This file contains Special Provisions for Maintenance Highway Construction issued by the Oregon Department of Transportation (ODOT) for the US97 WIM Sensor and Pavement Replacement Project in Klamath Falls, located on the Dalles-California Highway in Klamath County, Oregon. The project consists of five primary work components: installing temporary traffic control, removing existing portland cement concrete and asphalt concrete pavement with replacement sections, installing Weigh In Motion (WIM) equipment, installing permanent pavement markings, and performing additional incidental work. The contract specifies a single contract time of 21 consecutive calendar days for removal, installation, and activation of the WIM system, with a substantial completion date of June 4, 2027, and a final completion date of June 27, 2027. ODOT will furnish agency materials including eight WIM sensors, grounding kits, epoxy, and one pan-tilt-zoom camera, available 90 calendar days after contract award at a specified Bend, Oregon location. The project manager is Jason Armstrong (jason.l.armstrong@odot.oregon.gov, 541-883-5789). Traffic lane closures are permitted only during specified periods: single lane closures on US97 between 7 p.m. and 7 a.m., Sunday night through Friday morning, with all lanes to remain open during daytime hours and holidays.
Liquidated damages of $700 per calendar day apply for failure to achieve substantial completion by the specified date, with additional liquidated damages of $500 per 15-minute interval per lane for any lane closures exceeding permitted limits. The Special Provisions incorporate the 2024 Oregon Standard Specifications for Construction and reference multiple sections addressing traffic control, pavement removal and installation, electrical systems, and fasteners. All work must comply with the Manual on Uniform Traffic Control Devices (MUTCD), National Cooperative Highway Research Program (NCHRP) Report 350 or AASHTO MASH standards for crashworthiness, and applicable electrical codes including the National Electrical Code (NEC). The document specifies requirements for traffic control supervisors who must hold current Oregon Certified TCS cards, automated flagger assistance devices from a qualified products list, and personnel performing WIM sensor installation must provide proof of training from sensor manufacturer Intercomp Company. No separate payment will be made for erosion and sediment control, environmental protection, or emulsified asphalt tack coat; these costs are included within other contract items.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit 6 Plans~3.pdf | ||
| 00018455 ITB.docx | DOCX document | |
| 00018455 Sample Contract.docx | DOCX document | |
| 00018455 ATT A Form A-2 Bid Pricing Form~2.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
FOR MAINTENANCE HIGHWAY CONSTRUCTION
OREGON DEPARTMENT OF TRANSPORTATION
SALEM, OREGON
PAVING & SIGNAL
US97
WIM SENSOR AND PAVEMENT REPLACEMENT PROJECT
(KLAMATH FALLS)
DALLES – CALIFORNIA HIGHWAY
KLAMATH COUNTY
November 2026
US97 WIM SENSOR AND PAVEMENT REPLACEMENT PROJECT (KLAMATH FALLS)
WORK TO BE DONE
The Work to be done under this Contract consists of the following:
1. Install temporary traffic control.
2. Remove existing PCC and AC pavement with new pavement sections.
3. Install Weigh In Motion (WIM) equipment.
4. Install permanent pavement markings.
5. Perform additional and Incidental Work as called for by the
Specifications and Plans.
APPLICABLE SPECIFICATIONS
The 2024 Oregon Standard Specifications for Construction (“Standard Specifications”) include detailed technical specifications in Sections 00200 and beyond that apply to this ITB and any resulting Contract. Some sections of the technical specifications may be identified and modified in the Plans and Special Provisions. Sections of the technical specifications not identified in the Plans and Special Provisions remain applicable to the Contract according to their original terms.
Sections in Part 00100 of the Standard Specifications (General Conditions) are not applicable to the Contract unless they are specifically identified in the Plans and Special Provisions as being applicable. However, if a Part 00100 section that has been identified as being applicable references another section in Part 00100, or a technical specification (Parts 00200 and beyond) references a section from Part 00100, that section from Part 00100 applies to the Contract for purposes of supporting and giving full effect to the specification that referenced it. Bidders can access the Standard Specifications online at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
Standard drawings referenced in the Standard Specifications/Special Provisions are available at:
http://www.oregon.gov/ODOT/Engineering/Pages/Standards.aspx
OWNERS AUTHORIZED REP (PROJECT MANAGER)
Jason Armstrong - jason.l.armstrong@odot.oregon.gov (541) 883-5789
SUBSTANTIAL COMPLETION DATE: 04th of June, 2027
FINAL COMPLETION DATE: 27th of June, 2027.
CONTRACT TIME: There is one Contract Time on this Project as follows:
The Contractor shall complete all Work to be done under the Contract, required to complete the removal, installation, and activation of the Weigh in Motion system, as shown before the elapse of 21 consecutive Calendar Days and no later than substantial completion date.
Recording of Calendar Days will begin when the Weigh in Motion system is taken out of service.
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx http://www.oregon.gov/ODOT/Engineering/Pages/Standards.aspx mailto:jason.l.armstrong@odot.oregon.gov
Agency-Furnished Material:
The Agency will furnish the following Equipment that will be available to the Contractor 90 Calendar Days after Contract Award. ODOT ITS personnel must be present during pick-up.
Located at 63055 N Highway 97, Building H Bend, OR 97703. Contact Ryan Groshong at
541.815.4948 to schedule pick-up at least one week in advance.
• Weigh-in-Motion sensors (1.75 meters long), grounding kits, and epoxy (quantity of 8).
• Pan-Tilt-Zoom camera with mounting brackets and power supply (quantity of 1).
