This document is the Special Provisions exhibit for a maintenance paving project issued by the Oregon Department of Transportation (ODOT) District 2C. The work encompasses grind and inlay paving operations at three locations: US26 westbound between the OR35 junction and Government Camp (two separate segments totaling approximately 4,000 linear feet) and Timberline Highway northbound and southbound (approximately 9,000 linear feet). The project scope includes cold planing asphalt concrete pavement to a 2-inch depth, placing a 2-inch Level 3 dense asphalt concrete inlay, providing temporary pavement markings, and laying out permanent striping to match existing conditions. Work is restricted to weekday hours Monday through Thursday from sunrise to sunset, excluding holidays unless approved by the Project Manager. All work must be completed by September 15, 2026. The contractor is required to submit a project schedule at least seven days prior to the preconstruction meeting and must provide a recently approved ODOT asphalt mix design for review at the same timeframe.
The contractor bears responsibility for locating suitable staging and equipment storage locations, though coordination with ODOT yards is available through Shane Jansen. All quantities listed in the bid are estimates provided as guides only, and ODOT reserves the right to adjust quantities or add and delete items as needed. Critical technical requirements include achieving a minimum compaction rate of 91 percent of MAMD, meeting pavement surface flatness tolerances of 1/8 inch when tested with a 12-foot straightedge, and providing weigh slips for each load of asphalt material placed. The contractor must implement quality control and quality assurance procedures and bears the cost of replacing any rejected material. All work must comply with the 2024 Oregon Standard Specifications for Construction, and the contractor is responsible for adherence to all applicable OSHA regulations, ANSI Z 133.1 safety standards, and Manual of Uniform Traffic Control Devices requirements. Invoicing and certified payroll documents should be submitted to the Agency Authorized Representative at the listed ODOT District 2C address.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Intent to Award 1.xlsx | XLSX spreadsheet | |
| Preliminary Bid Results~82.xlsx | XLSX spreadsheet | |
| Attachment A Form A-2 - Bid Pricing Form~1.xlsx | XLSX spreadsheet | |
| 00017241_Invitation to Bid.docx | DOCX document | |
| Attachment B - Sample Contract~4.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US26 & Timberline Hwy Maintenance Pave
Special Provisions 1
SPECIAL PROVISIONS FOR
US26: Government Camp – OR35 Jct. MP 53.9 to MP 57.5
HWY 174, Timberline Rd, MP 2.7 to MP 4.4 Maintenance Pave (Multiple Locations)
DESCRIPTION OF WORK
COMPLETION OF WORK
Complete all work to be done in the contract no later than September 15, 2026.
SCOPE OF WORK
The work to be done in this contract consists of the following:
1. Grind and inlay the following locations US26 westbound between OR35 Jct. to Government Camp and Timberline Hwy
a) US26 westbound MP 53.9 – MP 54.3 lane and right turn lane and one foot of the left and right shoulders. Approximately 1,700ft.
b) US26 westbound MP 57.2 – MP 57.5, left lane. Approximately 2300ft.
c) Timberline Hwy northbound and southbound MP 2.7 – MP 4.4 lanes and one foot of shoulders, approximately 9,000ft.
2. Cold Plane ACP removal 2” depth as specified.
3. Pave 2” depth inlay. Level 3 – ½ inch ACP.
4. ODOT will provide necessary traffic control to complete the work.
5. Contractor shall provide temporary pavement markings.
6. Contactor shall layout permanent striping to match existing striping.
7. ODOT will provide permanent pavement markings.
8. Work hours are weekday Monday through Thursday from sunrise to sunset excluding holidays unless approved by the Project Manager.
9. Comply with the 2024 Oregon Standard Specification for Construction
LOCATION OF WORK
The project is located as specified in the maps below.
Special Provisions 2
Figure 1: Vicinity of 2" Grind and Inlay on US26 / Timberline Hwy, multiple locations between Government Camp and
OR35 Jct.
Figure 2: Site Map of Approximate Grind and Inlay location a) westbound MP 53.9 – MP 54.3
Special Provisions 3
Figure 3: Site Map of Approximate Grind and Inlay location b) westbound MP 57.2 – MP 57.5
Figure 4: Site Map of Approximate Grind and Inlay Area c) Timberline Road northbound and southbound MP 2.7 –
MP 4.4
Special Provisions 4
STOCKPILE AND STAGING LOCATIONS
Contractor will be responsible for locating suitable locations for storing equipment throughout the project area. There is potential opportunity at ODOT yards for staging and shall be coordinated through Shane Jansen 503-799-3621
APPLICABLE SPECIFICATIONS
The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Special Provisions. Sections of the technical specifications not identified in the Plans and Special Provisions remain applicable to the Contract according to their original terms.
Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Plans and Special Provisions as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
Standard Drawings referenced in the Standard Specifications are available at:
http://www.oregon.gov/odot/engineering/pages/standards.aspx
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
CLASS OF PROJECT
This is a State Project.
Special Provisions 5
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the 2024 Standard Specifications.
SECTION 00220 – ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the Mount Hood Hwy and Timberline Hwy when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
• Weekdays Monday through Thursday, sunrise to sunset.
00220.40(e)(2)(b) Special Events - Add the following to the end of this subsection:
The following special events will occur during this Project:
• Hood to Coast – August 28th – 29th, 2026. Contractor to verify dates.
SECTION 00221 – COMMON PROVISIONS FOR WORK ZONE TRAFFIC
CONTROL
Comply with Section 00221 of the Standard Specifications.
SECTION 00225 – TEMPORARY PAVEMENT MARKINGS
Install temporary pavement markings in accordance with Section 00225 of the Standard Specifications. No separate measurement or payment will be made for Temporary pavement Markings and should be considered incidental to the Level 3, ½ inch dense ACP.
SECTION 00280 – EROSION AND SEDIMENT CONTROL
Perform any necessary environmental protection in accordance with the 2024 Standard Specifications. Any work or materials needed for erosion and sediment control will be considered incidental to the project. No separate or additional payments will be made for erosion and sediment control.
SECTION 00290 – ENVIRONMENTAL PROTECTION
Perform any necessary environmental protection in accordance with the 2024 Standard Specifications. Any work or materials needed for environmental protection will be considered incidental to the project. No separate or additional payments will be made for environmental protection.
SECTION 00620 – COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
Special Provisions 6
00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:
Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00744.51.
SECTION 00730 – EMULSIFIED ASPHALT TACK COAT
Comply with Section 00730 of the Standard Specifications, modified as follows:
00730.90 Payment – Replace this subsection, except for the name and number, with the following:
No separate measurement or payment will be made for tack coat and should be considered incidental to the Level 3, ½ inch ACP.
SECTION 00744 – ASPHALT CONCRETE PAVEMENT
Comply with Section 00744 of the Standard Specifications, modified as follows:
00744.16 Sampling and Testing – Replace this subsection, except for the subsection number and title, with the following:
When required under 00744.17, have a CAT-I perform a minimum of one of each of the following test methods as modified in the MFTP per day
• Asphalt Content – AASHTO T 308 with ODOT TM 323 determined Calibration Factor
• Gradation – AASHTO T 30
• Mix Moisture – AASHTO T 329
• Maximum Specific Gravity – AASHTO T 209
Provide test results to the Project Manager by the middle of the following work shift. The Project Manager may waive the requirement for any of AASHTO T 308, AASHTO T 30, AASHTO T 329, AASHTO T 209, and ODOT TM 326 on a daily basis.
Provide samples or split samples to the Project Manager when requested.
00744.17 Acceptance – Replace this subsection, except for the subsection number and title, with the following:
The mixture will be accepted by visual inspection by the Project Manager. If the mixture is considered suspect, the Project Manager may request verification that the mixture is within tolerances and limits of 00744.14. When requested by the Project Manager, provide sampling and testing according to 00744.16. If the test result for each mix gradation constituent, asphalt content, and density measurement is within the specification limits, the material will be accepted. If the asphalt content, one or more gradation constituents, or the density measurement are not within the specification limits, the material that is not within the specification limits will be accepted according to 00150.25.
00744.49 Compaction - Replace this subsection, except for the subsection number and title, with the following:
Special Provisions 7
Contractor shall meet the compaction requirements listed in this section of a minimum of 91% of MAMD. Contractor shall be responsible to provide quality control and quality assurance for the project. The Project Manager reserves the right to take and test material samples, and based upon such test results, to reject any material not meeting the referenced Specifications. It is agreed and understood that the contractor shall replace all rejected material with material meeting the Specifications at no additional cost to the State.
Add the following subsections:
00744.51 Opening Section to Traffic - Schedule Work so that, during the same shift, the surfaces being paved are paved full width and length through the wearing Course before opening to traffic.
SUPPLEMENTAL SPECIAL PROVISIONS
1. The quantities in the bid items list intended to serve only as a guide to bidders and are not to be construed as a guarantee. All quantities are estimated and are for bid purposes only. The quantities for each bid item include all labor, equipment and materials for all activities associated with this project. The Oregon Department of Transportation (ODOT) reserves the right to adjust quantities and add or delete, as needed.
