ESBD_File_350856_06-24554-addendum2.pdf
PDF 34 MB Posted
- Solicitation number
- 06-470424554.
- Issued by
- Winkler County, Texas
About this file
This document is an addendum for a state and local contract opportunity issued by the Texas Department of Transportation (TxDOT) for SITE WORK, NEW KERMIT MNT FACILITY located in Kermit, Texas. The project involves site work and has an estimated cost of $1,087,254.00. Interested bidders are required to attend a mandatory pre-bid meeting on February 29, 2024, at 12:00 PM CT and a mandatory site visit on the same day at 2:30 PM CT. Requests for Information (RFIs) are due by March 4, 2024, and bids are due on April 2, 2024, by 1:00 PM CT at the TxDOT State Headquarters in Austin, Texas. The contract for this work will be awarded by the Texas Transportation Commission, typically scheduled on the last Thursday of each month.
The bid guaranty/bid bond requirement is $22,000.00. The use of a HUB Subcontracting Plan (HSP) is required, as this project estimate is greater than or equal to $100,000. Bidders are cautioned to study the Standard Conditions documents carefully for compliance with the requirements. The Texas Department of Transportation reserves the right to reject any and all proposals, and the contract will not be awarded to any contractor, firm, or subcontractor currently debarred from bidding on Texas Department of Transportation projects.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO: 2 - issued by the
LOCATION: 979 COUNTY ROAD 133
CITY/ST: KERMIT, TEXAS 79745
SITE NO.: 069002
BLDG NO.: 068202
ESTIMATED COST:
BID GUARANTY or BID BOND:
PRE-BID DATE, TIME: *MANDATORY* FEBRUARY 29, 2024 @ 12:00 PM CT
BID DATE, TIME: APRIL 2, 2024 @ 1:00 PM CT
BIDS MUST BE RECEIVED BY: NOON (12:00 PM) FOR 1:00 PM READING
Project by the: TEXAS DEPARTMENT OF TRANSPORTATION
SUPPORT SERVICES DIVISION (SSD), FACILITIES PLANNING & MANAGEMENT
6230 EAST STASSNEY LANE, AUSTIN, TEXAS 78744
ADDENDUM NO. 2 IS ATTACHED WITH THIS NOTIFICATION.
Available to download from: Electronic State Business Daily (ESBD) Use Agency 601 for Requisition Number:
TxDOT Plans Online https://www.txdot.gov/business/letting‐bids/plans‐online.html
TxDOT Facilities Letting https://www.txdot.gov/business/suppliers‐vendors/facilities‐projects‐letting.html
NOTE:
NOTICE TO BIDDERS:
ADDENDUM NO. 2
This Addendum forms a part of the Contract Documents and modifies the original Project Drawings and Spcifications dated 01/27/2024. Included in this Addendum are the final Geotechnical Report, the removal and replacement of septic tank, associated piping, connections, and manhole access, and extension of water service line under existing high pressure gas lines to ROW.
Estimated COST has INCREASED:
from: TO:
New Bid Bond amount is now: $22,000.00 No changes to estimated TIME.
Total pages to this Addendum including cover pages: 111
$1,055,846.00 $1,087,254.00
$1,087,254.00 $22,000.00
Bidders are hereby notified that they shall make any necessary adjustment(s) in their estimates based on this Addendum. It will be by this Addendum shall remain in effect as a part of the Contract Documents.
construed that each bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified herein.
RECEIPT OF THIS ADDENDUM IN PROPOSAL PACKAGE 1 (CONTRACT DOCUMENTS), "ADDENDUM ACKNOWLEDGMENT" SHEET
$1,055,846.00 $21,000.00 http://www.txsmartbuy.com/sp
06-470424554
TEXAS DEPARTMENT OF TRANSPORTATION
March 14, 2024
OFFICIAL DATE OF ADDENDUM:
SITE WORK, NEW KERMIT MNT FACILITY
INCOMPLETE PROPOSAL PACKAGE 1 (CONTRACT DOCUMENTS) WILL BE REJECTED
WINKLER
ODESSA
PROJECT ID #:
COUNTY:
DISTRICT:
06-470424554
FAILURE TO ACKNOWLEDGE RECEIPT OF AN ADDENDUM WILL RESULT IN THE BID NOT BEING READ.
