Containerized_Modular_Solar_Power_Systems.pdf

PDF 148 KB Posted

Attached to
Expeditionary Support Equipment-Inflatable Refrigeration, Collapsible Transfer Cases, and Modular Solar Power
Solicitation number
Not on record
Issued by

About this file

This is a Performance Work Statement for the United States Air Force describing requirements for containerized modular solar power and energy storage systems. The USAF seeks rugged, rapidly deployable systems to support Mortuary Affairs Collection Points, expeditionary force support packages, and contingency operations, with the primary objective of reducing reliance on continuous diesel generator operation while providing reliable 24/7 power for Environmental Control Units, lighting, remains refrigeration, and associated loads in austere environments.

The acquisition is a commercial commodity purchase conducted under FAR Parts 12, 13, and/or 15. Key deliverables include: (1) a rugged enclosure based on standard 20-ft or 40-ft ISO shipping containers or modular steel-frame architecture; (2) integrated high-capacity Battery Energy Storage System (BESS) with lithium chemistry and advanced Battery Management System; (3) deployable solar photovoltaic arrays with high-efficiency mono-crystalline panels and dual MPPT inverters; (4) hybrid capability with optional diesel/bio-diesel backup generator integration; (5) power distribution and microgrid controls compatible with military equipment; and (6) commercial operation, maintenance, and safety manuals with standard commercial warranty (minimum 5-year battery, 3-year power electronics). Minimum technical specifications include 10 kW continuous AC output (120/208/240V), 20 kWh usable battery capacity, 6 kW deployable solar array, capability to support 5-ton class Environmental Control Units, 24/7 operation with seamless solar/battery/generator transition, operating temperature range of −20°F to +125°F, and 30–60 minute deployment by 2–4 personnel. All items must comply with the Buy American Act and Trade Agreements Act. Delivery is required within 90 calendar days After Receipt of Order to the designated FOB Destination point. Government acceptance testing includes power output verification, solar deployment demonstration, hybrid transition validation, and noise/signature assessment, with contractor responsibility for repair or replacement of non-conforming items within 15 calendar days at no additional cost.

View the file

Other files

File Type Posted
Collapsable_Inflatable Transfer Case.pdf PDF
Inflatable_Refridgeration_Units.pdf PDF
RFI.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNCLASSIFIED

UNCLASSIFIED | Page 1

PERFORMANCE WORK STATEMENT

FOR

Containerized Modular Solar Power and Energy Storage Systems

UNITED STATES AIR FORCE

Purchase Description and Commodity Acquisition

TABLE OF CONTENTS

1. GENERAL INFORMATION

2. REQUIREMENTS

3. CONTRACTOR DELIVERABLES

4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE

1. GENERAL INFORMATION

1.1 Statement of Need and Background

The United States Air Force (USAF) requires a rugged, rapidly deployable, high-capacity, containerized or modular steel-frame solar power and battery energy storage capability to support Mortuary Affairs Collection Points (MACP), expeditionary Force Support systems (including SPEK, JACKS, and similar packages), and other contingency operations. Specifically, a requirement exists for systems that can eliminate or significantly reduce reliance on continuous diesel generator operation while providing reliable 24/7 power for Environmental Control Units (ECUs), lighting, remains refrigeration, and associated loads in austere or high-tempo environments.

Containerized or modular steel-frame solutions offer greater continuous power output, integrated solar deployment, and enhanced environmental protection compared with purely portable systems. These assets will serve as low-signature, pre-positionable power nodes that can be air- or surface-transported and emplaced with minimal specialized equipment.

1.2 Scope of Acquisition

This is a commercial commodity acquisition conducted under FAR Part 12 (Acquisition of Commercial Items) in conjunction with FAR Part 13 or FAR Part 15.

The Contractor shall manufacture (or procure), inspect, pack, and deliver complete containerized or modular steel-frame solar power and energy storage systems. The deliverable encompasses:

1.2.1 Rugged enclosure based on standard shipping container or modular steel-frame architecture.

1.2.2 Integrated high-capacity Battery Energy Storage System (BESS) with lithium chemistry and advanced

BMS.

1.2.3 Deployable or fold-out solar photovoltaic arrays with high-efficiency mono-crystalline panels and dual MPPT inverters.

1.2.4 Hybrid capability with optional diesel or bio-diesel backup generator integration for extended low-sun periods.

1.2.5 Power distribution, microgrid controls, and interface hardware compatible with tactical ECUs and military generators.

1.2.6 Commercial operation, maintenance, and safety manuals.

1.2.7 Standard commercial product warranty (minimum 5-year battery / 3-year power electronics).

All items must fully comply with the Buy American Act (BAA) and/or the Trade Agreements Act (TAA).

1.3 Period of Performance and Delivery

All commodities, documentation, and accessories shall be delivered to the designated FOB Destination point within ninety (90) calendar days After Receipt of Order (ARO), unless an alternate delivery schedule is established in the contract order.

UNCLASSIFIED | Page 2

2. REQUIREMENTS

The delivered containerized modular solar power systems must meet or exceed the following salient technical characteristics:

2.1 Power Output and Capacity

2.1.1 Continuous AC Output: Minimum 10 kW continuous output (120/208/240 V, single- or three-phase capability preferred). Systems scalable to 30 kW or greater continuous output are highly desired for multi-ECU or theater-level support.

2.1.2 Battery Energy Storage: Minimum usable capacity of 20 kWh; systems of 40 kWh or greater preferred for overnight MACP operations without generator support.

2.1.3 Surge and Load Handling: System shall support starting and continuous operation of 5-ton class FDECU / ECU-39 Environmental Control Units and associated lighting/refrigeration loads.

2.2 Solar Generation and Hybrid Capability

2.2.1 Deployable Solar Array: System shall incorporate a fold-out, roof-mounted, or ground-deployable solar array with a minimum nameplate capacity of 6 kW (preferably 10–12 kW or greater for 40-ft class systems).

2.2.2 Hybrid Operation: System shall support automatic or manual transition to an integrated or external diesel/bio-diesel generator for extended periods of low solar irradiance while maintaining continuous power to critical loads.

2.2.3 Uptime: Designed for continuous 24/7 operation with solar priority and seamless failover to battery or generator.

2.3 Structural and Environmental Resilience

2.3.1 Enclosure: Based on standard 20-ft or 40-ft ISO shipping container or equivalent modular steel-frame structure, weather-resistant, and suitable for repeated transport and field emplacement.

2.3.2 Operating Environment: Ambient temperature range of at least −20°F to +125°F (−29°C to +52°C). Wind and snow load ratings consistent with expeditionary shelter standards.

2.3.3 Security and Access: Lockable access doors, internal lighting, and provisions for external monitoring of system status.

2.4 Deployability and Logistics

2.4.1 Transport: Fully compatible with standard military intermodal transport, 463L pallet systems (when applicable), and ISO container handling equipment.

2.4.2 Emplacement: System shall be capable of being made operational by a crew of 2–4 personnel within approximately 30–60 minutes of arrival at the site (solar array deployment included).

2.4.3 Noise Signature: When operating on battery/solar power, system shall produce significantly lower acoustic and thermal signatures than equivalent tactical diesel generators.

2.5 Safety and Compliance

2.5.1 Battery chemistry shall be lithium-based (preferably LFP) with integrated Battery Management System (BMS) providing cell-level monitoring, thermal management, and fault isolation.

2.5.2 Electrical protection shall include over-current, ground-fault, surge suppression, and phase-reversal protection compatible with military tactical generators.

3. CONTRACTOR DELIVERABLES

The Contractor shall deliver the commodities and technical data specified below:

Item Description Quantity Schedule / Milestone

CLIN 0001 Containerized / Modular Steel-Frame Solar Power System (complete with BESS, solar array, controls) As specified in order Within 90 Calendar Days ARO

CLIN 0002 Optional Integrated or Compatible Backup Generator Module As specified in order Within 90 Calendar Days ARO

UNCLASSIFIED | Page 3

CDRL A001 Commercial Technical Manuals (Setup, Operation, Maintenance, Safety)

1 Hard + 1 Digital per unit Concurrent with units

CDRL A002 Commercial Warranty Documentation (min 5-yr battery / 3-yr electronics) 1 Copy per shipment With final delivery

CDRL A003 Operator Training Media (video or digital demonstration of deployment and operation) 1 Digital Copy Within 30 days of award

4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE

4.1 Receiving Inspection

Upon delivery, Government Quality Assurance personnel will perform a 100% inspection to verify inventory, freedom from transit damage, structural integrity of the enclosure, and BAA/TAA certificates of origin.

4.2 Operational Acceptance Testing

4.2.1 Power Output Test: System shall demonstrate continuous rated output under simulated MACP/ECU load for a minimum of 60 minutes.

4.2.2 Solar Deployment and Charge Test: Fold-out or deployable array shall be erected and demonstrated to charge the BESS under available irradiance.

4.2.3 Hybrid Transition Test: Automatic or manual transition between solar/battery and generator (if provided) shall be demonstrated without interruption to critical loads.

4.2.4 Noise and Signature Assessment: Battery/solar mode operation shall produce substantially lower acoustic and thermal signatures than an equivalent-output tactical diesel generator.

4.3 Rejection and Rectification

Any unit that fails inspection or does not meet salient performance parameters shall be rejected. The Contractor shall repair or replace non-conforming items within fifteen (15) calendar days of notification at no additional cost to the Government.

1. GENERAL INFORMATION
1.1 Statement of Need and Background
1.2 Scope of Acquisition
1.3 Period of Performance and Delivery
2. REQUIREMENTS
2.1 Power Output and Capacity
2.2 Solar Generation and Hybrid Capability
2.3 Structural and Environmental Resilience
2.4 Deployability and Logistics
2.5 Safety and Compliance
3. CONTRACTOR DELIVERABLES
4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE
4.1 Receiving Inspection
4.2 Operational Acceptance Testing
4.3 Rejection and Rectification