This is a specification and bidding document for the City of Minneapolis Convention Center Parking Facility Repairs 2027 Construction project, prepared by Walker Consultants. The project involves comprehensive repairs and improvements to a 301' x 114' parking structure located at 1301 Second Avenue South, Minneapolis, Minnesota, consisting of five levels of cast-in-place concrete with a post-tensioned, one-way slab-and-beam floor system. Work includes concrete floor, ceiling, beam, joist, column, and wall repairs; expansion joint repair and replacement; crack and joint sealing; traffic coating application; post-tensioning barrier cable replacement; mechanical drainage improvements; electrical allowance work; painting; and related restoration activities. Unit price work items are listed across multiple categories with specified quantities, including floor repair operations (220 square feet partial depth, 45 square feet curbs/walks, 75 stair nosing repairs), concrete ceiling repair (6 square feet), beam repair (10 square feet), column repair (40 square feet), expansion joint work (10 linear feet premolded, 20 linear feet elastomeric, 30 linear feet header repair), crack and joint sealing (320 linear feet seal cracks, 205 linear feet repair sealant, 620 linear feet cove sealant), traffic topping (800 square feet partial recoat, 250 square feet complete recoat), barrier cable replacement (4,800 linear feet), and various other specialized repairs. The bid forms indicate that bids must remain open for 60 days after bid opening, with bidders required to submit within 15 days after the Owner's Notice of Award, and work quantities are subject to Owner adjustment of up to 25% at unit prices bid.

The contract documents specify unit price bidding methodology with mobilization as a lump sum item paid on a percentage-earned schedule, with payment not to exceed 25% upon execution, 50% when billing reaches 10-25% of original contract amount, 75% when billing reaches 25-50%, and 100% when billing reaches 50% or greater. Bid security is required, and bidders must submit within 7 days of bid opening a substitution listing, equipment suppliers' listing, list of alternates, unit prices, non-collusion affidavit, list of subcontractors, and bidders' qualification statement for structural restoration work. The specifications comply with City of Minneapolis General Conditions and Requirements, ACI standards for concrete work, OSHA and ANSI health and safety regulations, and various material manufacturer standards. The Owner reserves the right to delete any section of work and to increase or decrease quantities up to 25% at the stated unit prices, with variations beyond 25% subject to supplementary conditions. Final payment is based on actual approved work performed as measured in place, with testing and inspection services arranged and paid for by the Owner through a pre-approved testing agency.

View the file

Other files

File Type Posted
Event_4391_-_Pre-Bid_Meeting_Information.pdf PDF
Responsible_Contractor_Forms.pdf PDF
Event_4391_-_Drawings.pdf PDF
Event_4391_-_Call_for_Bids.pdf PDF
Event_4391_-_Bid_Form.xlsx XLSX spreadsheet
BID-MCC_-_Parking_Facility_Repairs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

City of Minneapolis

Convention Center Parking Facility Repairs 2027

Construction Documents

July 2027

Walker Project No: MN 21-005657.00

Convention Center Parking Facility Repairs 2027 Construction Documents 21-005657.00 July 22, 2027

©2026, Walker Consultants. All rights reserved.

SEALS PAGE 00 01 07- 1

SECTION 00 01 07 - SEALS PAGE

Professional Engineer:

Firm Name: Walker Consultants

Structural Engineer: Walker Consultants 7760 France Avenue South, Suite 820 Minneapolis, MN 55435

I hereby certify that these specifications were prepared by me or under my supervision and that I am duly licensed Professional Engineer under the laws of the State of Minnesota.

Patrick Lewis, P.E., License No. 50914

END OF SECTION 00 01 07

©Copyright 2026. All rights reserved. No part of this document may be reproduced in any form or by any means without permission from Walker Consultants.

