Exhibit A.3_Room Data Matrix.xlsx
XLSX spreadsheet 206 KB Posted
- Attached to
- X1DB--Replacement Lease for St. Louis County VA Clinic Old RLP #: 36C255-24-R-0006 NEW RLP #36C255-25-R-0080
- Solicitation number
- 36C25525R0080
About this file
This document is a Room Data Matrix (RDM) Excel spreadsheet detailing interior construction specifications for a VA medical facility, encompassing comprehensive design requirements for multiple departments and room types. The matrix provides exhaustive technical specifications for approximately 100 distinct room categories, including exam rooms, laboratories, imaging services, pharmacy, and administrative spaces, with detailed parameters for floor and wall finishes, door hardware, electrical and mechanical systems, lighting, power requirements, and environmental conditions such as temperature, humidity, and air exchange rates.
The RDM serves as a technical design guide, specifying precise requirements for each room's construction and operational characteristics, including specific technical notes for different functional areas like Audiology, Dental Services, Imaging, Mental Health, and Pharmacy. Each room entry includes standardized information such as floor and wall finishes, ceiling heights, sound isolation ratings, door and hardware specifications, electrical outlets, lighting configurations, HVAC parameters, and specialized environmental control requirements, which would be critical for contractors bidding on the St. Louis County VA Clinic replacement lease project (Solicitation Number: 36C25525R0080).
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RDM Org
| ROOM DATA MATRIX | INTERIOR CONSTRUCTION | DOORS AND HARDWARE | MECHANICAL | ELECTRICAL | IT | |||||||||||||||||||||
| ROOM IDENTIFICATION | FLOOR | WALLS | CEILING | NOTES | Note: Use parameters within FGI Guidelines for the noted FGI Equivalent category, unless noted otherwise. | POWER | LIGHTING | |||||||||||||||||||
| Functional Area | DEPARTMENT | ROOM NAME | ROOM NAMES (VA) | FGI EQUIVALENT FOR ASHRAE 170 | FGI EQUIVALENT FOR TABLE 1.2-5 Minimum Sound Isolation | Floor Finish | Base | Wall Finish | Wainscot Material | Wainscot Height | STC | Ceiling Finish | Height | Notes | Size (Width) | Type | Material | Glazing | Rating | Hardware Group | Hardware Notes | Indoor Temperature | ||||
| Cooling F | Indoor Temperature | |||||||||||||||||||||||||
| Heating F | Indoor Relative Humidity | |||||||||||||||||||||||||
| % RH Max | Indoor Relative Humidity | |||||||||||||||||||||||||
| % RH Min | Minimum Total ACH | Minimum OA ACH | Room Air Return | |||||||||||||||||||||||
| Gen. Exh G Spec Exh S | Maximum Noise | |||||||||||||||||||||||||
| Level NC | Room Air Balance | HVAC Notes | # Duplex Receptacles | # Quad Receptacles | Power - Notes | Fixture Type | Controls | Lighting - Special Requirements | Lighting - Notes | # Data Outlets (standard density WAO) | IT - |
Special Requirements 0 General Rooms/Spaces Exam Room PACT Exam EXAM EXAMINATION RFT RB P -- -- SEE FGI AT 9'-0" 10 3'-0"
| 3'-6" | Flush | Wood | _ | _ | 12 SE | 3 | 8 | 1 | Multilevel Switching, Dimming & Occupancy | Multi-level switching or manual dimming | N/A | 3 | |||||||||||||||||||||||||
| 0 | General Rooms/Spaces | Exam Room | Exam Room - Multi-Specialty, Exam / Treatment, Exam - Consult, Consult Room - PACT, Exam/Consult Room (Mental Health/Social Work), Exam Room EMG/EEG, Exam Room-Cardiology, Exam/Consult, Nurse Practitioner, Women's Health Exam, Tele-Health Exam, Optometry Exam Treatment Room, Eye Lane, Tele-Retinal, TECHS, Applicance Fitting Room, Fitting Room, Physical Therapy Room, Occupational Treatment Room | EXAM | EXAMINATION | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 10 | 3'-6" | Flush | Wood | _ | _ | 12 S | 8 | 1 | Multilevel Switching, Dimming & Occupancy | Multi-level switching or manual dimming | N/A | 3 | |||||||||||
| 0 | General Rooms/Spaces | Consult Room | Consult Room, Audiology Rehabilitation Counceling Room, Dental Consult Room | CONSULTATION | CPT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 75 | 70 | 60 | - | 4 | 2 | Return | 40 | NR | 6 | Multilevel Switching, Dimming & Occupancy | Multi-level switching or manual dimming | N/A | 1 | |||
| 0 | General Rooms/Spaces | Procedure Room | Procedure Room, General, Urology, Gynecology, Specialty Care, Multi-Specialty Care, Cast Room | PROCEDURE | TREATMENT | WSF | WSF | EP | RWC | 4'-0" | SEE FGI | AT | 9'-0" | 3 | 3'-0" |
| 3'-6" | Flush | Wood | -- | -- | 12 SE | 3 | 7 | P13 | Multilevel Switching, Dimming & Occupancy | Wall mounted exam light | N/A | 2 | |||||||||||||||||||||||||||||
| 0 | General Rooms/Spaces | Laboratory | Laboratory (Typical) | LABORATORY WORKROOM | __ | WSF | WSF | EP | -- | -- | 40 | AT-SP | 9'-0" | 3 | 3'-0" | Flush | Wood | _ | _ | 15 AG | 4 | 6 | P3, P4 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 5 | ||||||||||||||
| 0 | General Rooms/Spaces | Conference Room | Conference Room, Multi-Purpose Room, Group Room, Shared Medical Appointment Room, Education Room, Staff Training Room, Classroom | __ | CPT | RB | P | RWC | 4'-0" | 40 | AT | 9'-0" | 17 | 3'-6" | Flush | Wood | _ | _ | 15 S | _ | M2 | 8 | P14 | Multilevel Switching, Dimming & Occupancy | Provide 4 scene preset dimmable lighting for a variety of tasks. Consider placement and optics to mitigate glare and ceiling reflections. | N/A | 4 | Floor data for table | |||||||||||||
