reviews in the stated DRL/DRD;

B. Support the development and finalization of the agenda;

C. Support the development and finalization of the ToR;

D. Develop and present all necessary review material to meet the requirements of this contract and the ToR;

E. Coordinate review preparations with the Government by sharing plans, draft presentation charts and supporting documentation to the extent necessary to demonstrate that the Contractor is prepared for the review per the ToR;

F. Support all necessary pre-briefings and pre-reviews and respond to/resolve all questions/action items;

G. Conduct the review at the Contractor’s specified location;

H. Respond to, manage, report status, and resolve all Requests for Action (RFAs); and I. Prepare, host, and conduct a “delta” review of the non-compliant areas, including delivery of updated DRL/DRD data items, if the Government determines the success criteria for a review are not fully met.

The Contractor shall conduct a ATS Requirements Review (ATSRR) (DRL/DRD RE-01) [CLIN 1].

The Contractor shall conduct a GLIMR Spacecraft to GLIMR Payload Integration Review (ATSIR)

(DRL/DRD RE-02) [CLIN 1].

The Contractor shall conduct a GLIMR Observatory Test Readiness Review (ATSTRR) (DRL/DRD

RE-03) [CLIN 1].

4. Management

4.1. Schedule

4.2. Reviews and Meetings

4.2.1. Formal Contractor Reviews

The Contractor shall conduct a GLIMR Mission Operations Readiness Review (ATSORR) (DRL/DRD

RE-04) [CLIN 1].

The Contractor shall conduct a GLIMR Mission Post Launch Assessment Review (ATSPLAR) (DRL/DRD RE-

05) [CLIN 1].

The Contractor shall conduct a GLIMR Mission Decommissioning Review (ATSDR) (DRL/DRD RE-06).

The Contractor shall support the preparations and presentations of the Government led KDPs and reviews for the GLIMR Mission.

For each of the below reviews, the Contractor shall:

A. Review and comment on the Government-developed content, as requested by the Contracting Officer’s Representative (COR), in advance of each review; and

B. No later than thirty (30) calendar days prior to the review, provide input and presentations covering work detailed in this SOW (e.g., GLIMR Spacecraft, GLIMR Ground Segment, and Access to Space status;

technical and programmatic risks; plans as requested to support GLIMR Mission reviews).

The Contractor shall attend, present, and deliver the documentation required for GLIMR Payload Pre-Ship Review (PSR) (DRL/DRD RE-07) [CLIN 1].

The Contractor shall attend, present, and deliver the documentation required for GLIMR Extended Mission Review for Period 1 (EMR1) (DRL/DRD RE-08) [CLIN 2].

The Contractor shall attend, present, and deliver the documentation required for GLIMR Extended Mission Review for Period 2 (EMR2) (DRL/DRD RE-09) [CLIN 3]

The Contractor shall attend, present, and deliver the documentation required for GLIMR Mission KDP-E

(DRL/DRD RE-10) [CLIN 1].

The Contractor shall attend, present, and deliver the documentation required for GLIMR Mission KDP-F

(DRL/DRD RE-11) [CLIN 1] .

The Contractor shall prepare technical and programmatic data packages for distribution and presentation during TIM (typically held to discuss technical and schedule items, such as ICD formulation/finalization) (As requested by the Contractor or Government COR).

The Contractor shall deliver and present (virtually) a MPSR covering all aspects of the mission including the ATS technical and schedule status (reference DRL/DRD PM-01).

4.2.2. Support for Formal Government Led Key Decision Points (KDPs) and GLIMR Mission Reviews

4.2.3. Technical Interchange Meetings (TIM)

4.2.4. Monthly Progress Briefings

The Contractor shall provide facility access, office space, office furniture, copier and printer access, and internet access at the Contractor facilities for up to two (2) part-time Government representatives at the Contractor’s facilities beginning three (3) months prior to receipt of the GLIMR Payload through one (1) month following On-Orbit Checkout in order to perform all necessary Government support activities as detailed in this contract. The specific Government representatives may change to support activities appropriately throughout this time frame.