UNIT PRICE WORK ITEMS 00 43 00-1

SECTION 00 43 00 – UNIT PRICE WORK ITEMS

WORK

ITEM DESCRIPTION UNITS QUANTITY

UNIT

PRICE

1.0 GENERAL REQUIREMENTS

1.1 Project Mobilization L.S. 1 $

3.0 CONCRETE FLOOR REPAIR

3.1 Floor Repair - Partial Depth/Shallow S.F. 220 $

3.4 Floor Repair - Curbs/Walks S.F. 45 $

3.7 Floor Repair - Concrete Washes S.F. 5 $

3.10 Floor Repair - Stair Nosing Repair EA. 75 $

3.11 Floor Repair - Slab-on-Grade S.F. 35 $

4.0 CONCRETE CEILING REPAIR

4.1 Ceiling Repair - Partial Depth/Shallow S.F. 6 $

5.0 CONCRETE BEAM AND JOIST REPAIR

5.1 Beam Repair - Partial Depth/Shallow S.F. 10 $

6.0 CONCRETE COLUMN REPAIR

6.1 Column Repair - Partial Depth/Shallow S.F. 40 $

6.7 Column/Slab Repair – Grout Plugs S.F. 35 $

7.0 CONCRETE WALL REPAIR

7.1 Wall Repair - Partial Depth/Shallow S.F. 120 $

10.0 EXPANSION JOINT REPAIR AND

REPLACEMENT

10.1 Expansion Joint - Premolded (Floor to Floor) L.F. 10 $

10.3 Expansion Joint - Elastomeric Concrete Edged L.F. 20 $

10.10 Expansion Joint - Header Repair L.F. 30 $

11.0 CRACK AND JOINT REPAIR

11.1 Seal Cracks and Joints L.F. 320 $

11.2 Repair Crack/Joint Sealant L.F. 205 $

11.3 Vertical Joint Sealant L.F. 10 $

11.7 Cove Sealant L.F. 620 $

16.0 TRAFFIC TOPPING

16.4 Traffic Topping - Recoat (Partial System) S.F. 800 $

16.5 Traffic Topping - Recoat (Complete System) S.F. 250 $

21.0 P/T SYSTEM REPAIR - MONOSTRAND

21.13 Replace Barrier Cable L.F. 4800 $

25.0 MECHANICAL - DRAINAGE

25.3 Mechanical - Pipe and Hangers L.F. 25 $

30.0 ELECTRICAL - LIGHTING

30.1 Electrical – Allowance (Replace Junction Box) E.A. 3 $

45.0 PAINTING

45.4 Paint Doors and Frames E.A. 1 $

45.6 Paint Structural Steel L.S. 1 $

UNIT PRICE WORK ITEMS 00 43 00-2

WORK

ITEM

DESCRIPTION UNITS QUANTITY UNIT

PRICE

74.0 JOINT AND SEALANT REPAIR

74.11 Install Preformed Joint Sealant L.F. 405 $

84.0 EIFS FAÇADE

84.1 Repair Existing EIFS Cladding S.F. 20 $

95.0 DOORS AND WINDOWS

95.5.1 Re-Align Door Frame Assembly E.A. 1 $

TOTAL $

END OF SECTION 00 43 00

© Copyright 2026. All rights reserved. No part of this document may be reproduced in any form

TABLE OF CONTENTS 00 01 10 - 1

SECTION 00 01 10 – TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING AGREEMENTS

INTRODUCTORY INFORMATION

00 01 07 Seals Page 00 01 10 Table of Contents 00 01 15 List of Drawing Sheets

PROCUREMENT REQUIREMENTS

00 41 00 Bid Forms 00 43 00 Unit Price Work Items

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 Administration Requirements 01 11 10 Summary of Work - Restoration

DIVISION 02 – EXISTING CONDITIONS

02 00 10 Work Items 02 51 30 General Concrete Surface Preparation 02 51 40 Surface Preparation for Patching

DIVISION 03 – CONCRETE

03 30 21 Cast-in-Place Concrete Restoration 03 37 60 Prepackaged Repair Mortar

DIVISION 05 – METALS

05 16 17 Strand Guardrail System

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 18 00 Traffic Coatings 07 91 00 Preformed Joint Sealants 07 92 33 Concrete Joint Sealants 07 95 00 Expansion Joint Assemblies

DIVISION 09 – FINISHES

09 91 13 Exterior Painting

DIVISION 22 - PLUMBING

22 05 00 Common Work Results for Plumbing 22 14 13 Facility Drainage and Vent Piping

TABLE OF CONTENTS 00 01 10 - 2

DIVISION 26 - ELECTRICAL

26 05 00 Common Work Results for Electrical

END OF SECTION 00 01 10

LIST OF DRAWING SHEETS 00 01 15 - 1

SECTION 00 01 15 - LIST OF DRAWING SHEETS

Sheet No. Title

R – Restoration R-001 General Notes, Legends, & Work Item Schedule R-101 Level 1 Plan R-102 Level 2 Plan R-103 Level 3 Plan R-104 Level 4 Plan R-105 Level 5 Plan R-106 Level 6 Plan R-501 Repair Details R-502 Repair Details R-503 Repair Details

END OF SECTION 00 01 15

BID FORMS 00 41 00-1

VBSECTION 00 41 00 - BID FORMS

30.1 INSTRUCTIONS

Submit Bids on this Bid Form in accordance with Instructions to Bidders.

30.2 BID FORM

PART 1 - TERMS OF BID

PROJECT IDENTIFICATION: Convention Center Parking Facility Repairs 2027

THIS BID IS SUBMITTED TO: Marcus Travis

A. The undersigned BIDDER proposes and agrees, if this Bid is accepted, to enter into an Agreement with OWNER in form included in Contract Documents to complete all Work as specified or indicated in Contract Documents for Contract Price and within Contract Time indicated in this Bid and in accordance with Contract Documents.

B. BIDDER accepts all of terms and conditions of Instructions to Bidders, including without limitation those dealing with disposition of Bid Security. BIDDER will sign Agreement and submit Contract Security and other documents required by Contract Documents within 15 days after date of OWNER's Notice of Award. This Bid will remain open for 60 days after day of Bid opening.

C. In submitting this Bid, BIDDER represents, as more fully set forth in Agreement, that:

1. BIDDER has examined copies of all Contract Documents and of following addenda:

Date Number

(receipt of all of which is hereby acknowledged) and also copies of Advertisement or Invitation to Bid or Instructions to Bidders.

2. BIDDER has examined site and locality where Work is to be performed, legal requirements (federal, state and local laws, ordinances, rules and regulations) and conditions affecting cost, progress or performance of Work and has made such independent investigations as BIDDER deems necessary.

3. This Bid is genuine and not made in interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; BIDDER has not directly induced or solicited any other Bidder to submit false or sham Bid;

BIDDER has not solicited or induced any person, firm or corporation to refrain from bidding; and BIDDER has not sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER; and

BID FORMS 00 41 00-2

4. BIDDER agrees that Work Item quantities are estimates and that OWNER may increase or decrease these quantities at unit prices stated, so long as increases or decreases in Base Bid do not exceed 25% of Base Bid price. Increases or decreases beyond these limits shall be in accordance with Supplementary Conditions, Division 00.

5. BIDDER agrees that all alterations or additions to Work shall be performed in accordance with paragraph “Changes” and/or “Construction Change Directives” under Section "Supplementary Conditions."

6. OWNER reserves right to delete any Section of Work.

D. BIDDER agrees that Work shall be substantially completed and fully completed on or before dates or within number of calendar days indicated in Agreement.

shall be substantially completed on or before , 20 and fully completed by , 20 shall be substantially completed within ____ calendar days after date when Contract Time commences to run, and fully completed within ____ calendar days after date when Contract Time commences to run.

BIDDER accepts provisions of Agreement as to liquidated damages in event of failure to complete Work on time.