| 0 | General Rooms/Spaces | TOILET | General Toilet, Patient - Toilet, Toilet - Police, Toilet - Family, Toilet - Female Staff, Toilet - Male Staff, Toilet - Procedure Room, Toilet - Public, Toilet - RF Patient, Toilet - Women's Health, Toilet - Female, Toilet - Family Assist, Specimen Collection Toilet | TOILET ROOM | TOILET ROOM | PT | PT | P | CT | 7'-0" | SEE FGI | AT | 9'-0" | 1,2 | 3'-6" | Flush | Wood | _ | _ | 11 | _ | 1 | Downlights/Mirror or vanity | Occupancy Sensor | N/A | N/A | |||||||||||||||
| 0 | General Rooms/Spaces | OFFICE | Any Office | -- | CONSULTATION | CPT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 CS | 4 | 1 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | ||||||||||||||||
| 0 | General Rooms/Spaces | WAITING | Waiting - Family - PACT, Waiting - PACT 3, Waiting - General - 20 People, Waiting - General - 10 People, Waiting - General - 6 People, Waiting-General | EXAM - PUBLIC SPACE | CPT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 10, 17 | M4 | -- | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||||||||||
| 0 | General Rooms/Spaces | RECEPTION | Reception, Information Desk, Travel Window, Reception - Accessible | -- | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | -- | 3'-0" | Flush w/ narrow vision | Wood | _ | _ | 12 CG | 3 | M4 | 1 | 1 | Downlights, pendants, decorative, and accent | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 10 | Data/phone feeds to systems furniture | |||||||||||
| 0 | General Rooms/Spaces | COPY ALCOVE | Copy Alcove, Copier - Workroom, Copy / Office Supply Room, Copy Room | -- | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 6 | _ | _ | _ | _ | _ | _ | 6 | 3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 3 | |||||||||||||||
| 0 | General Rooms/Spaces | CLEAN UTILITY | Clean Utility, Clean Supply, Clean Workroom, Clean Linen, Sterile Storage, CBOC Steril Supply Storage Room, Clean Scope, Dental Clean Cart, Central Sterile | -- | -- | RFT | RB | P | RWC | 4'-0" | -- | AT | 9'-0" | -- | 3'-0" | Flush | Wood | -- | 45 MIN | 121 AG | _ | 66 | 75 | 55 | 30 | 4 | (+) | 1 | Occupancy Sensor | N/A | N/A | ||||||||||
| 0 | General Rooms/Spaces | SOILED UTILITY | Soiled Utility Room, Recycled Material, Soiled Holding, Soiled Linen, Soiled Workroom, Soiled Supply, Soiled Cart | SOILED HOLDING / SOILED WORK ROOM | -- | WSF | WSF | P | RWC | 4'-0" | -- | AT | 9'-0" | 3 | 3'-0" | Flush | Wood | -- | 45 MIN | 121 AG | _ | 2 | -- | Occupancy Sensor | N/A | N/A | -- | ||||||||||||||
| 0 | General Rooms/Spaces | STORAGE | Storage - Medical Equipment, Storage - Shared Medical Appointments, DME - Prosthetics Storage, Storage - Homeless, EMS Storage, Storage - Bistro/Coffee Bar, Storage - Patient Clothing and Luggage, Laundry / Storage, Tray Cart Storage Area, Buld Storage, General Storage, Secure Storage, | CLEAN WORKROOM/CLEAN SUPPLY | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 35 AG | 1 per wall, not to exceed 12' spacing | -- | Surface or chain mounted 1' x 4' | Occupancy Sensor | N/A | N/A | |||||||||||||||||
| 0 | General Rooms/Spaces | JANITOR'S CLOSET | Housekeeping Aides Closet (HAC) | ENVIRONMENTAL SERVICES ROOM | -- | CS | RB | P | FRP | 4'-0" | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 34 A | _ | 1 | -- | Occupancy Sensor | N/A | N/A | -- | |||||||||||||||
| 0 | General Rooms/Spaces | KITCHENETTE | Social Activities Space/ Kitchen | -- | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 17 | 3'-0" | Flush | Wood | -- | -- | 15 A | _ | 4 | -- | Multilevel switching/dimming/occupancy | N/A | N/A | -- | ||||||||||||||
| 0 | General Rooms/Spaces | EQUIPMENT ALCOVE | AED Alcove, Height and Weight Alcove, Scale Alcove, Stretcher Alcove, Med Alcove, Portable Patient Lift Alcove, Wheelchair Alcove, My Health eVet, Kiosk, | -- | -- | Match Adjacent | Match Adjacent | Match Adjacent | RWC | 4'-0" | -- | AT | Match Adjacent | 3 | -- | -- | -- | -- | -- | 6 | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | |||||||||||||||
| 0 | General Rooms/Spaces | STAFF LOUNGE | Staff Lounge | -- | -- | RSF | RB | P | -- | -- | 40 | AT | 9'-0" | 4 | 3'-0" | Flush w/ narrow vision | Wood | -- | -- | 13 | _ | Exh. (G) | (-) | 8 | -- | P7 | |||||||||||||||
| Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | ||||||||||||||||||||||||||||||||||||||
| 0 | General Rooms/Spaces | MEDICATION ROOM | Medication Room | MEDICATION ROOM | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 34 | 5 | 1 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||||||
| 0 | General Rooms/Spaces | LACTATION ROOM | Employee Wellness, Lactation Room, Quiet Room | -- | -- | RFT | RB | P | -- | -- | 50 | AT | 9'-0" | 10 | 3'-0" | Flush | Wood | -- | -- | 12 CS | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||||
| 0 | General Rooms/Spaces | LOCKER ROOM | Locker Room, Locker Room (Male/ Female) Locker - Staff Personal Property, Locker Room - Staff | -- | -- | RFT | RB | P | -- | -- | 40 | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | Push/Pull | Exh. (G) | (-) | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | ||||||||||||||