Liquidated Damages:
Failure to achieve Substantial Completion by the time specified above for Substantial Completion will result in damage to the State of Oregon. Since actual damage will be difficult to determine, it is agreed that the Contractor shall pay to the State of Oregon, not as a penalty but as liquidated damages, $700 per calendar day for each day elapsed in excess of the Substantial Completion date specified in Section 3 of this Agreement until Substantial Completion is achieved.
In addition, it is impractical to determine the actual damages Owner will sustain in the event traffic lanes are closed beyond the limits listed in Section 00220.40(e) of Attachment B – Special Provisions. Therefore, Contractor shall pay to Owner, not as a penalty, but as liquidated damages, $500 per 15 minutes, or for a portion of 15 minutes, per lane, for any lane closure beyond the limits listed in 00220.40(e). In addition to the liquidated damages, all added costs for traffic control measures, including flagging, required to maintain the lane closures beyond the allowed time limits, will be at no additional cost to Owner. The required traffic control measures will be as determined by Owner. Owner will determine when it is safe to reopen lanes to traffic.
Assessment of these liquidated damages will stop when all lanes have been safely reopened.
TABLE OF CONTENTS FOR SPECIAL PROVISIONS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT
ATTENUATORS
SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING
SECTION 00280 - EROSION AND SEDIMENT CONTROL
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00305 - CONSTRUCTION SURVEY WORK
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
SECTION 00331 - SUBGRADE STABILIZATION
SECTION 00440 - COMMERCIAL GRADE CONCRETE
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
SECTION 00641 - AGGREGATE SUBBASE, BASE, AND SHOULDERS
SECTION 00730 - EMULSIFIED ASPHALT TACK COAT
SECTION 00744 - ASPHALT CONCRETE PAVEMENT
SECTION 00857 - RUMBLE STRIPS
SECTION 00860 - LONGITUDINAL PAVEMENT MARKINGS - Paint
SECTION 00960 - COMMON PROVISIONS FOR ELECTRICAL SYSTEMS
SECTION 00985 – ITS ELECTRICAL SYSTEM INSTALLATION
SECTION 02560 - FASTENERS
FOR
Paving & Intelligent Transportation Systems US97 WIM Sensor and Pavement Replacement Project
The Dalles-California Highway Klamath County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Temporary Traffic Control and Permanent Pavement Markings. Modified Special Provisions were prepared by me or under my supervision.
Sections 00220, 00221, 00222, 00223, 00224, 00225, 00226, 00228 & 00860
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
2026.10.28 13:29:13 -07'00'
FOR
Paving & Intelligent Transportation Systems US97 WIM Sensor and Pavement Replacement Project
The Dalles-California Highway Klamath County
PROFESSIONAL OF RECORD CERTIFICATION:
I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Jeff Shambaugh. Modified Special Provisions were prepared by me or under my supervision.
Section(s) 00331, 00620, 00641, 00730, and 00744.
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
Jeff Shambaugh Digitally signed by Jeff Shambaugh Date: 2026.10.28 16:13:17 -07'00'
FOR
Paving & Intelligent Transportation Systems US97 WIM Sensor and Pavement Replacement Project
The Dalles-California Highway Klamath County
PROFESSIONAL OF RECORD CERTIFICATION:
Seal w/signature I certify the Special Provision Section(s) listed below are applicable to the design for the subject project for Intelligent Transportation Systems. Modified Special Provisions were prepared by me or under my supervision.
Sections 00960, 00985, 02560
FINAL ELECTRONIC DOCUMENT AVAILABLE UPON REQUEST
2026.10.27 15:41:14 -07'00'
SECTION 00210 - MOBILIZATION
Comply with Section 00210 of the Standard Specifications modified as follows.
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
Comply with Section 00220 of the Standard Specifications modified as follows:
00220.01(b) Abbreviations - Delete this subsection.
00220.02(a) General Requirements - Add the following bullet(s) to the end of the bullet list:
When performing trench excavation or other excavation across or adjacent to a Traffic Lane on a Roadway having a pre-construction posted speed greater than 35 mph, backfill the excavation, install Surfacing, and open the Roadway to traffic by the end of each work shift.
Install a "BUMP" (W8-1-48) sign approximately 100 feet before the backfilled area and a "ROUGH ROAD" (W8-8-48) sign approximately 500 feet ahead of the "BUMP" sign. If this requirement is not met, maintain all necessary lane or shoulder closures and provide additional TCM, including flagging, at no additional cost to the Agency. Do not use temporary steel plating to reopen the Roadway.
When an abrupt edge is created by excavation, protect traffic according to the "Excavation Abrupt Edge" and the "Typical Abrupt Edge Delineation" configurations shown on the Standard Drawings.
When paving operations create an abrupt edge, protect traffic by installing a "DO NOT PASS" (R4-1) sign before the Work Area at sign spacing "A" from the TCD Spacing Table" shown on the Standard Drawings. Alternate "ABRUPT EDGE" (CW21-7) signs with appropriate (CW21-8) rider and "DO NOT PASS" (R4-1) signs at 1/2 mile spacings. Install a "BUMP" (W8-1) sign 100 feet prior to the transverse paving edge.
Protect traffic by grinding and inlaying existing longitudinal rumble strips before staging traffic across them. Grind and inlay existing rumble strips according to the "Existing Rumble Strip Removal" detail shown on the Standard Drawings. Use Level 2, 1/2 inch ACP, or as directed.
Protect pedestrians in pole base excavation areas by placing approved covers over all pole base excavations. Place a minimum of two B(II)LR barricades adjacent to and on either side of the excavated area, facing pedestrian traffic, or place covers and barricades as directed.