E. BIDDER will complete Work for following price(s) based on unit prices stated in Division 00:

LUMP SUM CONTRACT PRICE _________________________________________

(use words)

________________________DOLLARS $ _________________________________

(figures)

F. BIDDER will complete Work for the prices shown in Section "List of Unit Prices."

BID FORMS 00 41 00-3

G. Communications concerning this Bid shall be addressed to: (BIDDER to provide bidder’s name, address, telephone number and name of individual familiar with this Bid and able and authorized to answer questions regarding this Bid.)

H. Terms used in this Bid which are defined in General Conditions of Construction Contract included as part of Contract Documents have meanings assigned to them in General Conditions.

SUBMITTED ON

, 20

PART 2 - MATERIAL AND EQUIPMENT ALTERNATES

Base Bid proposal price shall include materials and equipment selected from designated items and manufacturers listed. The purpose of this requirement is to establish uniformity in bidding and to establish standards of quality for items named.

If BIDDER wishes to quote alternate items for consideration by Owner, it may do so under this Section. Complete description of item and proposed price differential must be provided. Unless approved at time of award, substitutions where items are specifically named will be considered only as negotiated change in Contract Sum.

WORK ITEM DESCRIPTION OF ALTERNATE ITEM(S)

ADD/DEDUCT

AMOUNT

BID FORMS 00 41 00-4

PART 3 - TIME ALTERNATE

If BIDDER takes exception to time stipulated in Part 1, Terms of Bid, it shall stipulate below its proposed time for performance of Work. Consideration will be given to time in evaluating Bids.

BIDDER agrees that Work shall be substantially completed within ____ calendar days after date when Contract Time commences to run, and fully completed within ____ calendar days after date when Contract Time commences to run.

PART 4 - ATTACHMENTS

Following documents are attached to and made condition of this Bid, unless noted otherwise:

A. Required Bid Security in form of:

B. Substitution listing per the requirements of the Instructions to Bidders within 7 days after the day of the Bid opening.

C. Equipment Suppliers' Listing.

D. List of alternates/alternatives.

E. List of Unit Prices.

F. Non-Collusion Affidavit.

G. A list of Subcontractors and other persons and organizations required to be identified, if so requested, per the requirements of the Instructions to Bidders within 7 days after the day of the Bid opening.

H. Required Bidders Qualification Statement for Structural Restoration Work with supporting data per requirements of Instructions to Bidders within 7 days after day of Bid opening. Use form attached to Section "Instructions to Bidders." Copies of previously prepared statements on this form which are less than 12 months old will be acceptable.

BID FORMS 00 41 00-5

PART 5 - SIGNATURES

If BIDDER is:

An Individual

By ____________________________________________________________ (SEAL) (Individual's Name) doing business as ______________________________________________________

Business Address: _____________________________________________________

Phone Number: _______________________________________

A Partnership

By ____________________________________________________________ (SEAL) (Firm Name)

(General Partner)

(General Partner)

Business Address: _____________________________________________________

Phone Number: _______________________________________

BID FORMS 00 41 00-6

A Corporation

By __________________________________________________________________ (Corporation Name)

(State of Incorporation)

By __________________________________________________________________ (Name of Person Authorized to Sign)

(Title)

(Corporate Seal)

Attest ________________________________________________________________ (Secretary)

Business Address: _____________________________________________________

Phone Number: _______________________________________

A Joint Venture

By __________________________________________________________________ (Name)

(Address)

By _________________________________________________________________ (Name)

(Address)

Each joint venture member must sign. The manner of signing for each individual partnership and corporation that is party to joint venture should be in manner indicated above.

END OF SECTION 00 41 00

ADMINISTRATIVE REQUIREMENTS 01 00 00 - 1

SECTION 01 00 00 – ADMINISTRATIVE REQUIREMENTS

1.1 CONTRACTUAL

A. Project consists of providing all materials, labor, equipment, supervision and services to perform repairs and improvements to the Convention Center Parking Facility located in Downtown in Minneapolis, Minnesota.

B. Contractor shall perform the work in accordance with the Owner-provided executed contract with the Owner and these Contract Documents.

C. City of Minneapolis General Conditions and Requirements, latest edition, shall govern conduct of the contract. Where discrepancies may be encountered, the General Conditions and Requirements shall control.

1.2 PROJECT MANAGEMENT AND COORDINATION

A. Coordinate construction to ensure efficient and orderly installation of each part of the Work.

B. Conduct progress meetings at Project site at Owners request. Contractor, Owner and Engineer to agree on meeting dates and times. Require attendance of each subcontractor, major supplier or other entity concerned with current progress or involved with planning or coordination of future activities. Contractor shall record minutes and distribute to parties involved, including Owner and Engineer, within 3 working days of the meeting.

1.3 SUBMITTAL PROCEDURES

A. Shop Drawings: Submit Project-specific information drawn to scale. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

1. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

2. Engineer will not accept submittals from sources other than Contractor.

3. Engineer will not accept submittals without review and stamp by the Contractor

4. Identify deviations from the Contract Documents.

5. Submit 3 copies of each submittal or an electronic submittal in *.pdf format.

Electronic submittals shall be organized and of fewest separate files possible.

6. Submittals shall be organized and labeled by individual Work Item.

1.4 QUALITY REQUIREMENTS

A. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements. Contractor is responsible for scheduling inspections and tests and notifying testing agency.

B. Testing Agency: Owner shall arrange and pay for testing and inspection services.

Testing Agency to be pre-approved by Engineer.

ADMINISTRATIVE REQUIREMENTS 01 00 00 - 2

C. Regulations: Comply with industry standards and applicable laws and regulations of authorities having jurisdiction, including but not limited to, the following:

1. Building Code requirements.

2. Health and safety regulations (OSHA, ANSI)

3. Utility company regulations.

4. Police, Fire Department and Rescue Squad rules.

D. Inspections: Arrange for authorities having jurisdiction to inspect and test each temporary utility before use. Obtain required certifications and permits.

1.5 TEMPORARY FACILITIES AND CONTROLS

A. Use Charges: Contractor shall pay use charges for temporary utilities.

B. Provide field offices, storage trailers, and other support facilities as necessary for the Work.

C. Collect waste daily and, when containers are full, legally dispose of waste off-site.

D. Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and

NFPA 241.