| 0 | General Rooms/Spaces | OFFICE, CUBICLE, Open Office | Cubicle - Administrative, Data Processing, Workstation - Extended Team, Homeless, Workstation - MICHM, Workstation - Suicide Prevention, Workstation - VOC Rehab, Workstation - Rad Tech, Workstation - Shipping / Receiving, Workstation, Administration (MSA MH; Rad, LPN), Workstation-Sleep Tech, Work Station, Call Center (MSA), Workstation-Cart Case Dispatch, Workstation-Clerical, | -- | -- | CPT | RB | P | -- | -- | -- | AT | 9'-0" | 2 per workstation | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||||||||||||
| 0 | General Rooms/Spaces | SUB-WAITING | Sub-Waiting, MRI Sub-Waiting, CT Sub-Waiting, Mammo Sub-Waiting, Sub-Waiting - Diagnostic Patient, Sub-Waiting - Dilation Patient, CT Vestibule, Waiting, Waiting-Zone 1, Sub-Waiting-Zone 2 | -- | -- | CPT | RB | P | -- | -- | -- | AT | 9'-0" | 10, 17 | -- | -- | -- | -- | -- | - | 6 | M4 | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | |||||||||||||
| 0 | General Rooms/Spaces | VENDING | Vending Machine Area | RFT | RB | P | -- | -- | -- | AT | 9'-0" | -- | -- | -- | -- | -- | -- | 6 | M4 | 8 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||||||
| 0 | General Rooms/Spaces | TOILET/SHOWER ROOM | Toilet/Shower-Staff, Toilet/Shower-Patient, Toilet/Shower-Female Staff, Toilet/Shower-Male Staff | TOILET ROOM | TOILET ROOM | PT | PT | CT | -- | -- | SEE FGI | GWB/P | 9'-0" | 2, 19 | 3'-6" | Flush | Wood | -- | -- | 11 G | 2 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | ||||||||||||||||
| 0 | General Rooms/Spaces | CHANGING ROOM | Dressing room | RFT | RB | P | -- | -- | 40 | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 11 K | 75 | 70 | 60 | - | 4 | 2 | Return | NR | NR | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | ||||||||||
| 2 | Primary Care, Specialty Care, PACT | PACT TEAM WORK SPACE | PACT Team Work Space, Team Work Area- Home Based Primary Care | -- | CPT | RB | P | -- | AT | 9'-0" | -- | _ | _ | _ | _ | _ | 14 MP | 6 | M3 | 2 per workstation | -- | Multilevel Switching, Dimming & Occupancy | Provide dimming and switching to provide various light levels. Provide switching in refraction desk to control overhead lighting. | N/A | 1 per workstation | ||||||||||||||||
| 2 | Primary Care, Specialty Care, PACT | EXAM ROOM, AIRBORNE INFECTION ISOLATION | Exam, Isolation, Negative Pressure | AII Room | EXAMINATION | WSF | WSF | P | -- | -- | SEE FGI | GWB:P | 9'-0" | 3,7 | 3'-6" | Flush | Wood | -- | -- | 12 S | 6 | -- | Multilevel Switching, Dimming & Occupancy | Sealed fixture, flat lens surface on exterior | N/A | 1 | |||||||||||||||
| 5 | Audiology and SLP | AUDIOLOGY HEARING AID TESTING | Hearing Aid Lab, Hearing Aid Processing, Hearing Aid Repair | -- | RFT | RB | P | -- | -- | 40 | AT | 9'-0" | -- | 3'-0" | Flush | Wood | _ | _ | 15 S | _ | 75 | 70 | 60 | - | Exh. (G) | (-) | 7 | 0 | P4 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | ||||||||
| 5 | Audiology and SLP | AUDIOLOGY HEARING AID FITTING | Audiology Programming / Fitting, Hearing Aid Fitting Room, Cerumen Management Room, Speech Language Pathology Assistive Technology Romm, Speech Language Pathology Voice Treatment Room | EXAM | -- | CPT | RB | P | -- | -- | 60 | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 6 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||||||
| 5 | Audiology and SLP | AUDIOMETRIC EXAM BOOTH | Audiometric Exam Suite, Exam - Audiometric Booth, Aud: Suite - Audiometric Exam, Hearing/Diagnostics, Booth, 1-Person | EXAM | -- | Pre-Fab | Pre-Fab | Pre-Fab | -- | -- | SEE EQUIP LIST |
tc={DA07BD7C-343C-4CA6-BD5F-166A5EACAEF6}: [Threaded comment]
Your version of Excel allows you to read this threaded comment; however, any edits to it will get removed if the file is opened in a newer version of Excel. Learn more: https://go.microsoft.com/fwlink/?linkid=870924
Comment:
find out how booths are specified and what is the min requirement for VA. Pre-Fab 8'-0" -- 3'-0"
| 3'-6" | Pre-Fab | Pre-Fab | _ | _ | 1 | 2,4 | 9 | P1 | Typically pre-packaged unit including lighting and switching | N/A | L1 | 5 | ||||||||||||||||||||||||||
| 5 | Audiology and SLP | ELECTROPHYSIOLOGY | Electrophysiology, Posturography, Vestibulography | EXAM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 6 | P2, P3, P14 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 3 | |||||||||||
| 6 | Dental Service | SPECIALTY EQUIPMENT MECHANICAL ROOM | Dental Equipment Mech. Room, Mechanical Rooms - Electrical | -- | -- | CS | -- | P | -- | -- | 60 | EXP | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 14 S | Exh. (G) | (-) | 2 | -- | P3 | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | 1 | |||||||||
| 6 | Dental Service | DENTAL PROSTHETICS LABORATORY | Laboratory, Dental Prosthetics | -- | WSF | WSF | P | -- | -- | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 15 AG | 75 | 70 | 60 | 20 | 6 | 2 | Return |
Exh. (G)
| 45 | (-) | M13 | 7 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 5 | ||||||||||||||||||||||||||||||||
| 6 | Dental Service | DENTAL TREATMENT ROOM | Dental Treatment Room (DTR), Multi-Functional (4/Hygiene), Special Needs Patient, Bariatric | EXAM | TREATMENT | WSF | WSF | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 CS | (+) | 7 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||||