The Contractor shall provide access to two (2) Government representatives for in-person observation purposes during all GLIMR Spacecraft reviews held as part of the Contractor’s normal commercial practices, with virtual access provided to additional Government representatives as needed.

4.3. On-Site Representatives

The Contractor shall:

A. Utilize, in accordance with the Contractor’s commercial practices, and provide the Government with access (upon request of the COR) to, a configuration control/management process for the following:

1. Software configuration control/management for all GLIMR Payload-related GLIMR Spacecraft software configuration items and interfaces, including (in modifiable format) in-process and completed software designs, implementations, test procedures and data, static analysis results, software problem reports, software documentation, and other items related to software development activities; and

2. Engineering configuration control/management for all aspects of GLIMR Mission accommodation.

B. Utilize a Quality Management System compliant to SAE AS9100, Quality Systems - Aerospace - Model for Quality Assurance in Design, Development, Production, Installation and Servicing;

1. Grant the Government access (upon request of the COR) to its Quality Manual

(DRL/DRD MA-01);

2. Remain compliant with the AS9100 standard during the term of the contract; and

3. Notify the Contracting Officer within ten business days of any change in its AS9100 compliant status; and

4. The Government reserves the right to audit the Contractor's quality system at any time.

C. Develop the plans that detail the contamination control methods used during GLIMR Payload receipt through on-orbit operations, consistent with the contract requirements. (DRL/DRD TE-07);

D. Track, manage resolution (including involvement with the Government, as necessary), and deliver discrepancy reports for any problems, nonconformances, failures, and anomalies that are related to the GLIMR Payload, the GLIMR Payload interface with the GLIMR Spacecraft, or the GLIMR Spacecraft’s ability to support the GLIMR Payload, including flight and ground segment (DRL/DRD MA-02);

E. Notify the Contracting Officer within 24 hours of a suspected mishap (“mishap” as defined in NPR 8621.1C, NASA Procedural Requirements for Mishap and Close Call Reporting, Investigating, and Recordkeeping);

F. Perform functional and interface Failure Modes and Effects Analysis (FMEA) that analyzes the functions between the GLIMR Payload/Spacecraft and the GLIMR Spacecraft/Ground Segment and analyzes all elements that cross the interface boundaries between the GLIMR Ground Segment/GSDS (DRL/DRD MA-03);

G. Meet all legal and commercial requirements associated with access to space, On-Orbit operations, Radio Frequency compliance, decommissioning, orbital debris, and end-of-life disposal of the GLIMR Spacecraft; and

H. Apply, in accordance with the Contractor’s commercial practices, safety practices to protect personnel, data, and Government-Furnished Property during performance of all requirements of this contract.

5. Configuration Control/Management, Quality Control, and Safety and Mission Assurance

The Contractor shall meet all requirements (e.g., integration, launch, operations) specified in contract Exhibit C, GLIMR Access to Space Requirements Document (ATSRD).

The following activities are applicable to this effort:

A. Plan and design the GLIMR Observatory and Launch Segment [CLIN 1];

B. Plan GLIMR Spacecraft to GLIMR Payload integration [CLIN 1];

C. Design, integrate, and test the GLIMR Ground Segment [CLIN 1];

D. Perform GLIMR Payload to GLIMR Spacecraft integration;

E. Perform GLIMR Observatory testing, and Pre-Launch processing [CLIN 1];

F. Launch and perform GLIMR Mission In-Orbit checkout;

G. Perform On-Orbit operations [CLIN 1]; and H. Perform extended operations, if required [CLINs 2 and 3].

The Contractor shall host and conduct a Kick-Off TIM with representatives from Government at the Contractor’s facility within 30 calendar days after contract award and cover the following minimum topics:

A. Introductions and roles and responsibilities of the Contractor and the Government;

B. High level milestone schedule;

C. Contractor teaming arrangements;

D. Receivable and deliverable expectations;

E. Insight into the Contractors commercial systems, processes and practices; and F. The operations cadence planned for the I&T campaign.

A. Develop a plan to perform all engineering design activities (electrical, structural, mechanical, thermal, optical) required to meet the integration, test, and operational requirements in this contract;

B. Define the GLIMR Payload/GLIMR Spacecraft Mechanical and Thermal ICD, the GLIMR Payload/GLIMR Spacecraft Electrical ICD, and the GSDS/GMOC ICD (DRL/DRD TE-01);

NOTE: The items specified in the “GLIMR Payload to Host IDD” reference document shall not be changed by the Contractor when finalizing the documents required in DRL/DRD TE- 01 unless otherwise approved by the Contracting Officer.

C. Develop the plans to operate the GLIMR Observatory post launch, consistent with the contract Requirements. (DRL/DRD TE-08)

D. Develop and maintain a Verification and Validation Plan and Matrix that documents the approach for meeting the contract requirements (DRL/DRD TE-02);

E. Design electrical, mechanical, thermal, and software GLIMR Spacecraft interfaces to accommodate hosting the GLIMR Payload; this shall include addressing the various physical

6. ATS and Mission Operations

6.1. Plan and Design GLIMR Observatory and Launch Segment [CLIN 1]

6.1.1. GLIMR Observatory and Launch Segment Services Design, Planning, and Analyses [CLIN 1] and functional design elements of the accommodation flight hardware and Ground Support Equipment (GSE);

F. Develop a thermal model and provide analyses report of the thermal interaction between the GLIMR Spacecraft (including any other payloads) and GLIMR Payload (DRL/DRD TE- 04);

and

G. Manage the development of a Launch Vehicle coupled loads analysis and report results in accordance with the Launch Vehicle Coupled Loads Analysis and Dynamics Environment Report (DRL/DRD TE-05); and

H. Develop a GLIMR Spacecraft bus disturbance contributions to GLIMR Payload LOS jitter model (DRL/DRD TE-10).

I. Develop the GLIMR Launch Segment to fulfill the contract requirements.

6.2. Plan GLIMR Spacecraft to GLIMR Payload Integration [CLIN 1]

A. Verify the contract requirements and interface design are compatible with the GLIMR Spacecraft and GLIMR Ground Segment;

B. Develop the plans and procedures to handle, operate, test, inspect, calibrate, purge, and store the GLIMR Payload during integration and test, consistent with the contract requirements.

(DRL/DRD TE-06);

C. Evaluate GSE available for the GLIMR Payload integration and test (including availability of Contractor-provided GSE at the GLIMR Spacecraft integration facility) to determine all necessary GSE needed to support integration of the GLIMR Payload onto the GLIMR Spacecraft, including GSE not already identified in the Government- Furnished Property clauses of the contract; and

D. Design and fabricate, as necessary, GSE specific to the GLIMR Spacecraft integration facility that is needed to integrate and test the GLIMR Payload.

E. Develope the GLIMR Spacecraft’s (electrical, mechanical, thermal, and software) interfaces to accommodate hosting the GLIMR Payload; this shall include addressing the various physical and functional design elements of the accommodation flight hardware and Ground Support Equipment (GSE); and

The contractor's information systems will be incidental to any NASA IT systems and shall be operated as a nonfederal information system. Non-NASA data is part of this effort, and the entirety of the systems will be Contractor-owned and Contractor-operator.

A. Validate interfaces to ensure adequate data transmission including bit loss analysis and operational data throughput (DRL/DRD TE-03);

B. Perform the necessary requirements development and design efforts required for the GLIMR Ground Segment, including interfaces, and data handling;

C. Provide the infrastructure and communication paths required to route data and commands between the GLIMR Observatory and GMOC to meet the contract requirements;

D. Provide the infrastructure and communication paths required to route data and commands between the GMOC and GSDS to meet the contract requirements;

E. Provide all logistical support required to maintain the infrastructure and communication paths to route data and commands between the GLIMR Observatory and GMOC to meet the contract requirements;

F. Provide all logistical support required to maintain the infrastructure and communication paths to route data and commands between the GMOC and GSDS to meet the contract requirements;

and

G. Develop the plans and procedures to demonstrate GLIMR Observatory through GLIMR Ground Segment to GMOC/GSDS meet the contract requirements (DRL/DRD TE-09).