E. Barricades, Warning Signs and Lights: Comply with industry standards, code requirements and applicable laws and regulations of the authorities having jurisdiction.

Paint with appropriate colors, graphic signs to inform personnel and public of hazard being protected against. When appropriate and needed provide lighting, including warning lights.

F. Provide temporary environmental controls as required by authorities having jurisdiction including, but not limited to, erosion and sediment control, dust control, noise control, and pollution control.

G. Heating and Cooling: Provide temporary enclosures and heating and cooling required for curing materials or for protecting installed construction from adverse weather. Use equipment that will not have a harmful effect on workers, completed installations or elements being installed. Direct equipment exhaust away from building air intake locations.

H. Provide temporary fire protection. Comply with NFPA 241.

1.6 PRODUCT REQUIREMENTS

A. Provide products of same kind from a single source. The term "product" includes the terms "material," "equipment," "system," and similar terms.

B. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft. Comply with manufacturer's written instructions.

C. Provide products that comply with the Contract Documents, are undamaged, and are new at the time of installation.

ADMINISTRATIVE REQUIREMENTS 01 00 00 - 3

1. Provide products complete with accessories, trim, finish, and other devices and components needed for a complete installation and the intended use and effect.

D. Select products to comply with all of the following that are applicable:

1. Where only a single product or manufacturer is named, provide the item indicated.

No substitutions will be permitted.

2. Where two or more products or manufacturers are named, provide one of the items indicated. No substitutions will be permitted.

3. Where products are specified by name, accompanied by the term "available products" or "available manufacturers," provide one of the named items or comply with provisions for "comparable product" to obtain approval for use of an unnamed product or manufacturer.

1.7 SELECTIVE DEMOLITION REQUIREMENTS

A. This section pertains to general conduct of Work.

B. Unless otherwise indicated, demolished materials become Contractor's property.

Remove and dispose of legally from Project site. Do not burn demolished materials.

C. Items indicated to be removed and salvaged remain Owner's property. Remove, clean, and deliver to Owner's designated storage area.

D. Comply with EPA regulations and disposal regulations of authorities having jurisdiction.

E. Conduct demolition without disrupting Owner's use of the building.

F. It is not expected that hazardous materials will be encountered in the Work. If materials suspected of containing hazardous materials are encountered, do not disturb;

immediately notify Owner. Hazardous materials will be removed by Owner.

G. Maintain and protect existing utilities to remain in service before proceeding with demolition, providing bypass connections to other parts of the building.

H. Locate, identify, shut off, disconnect, and cap off utility services to be demolished.

I. Conduct demolition operations and remove debris to prevent injury to people and damage to adjacent buildings and site improvements.

J. Provide and maintain shoring, bracing, or structural support to preserve building stability and prevent movement, settlement, or collapse.

K. Protect building structure and interior from weather and water leakage and damage.

L. Protect walls, ceilings, floors, and exposed finishes that are to remain. Erect and maintain full height dustproof partitions. Cover and protect fixtures, furnishings, and equipment that are to remain.

M. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.

ADMINISTRATIVE REQUIREMENTS 01 00 00 - 4

N. Promptly patch and repair holes and damaged surfaces of building caused by demolition.

Restore exposed finishes of patched areas and extend finish restoration into remaining adjoining construction.

END OF SECTION 01 00 00

SUMMARY OF WORK - RESTORATION 01 11 10 - 1

SECTION 01 11 10 - SUMMARY OF WORK - RESTORATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division 01 Specification Sections apply to this Section.

1.2 PROJECT DESCRIPTION

A. Work will be performed at locations within parking structure as shown on Drawings.

B. Work required in these areas and estimated quantities are listed on Bid Form. Bid Quantities associated with Work Items listed on Drawings have been estimated and are subject to measurement as defined in Article "Measurements." Where additional Work Items are described, but not specifically located and/or shown on Drawings, Contractor shall be responsible for locating and marking areas to be repaired. Owner and/or Engineer/Architect reserves right to increase or decrease quantities up to 25% at same unit cost, as required by job conditions. Unit costs will be established in accordance with Supplementary Conditions, Article "Changes" for quantity variations exceeding 25%.

C. Work Item specifications and details shall govern all repair operations. Locations where Work Items apply are shown on Drawings as symbols.

D. Final payment shall be made on basis of actual approved Work performed as measured in place.

E. The project consists of a 301’ x 114’ parking structure at the Minneapolis Convention Center (1301 Second Avenue South). The structure includes five levels of cast-in-place concrete with a post tensioned, one-way slab-and-beam floor system supported by cast-in-place, conventionally reinforced columns.

1.3 MEASUREMENTS

A. Before ordering any material or doing any Work, Contractor shall verify all measurements at Project site and shall be responsible for correctness of same.

B. Before proceeding with each Work Item, Contractor shall locate, mark, and measure quantity of each item and report quantities to Engineer/Architect. If measured quantities exceed Engineer/Architect's estimate, Contractor shall obtain written authorization to proceed from Owner before executing Work required for that Work Item.

SUMMARY OF WORK - RESTORATION 01 11 10 - 2

C. Measurement of quantities for individual Work Items will be performed by Contractor and reviewed by Engineer/Architect. Coordinate measurements with inspection as required in Section "Project Management and Coordination."

D. Cost of Work included in each Work Item for quantities as indicated in Contract Documents shall be included in Base Bid.

1. Additions to or deductions from lump sum price for quantities of each Work Item added to or deducted from Work respectively shall be at unit prices indicated in Bid Form and shall constitute payment or deductions in full for all material, equipment, labor, supervision and incidentals necessary to complete Work.

1.4 WORK SEQUENCE

A. Prior to commencement of work, meet with Engineer/Architect and Owner representatives to establish sequence and schedule of Work. Contractor shall give Owner notice of areas to be cleared of cars at least 2 working days in advance of actual Work.