| 6 | Dental Service | DENTAL X-RAY ROOM | X-Ray Room, Panoramic / Cephalometric (Cone Beam) | CLASS 1 IMAGING ROOM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 5 | 3'-6" | Flush | Wood | -- | LEAD LINED | 17 AGL | 8 | 7 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||
| 7 | Optometry | FITTING & DISPENSING, EYEGLASSES | Fitting & Dispensing, Eyeglasses | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | 6 | 75 | 70 | 60 | - | 4 | 2 | Return | 40 | NR | 2 | Downlights and accent/display | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||
| 7 | Optometry | LOW VISION EXAM/ THERAPY/ TRAINING | Low Vision Exam/ Therapy/ Training | EXAM | EXAMINATION | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 6 | Multilevel Switching, Dimming & Occupancy | Provide dimming and switching to provide various light levels. Provide switching in refraction desk to control overhead lighting. | N/A | 3 | ||||||||||||||
| 7 | Optometry | PRE-TESTING/ INTAKE | Pre-Testing/ Intake | EXAM | EXAMINATION | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 6 | 1 | Multilevel Switching, Dimming & Occupancy | Provide dimming and switching to provide various light levels. Provide switching in refraction desk to control overhead lighting. | N/A | 2 | |||||||||||||
| 7 | Optometry | VISUAL FIELDS ROOM | Visual Fields Room, Photography Room, Ultrasound Room, Tomography Room, Imaging Room, OCT Laser | EXAM | EXAMINATION | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | -- | 3'-6" | Flush | Wood | _ | _ | 12 S | _ | 7 | Multilevel Switching, Dimming & Occupancy | Provide dimming and switching to provide various light levels. Provide switching in refraction desk to control overhead lighting. | N/A | 2 | ||||||||||||||
| 8 | Mental Health | QUIET ROOM | Quiet Room for Patients | EXAM | TREATMENT | CPT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 35 S | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||||
| 8 | Mental Health | BIOFEEDBACK TREATMENT ROOM | Biofeedback Treatment Room | EXAM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 15 S | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||||||
| 9 | Specialty Care Services | PULMONARY FUNCTION ROOM | Pulmonary Function - Analysis | EXAM | TREATMENT | WSF | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 G | 6 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||||||
| 9 | Specialty Care Services | TREADMILL ROOM | Treadmill Room | EXAM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 MS | 6 | -- | P9 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | ||||||||||||||
| 9 | Specialty Care Services | EKG TESTING ROOM | EKG Testing Room | EXAM | EXAMINATION | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0 | 3'-6" | Flush | Wood | -- | -- | 12 S | One per wall | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||||||
| 9 | Recreation Therapy | GROUP THERAPY ROOM, MUSIC | Creative Arts - Group Therapy Room - Music | -- | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 CG | 8 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||||
| 9 | Recreation Therapy | GROUP THERAPY ROOM, ART | Creative Arts - Group Therapy Room - Large | -- | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 CG | 8 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||||
| 9 | Recreation Therapy | WEIGHT ROOM, SMALL | Recreation Therapy Exercise / Weight Room - Small | -- | TREATMENT | RF | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 34 AG | 12 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | |||||||||||||||
| 10 | PHYSICAL THERAPY | PHYSICAL THERAPY GYM | Treatment Exercise Area (includes workstations therapists) | EXAM | TREATMENT | RF | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 14 S | 14 | -- | P14 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||||
| 10 | PHYSICAL THERAPY | Activities Daily Living (ADL) Training | ADL Evaluation and Training Center, Toilet, Tub, Bed, Kitchen, Laundry | EXAM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0 | 3'-6" | Flush | Wood | -- | -- | 15 S | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | ||||||||||||||||
| 13 | Imaging Services | RADIOLOGY | Radiology, ES: General Purpose Radiology Room | CLASS 1 IMAGING ROOM | TREATMENT | WSF | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 5 | 4'-0" | Flush | Wood | -- | LEAD LINED | 15 LS | 8 | 5 | P3, P13 | Fully dimmable, occupancy sensor | N/A | L2 | 2 | |||||||||||||
| 13 | Imaging Services | C.T. CONTROL ROOM | CT Control Area, X-Ray - Computed Tomography - Control | TREATMENT | WSF | WSF | P | -- | -- | SEE FGI | AT | 9'-0" | 5 | 3'-0" | Flush | Wood | -- | LEAD LINED | 12 LS | 45 | M14 | 6 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||
| 13 | Imaging Services | C.T. EQUIPMENT ROOM | CT Equipment Room, X-Ray - Computed Tomography - Indep View Console | -- | WSF | WSF | P | -- | -- | -- | AT | 9'-0" | 5 | 6'-0" | Flush | Wood | -- | -- | 45 AG | 7 | 50 | M14 | 7 | -- | P3, P13 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||