6.3.1.1. GLIMR Payload Operations [CLIN 1]

A. Develop and test the GMOC for the purposes of supporting GLIMR payload on-orbit checkout, and science operations planning that provide for the acquisition, processing, storing, and distributing of GLIMR payload data;

B. Develop all required operator interfaces at the GMOC to display, monitor, and analyze the GLIMR payload operating state, operating condition, and trended behavior;

C. Support the GLIMR Payload operation and observation planning;

D. Build the associated commands and command loads for GLIMR payload operations;

E. Provide effective communication means for contact and coordination among the GSDS and

GMOC.

A. Verify the GLIMR Ground Segment performance meets system requirements (DRD/DRL TE- 03);

B. Verify the GLIMR GMOC performance meets system requirements (DRD/DRL TE-03);

C. Verify the GLIMR Ground Segment performance meets system interfaces as specified in

DRD/DRL TE-01 (DRD/DRL TE-03);

D. Verify the GMOC performance meets system interfaces (DRD/DRL TE-01); and E. Perform a GLIMR Ground Segment Interface Test in accordance with Section 6.3.2, System Level

Integration and Testing.

6.3. Design, Integrate, and Test the GLIMR Ground Segment [CLIN 1]

6.3.1. GLIMR Ground Segment Design, Analysis, and Integration [CLIN 1]

6.3.2. GLIMR Ground Segment Testing and Readiness [CLIN 1]

A. Develop a GLIMR Spacecraft Simulator and GMOC Simulator(s), that is designed to represent the interfaces to the GLIMR Payload and GLIMR Ground Segment/GSDS per the ICDs and shall have the following capabilities:

1. Simulates GLIMR Spacecraft commanding of the GLIMR Payload with rate and periodicity configurable to accommodate the GLIMR Payload Command Dictionary;

2. Collects GLIMR Payload engineering data and science telemetry, via the Government-provided GLIMR Payload simulator;

3. Simulates the GLIMR Observatory data stream, downlinked to the simulated GLIMR Ground Segment, distributed to representative GMOC and GSDS, with embedded simulated GLIMR Payload data that:

a. Is configurable to accommodate the GLIMR Payload Telemetry Dictionary/Processing;

b. Can directly de-commutate simulated GLIMR Payload data from other GLIMR

Spacecraft data;

c. Provides access to the collected data stream prior to hardware available downlink;

d. Simulates the GLIMR Spacecraft and GLIMR Ground Segment basic processing of the data (Science and Engineering);

e. Provides error checking, removing overlaps, and gap filling;

f. Simulates the granularity of the data to be received by GMOC and GSDS; and

g. Represents data flow configuration detailed in the ICDs

4. Provides a timing pulse to the Government-provided GLIMR Payload simulator in the format which will be utilized during operations;

5. Provides a IMU representative data to the Government-provided GLIMR Payload simulator in the format which will be utilized during operations; and

6. Simulates pre-defined anomaly responses to pre-defined faults.

B. For simulator(s) in 6.3.1A above:

1. Comply with cleanliness requirements (if applicable), handling constraints, and operating constraints documentation; and

2. Deliver harnesses corresponding to the harness from the simulator interface to the

Government-provided GLIMR Payload simulator connectors.

6.3.3. GLIMR Spacecraft and Ground Segment Simulators [CLIN 1]

Government-Furnished Property (GFP): The GLIMR Payload and Payload-specific GSE will be provided to the Contractor as GFP in accordance with the Government Property clauses in the contract. The GLIMR Payload will no longer be considered as GFP after the successful completion of the ATSIR.

A. Provide a work area and access for Government personnel (reference SOW Section 4.3, On- Site Representatives) to prepare for and perform GLIMR checkout activities (i.e., unpacking and initial checkout of the GLIMR Payload at the spacecraft processing facility) that meets the following minimum requirements:

1. Class 100,000 (or better) clean room area (minimum of 12ft x 12ft) that includes all necessary accommodations to handle and store the GLIMR Payload, including:

a. Environmental controls and N2 purge;

b. 120 VAC Power;

c. Crane for lifting the flight Payload; and

d. Cleanroom-compatible Table (minimum of 4ft x 8ft).