B. Contractor shall notify Owner's representative at least 24 hr prior to beginning any abrasive blasting operations.

C. Contractor shall remove all broken concrete and debris from Work area on daily basis and dispose of same at authorized dump sites.

D. Contractor shall remove dust and air transported sand/debris from remainder of facility at conclusion of operations in Work area.

1.5 CONTRACTOR USE OF PREMISES

A. General: During construction period Contractor shall have full use of premises for construction operations, including use of site. Contractor's use of premises is limited only by Owner's right to perform construction operations with its own forces or to employ separate contractors on portions of project.

B. General: Limit use of premises to construction activities in areas indicated; allow for Owner occupancy and use by public.

1. Confine operations to areas within Contract limits indicated. Portions of the site beyond areas in which construction operations are indicated are not to be disturbed.

2. Keep driveways and entrances serving the premises clear and available to the Owner and Owner's employees at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on site.

3. Burial of Waste Materials: Prior to final grading and landscape development, existing grade depression near the southwest corner of site, as indicated, may be

SUMMARY OF WORK - RESTORATION 01 11 10 - 3

used for disposal of inert waste material from construction process. Do not dispose of organic and hazardous material on site, either by burial or by burning.

C. Contractor's use of premises shall not interfere with operation of same. Elevators shall not be used for transfer of materials or equipment.

D. Contractor's debris removal path shall be over non-repaired services unless physical restraints prevent use of such path.

E. Contractor shall confine its apparatus, materials, equipment, tool cribs, field offices and operations to areas designated by Owner and/or Engineer/Architect. Premises shall not be unreasonably encumbered with materials and equipment. Neat and orderly stockpiling and other operations shall be maintained and debris shall be regularly removed from site. Contractor shall not load or permit any part of structure to be loaded with weight that will endanger structural integrity or safety of facility. Contractor shall limit axle loads to maximum 4000 lb per axle and gross weight of 8000 lb, or stockpiling of materials and equipment to 50 lb per sq ft. Contractor to note existing height restrictions within parking structure.

F. Contractor Parking: Contractor's employees shall park within confines of work area or pay prevailing parking rates.

G. On-Site Storage: Contractor shall not store materials or equipment at site of Work for more than one week prior to time that materials or equipment are incorporated into Work.

1.6 BARRICADES

A. Provide positive barricading to separate Work areas from areas open to public and to prevent the need for washing cars parked adjacent to the work area. Minimum acceptable separation: 4 ft. 0 in. high solid temporary barrier constructed of wood or concrete. Provide additional barriers as required to prevent damage to vehicle due to airborne debris. See "Temporary Facilities" for additional requirements.

1.7 TRAFFIC OFFICERS AND FLAGMEN

A. When, in Owner's opinion, it is necessary that uniformed police or security officers be used to protect and control pedestrian traffic, to direct vehicular traffic during construction and to keep traffic off any part of Work, or to protect public safety, a police/security detail will be obtained. All expenses for uniformed officers shall be assumed by Contractor and included in bid price or in prices bid for items of Work to be performed under this Contract.

1.8 CLAIMS

A. Contractor shall promptly address all damages claims. Owner reserves right to resolve any claims not addressed by Contractor within 3 wks after claim is received by

SUMMARY OF WORK - RESTORATION 01 11 10 - 4

Contractor. Any amounts paid by Owner will be deducted from Contractor's next progress payment.

1.9 OWNER OCCUPANCY

A. Partial Owner Occupancy: Owner reserves the right to occupy and to place and install equipment in completed areas of building, prior to Substantial Completion provided that such occupancy does not interfere with completion of Work. Such placing of equipment and partial occupancy shall not constitute acceptance of total Work.

1. Certificate of Substantial Completion will be executed for each specific portion of Work to be occupied prior to Owner occupancy.

2. Obtain Certificate of Occupancy from local building officials prior to Owner occupancy.

3. Prior to partial Owner occupancy, mechanical and electrical systems shall be fully operational. Required inspections and tests shall have been successfully completed. Upon occupancy Owner will provide operation and maintenance of mechanical and electrical systems in occupied portions of building.

1.10 PRE-ORDERED PRODUCTS

A. General: Owner has negotiated purchase orders with suppliers of material and equipment to be incorporated into the Work. These purchase orders are assigned to Contractor and costs for receiving, handling, storage, if required, and installation are included in Contract Sum.

1. Contractor's responsibilities are same as if Contractor negotiated purchase orders, including responsibility to renegotiate purchase if necessary and to execute final purchase order agreements.

2. "Schedule of Pre-Negotiated Orders" is included at the end of this Section.

1.11 OWNER-FURNISHED ITEMS

A. Owner will provide furniture for office area. Work includes providing support systems to receive Owner's equipment, and mechanical and electrical connections.

1. Owner will arrange and pay for delivery of Owner-furnished items in accordance with Contractor's Construction Schedule, and will inspect deliveries for damage.

2. If Owner-furnished items are damaged, defective or missing, Owner will arrange for replacement. Owner will also arrange for manufacturer's field services, and the delivery of manufacturer's warranties and bonds to Contractor.

3. Contractor is responsible for designating delivery dates of Owner-furnished items in Contractor's Construction Schedule and for receiving, unloading and handling Owner- furnished items at site. Contractor is responsible for protecting Owner-furnished items from damage, including damage from exposure to the elements, and to repair or replace items damaged as a result of its operations.

SUMMARY OF WORK - RESTORATION 01 11 10 - 5

1.12 MISCELLANEOUS PROVISIONS

A. Environmental Performance: In order to secure approval to proceed with construction, Owner committed to comply with terms of an "Environmental Impact Statement" dated May 4, 1987. A copy of this Statement shall be transmitted to Contractor prior to execution of the Owner-Contractor Agreement. Project has been designed and Contract Documents prepared with the intention that resulting Work will comply with terms of that Statement.

1. Before Substantial Completion inspect, test and adjust performance of every system or facility of Work to ensure that overall performance is in compliance with terms of Environmental Impact Statement.