| 13 | Imaging Services | C.T. SCAN ROOM | CT Scanning Room (Ceiling Lift), X-Ray - Computed Tomography - Scanner | CLASS 1 IMAGING ROOM | TREATMENT | WSF | WSF | P | -- | -- | SEE FGI | AT | 9'-0" | 5 | 4'-0" | Flush | Wood | -- | LEAD LINED | 15 ALG | 7 | -- | P3, P13 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||
| 13 | Imaging Services | MAMMOGRAPHY SCAN ROOM | Mammo - X-ray, Mammography Room | CLASS 1 IMAGING ROOM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 5 | 3'-6" | Flush | Wood | -- | LEAD LINED | 12 LS | 7 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||
| 13 | Imaging Services | RADIOGRAPHIC / FLOURO SCAN ROOM | Radiographic / Fluoroscopic (R/F) Room | CLASS 1 IMAGING ROOM | TREATMENT | WSF | WSF | P | - | - | SEE FGI | AT | 9'-0" | 5 | 3'-6" | Flush | Wood | -- | LEAD LINED | 15 AGL | 7 | -- | P3, P13 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||||||||||
| 13 | Imaging Services | ULTRASOUND SCAN ROOM | Ultrasound Room | CLASS 1 IMAGING ROOM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 12 S | |||||||||||||||||||||
| 7 | -- | P3, P13 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||||||||||||||||||||||||
| 13 | Imaging Services | PACS SERVER ROOM | X-Ray - Storage - Digital Files, Viewing Room - Picture Archiving and Communication System (PACS) | -- | RFT | RB | P | - | - | - | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 15 GK | 50 | 4 | -- | P3, P13 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||||
| 13 | Imaging Services | MRI CONTROL ROOM | MRI Control Room, X-Ray - Magnetic Resonance - Control, MRI Zone 3 | CLASS 1 IMAGING ROOM | EXAM - MRI | RFT | RB | P | -- | -- | 40 | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 12 GS | 45 | M14 | 6 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||
| 13 | Imaging Services | MRI EQUIPMENT ROOM | MRI System Component Room, X-Ray - Magnetic Resonance - System Component | TREATMENT | RFT | RB | P | RWC | 4'-0" | AT | 9'-0" | 11 | 4'-0" | Flush | Wood | -- | -- | 35 AG | 40 | 50 | M14 | 7 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||||||
| 13 | Imaging Services | MRI FERROMAGNETIC DETECTION | X-Ray - Magnetic Resonance - Ferromagnetic Detection, MRI Zone 2, MRI Viewing Room | EXAM - MRI | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 11, 16 | 4'-0" | Flush | Wood | -- | -- | 15 G | 75 | 70 | 60 | 40 | 12 | 2 | Return | 40 | NR | 1 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | |||||
| 13 | Imaging Services | MRI SCAN ROOM | MRI Scanning, X-Ray - Magnetic Resonance - Scanner, | EXAM - MRI | WSF | RB | P | -- | -- | SEE FGI | AT | VARIES | 11,13,16 | 4'-0" | Flush | Wood | -- | R/F Shielded | 1 | 75 | 70 | 60 | 40 | 12 | 2 | Return | ||||||||||||||
| Exh. (S) | 50 | NR | M17 | 2 | -- | P3 | Multilevel Switching, Dimming & Occupancy | MRI rated fixtures | N/A | 1 | ||||||||||||||||||||||||||||||
| 13 | Imaging Services | READING ROOM | MRI Viewing Room, X-Ray - Magnetic Resonance - Viewing | -- | CPT | RB | P | -- | -- | 40 | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 12 GS | 40 | 6 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 6 | ||||||||||||||
| 13 | Imaging Services | BONE DENSITOMETRY | Bone Densitometer | EXAM | TREATMENT | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 35 S | 7 | -- | P3 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | ||||||||||||||
| 14 | Pathology and Laboratory Medicine | SPECIMEN COLLECTION | Blood Specimen Collection, Alcove - Specimen Collection Point of Care (also for Substance Abuse plus Coumadin), Blood Draw Alcove, Support Area, Laboratory-Satellite, Laboratory-Venipuncture, Blood Draw | EXAM | __ | WSF | WSF | EP | -- | -- | -- | AT | 9'-0" | 3 | -- | _ | _ | _ | _ | _ | 6 | 4 | Multilevel Switching, Dimming & Occupancy | Multi-level switching or manual dimming | N/A | 2 | ||||||||||||||
| 14 | Pathology and Laboratory Medicine | SPECIMEN ACCESSIONING, PROCESSING & DISTRIBUTION ROOM | Specimen Accessioning, Processing & Distribution Room | LABORATORY WORK ROOM | -- | WSF | WSF | EP | -- | -- | -- | GYP/EP or AT-SP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Wood | Narrow Vision | -- | 15 AG | One per wall, 6' spacing, one adjacent to sink | One at each workstation | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | One at each workstation | ||||||||||||||
| 15 | Pharmacy Service | PHARMACY | Pharmacy, Pharmacy, PACT 3 (Controlled Substance) (w/3 AutoDispensing) | PHARMACY | -- | RF | RB | P | -- | -- | -- | AT | 9'-0" | -- | 6'-0" | Flush | Metal | - | - | 200 AS | 7 | 15 | P5 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 9 | |||||||||||||
| 15 | Pharmacy Service | PHARMACY DISPENSING WINDOW | Dispense/Consult Window, Workroom, Pharmacist | PHARMACY | -- | RF | RB | P | -- | -- | -- | AT | 9'-0" | -- | - | - | - | - | - | - | OPEN | 12 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 5 | ||||||||||||||
| 15 | Pharmacy Service | CLEAN ROOM, COMPOUNDING | Pharmacy - Clean Room - Chemotherapy Compounding | -- | -- | RF | RF | P | -- | -- | -- | GWB:P | 9'-0" | 3 | 7'-0" | Single Slide Auto Sliding Door | Aluminum/ Glass | Yes | -- | 850 | 68 | 68 | 60 | 20 | 30 | 2 | Exh. (S) | 55 | (-) | M12 | 14 | -- | P10 | |||||||
| Multilevel Switching, Dimming & Occupancy | Sealed fixture, flat lens surface on exterior | N/A | 5 | |||||||||||||||||||||||||||||||||||||