00220.02(b) Temporary Pedestrian Accessible Route Plan - Replace the title of this subsection with “Temporary Pedestrian Accessible Route”
Replace the paragraph that begins "For the safety and accessibility …" with the following paragraph:
For the safety and accessibility of pedestrians, provide and maintain TPAR for pedestrian pathways impacted by construction or construction staging, and the following:
Replace the bullet that begins "TPAR shall meet …" with the following bullet:
• Meet the requirements of Part 6 of the MUTCD.
Replace the bullet that begins "Mount signs between the panels…" with the following bullet:
• Mount signs between the panels of a Type II barricade, on a PCD, or on a single-post temporary sign support, as shown. Place signs facing pedestrian traffic.
Add the following bullet(s) to the end of the bullet list:
• Maintain access to bus stops and Pedestrian Accessible Routes.
00220.40(e)(1) Closed Lanes - Replace this subsection, except for the subsection number and title, with the following:
Traffic Lanes may be closed on the Dalles - California Highway US97 when allowed, shown, or directed during the following periods of time except as specified in 00220.40(e)(2):
Single Lane Closures - One Traffic Lane on the Dalles-California Highway (US97) may be closed during the following times:
• Nightly, Sunday night through Friday morning, between 7 p.m. and 7 a.m.
00220.40(e)(2) Opened Lanes - Replace the paragraph that begins "Keep all Traffic Lanes and …" with the following paragraph:
Keep all Traffic Lanes and pedestrian facilities open during the following periods. Remove all barricades and objects from the Roadway during the periods that Traffic Lanes are to remain open.
00220.40(e)(2)(a) Holidays - Replace the paragraph that begins "When a holiday falls …" with the following paragraph:
When a holiday falls on Sunday, the following Monday is recognized as a legal holiday. When a holiday falls on Saturday, the preceding Friday is recognized as a legal holiday.
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
Comply with Section 00221 of the Standard Specifications modified as follows:
00221.05 Regulations and Codes - Replace this subsection with the following subsection:
Provide all electrical Equipment, Materials, and Work conforming to NEC requirements and all other laws that apply.
00221.06 Traffic Control Plan - Replace this subsection with the following subsection:
00221.06 Traffic Control Plan and Tourist-Oriented Directional and Business Logo Signs -
(a) Traffic Control Plan - Submit one of the following, 5 Calendar Days before the preconstruction conference:
(1) Agency Traffic Control Plan - If the Contractor intends to use the Agency TCP without modification, a written notification indicating that the Agency TCP will be used without modification.
(2) Contractor-Modified Traffic Control Plan - The Contractor may request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor. Do not use a modified TCP, or a TCP developed by the Contractor, unless approved by the Engineer.
Use the Agency TCP unless a modified TCP, or a TCP developed by the Contractor is accepted.
The Engineer is not obligated to consider any modified Agency TCP or a TCP developed by the Contractor. The Agency will not be liable to the Contractor for failure to accept or act upon any request for a modified Agency TCP or a TCP developed by the Contractor.
To conserve time and funds, the Contractor may first submit a written request for a preliminary review by the Engineer. The request should contain a description of the proposal together with a rough estimate of anticipated dollar and time impacts. The Engineer will, within a reasonable time, respond to the Contractor in writing whether or not the request would be considered by the Agency.
Meet all requirements of the Contract documents and comply with the Project transportation management plan (TMP) if requesting a Contractor-modified Agency TCP, or a Contractor developed TCP. Provide the following information:
• Stamped Working Drawings according to 00150.35 that include the proposed TCP showing all TCM and quantities of TCD.
• A TPAR plan that includes:
• Details and features used to provide pedestrian accessibility.
• Pedestrian staging Plans at a scale no smaller than 1 inch = 50 feet.
• Temporary alternate facilities or detour routes for pedestrian traffic.
• Staging sequences and details for Work affecting vehicular, pedestrian, and bicycle traffic.
• Proposed order and duration of the TCM.
• A detailed temporary striping plan.
If the Contractor’s request to use a Contractor-modified Agency TCP, or a TCP developed by the Contractor is approved in whole or in part, acceptance will be made by a Change Order.
The Engineer will establish prices that represent a fair measure of the value of Work to be added, changed, or deleted as a result of any accepted modifications to the Agency TCP or an accepted TCP developed by the Contractor.
Once a TCP has been accepted by the Engineer, submit any additional modifications for Agency review following the procedure described above. The Engineer is not obligated to consider additional modifications to a previously approved TCP.
(b) Tourist-Oriented Directional and Business Logo Signs - Submit one of the following for approval, at least 5 Calendar Days before the preconstruction conference:
(1) No Signs - If there are no tourist-oriented directional (TOD) or business logo signs on the Project, a written notification that no TOD or business logo signs exist within the Project limits or
(2) Signs - Submit one copy of a sketch map of the Project showing all existing TOD and business logo signs and a written narrative describing how these signs will be kept in service and protected throughout all the construction stages. If modifications are necessary, submit updated information to the Engineer for approval at least 21 Calendar Days before the change is needed.
00221.10 General - Replace the paragraph that begins “All Work Zone TCD shall…” with the following paragraph:
Provide Work Zone TCD complying with the crashworthiness requirements of the National Cooperative Highway Research Program (NCHRP) Report 350 or with the AASHTO Manual for Assessing Safety Hardware (MASH).
00221.20 Safety Apparel - Replace the paragraph that begins “Workers, except flaggers, working …” with the following paragraph:
Workers, except flaggers, working within Highway Right of Way and exposed to traffic or construction Equipment are required to wear high visibility safety apparel that meets the Performance Class requirements of the most current version of ANSI/ISEA 107, American National Standard for High Visibility Safety Apparel and Headwear Devices. Wear safety apparel that at least meets the following minimum requirements:
00221.40 General - Replace the paragraph that begins “Existing operational TCD’s shall remain…” with the following paragraph:
Maintain existing TCD’s in operation throughout the Contract or until replaced by new, permanent TCD as appropriate.