2. No later than 300 days after date of Substantial Completion, and after Owner occupancy and use of Project, return and again inspect, test and adjust Work.

Measure performance relative to terms of Environmental Impact Statement to demonstrate and record compliance.

3. Submit report of results to Owner.

4. Instruct Owner's operating personnel on operational requirements needed to maintain compliance.

5. Report performance of completed installations after adjustment that appear unable to comply with requirements of Environmental Impact Statement.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 01 11 10

WORK ITEMS 02 00 10 - 1

SECTION 02 00 10 - WORK ITEMS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Divisions 1 – 84 Specification Sections apply to this Section.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION

WI 1.0 GENERAL REQUIREMENTS

A. Scope of Work

1. Work consists of performing all tasks, specifically required and incidental, which are not identified under separate Work Item designation, but necessary to perform the work identified in this project. This work includes, but is not limited to the following items:

WI 1.1 - Mobilization WI 1.2 - Concrete Formwork WI 1.3 - Concrete Shores and Reshores WI 1.4 - Concrete Reinforcement WI 1.5 - Temporary Signage

WI 1.1 PROJECT MOBILIZATION

A. Scope of Work

1. Work consists of coordinating, scheduling, obtaining and assembling at construction site all equipment, materials, permits, supplies, manpower and other essentials and incidentals necessary to perform Work defined in this Contract.

Payment of lump sum amount for mobilization shall be according to following schedule and shall be based on percentage of original contract amount earned.

B. Materials

1. None

C. Execution

1. At execution of agreement by all parties, mobilization payment shall not be more than 25% of mobilization lump sum amount.

WORK ITEMS 02 00 10 - 2

2. When billing amount earned is greater than 10% but less than 25% of original contract amount, total payment for mobilization shall not be more than 50% of mobilization lump sum amount.

3. When billing amount earned is equal to or greater than 25% but less than 50% of original contract amount, total payment for mobilization shall not be more than 75% of mobilization lump sum amount.

4. When billing amount earned is equal to or greater than 50% of original contract amount, total payment for mobilization shall be 100% of mobilization lump sum amount.

WI 1.2 CONCRETE FORMWORK

A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to install formwork as required for cast-in-place concrete.

B. Materials

1. Forms for Exposed Finish Concrete: Plywood, metal, metal-framed plywood faced, or other acceptable panel-type materials, to provide continuous, straight, smooth, exposed surfaces. Furnish in largest practicable sizes to minimize number of joints and to conform to joint system shown on Drawings.

a. Use overlaid plywood complying with U.S. Product Standard PS-1 "A-C or B-B High Density Overlaid Concrete Form," Class I

b. Use plywood complying with U.S. Product Standard PS-1 "B-B (Concrete Form) Plywood," Class I, Exterior Grade or better, mill-oiled and edge-sealed, with each piece bearing legible inspection trademark.

2. Forms for Unexposed Finish Concrete: Plywood, lumber, metal, or other acceptable material. Provide lumber dressed on at least 2 edges and one side for tight fit.

3. Form Coatings: Provide commercial formulation form-coating compounds with a maximum VOC meeting local requirements that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces, including but not limited to water-curing, curing compound, stains, or paints.

4. Form Ties: Factory-fabricated, adjustable-length, removable or snap-off metal form ties, designed to prevent form deflection and to prevent spalling concrete upon removal. Provide units that will leave no metal closer than 1.5 in. to exposed surface.

a. Provide ties that, when removed, will leave holes not larger than 1.0 in.

diameter in concrete surface.

5. Shores:

a. Nail Ellis clamps, if used with wood shores, to shores with minimum of two nails to prevent slipping.

WORK ITEMS 02 00 10 - 3

b. Wedges: Hardwood or steel. Softwood wedges prohibited.

C. Execution

1. Work shall conform to requirements of latest edition of ACI 301 “Standard Specifications for Structural Concrete,” ACI 302.1 R “Guide for Concrete Floor Slab Construction,” ACI 318 “Building Code Requirements for Reinforced Concrete,” and ACI 347 “Recommended Practice for Concrete Formwork” except as modified by the following paragraphs.

2. Store all formwork and formwork materials clear of ground, protected, so as to preclude damage.

3. Construct forms to sizes, shapes, lines, and dimensions shown and to obtain accurate alignment, location, grades, level, and plumb work in finished structures.

Provide for openings, offsets, sinkages, keyways, recesses, moldings, rustications, reglets, chamfers, blocking, screeds, bulkheads, anchorages and inserts, and other features required in work. Use selected materials to obtain required finishes. Solidly butt joints and provide backup at joints to prevent leakage of cement paste.

4. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush plates or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces where slope is too steep to place concrete with bottom forms only. Kerf wood inserts for forming keyways, reglets, recesses, and the like, for easy removal.

5. Provide temporary openings where interior area of formwork is inaccessible for cleanout, for inspection before concrete placement, and for placement of concrete.

Securely brace temporary openings and set tightly to forms to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

6. Chamfer exposed corners and edges as indicated, using wood, metal, PVC, or rubber chamfer strips fabricated to produce uniform smooth lines and tight edge joints.

7. Provisions for Other Trades: Provide openings in concrete formwork to accommodate work of other trades. Determine size and location of openings, recesses, and chases from trades providing such items. Accurately place and securely support items built into forms.

8. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, or other debris just before concrete is placed. Retighten forms and bracing before concrete placement as required to prevent mortar leaks and maintain proper alignment.

9. Set edge forms or bulkheads and intermediate screed strips for slabs to obtain required elevations and contours in finished slab surface. Provide and secure units sufficiently strong to support types of screed strips by use of strike-off templates or accepted compacting type screeds.

10. Coat contact surfaces of forms with accepted, nonresidual, low-VOC form-coating compound before reinforcement is placed.

11. Coat steel forms with non-staining, rust-preventive form oil or otherwise protect against rusting. Rust-stained steel formwork not acceptable.

