This document contains a price schedule for a multiple award task order contract (MATOC) replacement solicitation. It includes maximum hourly ceiling rates for various labor categories over a five year period, with rates separated by level of experience. Indirect cost rates are also included, with overhead and general/administrative rates proposed as a percentage. Profit rates are provided on a sliding scale based on the rough order of magnitude of the task order, ranging from 75 thousand to over 5 million dollars. The solicitation number and details are provided for the General Services Administration Public Buildings Service Region 10 opportunity to replace its existing MATOC.
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6. VOL IV-PRICE SCHEDULE
VOLUME IV: PRICE PROPOSAL
| MATOC PRICE SCHEDULE | Maximum Hourly Ceiling Rates | ||||||
| MATOC - DIRECT LABOR RATES - UNBURDENED | |||||||
| ITEM # | LABOR DISCIPLINES | UNIT | YEAR 1 | YEAR 2 | YEAR 3 | YEAR 4 | YEAR 5 |
| Construction Foreman | |||||||
| 0001 | Early Career (< 5 years) | HR | |||||
| 0002 | Mid Career (5 - 10 years) | HR | |||||
| Construction Superintendent (Site) | |||||||
| 0003 | Early Career (< 5 years) | HR | |||||
| 0004 | Mid Career (5 - 10 years) | HR | |||||
| 0005 | Experienced (10 - 20 years) | HR | |||||
| Commercial Construction Superintendent | |||||||
| 0006 | Early Career (< 5 years) | HR | |||||
| 0007 | Mid Career (5 - 10 years) | HR | |||||
| 0008 | Experienced (10 - 20 years) | HR | |||||
| Construction Manager | |||||||
| 0009 | Early Career (< 5 years) | HR | |||||
| 0010 | Mid Career (5 - 10 years) | HR | |||||
| 0011 | Experienced (10 - 20 years) | HR | |||||
| Construction Project Manager | |||||||
| 0012 | Early Career (< 5 years) | HR | |||||
| 0013 | Mid Career (5 - 10 years) | HR | |||||
| 0014 | Experienced (10 - 20 years) | HR | |||||
| Sr. Project Manager (>10 years experience) | |||||||
| 0015 | Experienced (10 - 20 years) | HR | |||||
| MATOC - INDIRECT COSTS | |||||||
| 0016 | Overhead, General and Administrative (G&A) | % | |||||
| Proposed Profit Table | |||||||
| 0017 | ROM: $75k - 250k | % | |||||
| 0018 | ROM: 250k - 750k | % | |||||
| 0019 | ROM: $750k - $1.5M | % | |||||
| 0020 | ROM: $2M - $5M | % | |||||
| *ROM = Rough Order of Magnitude |