| 15 | Pharmacy Service | IV ADMIXTURE | Pharmacy - IV Admixture - Low Volume | -- | -- | RF | RF | P | -- | -- | -- | GWB:P | 9'-0" | 3 | 7'-0" | Single Slide Auto Sliding Door | Aluminum/ Glass | Yes | -- | 850 | 68 | 68 | 60 | 20 | 30 | 2 | Return | 55 | (++) | M12 | 14 | -- | P10 | |||||||
| Multilevel Switching, Dimming & Occupancy | Sealed fixture, flat lens surface on exterior | N/A | 5 | |||||||||||||||||||||||||||||||||||||
| 15 | Pharmacy Service | PRESCRIPTION DISPENSING AREA | Prescription Dispensing Area - OmniCell Station | -- | -- | RF | RF | P | -- | -- | -- | AT | 9'-0" | 3 | -- | -- | -- | -- | -- | - | 6 | 8 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 2 | |||||||||||||
| 15 | Pharmacy Service | SECURE STORAGE VAULT | Secure Storage, Vault | CLEAN WORK ROOM/ CLEAN SUPPLY | -- | RFT | RB | P | RWC | 4'-0" | -- | GWB:P | 9'-0" | 3'-0" | Flush | Hollow Metal | -- | -- | 1 | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | |||||||||||||||
| 15 | Pharmacy Service | ANTEROOM | Anteroom, Compound Sterile Preparation | -- | WSF | WSF | EP | -- | -- | -- | GWB:SP | 9'-0" | 3 | 7'-0" | Single Slide Auto Sliding Door | Aluminum/ Glass | Yes | -- | 850 | 68 | 68 | 60 | 20 | 30 | 2 | Return | 55 | (+) | M12 | 2 | -- | Multilevel Switching, Dimming & Occupancy | Sealed fixture, flat lens surface on exterior | N/A | -- | |||||
| 17 | Business Office | SECURE CASH ROOM | Secure Money Handling Room | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0 | 3'-0" | Flush w/ 1-Way Viewer | Steel | -- | -- | 200 GV | 4 | -- | Multilevel switching/dimming/occupancy | N/A | N/A | 1 | ||||||||||||||||
| 18 | Engineering | BIOMED. REPAIR SHOP | Repair Shop, Biomedical Eng. | -- | -- | RF | RB | P | -- | -- | -- | AT | 9'-0" | 3'-6" | Flush | Wood | -- | -- | 35 AG | Exh. (G) | (-) | M7 | 10 | -- | P4, P6 | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | 2 | ||||||||||
| 19 | Logistics | LOADING DOCK | Receiving/ Shipping Dock | -- | -- | CS | RB | EP | -- | -- | -- | EXP. | -- | 8 | 6'-0" | Flush | Wood | -- | -- | 44 APW | 7 | - | 60 | - | - | Exh. (G) | (+) | M5 | 2 | -- | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | 2 | |||||
| 19 | Logistics | MAIL ROOM | Support: Mail Room and Dist. Center, Mailing Room - Prosthetic Appliances | -- | -- | RF | RB | P | RWC | 4'-0" | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 15 G | 4 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | |||||||||||||||
| 19 | Logistics | GAS CYLINDER STORAGE | Storage - Gas Cylinders - MRI, Storage - Gas Cylinders - Interior | -- | -- | WSF | RB | P | RWC | 4'-0" | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | 45 MIN | 34 G | Exh. (S) | ||||||||||||||||||||
| (-) | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | ||||||||||||||||||||||||||||||||||
| 19 | Logistics | BIO-HAZARD STORAGE | Storage - Bio Hazardous Material, Storage - Hazardous Material, Infectious / Hazardous Waste | REGULATED WASTE | -- | WSF | WSF | EP | RWC | 4'-0" | -- | GWB:SP | 9'-0" | 3 | 3'-6" | Flush | Hollow Metal | -- | -- | 34 G | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | -- | ||||||||||||||
| 19 | Logistics | STORAGE WAREHOUSE | Bulk Storage, General Storage, Warehouse | CLEAN WORKROOM/CLEAN SUPPLY | CS | RB | P | -- | -- | -- | Exp | 10'-0" | 6'-0" | Flush | Wood | -- | -- | 45 AG | minimum, 1 per wall, not to exceed 12' spacing | -- | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | ||||||||||||||||
| 19 | Logistics | BREAK DOWN | Break Down | CLEAN WORKROOM/CLEAN SUPPLY | RPT | RB | EP | -- | -- | -- | AT | 9'-0" | 8 | 4'-0" | Flush | Wood | -- | -- | 34 AG | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | ||||||||||||||||
| 20 | Police Service | POLICE HOLDING ROOM | Holding Room | -- | -- | CS | RB | P | -- | -- | -- | GWB-PT | 9'-0" | 3,15 | 3'-6" | Flush | Hollow Metal | Half Glass w/ Laminated Glass | 18 P | 0 | -- | Multilevel Switching, Dimming & Occupancy | Tamperproof fixture design | N/A | -- | |||||||||||||||
| 20 | Police Service | OPERATIONS ROOM | Operations Room | RFT | RB | P | -- | -- | 40 | AT | 9'-0" | 3'-6" | Flush | Hollow Metal | -- | -- | 200 APS | M15 | 0 | 8 | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 4 | ||||||||||||||||
| 20 | Police Service | SECURE STORAGE | Small Arms Armory, Storage - Secure | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 3'-0" | Flush | Hollow Metal | -- | -- | 200 P | 75 | 70 | 60 | - | 4 | 2 | Return | NR | NR | 1 | -- | Multilevel Switching, Dimming & Occupancy | N/A | N/A | 1 | ||||||||
| 21 | VCS | RETAIL AREA | Retail Area | EXAM - PUBLIC SPACE | RFT | RB | P | -- | -- | SEE FGI | AT | 9'-0 | 17 | 6'-0" | Flush w/ Full Vision | Wood | Full Vision | 47 KM | 7, 9 | M4 | One per wall, 6' spacing | -- | Multilevel Switching, Dimming & Occupancy | Track or adjustable accent lighting for retail displays. | L5 | 3 | ||||||||||||||
| 23 | OI&T | TELECOMM. | Telecommunications Room/ Closet, IT Telecommunications Room | -- | -- | RFT | RB | P | -- | -- | -- | EXP. | 12'-0" | 3'-6" | Flush | Wood | -- | -- | 34 AS | 64 | 75 | 55 | 30 | - | - | - | - | NR | 6 | -- | P15 | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | -- | ||||
| 23 | OI&T | SERVER ROOM | Central Server Room | -- | -- | RFT | RB | P | -- | -- | -- | EXP. | 12'-0" | 3'-6" | Flush | Wood | -- | -- | 34 AS | 72 | 81 | 60 | 6 | M8 | 10 | -- | P15 | Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | -- | ||||||||
| 23 | OI&T | I.T. WORKROOM | IT Workroom, Equip. Configuration/ Repair | -- | -- | RFT | RB | P | -- | -- | -- | AT | 9'-0" | 3'-0" | Flush | Wood | -- | -- | 35 AG | 10 | -- | P4, P6 | ||||||||||||||||||
| Surface or chain mounted 1' x 4' | Occupancy/vacancy | N/A | N/A | 8 | ||||||||||||||||||||||||||||||||||||
| 24 | SPS | ANTEROOM, SOILED TRANSITION | Anteroom, Soiled Transition/Drop-Off | DECONTAM | ||||||||||||||||||||||||||||||||||||
| ROOM | -- | RES | RES | EP | -- | -- | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 72 | 60 | 30 | 10 | 10 | Exhaust (G) | 40 | (-) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 2 | ||||||||
| 24 | SPS | DECONTAMINATION ROOM | Decontamination Work Room, Scope Decontamination Room | DECONTAM | ||||||||||||||||||||||||||||||||||||
| ROOM | -- | RES | RES | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 72 | 60 | 30 | 6 | 6 | Exhaust (G) | 40 | (--) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 4 | ||||||||||
| 24 | SPS | Cart Wash | Cart Wash | -- | RES | RES | CT | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 70 | 75 | 10 | 10 | Exhaust (S) | 40 | (-) | M18, M19 | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | |||||||||
| 24 | SPS | Water Treatment Storage Room | Water Treatment Storage Room | -- | RES | RES | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush | Steel | -- | 15 AG | 70 | 75 | 10 | 10 | Exhaust (G) | 40 | (-) | M18, M19 | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 1 | |||||||||
| 24 | SPS | REPROCESSING ROOM, SCOPE | Reprocessing Room, Scope | -- | RES | RES | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 72 | 60 | 30 | 6 | 6 | Exhaust (G) | 40 | (-) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 2 | |||||||
| 24 | SPS | Instrument Assembly | Instrument Assembly | -- | WSF | WSF | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 72 | 60 | 30 | 4 | 4 | Exhaust (G) | 40 | (++) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 4 | |||||||
| 24 | SPS | Sterilization Area | Steam Sterilization Area, Low Temp Sterilization Area | -- | RES | RES | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 75 | 60 | 30 | 10 | 10 | Exhaust (G) | 40 | (++) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 2 | |||||||
| 24 | SPS | Cooling Area | Cooling Area | -- | RES | RES | EP | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Steel | Narrow Vision | -- | 15 AG | 66 | 75 | 60 | 30 | 10 | 10 | Exhaust (G) | 40 | (++) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 1 | |||||||
| 24 | SPS | Equipment Room, Steam Generator | Equipment Room, Steam Generator | -- | RFT | RB | EP | -- | ACT-SP | 9'-0 | 3, 7 | 3'-6" | Flush | Steel | -- | 15 AG | 85 | 10 | 10 | Exhaust (G) | 45 | (-) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | -- | |||||||||||
| 24 | SPS | Clean Dispatch | Clean Dispatch | -- | RFT | RB | EP | -- | ACT-SP | 9'-0 | 3, 7 | 70 | 75 | 60 | 30 | 4 | 4 | Exhaust (G) | 40 | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | 1 | ||||||||||||||
| 24 | SPS | STORAGE, CLEAN SCOPE | Storage, Clean Scope | CLEAN SUPPLY | -- | RES | RES | EP | RWC | 4'-0" | -- | GYP-EP | 9'-0 | 3, 7 | 3'-6" | Flush w/ Narrow Vision | Wood | Narrow Vision | -- | 15 AG | 66 | 75 | 55 | 30 | 4 | (+) | One per wall | -- | 2 X 2 recessed lensed | Multilevel Switching, Dimming & Occupancy | Gyp ceiling - lights to be sealed type/flange mounted | N/A | -- |
Interior Finishes Notes Interior Finishes Notes
| General Notes | |
| A. | Hollow metal frames and doors to be painted. |
| B. | Window sills to be solid surface fabrication. |
| C. | Resilient base to be 4", unless otherwise noted. |
| D. | Provide painted finishes only on inside of exterior walls (no wall covering). |
| E. | Floor material transitions to occur at centerline of door, unless otherwise noted. |
| F. | Wall brackets, grills, fire extinguisher cabinets, fin tube radiation, etc. to be painted to match adjacent wall color. |
| G. | Interior stairwell treads to be concrete with rubber nosings and RFT, LVT or RF landings. Stair nosings to be a contrasting color for safety. |
| H. | Coordinate height of wall protection with wall-mounted devices. |
| I. | Gypsum board soffits may be substituted for ACT above locations such as nurse stations, patient transaction/consultation desks, reception desks and |
| lobby/waiting areas. | |
| J. | Soffit above upper cabinets to be gypsum board. |
| K. | Refer to FGI recommendations regarding indoor air quality, sustainability and life cycle of materials. |
| L. | Solid surface countertops to have sides and backsplash at walls. |
| Schedule Notes | |
| 1. | CT tile to 7'-0" on plumbing and adjacent wall(s) with paint above to ceiling. |
| 2. | Tile base to be coved. |
| 3. | Integral coved base 6" high tightly sealed to walls. |
| 4. | If sink is present, use hard suface flooring as noted. |
| 5. | Lead lined walls and control area view window. |
| 6. | Flooring and base to match adjacent area flooring material and base. |
| 7. | Use gasketed, clip down ACT/grid system |