12. For post-tensioned concrete, formwork shall remain in place until post-tensioning has been completed. Do not place additional loads on structure until concrete has been properly reshored.

WORK ITEMS 02 00 10 - 4

13. For non-post-tensioned concrete, formwork shall remain in place until concrete has reached minimum two-thirds of 28-day strength. Do not place additional loads on structure until concrete has been properly reshored.

14. Clean and repair surfaces of forms to be re-used in Work. Split, frayed, delaminated or otherwise damaged form facing material will not be acceptable for exposed surfaces. Apply new form coating compound as specified for new formwork.

15. When forms are extended for successive concrete placement, thoroughly clean surfaces, remove fins and laitance, and tighten forms to close joints. Align and secure joint to avoid offsets. Do not use "patched" forms for exposed concrete surfaces, except as acceptable to Engineer/Architect.

WI 1.3 CONCRETE SHORES AND RESHORES

A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to install temporary shoring and to maintain shores in place until Work requiring shores is complete and associated concrete has properly cured.

B. Materials

1. Shores shall be steel, rated at a minimum allowable load of 4,500 lb at 12 ft extension or steel shoring towers rated at a minimum allowable load of 40,000 lbs per four leg tower (based on two 20,000 lb crossed braced frames.).

C. Execution

1. Comply with ACI 301 and ACI 347 for shoring and reshoring in multi-story construction, except as modified in this Section.

2. For purpose of calculations: Construction Load = 50 psf; Dead Load = Actual Weight of the floor slab plus the dead load of beams and girders.

3. Shore/Reshore loads on the structure shall not exceed 40 psf distributed load on the slab, and concentrated loads shall not exceed posted wheel loads or 2,000 lbs., whichever is less. Concentrated bearing pressures shall not exceed 1,200 psi.

4. Shore/Reshore loads on concrete slab-on-grade shall be distributed by steel grillage or timber grillage so as not to exceed soil bearing capacity or 1,500 psf, whichever is smaller.

5. Shore/Reshore loads on asphalt slab-on-grade shall be distributed by steel grillage so as not to exceed asphalt/soil bearing capacity, with consideration of reduced asphalt bearing capacity during extreme hot weather.

6. Shore/Reshore loads shall be distributed horizontally and/or distributed to more than one level to meet shore/reshore load limitations.

7. Shore/Reshore loads shall be distributed to multiple framing members (beams/joists/double tee stems) and extend beyond the immediate work area to ensure proper distribution of loads throughout the structure.

8. Prior to installation of shores, Contractor shall submit shoring scheme prepared and sealed by registered Professional Engineer in Minnesota.

WORK ITEMS 02 00 10 - 5

9. Engineer/Architect will review shoring scheme for general conformance to requirements stated herein. If it does not conform, Contractor will be informed to resubmit another shoring scheme.

10. Remove shores and reshore in planned sequence to avoid damage to partially cured concrete. Locate and provide adequate reshoring to safely support Work without excessive stress or deflection.

11. Keep reshores in place as required until heavy loads due to construction operations have been removed.

12. If during construction, modifications are necessary to accommodate other trades, revise and resubmit erection plan to Engineer/Architect for review.

WI 1.4 CONCRETE REINFORCEMENT

A. Scope of Work

1. Work consists of furnishing all labor, materials, equipment, supervision, and incidentals necessary to fabricate and install all mild steel reinforcement and epoxy coated reinforcement.

B. Materials

1. Reinforcement materials shall be as specified in ACI 301 “Standard Specifications for Structural Concrete.”

2. Plain Steel reinforcing Bars: ASTM A 615/A 615M or ASTM A 706, Grade 60 (Grade 420), deformed.

3. Epoxy-coated reinforcing Bars: ASTM A775

4. Welded wire reinforcement: provide mats only. Roll stock prohibited.

a. Plain-Steel Welded Wire Fabric: ASTM A 1064

b. Epoxy-Coated Welded Wire Fabric: ASTM A884

5. Epoxy coated reinforcing supplier shall be certified currently under CRSI Fusion Bonded Epoxy Coating Applicator Plant Certification Program.

6. Provide one of following epoxy coatings for reinforcement and steel accessories as noted on the Drawings:

a. “Resicoat RB-600”, Akzo Nobel Coatings, Inc.

b. “Nap-Gard 7-2719,” Axalta Coating Systems.

c. “Sher-Bar Green Fusion Bonded Epoxy”, Sherwin Williams.

d. “Pureflex Fusion Bonded Epoxy”, IFS Coatings.

7. Use patching material recommended by epoxy powder manufacturer, compatible with epoxy coating and inert in concrete. Acceptable materials are as follows:

a. “Scotchkote 413 PC,” 3M Company.

b. “Nap-Gard 7-1868” Epoxy Patch Compound, Axalta Coating Systems.

c. “Tammsbar Rebar Touch-up Epoxy Coating,” The Euclid Chemical

Company.

d. ”Greenbar Touchup Coating Kit”, Sherwin Williams.

8. Coating for Existing Exposed Non-prestressed Steel Reinforcement or Welded Wire Reinforcement and Extended Open Time Epoxy Bonding Agent:

Three component, water based, epoxy modified portland cement corrosion inhibiting coating and bonding agent providing the recommended Manufacturer’s

WORK ITEMS 02 00 10 - 6

open time in which to apply repair mortar. Product shall be capable of achieving bond strength of 1,500 psi per ASTM C 882. Coating of existing exposed non-prestressed steel reinforcing is required on all projects, unless specifically excluded on a case-by-case basis elsewhere in Construction Documents. Acceptable materials for this Work are:

a. “Armatec 110 EpoCem,” Sika Chemical Corp.

b. ”Planibond 3C”, Mapei.

c. ”HP Bondit III”, US Concrete Products.

d. “Duralprep A.C.,” The Euclid Chemical Company.