2. ODOT Maintenance will provide traffic control and shall coordinate with Government Camp Maintenance for this work.
3. Contractor shall provide a schedule to the Project Manager at least seven (7) days prior to the preconstruction meeting to allow for review.
4. Contractor shall schedule a pre-construction meeting with the Project Manager at least seven (7) days prior to the proposed start of construction.
5. Contractor shall provide a recently approved ODOT asphalt mix design for Level 3, ½ inch dense, ACP at least seven (7) days prior to the pre-construction meeting for review.
The submittal shall be the Oregon Department of Transportation Materials Laboratory approval form.
6. Contractor shall provide weigh slips for each load of ACP material placed in performance of Work under contract. Contractor shall collect weight slips during shift and give the group of them to the inspector at the end of shift.
7. Contractor will follow all oversize traffic restrictions as specified by the Commerce and Compliance Division, Over-Dimension Operations guidelines. ODOT will submit the mobility restriction request for the project. Any schedule changes will be subject to the approval of the mobility restriction notice. Contractor schedules will be subject to the approval of the mobility restriction notice. Over Dimensional Restriction notices need to be submitted at least 35 days before work begins.
Special Provisions 8
8. Contractor shall furnish a 12 foot straight edge. Test with a 12 foot straight edge parallel to and perpendicular to the centerline and at joints as directed. The pavement surface shall not vary by more than ¼ inch. District 2C manager will determine when corrective action from section 00744.75 of the Oregon Standard Specifications for Construction for pavement roughness is acceptable for the project.
9. Contractor shall be responsible to provide quality control and quality assurance for the project. The contractor shall meet the compaction requirement listed in section 0744.49 of a minimum of 91% of MAMD. The Project Manager reserves the right to take and re-test material samples, and based on such test results, to reject any material not meeting the referenced Specifications. It is agreed and understood that the Contractor shall replace all rejected material with material meeting the Specifications at no additional cost to the State.
10. Defective pavement will be repaired, at no additional cost to the state, according to the Region 1 Maintenance: Guideline for Pavement Restoration or Defective Work.
11. All new transverse joints pavement edges shall be sand sealed. This work will be considered incidental to the bid item “Level 3, ½ inch ACP”.
12. No separate measurement or payment will be made for tack coat and should be considered incidental to the bid item “Level 3, ½ inch ACP”.
13. No separate measurement or payment for temporary pavement markers will be made and should be considered incidental to the bid item “Level 3, ½ inch ACP.
14. Contractor is responsible for layout of all new lines in the same location and configuration as all existing lines. Cost to control work to meet this responsibility is incidental to the bid item “Level 3, 1/2 Inch ACP”.
15. Contractor shall submit invoices and certified payroll documents to the Project Manager via email, reference the ODOT project name in the subject line.
16. Contractor’s employees and their subcontractors shall not wear clothing, hats, vests, ect. that have the ODOT name or “flying T” symbol.
17. There is public interest in the work. Contractor is advised to use courtesy and respect in any work site interaction with the public and to refer all public relation matters to the ODOT Project Manager.
18. Contractor shall implement safety policies, procedures and practices in conformance with all applicable local, state, and federal laws, rules and regulations including but not limited to:
a. Applicable OSHA safety regulations
b. ANZI Z 133.1 Safety standards agreed upon by ODOT and local jurisdiction
c. The Manual of Uniform Traffic Control Devices (MUTCD)
d. Any other applicable safety laws, regulations and codes
Special Provisions 9
19. All equipment utilized during this contract shall be in good and serviceable condition.
20. In addition to notifications required under the Standard Specifications and Special
Provisions, Contractor will also:
a. At least 72 hours prior to executing lane and/or complete closures notify:
The Project Manager, Jason McNeil: (503) 702-9080
b. At the time of lane and/or complete roadway closure and again when the lane and/or complete roadway is open notify:
ODOT Traffic Management Operations Center (TMOC): (503) 283-5859
21. Correspondence for the project is required to have the project name in the subject line.
22. The invoices, certified payrolls (if applicable) and project submittals are to be via email to the Agency Authorized Representative:
Jason.P.MCNEIL@odot.oregon.gov
23. Invoices must have the following certified statement on the along with a signature by the Contractor’s Authorized Representative.
“I the undersigned, herby certify that the above bill is true and correct and that payment has not been received. Signature:_____________________________”
24. Invoices are to have the contract number and service period listed on them and the following billing address: