This is a Performance Work Statement (PWS) for the acquisition of collapsible or inflatable mortuary transfer cases by the United States Air Force under FAR Part 12 (commercial items).
The Air Force seeks to replace its current rigid aluminum transfer cases (88" L × 28" W × 18" H) with next-generation collapsible or inflatable alternatives that maintain identical external dimensions and operational capability when deployed but occupy significantly reduced volume when stored or transported. The contractor must design, manufacture, test, and deliver complete systems including inflation mechanisms and repair kits. Key performance requirements include: external dimensions of 88" × 28" × 18" (±0.5" tolerance) when fully deployed; maintenance of full structural rigidity for a minimum 72 hours after inflation without additional maintenance; deployment from packed state to full operational status within 10 minutes using standard low-pressure air pump or manual inflation; complete watertight integrity demonstrated through 24-hour static water testing with zero leakage; chemical resistance to human remains, bodily fluids, embalming fluids, formaldehyde, bleach, and decontamination solutions without degradation; handles and lifting points matching the current military transfer case in style, quantity, placement, and load-bearing capacity; and structural capacity to safely support a standard human remains load plus ice without deformation. The contractor may propose purely inflatable designs, hybrid designs combining inflatable and rigid lightweight components, fully rigid collapsible/folding designs with hinges, or innovative alternative approaches meeting all performance requirements.
Deliverables include the transfer cases (as specified in order, within 90 calendar days ARO), operator and maintenance technical manuals (1 hard copy plus 1 digital per unit, concurrent with delivery), rapid field repair kits with patches and adhesive (1 per unit, included with each case), commercial warranty documentation (1 copy per shipment with final delivery), and operator training video or digital media (1 digital copy within 30 days of award). The contractor must provide a minimum three-year commercial warranty covering materials, seams, valves, and workmanship. Quality assurance includes government receiving inspection for dimensional compliance, material defects, and handle integrity, followed by performance testing for inflation hold time, leak integrity, deployment time, chemical resistance, and load capacity. Any units failing tests must be repaired or replaced at no additional cost to the government.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Inflatable_Refridgeration_Units.pdf | ||
| RFI.pdf | ||
| Containerized_Modular_Solar_Power_Systems.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
UNCLASSIFIED | Page 1
PERFORMANCE WORK STATEMENT
FOR
Collapsible / Inflatable Mortuary Transfer Case
UNITED STATES AIR FORCE
Purchase Description and Commodity Acquisition
TABLE OF CONTENTS
1. GENERAL INFORMATION
2. REQUIREMENTS
3. CONTRACTOR DELIVERABLES
4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE
1. GENERAL INFORMATION
1.1 Statement of Need and Background
The United States Air Force currently utilizes rigid aluminum transfer cases with external dimensions of 88" L x 28" W x 18" H. While these cases provide necessary dignity and structural integrity, they consume significant cargo and storage space when empty. This creates substantial logistical burdens during mass casualty operations, humanitarian missions, and routine mortuary affairs movements.
USAF requires a next-generation collapsible or inflatable mortuary transfer case that maintains the same external dimensions and operational capability as the current rigid cases when deployed but collapses or deflates for dramatically reduced storage and transportation volume when not in use.
1.2 Scope of Acquisition
This is a commercial commodity acquisition conducted under FAR Part 12 (Acquisition of Commercial Items).
The Contractor shall design, manufacture, test, and deliver a collapsible or inflatable mortuary transfer case that is fully compatible with current mortuary affairs procedures while providing significant space savings.
2. REQUIREMENTS
The delivered system shall meet or exceed the following salient characteristics:
2.1 Dimensions and Form Factor
2.1.1 External Dimensions:
When fully deployed (inflated or assembled), the transfer case shall measure 88 inches in length × 28 inches in width × 18 inches in height (± 0.5 inch tolerance).
2.1.2 Collapsed Volume:
When fully deflated, folded, or collapsed, the system shall occupy significantly less volume than a standard rigid transfer case to optimize cargo space and storage efficiency.
UNCLASSIFIED | Page 2
2.2 Inflation / Deployment and Structural Integrity
2.2.1 Inflation Hold Time:
Once inflated or deployed to operational pressure, the system shall maintain full structural rigidity and internal pressure for a minimum of 72 hours without requiring additional inflation or maintenance.
2.2.2 Deployment Time:
The system shall be capable of transitioning from its packed state to fully operational condition in under 10 minutes using either a standard low-pressure air pump or manual inflation method.
2.3 Leak-Proof Integrity
The transfer case shall be completely watertight. It shall demonstrate zero leakage when subjected to a 24-hour static water test at operational pressure and during normal handling.
2.4 Material and Chemical Resistance
All interior and exterior surfaces that may come into contact with human remains, bodily fluids, embalming fluids, formaldehyde, bleach, or decontamination solutions shall be constructed of durable, non-porous, chemical-resistant materials. The materials shall show no signs of degradation, delamination, cracking, or leakage after exposure to these substances.
2.5 Handles and Lifting Points
The system shall be equipped with the same style, quantity, placement, and load-bearing capacity of heavy-duty lift handles as the current military transfer case to ensure full compatibility with existing lifting protocols and equipment.
2.6 Load Bearing and Structural Performance
When fully deployed, the system shall safely support the weight of a standard human remains load plus ice without deformation, collapse, or loss of structural integrity.
2.7 Technical Approach Flexibility
Offerors are encouraged to propose any of the following technical solutions (or innovative combinations thereof):
• Purely inflatable design (similar to high-quality inflatable medical or recreational products)
• Hybrid design (inflatable components combined with rigid lightweight aluminum, composite, or polymer panels)
• Fully rigid collapsible / folding design using hinges or interlocking mechanisms
• Any other approach that meets all performance requirements while providing significant space savings
UNCLASSIFIED | Page 3
3. CONTRACTOR DELIVERABLES
Item Description Quantity Schedule
CLIN
Collapsible / Inflatable Mortuary Transfer Case (complete with inflation system and repair kit)
As specified in order
Within 90 Calendar Days
ARO
CDRL
A001
Operator and Maintenance Technical Manuals (including inflation, deflation, cleaning, and repair procedures)
1 Hard Copy + 1 Digital per unit
Concurrent with delivery
CDRL
A002
Rapid Field Repair Kit (patches, adhesive, valve tools, etc.)
1 Kit per unit Included with each case
CDRL
A003
Commercial Warranty Documentation 1 Copy per shipment
With final delivery
CDRL
A004
Operator Training Video / Digital Media 1 Digital Copy Within 30 days of award
Warranty: The Contractor shall provide a minimum commercial warranty of 3 years on materials, seams, valves, and workmanship.
4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE
4.1 Receiving Inspection
Government personnel will inspect for dimensional compliance, material defects, handle integrity, and completeness of repair kits.
4.2 Performance Testing
The Government reserves the right to conduct the following tests:
4.2.1 Inflation Hold Test: System must maintain pressure and rigidity for minimum 72 hours.
4.2.2 Leak Test: 24-hour water fill test with zero leakage allowed.
4.2.3 Deployment Time Test: Must fully deploy in under 10 minutes.
4.2.4 Chemical Resistance Test: Samples shall be exposed to embalming fluid and decontamination solutions with no degradation.
4.2.5 Load Test: Must support rated load without structural failure.
4.3 Rejection
Any unit failing the above tests shall be rejected. The Contractor shall repair or replace rejected units at no additional cost to the Government.
| 1. GENERAL INFORMATION |
| 1.1 Statement of Need and Background |
| 1.2 Scope of Acquisition |
| 2. REQUIREMENTS |
| 2.1 Dimensions and Form Factor |
| 2.2 Inflation / Deployment and Structural Integrity |
| 2.3 Leak-Proof Integrity |
| 2.4 Material and Chemical Resistance |
| 2.5 Handles and Lifting Points |
| 2.6 Load Bearing and Structural Performance |
| 2.7 Technical Approach Flexibility |
| 3. CONTRACTOR DELIVERABLES |
| 4. QUALITY ASSURANCE AND GOVERNMENT ACCEPTANCE |
| 4.1 Receiving Inspection |
| 4.2 Performance Testing |
| 4.3 Rejection |