Exhibit D - GLIMR Milestone Payments_DRFP.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- Geostationary Littoral Imaging and Monitoring Radiometer (GLIMR) Access to Space (ATS) “GLIMR ATS"
- Solicitation number
- 80LARC26R00002
About this file
This file is a draft milestone payment table for the Geostationary Littoral Imaging and Monitoring Radiometer (GLIMR) Access to Space (ATS) contract. The document outlines the payment structure for CLIN 0001 (Base Period), CLIN 0002 (Option Period 1), CLIN 0003 (Option Period 2), and CLIN 0004 (6-month extension), with all prices listed as "To Be Proposed" (TBP).
The Base Period (CLIN 0001) consists of eight milestones totaling 100% of the contract value: Kick-Off Technical Interchange Meeting (5%), ATS Requirements Review (15%), GLIMR Payload Pre-Ship Review (10%), GLIMR Payload Integration Review (10%), GLIMR Observatory Test Readiness Review (10%), GLIMR Mission Operations Readiness Review (10%), GLIMR Mission Post Launch Assessment Review (30%), and GLIMR Operations Base Period monthly payments (10% paid as 1/12th monthly over 12 months following the 90-day on-orbit checkout period). Each milestone requires government approval of specified Delivery Requirements Lists (DRLs) and Delivery Data Requirements (DRDs), including security plans, interface control documents, verification and validation plans, thermal analyses, and operations plans. Option Period 1 and Option Period 2 each consist of monthly operational payments at 100% of their respective CLIN values (1/12th monthly), with invoicing contingent upon successful completion of on-orbit requirements. The 6-month extension under CLIN 0004 allows for monthly payments not to exceed six months. All invoices are due within 30 calendar days of milestone or monthly period completion and government approval of required deliverables.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| DRAFT GLIMR ATS MILESTONE PAYMENT TABLE | ||||||||
| CLIN | # | Event Name | Event Deliverable(s) | Accomplishment Criteria | Estimated Invoice Schedule | Payment % of Total CLIN value | Total Milestone Value | |
| 0001 | 1a | Kick-Off Technical Interchange Meeting (TIM) | (1) DRL/DRD PM-02, System Security Management Plan. | |||||
| (2) DRL/DRD PM-05, Conflicts of Interest Avoidance Plan. | (1) Government approval of stated DRL/DRDs in |
accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 6.1 requirements for the Kick-Off TIM, to be held within 30 calendar days after contract award. | Within 30 calendar days after DRL/DRD approvals and completion of the TIM. (required 30 calendar days after the contract effective date). | 5% | TBP | |
| 1b | ATS Requirements Review (ATSRR) | (1) DRL/DRD RE-01, ATSRR |
(2) DRL/DRD TE-01, ICDs
(3) DRL/DRD TE-08, GLIMR Observatory Operations Plan
(4) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures (1) Government approval of stated DRL/DRD in accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.1 requirements for the ATSRR. | Within 30 calendar days after DRL/DRD approval and the completion of the ATSRR. | 15% | TBP | |
| 1c | GLIMR Payload Pre-Ship Review (PSR) | (1) DRL/DRD RE-07, PSR |
(2) DRL/DRD MA-03, FMEA
(3) DRL/DRD TE-01, ICDs
(4) DRL/DRD TE-02, V&V Plan and Matrix
(5) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures
(6) DRL/DRD TE-07, Contamination Control Plan
(7) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures (1) Government approval of stated DRL/DRD in accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.2 requirements for the PSR. | Within 30 calendar days after the completion of the PSR. | 10% | TBP | |
| 1d | GLIMR Payload Integration Review (ATSIR) | (1) DRL/DRD RE-02, ATSIR |
(2) DRL/DRD MA-02, Reporting of Discrepancies
(3) DRL/DRD MA-03, FMEA
(4) DRL/DRD TE-01, ICDs
(5) DRL/DRD TE-02, V&V Plan and Matrix
(6) DRL/DRD TE-03, Verification Reports