00221.60 Temporary Traffic Control Devices - Replace the paragraph that begins “TCD delivered to the Project Site found…” with the following paragraph:
Repair or replace TCD delivered to the Project Site found to be in “marginal” or “unacceptable” condition, at no additional cost to the Agency.
00221.90(b) Temporary Protection and Direction of Traffic – Replace the bullet that begins “Providing, Surfacing, maintain…” with the following bullet:
• Providing, surfacing, maintaining, removing, and restoring the TPAR.
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
Comply with Section 00222 of the Standard Specifications modified as follows:
00222.10 Temporary Signs - Replace the paragraph that begins "Furnish temporary signs meeting …" with the following paragraph:
Furnish temporary signs meeting the requirements of the "Acceptable" category shown in the ATSSA Quality Guidelines for Temporary Traffic Control Devices and Features handbook, available from the ATSSA website. Use Materials and fabricate signs according to Section 00940, Section 02910 and the following:
00222.11(b) Portable Sign Supports - Replace the paragraph that begins "Use portable sign supports …" with the following paragraph:
Use portable sign supports from the QPL and according to the following:
00222.12(b) Permanent Signs - Replace the paragraph that begins "Sign covers for permanent signs …" with the following paragraph:
Provide sign covers for permanent signs according to Section 00941.
00222.13 Sign Flags - Replace the paragraph that begins "Sign flags shall be …" with the following paragraph:
Provide sign flags that are:
00222.40(e) Temporary Sign Placement - Add the following to the end of the bullet list:
Install a 54-inch "TRUCKS LEAVING HIGHWAY XXXX FT" sign, when construction vehicles are leaving a Roadway, in advance of each entrance point to the Work Area at sign spacing “A” from the “TCD Spacing Table” shown on the Standard Drawings.
Install a 54-inch "TRUCKS ENTERING HIGHWAY XXXX FT" sign, when construction vehicles are entering a Roadway, in advance of each exit point from the Work Area at sign spacing “A” from the “TCD Spacing Table” shown on the Standard Drawings.
Install "ROAD WORK AHEAD" (W20-1-48) signs with a 36 by 24-inch "FINES DOUBLE"
(R2-6aP) rider on The Dalles - California Highway, according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans except do not install the "FINES DOUBLE" rider on concrete barrier mounted signs.
Install beyond each end of the Project, facing outgoing traffic, an "END ROAD WORK"
(CG20-2A-24) sign a distance of (A ÷ 2) according to the "TCD Spacing Table" shown on the Standard Drawings or as modified by the Plans.
For paving operations on non-freeways, place “ABRUPT EDGE” (CW21-9) and “ROAD
WORK XX MPH” (CW20-1a) signs as shown. Use an “XX” value equal to 10 mph below the current posted regulatory speed. If a speed is posted for a temporary regulatory speed reduction, that speed is the current posted regulatory speed.
For all other moving operations that do not create an abrupt edge adjacent to traffic, omit the
“ABRUPT EDGE” signs.
During concrete removal and pavement reconstruction operations on The Dalles California Highway, install temporary signing and other required TCD as shown. Install temporary speed zone signing according to and as shown in the Temporary Speed Zone Order.
Add the following subsection:
00222.40(f) Temporary Speed Zone Reduction - Install a temporary regulatory speed zone, as directed. Use regulatory signs for all required temporary speed zone signage.
00222.41(d) Temporary Sign Supports - Replace the bullet that begins "Provide reflective sheeting …" with the following bullet:
• Furnish reflective sheeting on TSS posts as shown in the Standard Drawings.
00222.45(b) Portable Changeable Message Signs - Replace the bullet that begins "Messages shall not scroll …" with the following bullet:
• Do not use messages that scroll horizontally or vertically across the face of the sign.
00222.90 Payment - Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing, installing, moving, operating, maintaining, inspecting, and removing the Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
SECTION 00223 - WORK ZONE TRAFFIC CONTROL LABOR AND VEHICLES
Comply with Section 00223 of the Standard Specifications modified as follows:
00223.00 Scope - Replace this subsection, except for the subsection number and title, with the following:
In addition to the requirements of Section 00221, this Work consists of providing flaggers, traffic control supervisors, and providing, operating, and maintaining associated Work Zone traffic control vehicles.
00223.22 Flagger Station Lighting - Replace the paragraph that begins "Use flagger station lighting …" with the following paragraph:
Use flagger station lighting from the QPL and according to the following:
Replace the bullet that begins "Illuminates the flagger so that …" with the following bullet:
• Illuminate the flagger station so that it is visible, and is discernable as a flagger station, from a distance of 1,000 feet.
Replace the bullet that begins "Illuminates the flagger from above …" with the following bullet:
• Illuminate the flagger station from above at a height of 18 feet ± 3 feet.
00223.23 Automated Flagger Assistance Device - Replace the paragraph that begins "Furnish an automated flagger …" with the following paragraph:
Provide an automated flagger assistance device (AFAD) from the QPL. Submit the following information for approval for the use of an AFAD to the Engineer, according to 00150.37, a minimum of 21 Calendar Days in advance of using an AFAD. The Engineer will respond within 14 Calendar Days after receipt of the submittal.
00223.26 Pedestrian Transport Vehicle - Replace the bullet that begins "A roof or post-mounted rotating …" with the following bullet:
• A roof or post-mounted rotating amber light or strobe light that is visible for 360 degrees.
