ESBD_File_341194_Addendum 3.pdf
PDF 3 MB Posted
- Attached to
- Frank Garrett HVAC Project
- Solicitation number
- 152-11-2024-01
- Issued by
- Bexar County, San Antonio City, Texas
About this file
This document is an addendum related to a project called the Frank Garrett HVAC Project for the city of San Antonio, Texas. The project involves the renovation of the Frank Garrett Community Center, including the replacement of the HVAC system. The addendum provides changes and clarifications to the original bid documents, such as adding additional drawings, responding to questions about site visits, the existing chiller, pipe sizes, and permitting. The bid opening is scheduled for December 5, 2023 at 2:00 PM CT, and a non-mandatory pre-bid meeting was held on November 13, 2023. The deadline for questions is November 20, 2023 at 4:00 PM CT.
The addendum also includes detailed specifications for the new HVAC system, including a control sequence for the chilled water system, pipe sizing details, and electrical one-line diagrams. The project is funded by the city of San Antonio and Bexar County, and the successful contractor will be required to comply with all applicable state and local laws and regulations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ESBD_File_341194_Addendum 4.pdf | ||
| ESBD_File_341194_Addendum 2.pdf | ||
| ESBD_File_341194_010 IFB - LQB_Frank Garret.pdf | ||
| ESBD_File_341194_Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum #3, Frank Garrett HVAC Project No. 35-00282-02-03 Form09/22/2021AM Page 1 | 2
ADDENDUM 3
PROJECT NAME: Frank Garrett HVAC Project
DATE: 11/27/2023
PROJECT NO: 35-00282-02-03
This addendum is separated into sections for convenience; however, all respondents, bidders, contractors, subcontractors, material men, and other parties must be responsible for reading the entire addendum. The failure to list an item or items in all affected sections of this addendum does not relieve any party affected from performing as per instructions, providing that the information is set forth one time any place in this addendum. These documents will be attached to and will become part of the Contract Documents for this project. The respondent/bidder is required to acknowledge the receipt of this addendum.
GENERAL:
1. The following changes and/or additions to the Contract Documents, via this addendum, must apply to proposals made for and to the execution of the various parts of the work affected thereby.
2. Careful note of the Addendum must be taken by all interested parties and all trades affected must be fully advised in their performance of the work involved.
3. This Addendum is hereby made part of the project requirements and contract documents for the above reference project.
Ensure to acknowledge this Addendum in CivCast when downloading this Addendum. Acknowledgement of this Addendum is a requirement in order to submit bid in CivCast. This addendum consists of the items and their associated attachments as listed below:
A. ADMINISTRATIVE CHANGES TO BID DOCUMENTS:
1. Adding additional drawings to the bid documents.
B. CHANGES TO PLANS / SPECIFICATIONS:
1.
C. QUESTIONS & RESPONSES:
Question #1: Will there be an opportunity to walk the site?
Answer: A Site Visit was held on 11/13/2023.
Question #2: Is the existing chiller operational? At what point will the temporary chiller be needed and for what duration?
Answer: Yes. The temporary chiller will only be required while the existing chiller play is being replaced.
Question #3: The current lead time on the Trane Scroll chiller is 30 weeks (210 calendar days). Would like a time extension from the granted 210 days to account for submittal review, installation, commissioning for an additional 60 days (270 total calendar days from NTP).
Addendum #3, Frank Garrett HVAC Project No. 35-00282-02-03 Form09/22/2021AM Page 2 | 2
Answer: A split NTP will be provided to allow for the long lead time of the chiller.
Question #4: Will a building permit be required or just trade permits? if a building permit is required, who is paying for the permit review and building permit?
Answer: Trade permit only.
Question #5: Will COSA be providing lab testing for the new chiller pad?
Answer: Yes.
Question #6: Pipe sizes for the domestic cold water and sanitary sewer are the only pipe sizes shown.
Pipe sizes for the domestic hot water and hot water return are not shown. In order to price these systems, all pipe sizes will be required, and site visit is not enough time for us to do this.
Answer: See Addendum #3 drawings for pipe sizes.
Question #7: What are the pipe sizes to all new chilled water piping? Not shown on drawings.
Answer: See Addendum #3 drawings for pipe sizes.
SIGNED AND SEALED BY CONSULTANT (Engineer/Architect of Record) By signing and sealing this addendum, the Engineer/Architect of Record acknowledges that the sign/seal is only for changes/clarifications to the items associated with the Engineer’s/Architect’s work referenced in this addendum.
END OF ADDENDUM NO. 3
Date: 11/27/2023
Client: MARMONMOK ARCHITECTURE
Project Name: FRANK GARRETT COMMUNITY CENTER RENOVATION–PACKAGE 2
Project Number: 23002
This addendum is generally separated into sections for convenience; however, all contractors, subcontractors, material men and other parties shall be responsible for reading the entire addendum. The failure to list an item or items in all affected sections of this addendum does not relieve any part affected from performing as per instructions, providing that the information is set forth one time any place in this addendum. These documents shall be attached to and become part of the Contract Documents for this project.