THIS ADDENDUM SHALL BECOME AN OFFICIAL PART OF THE PLANS AND SPECIFICATIONS AND BIDDERS SHALL ACKNOWLEDGE
Contract Documents, this Addendum shall govern and take precedence. Work not specifically deleted, modified, changed or altered at the same time and incorporated therewith. Where provisions of the following supplementary data differ from those of the original This Addendum shall be considered as part of the Contract Documents for the above mentioned project as though it had been issued
Kermit Maintenance Facility
Odessa District (06), Winkler County
TxDOT Project No: 06-4704-24554
Texas Department of Transportation - 2023 Table of Contents
Support Services Division TOC - 1
Facilities Planning & Management Section
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 07 Seals Page
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 Summary
01 20 00 Price and Payment Procedures
01 25 15 Allowances
01 25 00 Substitution and Product Options
01 30 00 Administrative Requirements
01 32 16 Construction Progress Documentation
01 33 00 Submittal Procedures
01 40 00 Quality Requirements
01 40 15 Testing Laboratory Services
01 50 00 Temporary Facilities and Controls
01 60 00 Product Requirements
01 70 00 Execution and Closeout Requirements
DIVISION 02 - EXISTING CONDITIONS
02 23 10 Fence Sliding Gates
02 28 21 Chain Link Fences
02 82 70 Sliding Gate Operators
DIVISION 03 - CONCRETE
03 10 00 Concrete Forming and Accessories
03 20 00 Concrete Reinforcing and Embedded Metal Assemblies
03 30 00 Cast-in-Place Concrete
DIVISION 22 – PLUMBING
22 13 13 Facility Sanitary Sewers
22 13 53 Facility Septic Tanks
DIVISION 26 - ELECTRICAL
26 05 00 Common Work Results for Electrical
26 05 19 Low-Voltage Electrical Power Cables and Conductors
26 05 33 Raceways and Boxes for Electrical Systems
26 05 53 Identification for Electrical Systems
26 56 19 LED Exterior Lighting
CoodyJK Cloud
CoodyJK Text Box
Texas Department of Transportation - 2023 Table of Contents
Support Services Division TOC - 2
Facilities Planning & Management Section
DIVISION 31 - EARTHWORK
31 10 00 Site Clearing - Preparation of Work Site
31 20 00 Earth Moving
31 23 16.13 Trench Safety Systems
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 11 13.13 Lime Treatment for Subgrade
32 11 23 Crushed Limestone Flexible Base
32 12 16.13 Hot Mix Asphaltic Concrete
32 16 00 Concrete Curb and Gutter, Driveways, and Sidewalks
32 17 23.13 Painted Pavement Markings
DIVISION 33 - UTILITIES
33 05 16 Concrete for Utility Construction
33 10 00 Waterline Pipework
33 12 13 Water Tap & Service Line Installation
33 12 33 Valve Boxes, Meter Boxes, & Meter Vaults
END OF SECTION
CoodyJK Text Box
Cloud
Texas Department of Transportation - 2023 Facility Sanitary Sewers
Support Services Division 221313 - 1
Facilities Planning & Management Section
SECTION 221313 - FACILITY SANITARY SEWERS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1.
2. Nonpressure-type transition couplings.
3. Pressure-type pipe couplings.
4. Expansion joints and deflection fittings.
5. .
6. Manholes.
7. Concrete.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Shop Drawings: For manholes. Include plans, elevations, sections, details, and frames and covers.
1.3 INFORMATIONAL SUBMITTALS
A. Field quality-control reports.
PART 2 - PRODUCTS
2.1 PVC PIPE AND FITTINGS
A. PVC Corrugated Sewer Piping:
1. Pipe: ASTM F949, PVC corrugated pipe with bell-and-spigot ends for gasketed joints.
2. Fittings: ASTM F949, PVC molded or fabricated, socket type.
3. Gaskets: ASTM F477, elastomeric seals.
B. PVC Type PSM Sewer Piping:
1. Pipe: ASTM D3034, SDR 26, PVC Type PSM sewer pipe with bell-and-spigot ends for gasketed joints.
2. Fittings: ASTM D3034, PVC with bell ends.
3. Gaskets: ASTM F477, elastomeric seals.
CoodyJK Text Box
Support Services Division 221313 - 2
Facilities Planning & Management Section
2.2 NONPRESSURE-TYPE TRANSITION COUPLINGS
A. Comply with ASTM C1173, elastomeric, sleeve-type, reducing or transition coupling; for joining underground nonpressure piping. Include ends of same sizes as piping to be joined and include corrosion-resistant-metal tension band and tightening mechanism on each end.
B. Sleeve Materials:
1. For Plastic Pipes: ASTM F477, elastomeric seal or ASTM D5926, PVC.
2. For Dissimilar Pipes: ASTM D5926, PVC or other material compatible with pipe materials being joined.
C. Unshielded, Flexible Couplings:
1. Description: Elastomeric sleeve withstainless-steel shear ring andcorrosion-resistant-metal tension band and tightening mechanism on each end.
D. Ring-Type, Flexible Couplings:
1. Description: Elastomeric compression seal with dimensions to fit inside bell of larger pipe and for spigot of smaller pipe to fit inside ring.
E. Nonpressure-Type, Rigid Couplings:
1. Description: ASTM C1461, sleeve-type, reducing- or transition-type mechanical coupling; molded from ASTM C1440, TPE material; with corrosion-resistant-metal tension band and tightening mechanism on each end.
2.3 MANHOLES
A. Standard Precast Concrete Manholes:
1. Description: ASTM C478, precast, reinforced concrete, of depth indicated, with provision for sealant joints.
2. Diameter: 48 inches minimum unless otherwise indicated.
3. Ballast: Increase thickness of precast concrete sections or add concrete to base section, as required to prevent flotation.
4. Base Section: 6-inch minimum thickness for floor slab and 4-inch minimum thickness for walls and base riser section; with separate base slab or base section with integral floor.
5. Riser Sections: 4-inch minimum thickness, of length to provide depth indicated.
6. Top Section: Eccentric-cone type unless concentric-cone or flat-slab-top type is indicated; with top of cone of size that matches grade rings.
7. Joint Sealant: ASTM C990, bitumen or butyl rubber.
8. Resilient Pipe Connectors: ASTM C923, cast or fitted into manhole walls, for each pipe connection.
9. Steps: Individual FRP steps or FRP ladder; wide enough to allow worker to place both feet on one step and designed to prevent lateral slippage off step. Cast or anchor steps into sidewalls at 12- to 16-inch intervals. Omit steps if total depth from floor of manhole to finished grade is less than 60 inches]
Support Services Division 221313 - 3
Facilities Planning & Management Section
10. Adjusting Rings: Interlocking HDPE rings, with level or sloped edge in thickness and diameter matching manhole frame and cover, and with height as required to adjust manhole frame and cover to indicated elevation and slope. Include sealant recommended by ring manufacturer.
11. Grade Rings: Reinforced-concrete rings, 6- to 9-inch total thickness, with diameter matching manhole frame and cover, and with height as required to adjust manhole frame and cover to indicated elevation and slope.
B. Manhole Frames and Covers:
1. Description: Ferrous; 32-inch ID by 7- to 9-inch riser, with 4-inch-minimum-width flange. Include indented top design with lettering cast into cover, using wording equivalent to "SANITARY SEWER."
2. Material: ASTM A536, Grade 60-40-18 ductileiron unless otherwise indicated.
2.4 CONCRETE
A. General: Cast-in-place concrete complying with ACI 318, ACI 350, and the following:
1. Cement: ASTM C150/C150M, Type II.
2. Fine Aggregate: ASTM C33/C33M, sand.
3. Coarse Aggregate: ASTM C33/C33M, crushed gravel.
4. Water: Potable.
B. Portland Cement Design Mix: 4000 psi minimum, with 0.45 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A1064/A1064M, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A615/A615M, Grade 60 deformed steel.
C. Manhole Channels and Benches: Factory or field formed from concrete. Portland cement design mix, 4000 psi minimum, with 0.45 maximum water/cementitious materials ratio. Include channels and benches in manholes.
1. Channels: Concrete invert, formed to same width as connected piping, with height of vertical sides to three-fourths of pipe diameter. Form curved channels with smooth, uniform radius and slope.
a. Invert Slope: 1 percent through manhole.
2. Benches: Concrete, sloped to drain into channel.
a. Slope: 4percent.
D. Ballast and Pipe Supports: Portland cement design mix, 3000 psi minimum, with 0.58 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A1064/A1064M, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A615/A615M, Grade 60 deformed steel.
Support Services Division 221313 - 4
Facilities Planning & Management Section
PART 3 - EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling are specified in Section 312000 "Earth Moving."
3.2 PIPING INSTALLATION
A. General Locations and Arrangements: Drawing plans and details to indicate general location and arrangement of underground sanitary sewer piping. Location and arrangement of piping layout take into account design considerations. Install piping as indicated, to extent practical.
Where specific installation is not indicated, follow piping manufacturer's written instructions.
B. Install piping beginning at low point, true to grades and alignment indicated with unbroken continuity of invert. Place bell ends of piping facing upstream. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions for using lubricants, cements, and other installation requirements.
C. Install manholes for changes in direction unless fittings are indicated. Use fittings for branch connections unless direct tap into existing sewer is indicated.
D. Install proper size increasers, reducers, and couplings where different sizes or materials of pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited.
E.
F. Install gravity-flow, nonpressure, drainage piping according to the following:
1. Install piping pitched down in direction of flow, as indicated on drawings.
2. Install piping NPS 6and larger with restrained joints at tee fittings and at changes in direction. Use corrosion-resistant rods, pipe or fitting manufacturer's proprietary restraint system, or cast-in-place-concrete supports or anchors.
3. Install piping with 36-inch minimum cover.
4. Install PVC Type PSM sewer piping according to ASTM D2321 and ASTM F1668.
G. Clear interior of piping and manholes of dirt and superfluous material as work progresses.
Maintain swab or drag in piping, and pull past each joint as it is completed. Place plug in end of incomplete piping at end of day and when work stops.
3.3 PIPE JOINT CONSTRUCTION
A. Join gravity-flow, nonpressure, drainage piping according to the following:
1. Join PVC Type PSM sewer piping according to ASTM D2321 and ASTM D3034 for elastomeric-seal joints or ASTM D3034 for elastomeric-gasket joints.
2. Join dissimilar pipe materials with nonpressure-type, flexibleor rigid couplings.
Support Services Division 221313 - 5
Facilities Planning & Management Section
B. Pipe couplings, expansion joints, and deflection fittings with pressure ratings at least equal to piping rating may be used in applications below unless otherwise indicated.
1. Use nonpressure flexible couplings where required to join gravity-flow, nonpressure sewer piping unless otherwise indicated.
a. Unshielded flexible or rigidcouplings for pipes of same or slightly different OD.
b. Unshielded, increaser/reducer-pattern, flexible or rigidcouplings for pipes with different OD.
c. Ring-type flexible couplings for piping of different sizes where annular space between smaller piping's OD and larger piping's ID permits installation.
3.4 MANHOLE INSTALLATION
A. General: Install manholes complete with appurtenances and accessories indicated.
B. Install precast concrete manhole sections with sealants according to ASTM C891.
C. Form continuous concrete channels and benches between inlets and outlet.
D. Set tops of frames and covers flush with finished surface of manholes that occur in pavements.
Set tops 3 inchesabove finished surface elsewhere unless otherwise indicated.
3.5 CONCRETE PLACEMENT
A. Place cast-in-place concrete according to ACI 318.
3.6 CONNECTIONS
A. Connect nonpressure, gravity-flow drainage piping to building's sanitary building drains specified in Section 221316 "Sanitary Waste and Vent Piping."
B. Make connections to existing piping and underground manholes.
1. Protect existing piping and manholes to prevent concrete or debris from entering while making tap connections. Remove debris or other extraneous material that may accumulate.
3.7 IDENTIFICATION
A. Comply with requirements in Section 312000 "Earth Moving" for underground utility identification devices. Arrange for installation of green warning tapes directly over piping and at outside edges of underground manholes.
1. Use detectable warning tape over nonferrous piping and over edges of underground manholes.
Support Services Division 221313 - 6
Facilities Planning & Management Section
3.8 FIELD QUALITY CONTROL
A. Inspect interior of piping to determine whether line displacement or other damage has occurred.
Inspect after approximately 24 inches of backfill is in place, and again at completion of Project.
1. Submit separate report for each system inspection.
2. Defects requiring correction include the following:
a. Alignment: Less than full diameter of inside of pipe is visible between structures.
b. Deflection: Flexible piping with deflection that prevents passage of ball or cylinder of size not less than 92.5 percent of piping diameter.
c. Damage: Crushed, broken, cracked, or otherwise damaged piping.
d. Infiltration: Water leakage into piping.
e. Exfiltration: Water leakage from or around piping.
3. Replace defective piping using new materials, and repeat inspections until defects are within allowances specified.
4. Reinspect and repeat procedure until results are satisfactory.
B. Test new piping systems, and parts of existing systems that have been altered, extended, or repaired, for leaks and defects.
1. Do not enclose, cover, or put into service before inspection and approval.
2. Test completed piping systems according to requirements of authorities having jurisdiction.
3. Schedule tests and inspections by authorities having jurisdiction with at least 24 hours' advance notice.
4. Submit separate report for each test.
5. Hydrostatic Tests: Test sanitary sewerage according to requirements of authorities having jurisdiction and the following:
a. Fill sewer piping with water. Test with pressure of at least 10-foot head of water, and maintain such pressure without leakage for at least 15 minutes.
b. Close openings in system and fill with water.
c. Purge air and refill with water.
d. Disconnect water supply.
e. Test and inspect joints for leaks.
6. Manholes: Perform hydraulic test according to ASTM C969.
C. Leaks and loss in test pressure constitute defects that must be repaired.
D. Replace leaking piping using new materials, and repeat testing until leakage is within allowances specified.
END OF SECTION 221313
Texas Department of Transportation - 2023 Facility Septic Tanks
Support Services Division 221353 - 1
Facilities Planning & Management Section
SECTION 221353 - FACILITY SEPTIC TANKS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Septic tanks.
2. Pipe and fittings.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
1. Include construction details, material descriptions, dimensions of individual components, and profiles.
2. Include manhole openings, covers, and pipe connections.
B. Shop Drawings.
1. Include manhole openings, covers, pipe connections, and accessories.
2. Include piping with sizes and invert elevations.
3. Include underground structures.
4. Include other utilities.
PART 2 - PRODUCTS
2.1 CONCRETE SEPTIC TANKS
A. Description: ASTM C1227, precast, reinforced-concrete tank and covers; single chamber.
B. Design: For A-16 (HS20-44) traffic loading according to ASTM C890.
C. Manholes: 24-inchminimum diameter opening with reinforced-concrete risers to grade and access lid with steel lift rings. Include manhole in center of each septic tank compartment top.
D. Resilient Connectors: ASTM C923, of size required for piping, fitted into inlet and outlet openings.
E. Capacity and Characteristics:
1. Capacity: 1000 gal .
2. Inlet and Outlet Size: 6”.
CoodyJK Text Box
Support Services Division 221353 - 2
Facilities Planning & Management Section
2.2 FILTERS
A. Description: Removable, septic-tank-outlet filter that restricts discharge solids to 1/8 inch.
B. Housing: HDPE or PVC.
C. Outlet Size: NPS 6.
PART 3 - EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling for piping is specified in Section 312000 "Earth
Moving."
1. Stockpile topsoil for reuse in finish grading without intermixing with other excavated material. Stockpile materials away from edge of excavation and do not store within drip line of remaining trees.
2. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
B. Excavating and Backfilling for Septic Tanks:
1. Excavate sufficient width and length for tanks to depth determined by tank inlet elevation. Provide level bottom.
2. Backfill with excavated soil, mounding soil above original grade without compacting.
3.2 SEPTIC TANK INSTALLATION
A. Install precast concrete septic tanks according to ASTM C891.
B. Install septic tanks level.
C. Connect septic tank to concrete ballast pad.
D. Install filter in septic tank outlet. Secure filter to septic tank wall. Make direct connections to distribution piping.
E. Install insulation on exterior sides and top of septic tank.
F. Fill septic tank with water.
1.
G.
Support Services Division 221353 - 3
Facilities Planning & Management Section
3.3 IDENTIFICATION
A. Identification materials and their installation are specified in Section 312000 "Earth Moving."
Arrange for installation of green, detectable warning tape directly over piping, at outside edges of underground structures, and at outside edges of absorption systems.
3.4 FIELD QUALITY CONTROL
A. System Tests: Perform testing of completed septic tank system piping and structures according to authorities having jurisdiction.