Provide a light that is visible and functioning at all times while operating within the Project limits.
00223.31(a) Traffic Control Supervisor - Replace the paragraph that begins "When the Schedule of Items …" with the following paragraph:
When the Schedule of Items includes an item for a TCS, provide a TCS who meets the requirements of 00223.30. Do not designate the Project superintendent as the TCS. The TCS is required to possess a current ODOT "Oregon Certified Traffic Control Supervisor" card. A TCS with a current card from another state's transportation department, or from the American Traffic Safety Services Association, may obtain an Oregon Certified TCS card upon successful completion of ODOT's Recertification Class.
Replace the paragraph that begins "Before beginning Work …" with the following paragraph:
Before beginning Work on the Project, the TCS is required to:
Replace the bullet that begins "File with the Engineer and …" with the following bullet:
• File with the Engineer and local police, their name and a telephone number where the TCS can be contacted at all times.
Replace the bullet that begins "If the Contractor requests to …" with the following bullet:
• If the Contractor requests to use a modified Agency TCP or a TCP developed by the Contractor, ensure stamped Working Drawings showing the revisions are submitted according to 00221.06 and 00150.35.
Replace the paragraph that begins "The TCS shall not act as …" with the following paragraph:
The TCS cannot perform the duties of a flagger or pilot car operator, except in the event of an emergency. The TCS may relieve the flagger or pilot car operator for a period of less than 15 minutes, not to exceed 1 hour per construction work shift.
Replace the paragraph that begins "Make arrangements so that the …" with the following paragraph:
Make arrangements so that the TCS is available every Day, on call at all times, and available upon the Engineer's request at other than normal working hours.
Replace the paragraph that begins "The TCS shall report to the …" with the following paragraph:
The TCS is required to report to the Project Site within 1 hour after being notified in the event of a Work Zone incident during non-work periods. Have appropriate personnel, Equipment, and Material available at all times to expeditiously correct any deficiency in the TCM for the Project.
Replace the paragraph that begins "Notify the Engineer of an alternate …" with the following paragraph:
Notify the Engineer of an alternate TCS who can assume the duties of the assigned TCS in the event of that person's inability to fulfill the duties of the position. Provide an alternate TCS adequately trained and certified according to 00223.30 and 00223.31.
Notify the Engineer at least 12 hours before designating the TCS for the following 12-hour period. Make succeeding notifications within 24 hours every time a subsequent TCS is appointed to the Project.
00223.31(b) Traffic Control Inspection Without TCS - Replace the paragraph that begins "When the Schedule of Items does …" with the following paragraph:
When the Schedule of Items does not include an item for a TCS, or when TCS is not on-site for a work shift, designate a trained person who is on the Project Site during work hours and on call at all other times, and who:
Replace the bullet that begins "Notifies the Engineer of any …" with the following bullet:
• Notifies the Engineer of any corrective measures made to the TCP if the TCP is not functioning as required, or to accommodate site conditions. Follow the TCP and do not implement changes to the TCP before revisions are approved by the Engineer.
Replace the bullet that begins "Shall report to the Project …" with the following bullet:
• Reports to the Project Site within 1 hour after being notified in the event of a Work Zone incident during non-work periods.
Replace the bullet that begins "Designate an area for …" with the following bullet:
• Designates an area for pedestrians to wait for, load and unload the transport vehicle.
00223.32 Automated Flagger Assistance Device Operator - Replace this subsection, except for the subsection number and title, with the following:
Use a certified flagger who has been trained in the operation of the AFAD.
The AFAD operator duties include:
• Attending the AFAD at all times during the operation of the device.
• Not flagging traffic and operating an AFAD at the same time.
• Operating a single AFAD. Each AFAD is required to have a separate AFAD operator.
00223.40 Flaggers - Replace this subsection, except for the subsection number and title, with the following:
Locate flaggers far enough in advance of the Work Area to permit adequate time for the motorist to respond to the flagger's instructions. All flaggers, including advance flaggers, are required to use a STOP/SLOW paddle. Do not use roll-up STOP/SLOW paddles for non-emergency flagging operations.
During advance flagging operations, the advance flagger is required to only display the "SLOW" face of the paddle. Cover the "STOP" face of the paddle with a sign cover according to 00222.12(a).
Position flaggers, as directed, at locations where traffic can enter the Highway within the limits of the Work Zone.
Direct vehicles entering the Highway to follow the pilot car line.
Direct pedestrians to wait for flagger instructions. Stop and hold motor vehicle traffic to allow pedestrians to enter the TPAR or exit the TPAR. Ensure pedestrians are clear of all Traffic Lanes before flaggers release motor vehicle traffic.
Direct pedestrians to use the pedestrian transport vehicle to pass through or around the Work Zone. Direct pedestrians to wait for the pedestrian transport vehicle in designated areas identified under 00223.31.
If a TPAR is designed and installed with a width less than 5 feet, and 5-foot-by-5-foot passing spaces at 200-foot intervals are not provided, inform pedestrians of the narrowed TPAR. Before allowing pedestrians in wheelchairs or similar devices to use the TPAR, direct the flagger at the opposite end of the TPAR to stop and hold opposing pedestrian traffic until the pedestrian in the wheelchair has reached the other end of the narrowed TPAR.
Provide flaggers at flagging stations continuously or until the Engineer determines flagging is no longer required.
00223.41 Flagger Station Lighting - Replace this subsection, except for the subsection number and title, with the following:
Provide continuous flagger station lighting for nighttime flagging as follows:
• Locate the light Equipment on the same side of the Roadway as the flagger station between 5 and 10 feet from the edge of the Traffic Lane, on or beyond the Roadway Shoulder, or as directed.