(7) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model
(8) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report
(9) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures
(10) DRL/DRD TE-07, Contamination Control Plan
(11) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model (1) Government approval of stated DRL/DRDs in accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.1 requirements for the ATSRR. | Within 30 calendar days after DRL/DRDs approval and the completion of the ATSIR. | 10% | TBP | |
| 1e | GLIMR Observatory Test Readiness Review (ATSTRR) | (1) DRL/DRD RE-03, ATSTRR |
(2) DRL/DRD MA-02, Reporting of Discrepancies
(3) DRL/DRD TE-03, Verification Reports
(4) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model
(5) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report
(6) DRL/DRD TE-06, GLIMR Payload to GLIMR Spacecraft Integration and Test Plan and Procedures
(7) DRL/DRD TE-08, GLIMR Observatory Operations Plan
(8) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures
(9) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model (1) Government approval of stated DRL/DRDs in accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.1 requirements for the ATSTRR. | Within 30 calendar days after DRL/DRDs approval and the completion of the ATSTRR. | 10% | TBP | |
| 1f | GLIMR Mission Operations Readiness Review (ATSORR) | (1) DRL/DRD RE-04, ATSORR |
(2) DRL/DRD MA-02, Reporting of Discrepancies
(3) DRL/DRD TE-03, Verification Reports
(4) DRL/DRD TE-04, GLIMR Spacecraft Thermal Analysis Report and Thermal Model
(5) DRL/DRD TE-05, Coupled Loads Analysis and Dynamics Environment Report
(6) DRL/DRD TE-08, GLIMR Observatory Operations Plan
(7) DRL/DRD TE-09, GLIMR Mission Software Integration, Test Plan and Procedures
(8) DRL/DRD TE-10, GLIMR Spacecraft Bus Disturbance Contributions to LOS Jitter and Model (1) Government approval of stated DRL/DRDs in accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.1 requirements for the ATSORR. | Within 30 calendar days after DRL/DRDs approval and the completion of the ATSORR. | 10% | TBP | |
| 1g | GLIMR Mission Post Launch Assessment Review (ATSPLAR) | (1) DRL/DRD RE-05, ATSPLRA | ||
| (2) DRL/DRD MA-02, Reporting of Discrepancies | (1) Government approval of stated DRL/DRD in |
accordance with applicable DRL/DRD requirements.
| (2) Successful completion of SOW Section 4.2.1 requirements for the ATSPLRA. | Within 30 calendar days after DRL/DRD approval and the completion of the ATSPLAR. | 30% | TBP | |||
| 1h | GLIMR Operations Base Period | (1) DRL/DRD PM-01, MPSR | ||||
| (2) DRL/DRD MA-02, Reporting of Discrepancies | (1) Successful completion of SOW Sections 6.4.E; 6.4.F; 6.4.G requirements. | |||||
| (2) Contractor meets all on-orbit requirements for the month. | Monthly for 12 months following the 90-calendar day GLIMR Payload On- Orbit Checkout period. | 10% | ||||
| (monthly payment is 1/12th of this amount) | TBP | |||||
| 0002 | 2a | Extended Mission On-Orbit Operations | ||||
| Option Period 1 | (1) DRL/DRD PM-01, MPSR | |||||
| (2) DRL/DRD MA-02, Reporting of Discrepancies | (1) Successful completion of SOW Sections 6.5. | |||||
| (2) Contractor meets all on-orbit requirements for the month. | Monthly for 12 months following Baseline Operations | 100% | ||||
| (monthly payment is 1/12th of this amount) | TBP | |||||
| 0003 | 3a | Extended Mission On-Orbit Operations | ||||
| Option Period 2 | (1) DRL/DRD PM-01, MPSR | |||||
| (2) DRL/DRD MA-02, Reporting of Discrepancies | (1) Successful completion of SOW Sections 6.5. | |||||
| (2) Contractor meets all on-orbit requirements for the month. | Monthly for 12 months following Extended Mission Operations Option Period 1 | 100% | ||||
| (monthly payment is 1/12th of this amount) | TBP | |||||
| 0004 | 4a | 6 month extension (52.217-8) | 100% (monthly payment no more than 6 months) | TBP | ||
| Total Proposed Price | TBP |