PLAN ITEMS
RE: Plan Sheet M101:
Item 1: Added keyed notes.
Item 2: Added demolition work.
Item 3: Added new work.
RE: Plan Sheet M201:
Item 1: Added note
RE: Plan Sheet E102:
Item 1: Added keyed notes 9, 10, and 11.
Item 2: Revised floor plan, as indicated.
RE: Plan Sheet E103:
Item 1: Added keyed notes 6, and 7.
Item 2: Revised One-line diagram, as indicated.
RE: Plan Sheet E202:
Item 1: Revised floor plan, as indicated.
RE: Plan Sheet E302:
Item 1: Added keyed note 2.
Item 2: Revised One-line diagram, as indicated.
Alderson & Associates, Inc. | Consulting Engineers | TBPE Firm No. F1008
7700 Torino, Suite 101 | San Antonio, TX 78229 | (210) 614-1110 | www.alderson-inc.com
4"
4"
4"
1"
1"
4"
4"
LDR2 HV1
MDPL
1"
1"
1"
4"
4" 4" 4"
4" 4"
4"
M101
MECHANICAL NEW
WORK & DEMOLITION
ENLARGEMENT
E
D
C
B
A
654321
Drawn Checked Date Project No.
Revisions
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
23002 10/13/23
MEB
PEP
11-27-2023 Addendum #03
M201
MECHANICAL
SCHEDULES
E
D
C
B
A
654321
Drawn Checked Date Project No.
Revisions
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
MEB
PEP
PIPE CLAMPS PER
P-4000 UNISTRUT
3/8" THREAD ROD,
SECURE FROM BLDG.
STRUCTURE
STRUT USE
INSULATION PROTECTION
GRINNEL FIG. #167
WHERE INSULATION
IS IN CONTACT WITH
ALLOW ROOM FOR
FUTURE PIPE ADDITION
PIPE HANGER DETAIL
NO SCALE
OR EQUAL
SPECS, TYP.
SPECS AT UN-INSULATED
PROVIDE DIELECTRIC
SEPARATION PER
COPPER PIPING
ROD, CUT TO
PIPE HANGER
INSULATION
CLEVIS TYPE
LENGTH
THREADED
SHEET METAL SHIELD
FOR INSULATION - MIN.
HANGER POINT
LENGTH 1.5 TIMES
INSULATED PIPE DIAMETER
PROVIDE A SECTION
INSULATION AT EACH
OF INCOMPRESSABLE
PIPE
CARRIER
STRAP SADDLES WITH
ZIP TIES
STAINLESS STEEL
PUMPMOTOR
(NON-SLAM TYPE)
MANUAL AIR VENT
CONCENTRIC REDUCER
BALL VALVE (TYP.)
PRESSURE GAUGE
CHECK VALVE
BUTTERFLY VALVE W/
BASE
PUMP INERTIA
GROUTABLE)
(STEEL &
DRIP RIM BASE
PER SPECIFICATIONS
VIBRATION ISOLATION
ELBOW DOWN VALVE
Y-STRAINER W/ ELBOW
FLEXIBLE PIPE
CONNECTION (TYP.)
FLOOR
DISCHARGE SUCTION
MEMORY STOP (TYP.)
(TYP.)
ECCENTRIC REDUCER
SUCTION DIFFUSER
END SUCTION PUMP DETAIL
(N.O.) FLEXIBLE HOSE
3/4" DRAIN VALVE (N.C.)
FLOOR DRAIN
1" DRAIN TO
NO SCALE
KEEPING PAD
3-1/2" HOUSE-
SITE
FLOW
METER
FILTER/FEEDER
TANK
TO PUMP
SUCTION
FROM PUMP
DISCHARGE
1" PIPE
BALL VALVE
(TYP.)
3/4 " TO
FLOOR
DRAIN
3-1/2" TALL
HOUSEKEEPING
PAD
1" PIPE
FUNNEL
AIR DIRT SEPERATOR
LOCATE DRAIN VALVE FOR
EASY ACCESS FROM FLOOR
(WITHOUT LADDER).
1/2" AIR VENT
TO FLOOR
DRAIN
SUSPEND FROM STRUCTURE
OVERHEAD (PROVIDE ANGLE
BETWEEN JOISTS TO
DISTRIBUTE LOAD) (PROVIDE
SPRING VIBRATION ISOLATOR
HANGERS)
BUTTERFLY VALVE (TYP.)
AIR/DIRT SEPARATOR DETAIL
NO SCALE
FILTER FEEDER DETAIL
NO SCALE
ROUTE TO NEAREST
FLOOR DRAIN
ECCENTRIC TRANSITION,
(TOP FLAT, TYPICAL)
3 4
DOMESTIC
MAKEUP PIPING
CHECK BFP ASSY
DBL
DIGITAL FLOW METER W/
PULSE OUTPUT CAPABILITY.
CONNECT TO BAS FOR
MONITORING PURPOSES.
TO EXPANSION
TANK FEED
LINE
BALL VALVE
(N.C.)
3/4"
3/4"
BALL VALVE
(N.O.)
PRESSURE REDUCING
VALVE
PRESSURE RELIEF VALVE
PRESSURE GAUGE
3/4"3/4"
TO DRAIN
MAKE-UP WATER PIPING DETAIL
NO SCALE
4" CHWR
4" CHWS
FLEX
CONNECTOR,
(TYP.)
HOUSEKEEPING PAD
PRESSURE
GAUGE W/ COCK
(TYP.)
FLOW
SWITCH
P/T PORT (TYP.)
THERMOMETER (TYP.)
BUTTERFLY
VALVE
P
PFS
P
CONTROL SEQUENCE FOR CHILLED WATER SYSTEM:
1. SYSTEM DESCRIPTION: THE CHILLED WATER SYSTEM CONSISTS OF ONE AIR COOLED SCROLL
CHILLER AND TWO VFD CONTROLLED CHILLED WATER PUMPS PIPED IN PARALLEL FOR
LEAD/STAND BY OPERATION. LEAD/STAND-BY STATUS SHALL BE ROTATED BY THE BAS
WEEKLY FOR THE PUMPS.
2. CHILLER START: UPON CHILLER ENABLE, THE BAS SHALL ENABLE (SOFT START) THE LEAD
PUMP, RAMP THE SPEED OF THE PUMP TO THE DESIGN FLOW RATE AND MONITOR STATUS
VIA CURRENT SENSOR. ONCE CHILLED WATER FLOW IS PROVEN VIA THE FLOW SWITCH, THE
BAS SHALL ENABLE THE CHILLER. THE BAS SHALL MONITOR THE CHILLER VIA BACNET MS/TP
AND ALARM IF THE CHILLER FAILS. THE CHILLER'S FACTORY CONTROLS SHALL MAINTAIN
THE LEAVING WATER TEMPERATURE SET POINT OF 44F (ADJ.). THE BAS SHALL ENABLE THE
STAND-BY PUMP IN THE EVENT OF A LEAD PUMP FAILURE. THE BAS SHALL ALARM IN THE
EVENT OF EQUIPMENT FAILURE.
3. CHILLER STOP: WHEN THE CHILLER IS COMMANDED TO STOP, THE BAS SHALL DISABLE THE
CHILLER AND DISABLE THE CHILLED WATER PUMP.
4. FREEZE PROTECTION: IN THE EVENT OF AN EVAPORATOR LOW TEMPERATURE ALARM, THE
BAS SHALL ENABLE THE CHILLED WATER PUMP AND OPERATE IT AT THE DESIGN FLOW
RATE.
CH-1
BACnet MS/TP
(CONNECT TO BAS)
P-1
BUILDING LOAD
AHUS WITH
EXISTING 3-WAY
CHILLED WATER
CONTROL VALVES
AIR COOLED
CHILLER
S/S
STATUS
ALARM TS
TS
TS
BI
BI
BO
P-2
T
CHW RETURN
TEMP
AI IMMER
T
CHW SUPPLY
TEMP
AI IMMER
FS
CHW FLOW
BI DPS
S/S TS
STATUS TS
SPEED TS
CHILLED WATER
PUMP (2 THUS)
VFD
VFD
THE NEW CHILLER SYSTEM SHALL BE
INTEGRATED INTO THE EXISTING
TRANE TRACER SUMMIT BUILDING
AUTOMATION SYSTEM
CONNECT
NEW MAKEUP
WATER PIPING
TO EXISTING
ISOLATION
VALVE.
'MSB'
CH-1
CHP-1 CHP-2
B-1
MOTOR
STARTERS
XFMR 'T-LDR2'
EXISTING CPS
TRANSFORMER
WATER VALVES &
BACKFLOW PREV
UTILITY YARD
WIREWAY
PULLBOX
LDR2 HV1
MDPL
GND
T-MDPL
CENTRAL PLANT
CONTROLLER
AHU CONTROLLER
HVAC CONTROLS
SEC 1 SEC 2
EXISTING CPS
TRANSFORMER
UTILITY YARD
MOTOR
STARTERS
LDR2 HV1
B-1
'MSB'
'MSB'
MDPL
GND
SEC 1 SEC 2
T-MDPL
CENTRAL PLANT
CONTROLLER
AHU CONTROLLER
HVAC CONTROLS
CH-1
CHP-1 CHP-2
1. PROVIDE NEW ELECTRICAL EQUIPMENT, AS INDICATED. REFER TO ELECTRICAL ONE-LINE
DIAGRAM ON SHEET E103 FOR ADDITIONAL INFORMATION.
2. REMOVE AND RELOCATE EXISTING CPS METER. SALVAGE ASSOCIATED FEEDERS FOR
RECONNECTION. REFER TO DETAIL 2 ON THIS SHEET AND ELECTRICAL ONE-LINE DIAGRAM
ON SHEET E103 FOR ADDITIONAL INFORMATION.
3. PROVIDE GALVANIZED ELECTRICAL RACK FOR MOUNTING OF ELECTRICAL EQUIPMENT.
REFER TO ELECTRICAL ONE-LINE DIAGRAM ON SHEET E103 FOR ADDITIONAL INFORMATION.
4. NEW LOCATION OF SALVAGED CPS METER.
5. EXTEND PAD PER CPS STANDARD TO ALLOW FOR THE INSTALLATION OF NEW TAP BOX.
6. RECONNECT SALVAGED FEEDERS, AS INDICATED. EXTEND FEEDERS TO CONNECT TO
DISCONNECT, AS INDICATED.
7. PROVIDE CONDUIT, AS INDICATED. FIELD COORDINATE ROUTING WITH EXISTING
CONDITIONS. REFER TO ELECTRICAL ONE-LINE DIAGRAM ON SHEET E103 FOR ADDITIONAL
INFORMATION.
8. PROVIDE NEW FEEDERS TO EXISTING DISCONNECT TO FEED NEW 'MSB'. REFER TO
ELECTRICAL ONE-LINE DIAGRAM ON SHEET E103 FOR ADDITIONAL INFORMATION.
9. PROVIDE FUSED DISCONNECT AND ASSOCIATED LINE-SIDE FEEDER FOR CONNECTION TO
TEMPORARY CHILLER. COORDINATE FUSE SIZE WITH TEMPORARY CHILLER PROVIDER
PRIOR TO INSTALLATION.
10. REMOVE EXISTING AHU CONTROLLER. SALVAGE ASSOCIATED CIRCUITRY AND CONTROL
WIRING.
11. NEW LOCATION OF AHU CONTROLLER. RECONNECT SALVAGE CIRCUITRY AND CONTROL
WIRING. EXTEND WIRING AS REQUIRED FOR A COMPLETE FUNCTIONAL SYSTEM.
KEYED NOTES: (APPLIES TO THIS SHEET)
1. COMPLETE WORK IN ACCORDANCE WITH APPLICABLE CODES, ORDINANCES, AND
INTERPRETATIONS OF AHJ.
2. COORDINATE WORK WITH OTHER TRADES AS REQUIRED TO PROVIDE COMPLETE SYSTEMS
AND AVOID CONFLICTS.
3. COORDINATE INSTALLATION OF ELECTRICAL WORK ABOVE THE CEILING TO PROVIDE THE
GREATEST POSSIBLE CLEARANCE FOR PLUMBING AND MECHANICAL EQUIPMENT BOTH
CURRENT AND FUTURE. CONDUITS SHALL BE KEPT TIGHT TO STRUCTURE OR ROUTED
THROUGH STRUCTURAL TRUSSES WHEREVER POSSIBLE.
4. COORDINATE LOCATION OF ALL DISCONNECT SWITCHES TO ENSURE THAT ALL NEC
MINIMUM WORKING CLEARANCES ARE MAINTAINED.
5. SINGLE HOMERUNS ARE SHOWN FOR CIRCUIT IDENTIFICATION ONLY. CIRCUITS MAY BE
GROUPED UP TO THREE (3) PHASE CONDUCTORS PER RACEWAY, UNLESS NOTED
OTHERWISE.
6. HOMERUNS AND RUNS BETWEEN JUNCTION BOXES SHALL BE MINIMUM OF 3/4" CONDUIT
AND SHALL INCLUDE #10 (MINIMUM) CONDUCTORS AND INSULATED GROUNDING
CONDUCTOR. CIRCUIT SHALL EXTEND FROM OCPD TO A JUNCTION BOX IN THE AREA OF
THE RECEPTACLES OR UTILIZATION EQUIPMENT. DROPS TO INDIVIDUAL 20-AMP WIRING
DEVICES SHALL INCLUDE #12 (MINIMUM) CONDUCTORS.
7. VOLTAGE DROP TO LAST DEVICE ON BRANCH CIRCUIT SHALL NOT EXCEED 3 PERCENT
FROM PANEL. INCREASE BRANCH CIRCUIT CONDUCTOR SIZES AS REQUIRED TO ALLOW
FOR CIRCUIT LENGTH.
8. FMC OR LFMC SHALL BE USED FOR CONNECTIONS TO VIBRATION PRODUCING EQUIPMENT,
SUCH AS MOTORS, TRANSFORMERS, AND HVAC EQUIPMENT. LFMC SHALL BE USED IN DAMP
AND WET LOCATIONS.
9. PROVIDE UL LISTED FIRE STOP SYSTEMS AT ALL PENETRATIONS THROUGH RATED
PARTITIONS.
10. WIRING DEVICES SHALL BE SPECIFICATION-GRADE DEVICES, LISTED AND LABELED BY A
NRTL.
11. ALL FEEDER AND BRANCH CIRCUIT WIRING SHALL BE COPPER.
12. MARK JUNCTION BOX COVERS USING PERMANENT MARKER INDICATING THE PANEL AND
CIRCUIT NUMBERS SERVING THE JUNCTION BOX.
(APPLIES TO ALL ELECTRICAL SHEETS)
GENERAL
POWER NOTES:
E102
ENLARGED
ELECTRICAL FLOOR
PLANS - PHASE 1
SCALE:
NORTH
1 ENLARGED ELECTRICAL PLAN - MECH RM - STEP 1 - PHASE 1
1/4" = 1' - 0"
1. DRAWINGS INDICATE APPROXIMATE LOCATION AND QUANTITY OF TELEPHONE OUTLETS, DATA
OUTLETS, FLOOR OUTLETS, RECEPTACLES, AND ELECTRICAL CONNECTIONS TO BE REMOVED.
FIELD VERIFY LOCATION AND QUANTITY OF ITEMS TO BE REMOVED, AS NO ALLOWANCE WILL BE
MADE BECAUSE OF UNFAMILIARITY WITH THESE DETAILS.
2. EXISTING CIRCUITS INDICATED WERE OBTAINED FROM AS-BUILT DRAWINGS AND MAY NOT BE
CORRECT. IDENTIFY AND LOCATE EXISTING BRANCH CIRCUITRY.
3. REMOVE BRANCH CIRCUITS SERVING EQUIPMENT, RECEPTACLES, LIGHT FIXTURES, MOTORS, AND OTHER ITEMS SHOWN TO BE REMOVED BACK TO OCPD IN SWITCHBOARD, PANEL, LOAD
CENTER, OR J-BOX GRID SYSTEM, EXCEPT AS OTHERWISE REQUIRED BY NOTES BELOW.
3.1. BRANCH CIRCUIT: CONDUCTORS, RACEWAYS, BOXES, WIREWAYS, WIRING DEVICES,
COVERPLATES, DISCONNECTING MEANS, STARTERS, CONTROLLERS, AND SUPPORTS.
3.2. OCPD SHALL REMAIN AS AN INTEGRAL PART OF EXISTING SWITCHBOARD, PANEL, OR LOAD
CENTER, AND IF NOT BEING REUSED, SHALL BE LABELED AS SPARE.
3.3. CONDUITS IN INACCESSIBLE AREAS: REMOVE CONDUCTORS AND ABANDON IN PLACE,
CAPPED AND SEALED. IN A FINISHED SPACE, REMOVED CONDUIT TO BELOW FINISHED
SURFACE, FILL VOID WITH NON-SHRINKING GROUT, AND RESURFACED TO MATCH
SURROUNDING SURFACES.
4. MAINTAIN INTEGRITY OF BRANCH CIRCUITS WITH A PORTION OF THE LOAD REMOVED. REMOVE
PORTION OF BRANCH CIRCUIT ASSOCIATED WITH REMOVED DEVICE TO A POINT AS NECESSARY
TO SERVE REMAINING LOAD.
5. EXTEND BRANCH CIRCUITS WHERE INDICATED TO SERVE NEW LOADS OR TO RECONNECT
RELOCATED EQUIPMENT. RUN CONDUIT CONCEALED WHERE POSSIBLE, AND ROUTE TO AVOID
INTERFERENCE WITH EQUIPMENT OR AESTHETICS. REPLACE WITH NEW CONDUCTORS FROM
OCPD TO LOAD.
6. INCLUDE IN BID COSTS RESULTING FROM OVERTIME, EVENING, AND WEEKEND WORK.
COORDINATE WITH OWNER ON OPERATION SCHEDULES AND ASSOCIATED REQUIREMENTS.
7. SALVAGED ITEMS AND MATERIALS SHALL REMAIN THE PROPERTY OF THE OWNER AND SHALL
BE DELIVERED TO OWNER’S DESIGNATED STORAGE FACILITY.
8. REMOVE FROM PROJECT SITE DEMOLISHED MATERIALS AND EQUIPMENT. DISPOSE OF IN
ACCORDANCE WITH APPLICABLE ENVIRONMENTAL LAWS AND REGULATIONS. REMOVE PCB
CONTAINING BALLASTS AND DISPOSE OF THROUGH AUTHORIZED DISPOSAL FACILITY.
9. PROVIDE CLOSURE CAPS IN EXISTING CORE DRILLED HOLES. FILL IN REMAINING HOLES WITH
FLOOR STONE CEMENT FLUSH WITH SURROUNDING AREA.
10. SEAL OPENINGS IN FIRE RESISTANCE RATED PARTITIONS TO PRESERVE RATING OF PARTITION.
11. DAMAGE CAUSED BY THE WORK, WHICH IS NOT CONCEALED BY NEW CONSTRUCTION, SHALL BE
REPAIRED TO MATCH EXISTING SURFACES.
12. IDENTIFY AND LOCATE EXISTING UTILITIES THAT MAY CONFLICT WITH NEW WORK, AND INCLUDE
IN BID COSTS NECESSARY TO COORDINATE THE INSTALLATION OF THE NEW WORK WITH THE
EXISTING UTILITIES.
13. COORDINATE AND VERIFY ACTUAL LENGTHS AND ROUTES OF CONDUIT AND FEEDER RUNS
WITH ENGINEERED DRAWINGS AS WELL AS EXISTING SITE CONDITIONS PRIOR TO SUBMISSION
OF BID OR PROPOSAL.
14. COORDINATE AND SCHEDULE ELECTRICAL AND COMMUNICATION SERVICE OUTAGES TO
EXISTING FACILITIES WITH OWNER IN ADVANCE OF OUTAGE.
15. PERFORM WORK IN A MANNER TO MINIMIZE INTERRUPTION OF SERVICES TO OCCUPIED SPACES
AND TO MAINTAIN SERVICE TO ROOMS NOT UNDERGOING ACTIVE CONSTRUCTION.
16. PRIOR TO BID, VISIT THE PROJECT SITE, BECOME FAMILIAR WITH THE CONDITIONS AS THEY
EXIST, AND CONFIRM LOCATIONS, SIZES, AND QUANTITIES OF MATERIALS AND ITEMS TO BE
REMOVED OR INSTALLED. LOOK ABOVE CEILINGS IN AREAS TO BE RENOVATED, AND IDENTIFY
QUANTITIES MATERIALS TO BE REMOVED.
(APPLIES TO ALL ELECTRICAL SHEETS)
GENERAL ELECTRICAL
DEMOLITION NOTES:
E
D
C
B
A
654321
Drawn Checked Date Project No.
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
LME
TJS
23002 10/13/23
SCALE:
NORTH
2 ENLARGED ELECTRICAL PLAN - MECH RM - STEP 2 - PHASE 1
1/4" = 1' - 0"
Revisions 1 11-27-2023 Addendum #03
1 1
/2
7/
FEEDER SCHEDULE
3 PHASE, 4 WIRE
TAG CONDUIT PHASE CONDUCTORS NEUTRAL CONDUCTORS GROUND CONDUCTORS
1000N (3)3" EACH WITH (3)#400 KCMIL (1)#400 KCMIL (1)# 2/0 GND.
400N (1)4" EACH WITH (3)#600 KCMIL (1)#600 KCMIL (1)# 3 GND.
3 PHASE, 3 WIRE
TAG CONDUIT PHASE CONDUCTORS NEUTRAL CONDUCTORS GROUND CONDUCTORS
175 (1)1-1/2" EACH WITH (3)2/0 AWG NA (1)#3 GND.
NOTES:
1. CONDUIT SIZES ARE FOR CONDUIT INDICATED WITH THHN, THWN INSULATED COPPER CONDUCTORS WITH MAXIMUM 40% FILL. CONTRACTOR SHALL ADJUST CONDUIT SIZE AS REQUIRED PER NEC APPENDIX C, CONDUIT FILL TABLES FOR ALL OTHER CONDUIT AND INSULATION TYPES.
2. REFER TO SPECIFICATIONS FOR ADDITIONAL CONDUIT APPLICATION AND INSTALLATION REQUIREMENTS.
3. PROVIDE LUGS AS REQUIRED FOR FEEDERS INDICATED.
E103
ELECTRICAL
ONE - LINE DIAGRAM
PHASE 1
200A
125AF
200A
200AF
200A
125AF
200A
175AF
400A
300AF
200A
200AF
G N
75 kVA
XFMR
T-LC
CHILLER
CH-1
T-LDR2
15kVA XFMR
1000A
1000AF
30A
30AF
30A
30AF
400A
225AF
75 kVA
XFMR
T-LB
400A
225AF
400A
350AF
112.5 kVA
XFMR
T-LA
EMERG
LIGHTS
MAIN SWITCHBOARD 'MSB', 480/277V, 1000A, 3PH, 4W
200A
200AF
EXISTING
PANEL
'LC'
225A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'LC'
100A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'HA'
225A MLO
480/277V
3PH, 4W
N1
EXISTING
PANEL
'LB'
225A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'LA'
400A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'LD'
225A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'HV1' SEC1
200A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'HV1' SEC 2
200A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'LDR2'
100A MLO
208/120V
3PH, 4W
N1
NOTE TO CONTRACTOR:
PRIOR TO CONSTRUCTION, CONTRACTOR SHALL COORDINATE
AND SCHEDULE ELECTRICAL SERVICE OUTAGES TO EXISTING
FACILITIES WITH OWNER IN ADVANCE OF OUTAGE.
E
D
C
B
A
654321
Drawn Checked Date Project No.
Revisions
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
LME
TJS
23002 10/13/23
112.5 kVA
XFMR
T-MDPL
NEW
PANEL
'MDP'
400A MLO
208/120V
3PH, 4W
N1
CAP
BANK
400N
1000N
1000N
11-27-2023 Addendum #03
400N
400A
400AF
/2
7/
CHILLER - SEE MECH
'MSB'
CH-1
CHP-1 CHP-2
B-1
MOTOR
STARTERS
XFMR 'T-LDR2'
EXISTING CPS TRANSFORMER
WATER VALVES & BACKFLOW PREV
XFMR
SEC DISC
XFMR 'T-LC'
(ABOVE)
UTILITY YARD
WIREWAY
PULLBOX
LDR2 HV1
LE
LC
5 'MSB'
MDPL
GND
SEC 1 SEC 2
T-MDPL
CENTRAL PLANT
CONTROLLER
AHU CONTROLLER
HVAC CONTROLS
AHU
CONTROLLER
XFMR
SEC DISC
XFMR 'T-LB'
(ABOVE)
3 LB
HA
LD
XFMR 'T-LA'
(ABOVE CEILING)
XFMR
SEC DISC
LA
CU-1 4
1. REMOVE EXISTING TRANSFORMER, ASSOCIATED DISCONNECT AND FEEDERS BACK TO
SOURCE PANELBOARD.
2. EXISTING TRANSFORMER TO BE ABANDONED IN PLACE. REMOVE ASSOCIATED DISCONNECT
AND FEEDERS BACK TO SOURCE PANELBOARD.
3. REMOVE EXISTING PANELBOARD. ASSOCIATED BRANCH CIRCUITRY TO REMAIN FOR
RECONNECTION.
4. REMOVE POWER AND MAKE SAFE. REMOVE FEEDERS BACK TO SOURCE PANEL.
5. REMOVE EXISTING MSB AND ASSOCIATED BRANCH CIRCUITRY, UNLESS NOTED
OTHERWISE. REFER TO ONE-LINE DIAGRAM ON SHEET RE:1/E203 FOR ADDITIONAL
INFORMATION.
KEYED NOTES: (APPLIES TO THIS SHEET)
E202
ENLARGED
ELECTRICAL FLOOR
PLANS - PHASE 2
SCALE:
NORTH
1 GIRLS DRESSING ROOM - PHASE 2
ENLARGED ELECTRICAL PLAN - MECH RM AND
1/4" = 1' - 0"
SCALE:
NORTH
3 WORK ROOM - PHASE 2
ENLARGED ELECTRICAL PLAN -
1/4" = 1' - 0" SCALE:
NORTH
4 JANITOR CLOSET - PHASE 2
ENLARGED ELECTRICAL PLAN -
1/4" = 1' - 0"SCALE:
NORTH
2 AND STORAGE - PHASE 2
ENLARGED ELECTRICAL PLAN - MECH RM
1/4" = 1' - 0"
E
D
C
B
A
654321
Drawn Checked Date Project No.
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
LME
TJS
23002 10/13/23
NOTE TO CONTRACTOR:
PRIOR TO CONSTRUCTION, CONTRACTOR SHALL COORDINATE
AND SCHEDULE ELECTRICAL SERVICE OUTAGES TO EXISTING
FACILITIES WITH OWNER IN ADVANCE OF OUTAGE.
SCALE:
NORTH
5 ENLARGED ROOF PLAN - PHASE 2
1/4" = 1' - 0"
Revisions 1 11-27-2023 Addendum #03
/2
7/
MOTOR
STARTERS
EXISTING CPS TRANSFORMER
WATER VALVES & BACKFLOW PREV
UTILITY YARD
WIREWAY
LDR2 HV1
LE
LC
EF-2 EF-1
B-1
FD
FD
AS-1
CH-1
CHP-1
CHP-2
VFD-1
VFD-2
'MSB'
MDPL
GND
SEC 1 SEC 2
T-MDPL
CENTRAL PLANT
CONTROLLER
AHU CONTROLLER
HVAC CONTROLS
HV1-56,58,60
HV1-55,57,59
MSB-7 3
AHU
CONTROLLER
LB
HA 1
LD
LA
1. PROVIDE NEW PANELBOARD, AS INDICATED. RECONNECT BRANCH CIRCUITRY SALVAGED
DURING DEMOLITION. REFER TO PANELBOARD SCHEDULE FOR ADDITIONAL INFORMATION.
2. PROVIDE POWER CONNECTION TO HVAC EQUIPMENT, AS INDICATED. REFER TO PANEL
SCHEDULES FOR ADDITIONAL INFORMATION.
3. PROVIDE POWER CONNECTION TO CHILLER WITH INTEGRAL DISCONNECT.
KEYED NOTES: (APPLIES TO THIS SHEET)
E302
ENLARGED
ELECTRICAL FLOOR
PLANS - PHASE 3
SCALE:
NORTH
1 GIRLS DRESSING ROOM - PHASE 3
ENLARGED ELECTRICAL PLAN - MECH RM AND
1/4" = 1' - 0"
SCALE:
NORTH
3 WORK ROOM - PHASE 3
ENLARGED ELECTRICAL PLAN -
1/4" = 1' - 0" SCALE:
NORTH
4 JANITOR CLOSET - PHASE 3
ENLARGED ELECTRICAL PLAN -
1/4" = 1' - 0"SCALE:
NORTH
2 AND STORAGE - PHASE 3
ENLARGED ELECTRICAL PLAN - MECH RM
1/4" = 1' - 0"
E
D
C
B
A
654321
Drawn Checked Date Project No.
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
LME
TJS
23002 10/13/23
Revisions 1 11-27-2023 Addendum #03
/2
7/
E303
ELECTRICAL
ONE - LINE DIAGRAM
PHASE 3
E
D
C
B
A
654321
Drawn Checked Date Project No.
Revisions
2023 Marmon Mok, LLP Unauthorized reproduction is prohibited.
c
SHEET TITLE
SHEET NO.
Fi le
P at h
2/ 8/
:3
4:
P M
FR
AN
K G
AR
R
ET
T
C O
M M
U N
IT
Y
C
EN
TE
R
R
EN
O
VA
TI
O
N
PA
C
KA
G
E
N W
8t h St
Sa n An to ni o, T
X
LME
TJS
23002 10/13/23
CHILLER
CH-1
T-LDR2
15kVA XFMR
112.5 kVA
XFMR
T-MDPL
NEW
PANEL
'LC'
125A MLO
208/120V
3PH, 4W
N1
NEW
PANEL
'HA'
225A MLO
480/277V
3PH, 4W
N1
NEW
PANEL
'LB'
225A MLO
208/120V
3PH, 4W
N1
NEW
PANEL
'LE'
125A MLO
208/120V
3PH, 4W
N1
NEW
PANEL
'LD'
100A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'HV1' SEC1
200A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'HV1' SEC 2
200A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'LDR2'
100A MLO
208/120V
3PH, 4W
N1
EXISTING
PANEL
'MDPL'
400A MCB
208/120V
3PH, 4W
N1
FEEDER SCHEDULE
3 PHASE, 4 WIRE
TAG CONDUIT PHASE CONDUCTORS NEUTRAL CONDUCTORS GROUND CONDUCTORS
1000N (3)3" EACH WITH (3)#400 KCMIL (1)#400 KCMIL (1)# 2/0 GND.
400N (1)4" EACH WITH (3)#600 KCMIL (1)#600 KCMIL (1)# 3 GND.
225N (1)3" EACH WITH (3)#4/0 AWG (1)#4/0 AWG (1)# 4 GND.
125N (1)2" EACH WITH (3)#1 AWG (1)#1 AWG (1)# 6 GND.
100N (1)2" EACH WITH (3)#3 AWG (1)#3 AWG (1)# 8 GND.
3 PHASE, 3 WIRE
TAG CONDUIT PHASE CONDUCTORS NEUTRAL CONDUCTORS GROUND CONDUCTORS
175 (1)1-1/2" EACH WITH (3)2/0 AWG NA (1)#3 GND.
NOTES:
1. CONDUIT SIZES ARE FOR CONDUIT INDICATED WITH THHN, THWN INSULATED COPPER CONDUCTORS WITH MAXIMUM 40% FILL. CONTRACTOR SHALL ADJUST CONDUIT SIZE AS REQUIRED PER NEC APPENDIX C, CONDUIT FILL TABLES FOR ALL OTHER CONDUIT AND INSULATION TYPES.
2. REFER TO SPECIFICATIONS FOR ADDITIONAL CONDUIT APPLICATION AND INSTALLATION REQUIREMENTS.
3. PROVIDE LUGS AS REQUIRED FOR FEEDERS INDICATED.
400N
225N
NEW
PANEL
'LA'
225A MLO
208/120V
3PH, 4W
N1
225N 225N 125N 125N
100N
11-27-2023 Addendum #03
400N
400A
400AF
/2
7/
| Addendum 3 |
| 2023-11-27 - Frank Garrett Package 2 - Add 04 - Narrative |
| 2023-11-27 - Frank Garrett Package 2 - Add 04 - MP Drawings |
| Sheets and Views |
| 23002 - M201 - Mech Schedules & Details-30x42 M201 |
| 2023-11-27 - Frank Garrett Package 2 - Add 04 - E Drawings |
| Sheets and Views |
| 30x42 E102 |
| 30x42 E103 |
| 30x42 E202 |
| 30x42 E302 |
| 30x42 E303 |
File details come from the government source that posted it. Updated .