2. Area adjacent to clean area (minimum of 10ft x 10ft) that includes:

a. Two computer stations;

b. 120 VAC Power for the GLIMR Payload and GSE operations;

c. Network access; and

d. Electronic Support Fixture/ESD Bench.

B. Be accountable for the GLIMR Payload as GFP after completion of the post-ship testing through the period up to successful completion of the ATSIR in accordance with the Government Property clauses in the contract. The Government will test the GLIMR Payload prior to transfer of accountability to the Contractor at the Contractor’s facility for integration with the spacecraft;

C. Upon receipt of the GLIMR Payload as GFP, store and secure the GLIMR Payload and Payload-specific GSE at the spacecraft processing facility in accordance with the contract requirements, and the Contractor’s commercial practices;

D. Operate and physically handle the GLIMR Payload, in coordination with Government personnel, by providing power, command link, and data transfer via the spacecraft bus and associated spacecraft GSE;

E. Provide logistical support required for the receipt, unpacking, and transport of the GLIMR Payload from the Contractor’s receiving area to the clean room area; and

F. Store the GLIMR Payload shipping container, packing material, and Payload-specific GSE until launch of the spacecraft and ship the GLIMR Payload shipping container and Payload-specific GSE to a Government-selected location upon request of the Government COR. The Contractor shall dispose of any packing crates or material as requested by the Government

COR.

6.4. Perform GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]

6.4.1. GLIMR Payload Delivery, Receipt, Inspection, and Handling [CLIN 1]

A. Integrate the GLIMR Payload with the GLIMR spacecraft and perform the required environmental and interface testing to demonstrate that the GLIMR Observatory meets the contract requirements;

B. Deliver as-planned and as-run procedures, test data, and results associated with all Contractor Integration and Test Procedures (reference DRL/DRD TE-06); and

C. Provide access for Government personnel (reference SOW Section 4.3, On-Site Representatives) to the installed GLIMR Payload so that the Government can perform contamination swab inspections, and so Government personnel can take photographs of the GLIMR Payload throughout I&T and before final GLIMR Observatory close-out prior to launch.

6.4.2. GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]

A. Perform the following tests on the GLIMR Observatory and report the results in the Verification Reports (in accordance with DRL/DRD TE-03); and

B. Verify and provide associated objective evidence that the GLIMR Observatory performance meets system and interface requirements in accordance with the contract requirements, ICDs, and the V&V Plan and Matrix (DRL/DRD TE-01 and TE-03).

Test

Description Test Requirement Test occurrence

GLIMR

Payload Alignment Test

The Contractor shall measure alignment of the GLIMR Payload to the GLIMR Spacecraft.

1. Post GLIMR Payload integration with

GLIMR

Spacecraft.

2. Post dynamics test.

3. Post thermal vacuum test.

Electromagnetic Self Compatibility Test

The GLIMR Observatory, in a Contractor-certified Electromagnetic Interference and Compatibility (EMI/EMC) chamber, shall demonstrate power on compatibility of the GLIMR Spacecraft, other payloads (if any) and the GLIMR Payload while all are operating.

1. During Environmental Testing

GLIMR

Payload Full Functional Test

1. The Contractor shall perform functional tests of the GLIMR Payload after integration.

2. Full Functional tests shall include:

• Demonstration of all GLIMR Spacecraft to GLIMR Payload commands and safety actions including: power on and safing commands

• Release launch locks, if applicable

• Science imaging with or without

GLIMR Payload supplied stimulus

• Demonstration of all GLIMR Payload to GLIMR Spacecraft telemetry.