B. Additional Tests: Fill underground structures with water and let stand overnight. If water level recedes, locate and repair leaks and retest. Repeat tests and repairs until no leaks exist.
3.5 CLEANING
A. Clear interior of piping and structures of dirt and other superfluous material as work progresses.
B. Maintain swab or drag in piping, and pull past each joint as it is completed. Place plugs in ends of uncompleted pipe at end of workday or when work stops.
END OF SECTION 221353
Texas Department of Transportation - 2023 Earth Moving
Support Services Division 31 20 00 - 1
Facilities Planning & Management Section
SECTION 31 20 00 - EARTH MOVING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Excavating and filling for rough grading the Site.
2. Preparing subgrades for slabs-on-grade, walks, pavements, turf and grasses, and plants.
3. Excavating and backfilling for buildings and structures.
4. Drainage course for concrete slabs-on-grade.
5. Subbase course for concrete walks and pavements.
6. Subbase course and base course for asphalt paving.
7. Subsurface drainage backfill for walls and trenches.
8. Excavating and backfilling trenches for utilities and pits for buried utility structures.
B. Related Requirements:
1. Section 31 10 00 "Site Clearing" for site stripping, grubbing, stripping and stockpiling topsoil, and removal of above- and below-grade improvements and utilities.
1.2 DEFINITIONS
A. Backfill: Soil material or controlled low-strength material used to fill an excavation.
1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.
2. Final Backfill: Backfill placed over initial backfill to fill a trench.
B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.
C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe.
D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.
E. Drainage Course: Aggregate layer supporting the slab-on-grade that also minimizes upward capillary flow of pore water.
F. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.
1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Architect. Authorized additional excavation
CoodyJK Text Box
Support Services Division 31 20 00 - 2
Facilities Planning & Management Section and replacement material will be paid for according to Contract provisions for changes in the Work.
2. Bulk Excavation: Excavation more than 10 feet in width and more than 30 feet in length.
3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Architect. Unauthorized excavation, as well as remedial work directed by Architect, will be without additional compensation.
G. Fill: Soil materials used to raise existing grades.
H. Rock:
1. Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material that exceed 1 cu. yd. for bulk excavation or 3/4 cu. yd. for footing, trench, and pit excavation that cannot be removed by rock-excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, ripping, or blasting, when permitted:
a. Equipment for Footing, Trench, and Pit Excavation: Late-model, track-mounted hydraulic excavator; equipped with a 42-inch-maximum-width, short-tip-radius rock bucket; rated at not less than 138-hp flywheel power with bucket-curling force of not less than 28,700 lbf and stick-crowd force of not less than 18,400 lbf with extra-long reach boom.
b. Equipment for Bulk Excavation: Late-model, track-mounted loader; rated at not less than 230-hp flywheel power and developing a minimum of 47,992-lbf breakout force with a general-purpose bare bucket.
2. Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material 3/4 cu. yd. or more in volume that exceed a standard penetration resistance of 100 blows/2 inches when tested by a geotechnical testing agency, according to ASTM D1586.
I. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other fabricated stationary features constructed above or below the ground surface.
J. Subbase Course: Aggregate layer placed between the subgrade and base course for hot-mix asphalt pavement, or aggregate layer placed between the subgrade and a cement concrete pavement or a cement concrete or hot-mix asphalt walk.
K. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, drainage fill, drainage course, or topsoil materials.
L. Utilities: On-site underground pipes, conduits, ducts, and cables as well as underground services within buildings.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct preexcavation conference at Project site.
Support Services Division 31 20 00 - 3
Facilities Planning & Management Section
1. Review methods and procedures related to earthmoving, including, but not limited to, the following:
a. Personnel and equipment needed to make progress and avoid delays.
b. Coordination of Work with utility locator service.
c. Coordination of Work and equipment movement with the locations of tree- and plant-protection zones.
d. Extent of trenching by hand or with air spade.
e. Field quality control.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of the following manufactured products required:
1. Geotextiles.
2. Controlled low-strength material, including design mixture.
3. Geofoam.
4. Warning tapes.
B. Samples for Verification: For the following products, in sizes indicated below:
1. Geotextile: 12 by 12 inches.
2. Warning Tape: 12 inches long; of each color.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified testing agency.
B. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows:
1. Classification according to ASTM D2487.
2. Laboratory compaction curve according to ASTM D698.
C. Blasting is not permitted.
D. Seismic survey report from seismic survey agency.
E. Preexcavation Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces that might be misconstrued as damage caused by earth-moving operations. Submit before earth moving begins.
1.6 QUALITY ASSURANCE
A. Seismic Survey Agency: An independent testing agency, acceptable to authorities having jurisdiction, experienced in seismic surveys and blasting procedures to perform the following services:
Support Services Division 31 20 00 - 4
Facilities Planning & Management Section
1. Report types of explosive and sizes of charge to be used in each area of rock removal, types of blasting mats, sequence of blasting operations, and procedures that will prevent damage to site improvements and structures on Project site and adjacent properties.
2. Seismographic monitoring during blasting operations.
B. Geotechnical Testing Agency Qualifications: Qualified according to ASTM E329 and
ASTM D3740 for testing indicated.
1.7 FIELD CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth-moving operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction.
B. Improvements on Adjoining Property: Authority for performing earth moving indicated on property adjoining Owner's property will be obtained by Owner before award of Contract.
