EsT1657fromAlvaradoPlumbingInc.12368 .pdf

PDF 511 KB Posted

Attached to
EMERGENCY FINAL COST NOTICE-Morrison Rockwood-Emergency well repair
Solicitation number
27-422DNR-DIREC-B-53781
Issued by
Vermilion County, Illinois

About this file

This is a proposal document submitted by Alvarado Plumbing, Inc. to Morrison Rockwood State Park in Morrison, Illinois for emergency well repair services. The proposal outlines a comprehensive well system renovation project that includes removal and reinstallation of the existing well pump, well drop pipe, and electrical wiring; excavation and removal of the existing pitless adapter tank; extension of the well casing 18 inches above ground; installation of a new 2-inch pitless adapter and Franklin Electric SubDrive 50 well pump control box; construction of a new 4-foot by 4-foot by 6-foot concrete vault within 10 feet of the well casing to house pressure equipment; installation of new 2-inch water lines connecting the pitless adapter to the concrete vault and from the vault to the existing underground water line; installation of a new constant pressure manifold; installation of a new well cap; and sanitization and testing of the complete well pump system. All materials and labor necessary to complete the work are included in the proposal scope.

The total project cost is $31,700.00, with payment due in full upon job completion. The proposal was dated September 5, 2025 (Proposal No. 1657) and is valid for acceptance within 30 days of submission. Alvarado Plumbing, Inc. guarantees all materials to specification and commits to workmanlike completion according to standard practices. The company maintains full workers' compensation insurance coverage, while the owner is responsible for fire, tornado, and other necessary insurance. Any alterations or deviations from specifications requiring additional costs require written authorization and will be charged as extras above the estimate price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposal

Date

9/5/25

Proposal No.

Name/Address Morrison Rockwood State Park 18750 Lake Road Morrison, IL 61270

Alvarado Plumbing, Inc.

P.O. Box 131 Morrison, IL 61270

"Where there is pride, you will find excellence."

Signature: _____________________________________

The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work as specified. Payment will be made as outlined above.

Date

Acceptance of Proposal:

We propose hereby to furnish material and labor - complete in accordance with above specifications, for the sum of:

Note: This proposal may be withdrawn by us if not accepted within 30 days. A 1.65% late penalty (Annual percentage rate 19.8%) is applied to all past due accounts. All material is guaranteed to be as specified. All work to be completed in a workmanlike manner according to standard practices.

Any alteration or deviation from above specifications involving extra costs will be executed only upon written orders, and will become an extra charge over and above the estimate. All agreements contingent upon strikes, accidents, or delays beyond our control. Owner to carry fire, tornado, and other necessary insurance. Our workers are fully covered by Workman's Compensation Insurance.

Authorized Signature: ______________

Date

Website: alvarado.plumbing Email: njalvarado@hotmail.com

Description

- Remove the existing well pump, well drop pipe, and well pump electrical wiring from the well casing.

- Excavate, remove, and dispose of the existing pitless adapter tank attached to the well casing.

- Extend the existing well casing 18 inches above the ground.

- Provide and install a new 2" pitless adapter on to the well casing.

- Re-install the existing well pump, well drop pipe, and well pump electrical wiring back into the well casing.

- Provide and install a new Franklin Electric SubDrive 50 well pump control box.

- Provide and install a new 4' x 4' x 6' concrete vault within 10 feet of the well casing to house the pressure tank and pressure sensor.

- Provide and install a new 2" water line from the pitless adapter to the inside of the concrete vault.

- Provide and install a new constant pressure manifold inside the concrete vault.

- Provide and install a new 2" water line from the constant pressure manifold in the concrete vault to the existing 2" underground water line.

- Provide and install a new well cap.

- Sanitize and test the well pump system.

All materials and labor needed to complete the work as listed above is included in this proposal. Payment is due in full upon completion of the job.

$31,700.00