• Reset the launch locks, if applicable

• Relay GLIMR Payload data to GLIMR

Ground Segment (During End-to- END test only)

1. Post integration with the GLIMR Spacecraft.

2. During Electromagnetic Self Compatibility Test

3. During Spacecraft Thermal Vacuum Test

4. During End-to-End Test

5. Post shipment to launch site.

6.5. Perform GLIMR Observatory Testing, and Pre-Launch Processing [CLIN 1]

GLIMR Limited Functional Test

1. The Contractor shall perform limited functional tests on the GLIMR Payload after each stage of environmental testing.

2. Limited Functional tests shall include:

• Demonstration of a selected set of

GLIMR Spacecraft to GLIMR Payload commands

3. Science imaging with or without GLIMR Payload supplied stimulus

1. Post GLIMR Observatory dynamics test.

2. Post GLIMR Observatory acoustics test (if applicable).

Spacecraft Dynamics Test

1. The GLIMR Observatory, in a Contractor-certified dynamics facility, shall verify contract requirements during dynamics testing with accelerometers and other sensors as needed to verify the Coupled Loads Analysis.

1. GLIMR

Observatory dynamics test

Spacecraft Acoustics Test, if applicable

1. The GLIMR Observatory, in a Contractor-certified acoustics facility, shall verify contract requirements during acoustics testing with accelerometers and other sensors as needed to support the test.

1. Post GLIMR Observatory acoustics test

Ground Segment Interface Test

1. The Contractor shall perform testing of the communication paths and processes between the GMOC to the GSDS.

1. Prior to End-to- End Test

End-to-End Test

1. The Contractor shall perform end-to-end testing of the uplink and downlink data paths from the GLIMR Payload through the GLIMR Spacecraft to the GLIMR Ground Segment, at the full GLIMR Payload data rate.

Note: The Contractor may perform the End-to- End Test as part of GLIMR Observatory Thermal Vacuum Test.

1. Post- Integration, but prior to GLIMR Observatory Ship to Launch Site

Observatory Thermal Vacuum Test

1. The Contractor shall test the GLIMR Observatory in a Thermal Vacuum Test in order to correlate integrated GLIMR Payload/GLIMR Spacecraft thermal models and verify contract requirements.

2. The Contractor shall utilize temperature sensors located on and/or in the GLIMR Payload; perform Full/Limited functional tests at hot, cold, and nominal thermal conditions, a minimum of four cycles, adequate to confirm GLIMR Payload functionality and connectivity over temperatures; and validate thermal models.

3. The Contractor shall, for all GLIMR Spacecraft-controlled GLIMR Payload survival heater zones, verify the functionality of all GLIMR Spacecraft monitored Platinum Resistance Thermometers (PRTs) and demonstrate survival heater telemetry monitoring and control capabilities.

1. Prior to GLIMR Observatory Ship to Launch Site

The Contractor shall in coordination with the Government COR:

A. Conduct a GLIMR Observatory functional test post shipment to Launch Segment Facility that includes GLIMR Payload full functional test per Section 6.3.2;

B. Integrate the GLIMR Observatory to the Launch Segment;

C. Perform the “Remove before Flight” items per the contract requirements; and D. Take close-out photography of the GLIMR Observatory.

A. Launch the GLIMR Observatory to an Earth viewing orbit;

B. Transit the GLIMR Observatory to the contract requirement GEO location;

C. Provide and conduct (in coordination with the Government) a GLIMR Observatory In-Orbit

Checkout while the Observatory is transitioning to the contract requirement GEO location.

(DRL/DRD TE-08);

D. Conduct a GLIMR Payload On-Orbit checkout prior to the beginning of the GLIMR Mission Baseline Operations period when the GLIMR Spacecraft has completed its own checkout, is located at the operational orbit, and has initiated power-on of the GLIMR Payload. The GLIMR Payload On-Orbit Checkout Period shall follow any required GLIMR Spacecraft checkout activities and/or outgassing periods required to meet On-Orbit contamination requirements

(DRL/DRD TE-08);

E. Provide effective communication means for contact and coordination of GLIMR Payload operations among the GSDS and GMOC;

F. Conduct weekly meetings with the GSDS for GLIMR Payload operation and observation planning; and G. Provide GLIMR Mission status reports during GLIMR Observatory In-Orbit checkout.