1. Do not proceed with work on adjoining property until directed by Architect.
C. Utility Locator Service: Notify Owner for area where Project is located before beginning earth-moving operations.
D. Do not commence earth-moving operations until temporary site fencing and erosion- and sedimentation-control measures specified in Section 31 10 00 "Site Clearing" are in place.
E. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Foot traffic.
4. Erection of sheds or structures.
5. Impoundment of water.
6. Excavation or other digging unless otherwise indicated.
7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
F. Do not direct vehicle or equipment exhaust towards protection zones.
G. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones.
Support Services Division 31 20 00 - 5
Facilities Planning & Management Section
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.
B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, GC, GC-GM, GP-GM, GP-GC, SW, SP, SM, SC, SP-SM, SP-SC, SC-SM, CL according to ASTM D2487, or a combination of these groups; free of rock or gravel larger than 3 inches in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.
1. Liquid Limit: 35.
2. Plasticity Index: 12.
C. Unsatisfactory Soils: Soil Classification Groups ML, OL, CH, MH, OH, and PT according to
ASTM D2487, or a combination of these groups.
1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.
D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a 1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 95 percent passing a
1-1/2-inch sieve and not more than 8 percent passing a No. 200 sieve.
F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; with at least 90 percent passing a
1-1/2-inch sieve and not more than 12 percent passing a No. 200 sieve.
G. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D2940/D2940M; except with 100 percent passing a
1-inch sieve and not more than 8 percent passing a No. 200 sieve.
H. Drainage Course: Narrowly graded mixture of washed or crushed stone, or crushed or uncrushed gravel; ASTM D448; coarse-aggregate grading Size 57; with 100 percent passing a
1-1/2-inch sieve and zero to 5 percent passing a No. 8 sieve.
I. Filter Material: Narrowly graded mixture of natural or crushed gravel, or crushed stone and natural sand; ASTM D448; coarse-aggregate grading Size 67; with 100 percent passing a 1-inch sieve and zero to 5 percent passing a No. 4 sieve.
J. Sand: ASTM C33/C33M; fine aggregate.
K. Impervious Fill: Clayey gravel and sand mixture capable of compacting to a dense state.
Support Services Division 31 20 00 - 6
Facilities Planning & Management Section
2.2 GEOTEXTILES
A. Subsurface Drainage Geotextile: Nonwoven needle-punched geotextile, manufactured for subsurface drainage applications, made from polyolefins or polyesters; with elongation greater than 50 percent; complying with AASHTO M 288 and the following, measured per test methods referenced:
1. Survivability:
a. Class 2; AASHTO M 288.
b. As follows:
1) Grab Tensile Strength: 157 lbf; ASTM D4632.
2) Sewn Seam Strength: 142 lbf; ASTM D4632.
3) Tear Strength: 56 lbf; ASTM D4533.
4) Puncture Strength: 56 lbf; ASTM D4833.
c. Apparent Opening Size: No. 40 sieve, maximum; ASTM D4751.
d. Permittivity: 0.5 per second, minimum; ASTM D4491.
e. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.
B. Separation Geotextile: Woven geotextile fabric, manufactured for separation applications, made from polyolefins or polyesters; with elongation less than 50 percent; complying with
AASHTO M 288 and the following, measured per test methods referenced:
1. Survivability:
a. Class 2; AASHTO M 288.
b. As follows:
1) Grab Tensile Strength: 247 lbf; ASTM D4632.
2) Sewn Seam Strength: 222 lbf; ASTM D4632.
3) Tear Strength: 90 lbf; ASTM D4533.
4) Puncture Strength: 90 lbf; ASTM D4833.
c. Apparent Opening Size: No. 60 sieve, maximum; ASTM D4751.
d. Permittivity: 0.02 per second, minimum; ASTM D4491.
e. UV Stability: 50 percent after 500 hours' exposure; ASTM D4355.
2.3 CONTROLLED LOW-STRENGTH MATERIAL
A. Controlled Low-Strength Material: Self-compacting, flowable concrete material produced from the following:
1. TxDOT Item 401 Flowable Backfill
B. Produce conventional-weight, controlled low-strength material between 50-psi and with 150-psi according to ASTM D 4832. Slump between 5- to 10-inches.
Support Services Division 31 20 00 - 7
Facilities Planning & Management Section
2.4 ACCESSORIES
A. Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
B. Detectable Warning Tape: Acid- and alkali-resistant, polyethylene film warning tape manufactured for marking and identifying underground utilities, a minimum of 6 inches wide and 4 mils thick, continuously inscribed with a description of the utility, with metallic core encased in a protective jacket for corrosion protection, detectable by metal detector when tape is buried up to 30 inches deep; colored as follows:
1. Red: Electric.
2. Yellow: Gas, oil, steam, and dangerous materials.
3. Orange: Telephone and other communications.
4. Blue: Water systems.
5. Green: Sewer systems.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth-moving operations.
B. Protect and maintain erosion and sedimentation controls during earth-moving operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.
3.2 DEWATERING
A. Provide dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.
B. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.
Support Services Division 31 20 00 - 8
Facilities Planning & Management Section
C. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.
1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.
D. Dispose of water removed by dewatering in a manner that avoids endangering public health, property, and portions of work under construction or completed. Dispose of water and sediment in a manner that avoids inconvenience to others.