• Position and orient the flagger station lighting to direct the maximum amount of light toward the flagger station and away from the approaching traffic in the near lane.
• Aim all of the luminaires directly at the flagger station.
• Increase the output wattage or number of luminaires as the luminance from, and number of, surrounding and background lights increases. Do not provide a total output greater than 2,500 watts, unless otherwise directed.
00223.43 Automated Flagger Assistance Device - Replace this subsection, except for the subsection number and title, with the following:
Use the AFAD to control traffic through the Work Zone and as follows:
• Position the AFAD operator’s control location a safe distance from traffic.
• Install and operate the AFAD according to the manufacturer’s instructions and as shown.
• Do not use the AFAD to control more than one lane of approaching traffic. If necessary, close additional Traffic Lanes, left turn lanes or right turn lanes approaching the AFAD to limit approaching traffic to one lane.
• Provide flagger station lighting when using an AFAD during nighttime hours. Provide flagger station lighting according to 00223.22 and 00223.41.
• Do not use an AFAD to replace a continuously operating temporary traffic control signal.
The Engineer may order adjustments to the operation of the AFAD or substitute flagging for the AFAD based on traffic delay, field conditions, and safety concerns.
• When providing an AFAD for each direction of traffic, use AFADs of the same type and from the same manufacturer.
• When an AFAD is not in use during a work shift either turn it off or switch the yellow lens to flash mode. When the AFAD is not in use for more than one work shift, remove it and all accompanying signing from the Roadway.
00223.80 Measurement - Replace the bullet that begins ”The replacement of TCD and TCM…” with the following bullet:
• The replacement of flagger station lighting damaged by Public Traffic and replaced by the Contractor.
Add the following paragraph to the end of the bullet list:
No additional measurement will be made for automated flagger assistance devices damaged by Public Traffic and replaced or repaired by the Contractor.
00223.90 Payment - Replace the paragraph that begins "Item (c) includes furnishing…" with the following paragraph:
Item (c) includes providing, operating, moving, and removing the flagger station lighting.
No separate or additional payment will be made for backup unit in event it is used or not.
Replace the paragraph that begins "Item (f) includes furnishing…" with the following paragraph:
Item (f) includes furnishing, operating, maintaining, repairing, replacing moving and removing each AFAD device, regardless of size or type. No separate or additional payment will be made for AFAD replacement or repair. The AFAD operator will be paid for as a flagger.
Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing, installing, moving, operating, maintaining, inspecting, and removing the Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
SECTION 00224 - TEMPORARY TRAFFIC CHANNELIZING DEVICES
Comply with Section 00224 of the Standard Specifications modified as follows:
00224.00 Scope - Replace this subsection, except for the subsection number and title, with the following:
In addition to requirements of Section 00221, this Work consists of providing, installing, moving, maintaining, inspecting, and removing channelizing devices including, but not limited to, tubular markers, conical markers, surface mounted tubular markers, plastic drums, and delineators throughout the Project area as shown or specified.
00224.14 Delineators - Replace the paragraph that begins "Use new delineators from …" with the following paragraph:
Use new delineators from the QPL or salvaged reflectorized delineators (W-1) or (Y-1), as appropriate, and according to the requirements of Section 00840 and the following:
00224.90 Payment - Replace the paragraph that begins "Item (a) includes …" with the following paragraph:
Item (a) includes providing and installing the complete assembly of each device in its initial location and for removing the device from the surface.
Replace the paragraph that begins "Item (b) includes …" with the following paragraph:
Item (b) includes providing new or refurbished devices to replace damaged or missing devices.
Replace the paragraph that begins "In item (e), the type …" with the following paragraph:
In item (e), the type of barricade is inserted in the blank.
Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing, installing, moving, operating, maintaining, inspecting, and removing the Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
SECTION 00225 - TEMPORARY PAVEMENT MARKINGS
Comply with Section 00225 of the Standard Specifications modified as follows:
00225.40 Temporary Pavement Markers - Replace the paragraph that begins "Temporary pavement markers..." with the following paragraph:
Maintain temporary pavement markers in place until the permanent markings are complete.
Replace damaged or missing markers when directed by the Engineer. On the final Pavement wearing Course and along final alignment, place permanent markings a maximum of 28 Calendar Days after placing temporary pavement markers, or as directed.
00225.45 Pavement Marking Removal - Replace the bullet that begins "Do not use grinding to …" with the following bullet:
• Do not use grinding to remove stripes, durable markings, legends, or bars from the wearing Course or existing surfaces, unless the area is paved over, obliterated, or the pavement markings are replaced to match the original striping configuration.
00225.60 Temporary Traffic Pavement Markings - Replace the paragraph that begins "Temporary pavement markings …" with the following paragraph:
Maintain temporary pavement markings in place until the permanent markings are complete.
Replace missing or damaged temporary markings when directed by the Engineer. On the final Pavement wearing Course and along final alignment, place permanent markings a maximum of 28 Calendar Days after placing temporary pavement markings, or as directed.
Replace the paragraph that begins "If permanent pavement …" with the following paragraph:
If permanent pavement markings are not placed within 28 Calendar Days after placing temporary pavement markings, replace missing or damaged temporary pavement markings on wearing Course and along final alignment at no additional cost to the Agency, unless otherwise directed.
00225.80 Measurement - Replace the paragraph that begins "(a) Unit Basis - Temporary …" with the following paragraph:
(a) Unit Basis - Temporary reflective pavement markers, temporary flexible pavement markers, and temporary pavement legends, will be measured on the unit basis, by actual count.
00225.90 Payment -
Replace the paragraph that begins “Item (a)…” with the following paragraph:
Item (a) includes installation and removal of temporary pavement markers having either one or two reflective faces.