6.7. Perform GLIMR Mission On-Orbit Operations [CLIN 1]

A. Provide a 12-month GLIMR Mission Baseline Operations period following the GLIMR Payload On-Orbit Checkout period (DRL/DRD TE-08);

B. Provide effective communication means for contact and coordination of GLIMR Payload operations among the GSDS and GMOC;

C. Conduct weekly meetings with the GSDS for GLIMR Payload operation and observation planning; and D. Provide GLIMR Mission status reports during GLIMR On-Orbit operations in the MPSR

(DRL/DRD PM-01).

The Contractor shall perform any required extended operations after completion of the Mission Operations Base Period and any previously exercised Extended Operations option period in accordance with all applicable requirements of this SOW.

6.5.1. Flight System Readiness, Pre-Ship, Launch Site Preparations [CLIN 1]

6.6. Launch and Perform GLIMR Observatory In-Orbit Checkout [CLIN 1]

6.8. Extended Operations [CLINs 2 and 3]

CLIN

Event Name

Event Deliverable(s)

Accomplishment Criteria

Planned Invoice Schedule

Payment % of Total CLIN value

1a Kick-Off Technical Interchange Meeting (TIM)

(1) DRL/DRD PM-02, System Security Management Plan.

(2) DRL/DRD PM-05, Conflicts of Interest Avoidance Plan.

(1) Government approval of stated DRL/DRDs in accordance with applicable DRL/DRD requirements.

(2) Successful completion of SOW Section 6.1 requirements for the Kick-Off TIM, to be held within 30 calendar days after contract award.

Within 30 calendar days after DRL/DRD approvals and completion of the TIM.

(required 30 calendar days after the contract effective date).

5%

1b ATS Requirements Review

(ATSRR)

(1) DRL/DRD RE-01, ATSRR

(2) DRL/DRD TE-01, ICDs

(3) DRL/DRD TE-08, GLIMR Observatory Operations Plan

(4) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures

(1) Government approval of stated DRL/DRD in accordance with applicable DRL/DRD requirements.

(2) Successful completion of SOW Section 4.2.1 requirements for the ATSRR.

Within 30 calendar days after DRL/DRD approval and the completion of the ATSRR.

15%

1c GLIMR Payload Pre-Ship Review (PSR)

(1) DRL/DRD RE-07, PSR

(2) DRL/DRD MA-03, FMEA

(3) DRL/DRD TE-01, ICDs

(4) DRL/DRD TE-02, V&V Plan and Matrix

(5) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures

(6) DRL/DRD TE-07, Contamination Control Plan

(7) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures

(1) Government approval of stated DRL/DRD in

(2) Successful completion of SOW Section 4.2.2 requirements for the PSR.

Within 30 calendar days after the completion of the

PSR.

10%

1d GLIMR Payload Integration Review (ATSIR)

(1) DRL/DRD RE-02, ATSIR

(2) DRL/DRD MA-02, Reporting of Discrepancies

(3) DRL/DRD MA-03, FMEA

(4) DRL/DRD TE-01, ICDs

(5) DRL/DRD TE-02, V&V Plan and Matrix

(6) DRL/DRD TE-03, Verification Reports

(7) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model

(8) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report

(9) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures

(10) DRL/DRD TE-07, Contamination Control Plan

(11) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model

(1) Government approval of stated DRL/DRDs in

(2) Successful completion of SOW

Section 4.2.1 requirements for the

ATSRR.

Within 30 calendar days after DRL/DRDs approval and the completion of the ATSIR.

10%

1e GLIMR Observatory Test Readiness Review (ATSTRR)

(1) DRL/DRD RE-03, ATSTRR

(2) DRL/DRD MA-02, Reporting of Discrepancies

(3) DRL/DRD TE-03, Verification Reports

(4) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model

(5) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report

(6) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures

(7) DRL/DRD TE-08, GLIMR Observatory Operations Plan

(8) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Paln and Procedures

(9) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model

(1) Government approval of stated DRL/DRDs in

(2) Successful completion of SOW Section 4.2.1 requirements for the ATSTRR.

Within 30 calendar days after DRL/DRDs approval and the completion of the ATSTRR.

10%

1f GLIMR Mission Operations Readiness Review (ATSORR)

(1) DRL/DRD RE-04, ATSORR

(2) DRL/DRD MA-02, Reporting of Discrepancies

(3) DRL/DRD TE-03, Verification Reports

(4) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model

(5) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report

(6) DRL/DRD TE-08, GLIMR Observatory Operations Plan

(7) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures

(8) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model

(1) Government approval of stated DRL/DRDs in requirements for the ATSORR.

Within 30 calendar days after DRL/DRDs approval and the completion of the ATSORR.

10%

1g GLIMR Mission Post Launch Assessment Review

(ATSPLAR)

(1) DRL/DRD RE-05, ATSPLRA

(2) DRL/DRD MA-02, Reporting of Discrepancies

(1) Government approval of stated DRL/DRD in requirements for the ATSPLRA.

Within 30 calendar days after DRL/DRD approval and the completion of the

ATSPLAR.

30%

1h GLIMR Operations Base Period

(1) DRL/DRD PM-01, MPSR

(1) Successful completion of SOW Sections 6.4.E; 6.4.F; 6.4.G requirements.

(2) Contractor meets all on-orbit requirements for the month.

Monthly for 12 months following the 90-calendar day GLIMR Payload On- Orbit Checkout period.

10% total;

monthly payment is 1/12th of this amount

2a

Extended Mission On-Orbit Operations Option Period 1

(1) DRL/DRD PM-01, MPSR

(1) Successful completion of SOW Section 6.5 requirements.

Monthly for 12 Months following Baseline Operations.

1/12th per month

7. Milestone Payments

3 3a

Extended Mission On-Orbit Operations Option Period 2 (1) DRL/DRD PM-01, MPSR

(1) Successful completion of SOW Section 6.5 requirements.

Monthly for 12 Months following Extended Mission Operations Option Period 1.

1/12th per month

1. Introduction and Definitions
1.1. Introduction
1.2. Definitions
2. Scope of Work
3. Reference Documents and Contract Data Requirements List
3.1. Reference Documents
3.2. Contract Data Requirements List
4. Management
4.1. Schedule
4.2. Reviews and Meetings
4.2.1. Formal Contractor Reviews
4.2.2. Support for Formal Government Led Key Decision Points (KDPs) and GLIMR Mission Reviews
4.2.3. Technical Interchange Meetings (TIM)
4.2.4. Monthly Progress Briefings
4.3. On-Site Representatives
5. Configuration Control/Management, Quality Control, and Safety and Mission Assurance
6. ATS and Mission Operations
6.1. Plan and Design GLIMR Observatory and Launch Segment [CLIN 1]
6.1.1. GLIMR Observatory and Launch Segment Services Design, Planning, and Analyses [CLIN 1]
6.2. Plan GLIMR Spacecraft to GLIMR Payload Integration [CLIN 1]
6.3. Design, Integrate, and Test the GLIMR Ground Segment [CLIN 1]
6.3.1. GLIMR Ground Segment Design, Analysis, and Integration [CLIN 1]
6.3.1.1. GLIMR Payload Operations [CLIN 1]
6.3.2. GLIMR Ground Segment Testing and Readiness [CLIN 1]
6.3.3. GLIMR Spacecraft and Ground Segment Simulators [CLIN 1]
6.4. Perform GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]
6.4.1. GLIMR Payload Delivery, Receipt, Inspection, and Handling [CLIN 1]
6.4.2. GLIMR Payload to GLIMR Spacecraft Integration [CLIN 1]
6.5. Perform GLIMR Observatory Testing, and Pre-Launch Processing [CLIN 1]
6.5.1. Flight System Readiness, Pre-Ship, Launch Site Preparations [CLIN 1]
6.6. Launch and Perform GLIMR Observatory In-Orbit Checkout [CLIN 1]
6.7. Perform GLIMR Mission On-Orbit Operations [CLIN 1]
6.8. Extended Operations [CLINs 2 and 3]
7. Milestone Payments