3.3 EXPLOSIVES
A. Explosives:
1. Do not use explosives.
3.4 EXCAVATION, GENERAL
A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.
1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials.
2. Remove rock to lines and grades indicated to permit installation of permanent construction without exceeding the following dimensions:
a. 24 inches outside of concrete forms other than at footings.
b. 12 inches outside of concrete forms at footings.
c. 6 inches outside of minimum required dimensions of concrete cast against grade.
d. Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments.
e. 6 inches beneath bottom of concrete slabs-on-grade.
f. 6 inches beneath pipe in trenches and the greater of 24 inches wider than pipe or 42 inches wide.
3.5 EXCAVATION FOR STRUCTURES
A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.
1. Excavations for Footings and Foundations: Do not disturb bottom of excavation.
Excavate by hand to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.
Support Services Division 31 20 00 - 9
Facilities Planning & Management Section
2. Pile Foundations: Stop excavations 6 to 12 inches above bottom of pile cap before piles are placed. After piles have been driven, remove loose and displaced material. Excavate to final grade, leaving solid base to receive concrete pile caps.
3. Excavation for Underground Tanks, Basins, and Mechanical or Electrical Utility
Structures: Excavate to elevations and dimensions indicated within a tolerance of plus or minus 1 inch. Do not disturb bottom of excavations intended as bearing surfaces.
3.6 EXCAVATION FOR WALKS AND PAVEMENTS
A. Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades.
3.7 EXCAVATION FOR UTILITY TRENCHES
A. Excavate trenches to indicated gradients, lines, depths, and elevations.
1. Beyond building perimeter, excavate trenches to allow installation of top of pipe below frost line.
B. Excavate trenches to uniform widths to provide the following clearance on each side of pipe or conduit. Excavate trench walls vertically from trench bottom to 12 inches higher than top of pipe or conduit unless otherwise indicated.
1. Clearance: 12 inches each side of pipe or conduit.
C. Trench Bottoms:
1. Excavate and shape trench bottoms to provide uniform bearing and support of pipes and conduit. Shape subgrade to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits. Remove projecting stones and sharp objects along trench subgrade.
a. For pipes and conduit less than 6 inches in nominal diameter, hand-excavate trench bottoms and support pipe and conduit on an undisturbed subgrade.
b. For pipes and conduit 6 inches or larger in nominal diameter, shape bottom of trench to support bottom 90 degrees of pipe or conduit circumference. Fill depressions with tamped sand backfill.
c. For flat-bottomed, multiple-duct conduit units, hand-excavate trench bottoms and support conduit on an undisturbed subgrade.
d. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course.
2. Excavate trenches 4 inches deeper than bottom of pipe and conduit elevations to allow for bedding course. Hand-excavate deeper for bells of pipe.
a. Excavate trenches 6 inches deeper than elevation required in rock or other unyielding bearing material to allow for bedding course.
Support Services Division 31 20 00 - 10
Facilities Planning & Management Section
D. Trenches in Tree- and Plant-Protection Zones:
1. Hand-excavate to indicated lines, cross sections, elevations, and subgrades. Use narrow-tine spading forks to comb soil and expose roots. Do not break, tear, or chop exposed roots. Do not use mechanical equipment that rips, tears, or pulls roots.
2. Do not cut main lateral roots or taproots; cut only smaller roots that interfere with installation of utilities.
3.8 Utility Boring
A. Refer to TxDOT Specifications
B. Coordinate with both Energy Transfer and Enterprise Products and their encroachment guidelines.
3.9 SUBGRADE INSPECTION
A. Notify Architect when excavations have reached required subgrade.
B. If Architect determines that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed.
C. Proof-roll subgrade below the building slabs and pavements with a pneumatic-tired and loaded 10-wheel, tandem-axle dump truck weighing not less than 15 tons to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.
1. Completely proof-roll subgrade in one direction, repeating proof-rolling in direction perpendicular to first direction. Limit vehicle speed to 3 mph.
2. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as determined by Architect, and replace with compacted backfill or fill as directed.
D. Authorized additional excavation and replacement material will be paid for according to
Contract provisions for changes in the Work.
E. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Architect, without additional compensation.
3.10 UNAUTHORIZED EXCAVATION
A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi, may be used when approved by Architect.
1. Fill unauthorized excavations under other construction, pipe, or conduit as directed by
Architect.
Support Services Division 31 20 00 - 11
Facilities Planning & Management Section
3.11 STORAGE OF SOIL MATERIALS
A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing.
Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.
3.12 BACKFILL
A. Place and compact backfill in excavations promptly, but not before completing the following:
1. Construction below finish grade including, where applicable, subdrainage, dampproofing, waterproofing, and perimeter insulation.
2. Surveying locations of underground utilities for Record Documents.
3. Testing and inspecting underground utilities.
4. Removing concrete formwork.
5. Removing trash and debris.
6. Removing temporary shoring, bracing, and sheeting.
7. Installing permanent or temporary horizontal bracing on horizontally supported walls.
B. Place backfill on subgrades free of mud, frost, snow, or ice.
3.13 UTILITY TRENCH BACKFILL
A. Place backfill on subgrades free of mud, frost, snow, or ice.
B. Place and compact bedding course on trench bottoms and where indicated. Shape bedding course to provide continuous support for bells, joints, and barrels of pipes and for joints, fittings, and bodies of conduits.