Replace the paragraph that begins “Item (b)…” with the following paragraph:
Item (b) includes installation of flexible temporary pavement markers and removal of flexible temporary pavement markers and temporary flexible pavement marker covers.
Add the following paragraph after the paragraph that begins “Item (b)…”:
Items (c) and (e) include removal of the temporary tape.
Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing and placing all Materials, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
SECTION 00226 - TEMPORARY ROADSIDE BARRIERS AND IMPACT ATTENUATORS
Comply with Section 00226 of the Standard Specifications modified as follows:
00226.00 Scope - Replace this subsection, except for the subsection number and title, with the following:
In addition to the requirements of Section 00221, this Work consists of providing, installing, moving, operating, maintaining, and removing guardrail, barrier, and impact attenuators for temporary traffic control, as shown and directed.
00226.11(a)(2) Temporary Concrete Barrier - Replace the paragraph that begins "The concrete barrier shall …" with the following paragraph:
Provide concrete barrier with functioning scuppers, unless otherwise approved.
00226.12 Temporary Impact Attenuators - Replace this subsection, except for the subsection number and title, with the following:
Provide temporary impact attenuators from the QPL and as shown on the Standard Drawings.
00226.23 Truck Mounted Attenuator - Replace the title of this subsection with “Temporary Impact Attenuator, Truck Mounted”.
Replace the paragraph that begins "The support vehicle …" with the following paragraph:
Provide a support vehicle for a TL-2 rated TMA with a minimum weight of 9,900 pounds.
Provide a support vehicle for a TL-3 rated TMA with a minimum weight of 22,000 pounds.
Replace the paragraph that begins "If used in a mobile …" with the following paragraph:
If a TMA support vehicle is used in a mobile operation, maintain a consistent distance from the mobile operation, as shown in Table 00226-1, or as directed.
00226.43 Truck Mounted Attenuator - Replace the title of this subsection with “Temporary Impact Attenuator, Truck Mounted”.
Replace the paragraph that begins “When workers or construction Equipment…” with the following paragraph:
If a Contractor elects to use a truck mounted impact attenuator (TMA) when not required, place the TMA in advance of the exposed workers or Equipment, located as shown in the TMA Support Vehicle Placement tables, or as directed.
00226.63 Truck Mounted Attenuators - Replace this subsection with the following subsection:
00226.63 Temporary Impact Attenuator, Truck Mounted - Repair damage to support vehicles that TMAs are mounted on at no additional cost to the Agency.
00226.90 Payment -
Replace the paragraph that begins "In items (a) and (b), the …" with the following paragraph:
In items (a) and (b), the type of guardrail or terminal is inserted in the blank.
Replace the paragraph that begins "Item (e) includes Type 5 …" with the following paragraph:
Item (e) includes Type 5 delineators, including removing and replacing Type 5 delineators on the barriers, as necessary. Item (e) also includes providing, installing, connecting, securing, unsecuring, maintaining, temporary storage, and final removal of the Temporary Barrier, including Minimum Deflection Temporary Barrier.
Replace the paragraph that begins "Item (f) includes Type …" with the following paragraph:
Item (f) includes Type 5 delineators, including removing and replacing Type 5 delineators on the barriers, as necessary. Item (f) also includes providing, installing, connecting, securing to the Bridge deck, unsecuring, maintaining, temporary storage, and final removal of the Minimum Deflection Bridge Temporary Barrier.
Add the following paragraphs after the paragraph that begins "In items (g) and (h)…":
Payment for items (g) performed beyond the quantity shown in the Contract Schedule of Items will be made at the Contract unit price if the Engineer determines that the Contract unit price does not exceed the value of the Work as determined according to Section 00197. If the Engineer determines that the Contract unit price exceeds the value of the Work, payment for the Additional Work will be made according to 00195.20.
Replace the paragraph that begins "In items (g) and (h) …" with the following paragraph:
In items (g) and (h), the type of attenuator is inserted in the blank.
Replace the paragraph that begins "In item (i), the …" with the following paragraph:
In item (i), the words "Sand Module" or the type of attenuator is inserted in the blank.
Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing, stockpiling, installing, moving, operating, maintaining, inspecting, placing, and removing the Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
Add the following paragraph to the end of this subsection:
No separate or additional payment will be made for TMAs when the Contractor elects to use them where they otherwise are not required.
SECTION 00228 - TEMPORARY PEDESTRIAN AND BICYCLIST ROUTING
Comply with Section 00228 of the Standard Specifications modified as follows:
00228.40 Pedestrian Channelizing Devices - Replace this subsection, except for the subsection number and title, with the following:
Install PCD as shown or directed. Provide a continuous route by interconnecting all adjacent PCD. Provide a clean unobstructed path for pedestrians according to 00220.02 and MUTCD requirements.
00228.80 Measurement - Replace this subsection, except for the subsection number and title, with the following:
The quantities of Work performed under this Section will be measured according to the following. The quantities for Work Zone Traffic Control Measures will be limited to the following:
• The initial installation of Pedestrian channelizing devices and bicycle channelizing devices necessary to complete the Project based on the Contract Schedule of Items further limited to the maximum simultaneous use as shown, specified, or directed.
• The initial installation of additional Pedestrian channelizing devices and bicycle channelizing devices that the Engineer and Contractor agree are necessary to ensure a safe Work Zone.
• The replacement of TCD and TCM damaged by Public Traffic and replaced by the Contractor.
(a) Length Basis - Pedestrian channelizing devices and bicycle channelizing devices will be measured on the length basis upon delivery to the Project.