| 8. | Use slip-retardant finish on floor material |
| 9. | Public and exposed open stairways to be treated similar to adjacent spaces using CT/PT/RF on treads. Stair nosings to be a contrasting color for safety. |
| 10. | Note that if wall saver designed chairs are used, no wall protection is required. |
| 11. | Extend all room partitions to structural deck. |
| 12. | CT above countertop on wall. |
| 13. | Ceiling height as required to acommodate equipment. |
| 14. | Cove QT base, 6" high. |
| 15. | No separate trim at top of base, use alternate method to seal to wall. |
| 16. | Ceiling suspension system should be fabricated from nonferromagnetic material. |
| 17. | Aesthetic specialty materials may be used as accents where the design and budget permits. |
| 18. | Ceiling tile to meet USDA regulations. |
| 19. | Floors to be slip-resistant and meet ANSI 326.3 for measuring dynamic coefficient of friction for hard surfaces |
| 20. | Wall base on gyp board but not needed on any exterior materials such as brick, metal, or stone walls. |
| 21. | Wall CT and ceiling to meet building code light reflectancy standards. |
| 22. | Space may be room or area within a room. Coordinate finishes with adjacent spaces. |
| 23. | Provide 3/4" painted plywood where required by Telecommunications. |
| Finish Codes | |
| AT | Acoustical Ceiling Tile |
| AT-SP | Acoustical Scrubbable Ceiling Tile (with sprayed plastic finish) |
| CPT | Carpet Tile |
| CS | Concrete, Sealed |
| CT | Ceramic Tile (Wall) |
| EP | Epoxy Paint |
| EXP | Exposed Ceiling |
| MAT | Modular Carpet Walk Off Mat |
| P | Paint |
| PT | Porcelain Tile |
| QT | Quarry Tile |
| RB | Resilient Base |
| RES | Resinous Flooring and Base |
| RF | Rubber Flooring |
| RFT | Resilient Floor Tile |
| RSF | Resilient Sheet Flooring - Heterogeneous |
| RWC | Rigid Wall Covering (Wall Protection) |
| SD | Static Dissipative Tile |
| S | Solid Surface Fabrication |
| WSF | Welded Seam Sheet Flooring - Homogeneous |
Doors and Hardware Notes Doors and Hardware Notes
| General Notes | |
| A. | Refer to Lease Design Narrative (LDN) Appendix for Hardware Groups and Modifiers which are added to numeric hardware group assignments to indicate a variation to |
| the group. | |
| B. | All doors to be 7'-0" high, unless otherwise noted. |
| C. | Coordinate acoustical requirements for doors with required wall acoustical ratings as shown in Room Data Matrix - Interior Finishes in Appendix. |
| Schedule Notes | |
| 1. | Hollow metal frame cased opening |
| 2. | Two door (in swing and swing out) acoustical door and frame assembly. |
| 3. | Two doors required at this room/space. |
| 4. | Narrow lite optional. Use insulated or laminated glass to meet acoustical criteria. |
| 5. | Provide STC 50 rated acoustical door. |
| 6. | No door in this room/space. |
| 7. | Equal leaf pair of doors. |
| 8. | Lead lined door and hardware. |
| 9. | Space may be a room or area within another room. Omit door if space is not a separate room. |
Electrical Notes
ELECTRICAL NOTES
POWER NOTES LIGHTING NOTES
| P1. | Multiple receptacles above and below desk for device charging, receptacles provided with Pre-Fab system. | L1. | EMI/RFI emissions to be controlled |
| P2. | Receptacles on all walls | L2. | Dimmable to 5 fc |
| P3. | Coordinate electrical connections with equipment to be installed. Receptacles on all walls. | L3. | May not have ceiling - then use industrial fixture type |
| P4. | Plug strip at 44" above counters | L4. | May not have ceiling. If no ceiling, use industrial fixture type |
| P5. | Multiple receptacles above and below desk for device charging | L5. | Treat like a store. Adjustable lighting, General lighting. |
| P6. | Cord reel(s) for freestanding workbenches | L6. | No ceiling in these rooms. No prescription for lighting. |
| P7. | All outlets on dedicated circuits. |
| P8. | Cord reel(s) for freestanding workbenches |
| P9. | Treadmill on dedicated circuit |
| P10. | Each hood on dedicated circuit |
| P11. | Provide receptacles per equipment plan |
| P12. | Electrical to review redundancy requirements with OIT guidelines. |
| P13. | Receptacle above ceiling for overhead lift |
| P14. | Recessed power quad floor box |
| P15. | L21-20R receptical above each rack |
| P16. |
Mechanical Notes
MECHANICAL HVAC NOTES
| M1. | Intentioanlly Left Blank |
| M2. | Per ASHRAE 62 for ventilation, and FGI Guidelines for NC |
| M3. | General Open Office area |
| M4. | General Open/Public area |
| M5. | Per ASHRAE 62 for ventilation if interior enclosed space. |
| M6. | Comply with ASHRAE 15 if Special Refrigeration Systems are used |
| M7. | If chemicals are used, provide specialized exhaust |
| M8. | Data Center |
| M9. | Transfer air to Food Prep Kitchen |
| M10. | Intentioanlly Left Blank |
| M11. | MEP Room |
| M12. | See USP-797 and -800 |
| M13. | Counter-height specialized exhaust system required |
| M14. | Provide air conditioning and ventilation per imaging manufacturer recommendations |
| M15. | General Office Area |
| M16. | Verify specific vendor/manufacturer requirements. |
| M17. | Non-ferrous construction |
| M18. | Provide cooling only air terminal unit to serve the manual equipment wash room. |
| M19. | Provide a dedicated wet exhaust system |