C. Trenches under Footings: Backfill trenches excavated under footings and within 18 inches of bottom of footings with satisfactory soil; fill with concrete to elevation of bottom of footings.
Concrete is specified in Section 03 30 00 "Cast-in-Place Concrete."
D. Trenches under Roadways: Provide 4-inch thick, concrete-base slab support for piping or conduit less than 30 inches below surface of roadways. After installing and testing, completely encase piping or conduit in a minimum of 4 inches of concrete before backfilling or placing roadway subbase course. Concrete is specified in Section 03 30 00 "Cast-in-Place
Concrete."
E. Backfill voids with satisfactory soil while removing shoring and bracing.
F. Initial Backfill:
1. Soil Backfill: Place and compact initial backfill of subbase material, free of particles larger than 1 inch in any dimension, to a height of 8 inches over the pipe or conduit.
Support Services Division 31 20 00 - 12
Facilities Planning & Management Section
a. Carefully compact initial backfill under pipe haunches and compact evenly up on both sides and along the full length of piping or conduit to avoid damage or displacement of piping or conduit. Coordinate backfilling with utilities testing.
2. Controlled Low-Strength Material: Place initial backfill of controlled low-strength material to a height of 12 inches over the pipe or conduit. Coordinate backfilling with utilities testing.
G. Final Backfill:
1. Soil Backfill: Place and compact final backfill of satisfactory soil to final subgrade elevation.
2. Controlled Low-Strength Material: Place final backfill of controlled low-strength material to final subgrade elevation.
H. Warning Tape: Install warning tape directly above utilities, 12 inches below finished grade, except 6 inches below subgrade under pavements and slabs.
3.14 SOIL FILL
A. Plow, scarify, bench, or break up sloped surfaces steeper than 1 vertical to 4 horizontal so fill material will bond with existing material.
B. Place and compact fill material in layers to required elevations as follows:
1. Under grass and planted areas, use satisfactory soil material.
2. Under walks and pavements, use satisfactory soil material.
3. Under steps and ramps, use engineered fill.
4. Under building slabs, use engineered fill.
5. Under footings and foundations, use engineered fill.
C. Place soil fill on subgrades free of mud, frost, snow, or ice.
3.15 SOIL MOISTURE CONTROL
A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 2 percent of optimum moisture content.
1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice.
2. Remove and replace, or scarify and air dry, otherwise satisfactory soil material that exceeds optimum moisture content by 2 percent and is too wet to compact to specified dry unit weight.
Support Services Division 31 20 00 - 13
Facilities Planning & Management Section
3.16 COMPACTION OF SOIL BACKFILLS AND FILLS
A. Place backfill and fill soil materials in layers not more than 8 inches in loose depth for material compacted by heavy compaction equipment and not more than 4 inches in loose depth for material compacted by hand-operated tampers.
B. Place backfill and fill soil materials evenly on all sides of structures to required elevations and uniformly along the full length of each structure.
C. Compact soil materials to not less than the following percentages of maximum dry unit weight according to ASTM D698:
1. Under structures, building slabs, steps, and pavements, scarify and recompact top 12 inches of existing subgrade and each layer of backfill or fill soil material at 95 percent.
2. Under walkways, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 92 percent.
3. Under turf or unpaved areas, scarify and recompact top 6 inches below subgrade and compact each layer of backfill or fill soil material at 85 percent.
4. For utility trenches, compact each layer of initial and final backfill soil material at 85 percent.
3.17 GRADING
A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes.
Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.
1. Provide a smooth transition between adjacent existing grades and new grades.
2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface tolerances.
B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to elevations required to achieve indicated finish elevations, within the following subgrade tolerances:
1. Turf or Unpaved Areas: Plus or minus 1 inch.
2. Walks: Plus or minus 1 inch.
3. Pavements: Plus or minus 1/2 inch.
C. Grading inside Building Lines: Finish subgrade to a tolerance of 1/2 inch when tested with a
10-foot straightedge.
3.18 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS
A. Place subbase course and base course on subgrades free of mud, frost, snow, or ice.
B. On prepared subgrade, place subbase course and base course under pavements and walks as follows:
Support Services Division 31 20 00 - 14
Facilities Planning & Management Section
1. Install separation geotextile on prepared subgrade according to manufacturer's written instructions, overlapping sides and ends.
2. Place base course material over subbase course under hot-mix asphalt pavement.
3. Shape subbase course and base course to required crown elevations and cross-slope grades.
4. Place subbase course and base course 6 inches or less in compacted thickness in a single layer.
5. Place subbase course and base course that exceeds 6 inches in compacted thickness in layers of equal thickness, with no compacted layer more than 6 inches thick or less than 3 inches thick.
6. Compact subbase course and base course at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight according to ASTM D698.
C. Pavement Shoulders: Place shoulders along edges of subbase course and base course to prevent lateral movement. Construct shoulders, at least 12 inches wide, of satisfactory soil materials and compact simultaneously with each subbase and base layer to not less than 95 percent of maximum dry unit weight according to ASTM D698.
3.19 FIELD QUALITY CONTROL
A. Special Inspections: Owner will engage a qualified special inspector to perform the following special inspections:
1. Determine prior to placement of fill that site has been prepared in compliance with requirements.
2. Determine that fill material classification and maximum lift thickness comply with requirements.
3. Determine,…