(b) Unit Basis - Temporary curb ramps will be measured on the unit basis, at each location where a temporary curb ramp is constructed or placed as shown or directed.
(c) Area Basis - Temporary walks will be measured on the area basis, at each location where a temporary walk is constructed or placed limited to the Neat Lines as shown or directed.
00228.90 Payment - Replace this subsection, except for the subsection number and title, with the following:
The accepted quantities of Work performed under this Section will be paid for at the Contract unit price, per unit of measurement, for the following items:
Pay Item Unit of Measurement
(a) Pedestrian Channelizing Devices ......................................................... Foot
Payment for items (a) will be payment in full for furnishing, installing, moving, operating, maintaining, inspecting, and removing the Materials and TCD, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified, except as covered in 00221.90(b).
TCD items included under this Section damaged by Public Traffic and replaced by the Contractor will be paid for at the Contract price for the Pay Items listed in the Contract Schedule of Items or in approved Contract Change Orders, unless otherwise specified. Payment for replacing damaged TCD will only be made when:
• The Engineer orders it.
• The replacement devices are used on the Project.
• The damaged devices are disposed of to the Engineer's satisfaction.
SECTION 00280 - EROSION AND SEDIMENT CONTROL
Comply with Section 00280 of the Standard Specifications modified as follows:
00280.06 Erosion and Sediment Control Manager - Delete this subsection.
00280.90 Payment – Replace this subsection, except for the subsection number and title, with
No separate or additional payment will be made for erosion and sediment control.
SECTION 00290 - ENVIRONMENTAL PROTECTION
Comply with Section 00290 of the Standard Specifications modified as follows:
00290.90 Payment – Replace this subsection, except for the subsection number and title, with
No separate or additional payment will be made for environmental protection.
SECTION 00305 - CONSTRUCTION SURVEY WORK
Comply with Section 00305 of the Standard Specifications.
SECTION 00310 - REMOVAL OF STRUCTURES AND OBSTRUCTIONS
Comply with Section 00310 of the Standard Specifications.
SECTION 00331 - SUBGRADE STABILIZATION
Comply with Section 00331 of the Standard Specifications modified as follows:
00331.10 Materials - Replace the Material that begins “Aggregate Base…” with the following Material:
Aggregate Base 02630.10
00331.90 Payment - Replace the paragraph that begins "The depth of stabilization …" with the following paragraph:
The depth of stabilization is inserted in the blank.
Replace the paragraph that begins "Payment will be payment …" with the following paragraph:
Payment will be payment in full for furnishing and placing all Materials, and for providing all Equipment, labor, and Incidentals necessary to complete the Work as specified.
SECTION 00440 - COMMERCIAL GRADE CONCRETE
Comply with Section 00440 of the Standard Specifications modified as follows:
00440.11 Proportions - Replace the paragraph that begins "Furnish, in writing to the Engineer …" with the following paragraph:
Provide, in writing to the Engineer, the proportions by weight of the following Materials before using any CGC:
• 00440.12 Properties of Commercial Grade Concrete - Replace the bullet that begins “Entrained Air…” with the following bullet:
• Entrained Air - 4.0 to 7.0 percent Entrained air not required for precast elements utilizing dry cast mix designs.
00440.13 Field-Mixed Concrete - Replace the paragraph that begins "CGC Work items listed in 00440.14(a)…" with the following paragraph:
CGC Work items listed in 00440.14(a) may be field-mixed conventionally, or by volumetric/mobile mixers according to ASTM C685. When approved, concrete sidewalks, concrete curb ramps, concrete driveways, and other flat concrete surfaces may be field-mixed using volumetric/mobile mixers according to ASTM C685, request approval prior to placement.
For all other CGC applications, submit written request to the Engineer for approval to use volumetric/mobile mixers according to ASTM C685 at least 21 Days prior to placement.
00440.14(a) General - Replace the paragraph that begins "Acceptance sampling…" with the following paragraph:
Acceptance sampling and testing is based on tests performed by the Contractor’s QCT from samples obtained at the site of placement from the discharge of the delivery vehicle.
00440.40(b) Placing - Replace the paragraph that begins "Place CGC…" with the following paragraph:
Place CGC according to the appropriate Sections where CGC is required and the following:
00440.40(c) Forms - Replace the paragraph that begins "Provide forms for CGC …" with the following paragraph:
Provide forms for CGC according to the appropriate Sections where CGC is required and best common practices. Place to the lines and grades shown or directed.
00440.40(e) Curing - Replace this subsection, except for the subsection number and title, with the following:
Cure CGC for a minimum of 7 Calendar Days by one of the following methods:
Cover with wet burlap, canvas, Sand, or other acceptable Material, and keep moist.
Apply curing compounds at a rate of not less than 1 gallon per 150 square feet. Do not use on surfaces that come into contact with adjacent pours and avoid overspray on exposed reinforcement. Use curing compounds according to the following:
Table 00440-1 Table
00440-1 Section
Item Type 1 or 1-D
(Clear)
Type
(White- Pigmented)
00480 Drainage Curbs * * 00599 Slope Paving Curbs and Berm
Paving Yes No
00759 Walks, Curb Ramps, Driveways, Surfacings, Curbs, and Islands
SECTION 00620 - COLD PLANE PAVEMENT REMOVAL
Comply with Section 00620 of the Standard Specifications modified as follows:
00620.43 Maintenance Under Traffic - Replace this subsection, except for the subsection number and title, with the following:
Traffic is not allowed on the cold planed surface. Before opening the area to traffic, pave the surface according to 00744.51.
SECTION 00641 - AGGREGATE SUBBASE, BASE, AND SHOULDERS
Comply with Section 00641…