9. Use of extended open time epoxy bonding agent to enhance bond between existing and new (plastic) concrete is not required, unless specifically included elsewhere in Construction Documents.

C. Execution

1. Work shall conform to requirements of latest edition of ACI 301 “Standard Specifications for Structural Concrete,” ACI 315 “Details and Detailing of Concrete Reinforcement,” ACI 318 “Building Code Requirements for Reinforced Concrete,” and Concrete Reinforcing Steel Institute (CRSI), “Manual of Standard Practice.”

2. Submittals required include: Product data for proprietary materials and items, including reinforcement and forming accessories, admixtures, patching compounds, waterstops, joint systems, curing compounds, and others as requested by Engineer/Architect including, but not limited to:

a. Manufacturer's product data and installation instructions for proprietary form coatings, manufactured form systems, ties, and accessories.

b. Steel producer's certificates of mill analysis, tensile tests, and bend tests.

c. Manufacturer's product data, specifications, and installation instructions for proprietary materials, welded and mechanical splices, and reinforcement accessories.

d. Corrosion Inhibitor for Reinforcement:

1) Written certification from coating manufacturer that coating resin for reinforcement has been approved by National Bureau of Standards.

2) Written information from coating manufacturer on proper use and application of coating resin.

3) Coating applicator's written certification of results of quality control program.

e. Submit all materials and methods for concrete curing to Engineer/Architect for approval before beginning concreting Work. Include certification of curing compound allowable moisture loss.

3. Store concrete reinforcement materials at site to prevent damage and accumulation of dirt or excessive rust.

4. Epoxy Coated Reinforcement:

a. Contact areas of handling and hoisting systems shall be padded or be made of nylon or other acceptable material.

WORK ITEMS 02 00 10 - 7

b. Use spreader bars to lift bundles of coated steel to prevent bar-to-bar abrasion.

c. Pad bundling bands or fabricate of nylon or other acceptable material.

d. Store coated steel on padded or wooden cribbing.

e. Do not drag coated steel members.

f. After placement, restrict traffic on coated steel to prevent damage.

5. Reinforcement with any of following defects will be rejected:

a. Lengths, depths and bends exceeding CRSI fabrication tolerances.

b. Bends or kinks not indicated on Drawings or final Shop Drawings.

c. Reduced cross-section due to excessive rusting or other cause.

6. General: Comply with Concrete Reinforcing Steel Institute's recommended practice for "Placing Reinforcing Bars," for details and methods of reinforcement placement and supports and as herein specified.

a. Avoiding cutting or puncturing vapor retarder during reinforcement placement and concreting operations.

b. Examine conditions under which concrete reinforcement is to be placed, and immediately notify Engineer/Architect in writing of unsatisfactory conditions.

Do not proceed with Work until unsatisfactory conditions have been corrected in acceptable manner.

c. Clean reinforcement of loose rust and mill scale, earth, ice, and other materials that reduce or destroy bond with concrete.

d. Fabricate reinforcement to conform to required shapes and dimensions, with fabrication tolerances complying with CRSI MSP. In case of fabricating errors, do not re-bend or straighten reinforcement in manner that will injure or weaken material.

e. Bends in reinforcement are standard 90 bends unless noted otherwise.

f. Reinforcement with any of following defects will be rejected:

1) Lengths, depths and bends exceeding CRSI fabrication tolerances.

2) Bends or kinks not indicated on Drawings or final Shop Drawings.

3) Reduced cross-section due to excessive rusting or other cause.

g. Perform all welding of mild steel reinforcement, metal inserts and connections with low hydrogen welding electrodes in accordance with AWS D1.4.

h. Epoxy coated reinforcement: Fabricator and applicator to provide installer with written instructions to handle, store and place epoxy coated reinforcement to prevent damage to coating.

i. Comply with ACI 301, Chapter 3 for placing reinforcement.

j. Use rebar chairs and accessories to hold all reinforcing positively in place.

Provide rebar chairs at all formed surfaces, both vertical and horizontal, to maintain minimum specified cover. Set wire ties so ends are directed into concrete, not toward exposed concrete surfaces. Maximum spacing of chairs and accessories shall be per CRSI Manual of Standard Practice. In situations not covered by CRSI, provide support at 4 ft on center maximum each way.

WORK ITEMS 02 00 10 - 8

k. Install welded wire reinforcement in as long lengths as practicable. Lap adjoining pieces at least one full mesh and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in either direction.

l. Splices:

1) Provide standard reinforcement splices by lapping ends, placing bars in contact, and tying tightly with wire. Comply with requirements of ACI 318 for minimum lap of spliced bars.

2) For mechanical tension splices of reinforcement:

a) Column bar lengths shall not exceed 30 ft between splices. In any bar, no splices shall occur at any floor level.

b) Exercise care to assure that no reduction of cross-sectional area of reinforcement occurs.

c) Use Barsplice Products, Inc., Bar-Grip or Grip-Twist, NMB Splice Sleeve, or Erico LENTON splices.

d) For all mechanical splices, perform splicing in strict accordance with manufacturer's requirements and instructions.

e) All splices to develop 125% of specified yield strength of bars, or of smaller bar in transition splices.

f) Stagger splices in adjacent bars.

g) Except where shown on Drawings, welding of reinforcement prohibited without prior written authorization by Engineer/ Architect.

3) Compression splices: Mechanically coupled splices in accordance with

ACI 318.

m. Epoxy Coated Reinforcement:

1) Rest epoxy coated steel members supported from formwork on coated wire bar supports, or on bar supports made of dielectric material or other suitable material.

2) Coat wire bar supports with dielectric material for minimum distance of 2 in. from point of contact with coated steel member.

3) Fasten epoxy-coated steel members with nylon-, epoxy-, or plastic-coated tie wire, or other suitable material acceptable to Engineer/Architect.

4) Mechanical connections, when required, shall be installed in accordance with splice device manufacturer's recommendations.

Repair any damage to coating.

5) All parts of mechanical connections on epoxy-coated steel, including steel splice sleeves,…