ESBD_File_331886_IFB CIPS23-012 16 Waterline Extension Lakeline Blvd._ATTACHMENT K - Technical Specifications.pdf
PDF 5 MB Posted
- Attached to
- Lakeline Boulevard 16” Waterline Extension
- Solicitation number
- CIPS23-012
- Issued by
- Williamson County, Laredo City, Texas
About this file
This document is an attachment related to a state and local contract opportunity for the City of Leander, Texas to construct a 16-inch waterline extension along Lakeline Boulevard between Stinnett Drive and Hero Way West, as well as install an off-site altitude valve at a 1.25 MGD elevated storage tank.
The scope of work includes approximately 4,400 linear feet of 16-inch water main, associated appurtenances, valves, and a service connection to existing water mains. Jacking and boring is required to cross existing box culverts. The contractor will be responsible for securing all construction-related permits, providing temporary utilities, and restoring all areas affected by construction. The project is being designed and managed by Walter P. Moore and Associates, Inc. No award date or contract term is provided.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 1
GENERAL
REQUIREMENTS
Division 1 - General Requirements
SUMMARY OF WORK
Section 01010
Rev. Date 08/28/2020 Summary of Work / 01010 Page 1 of 5
PART 1 - GENERAL
1.1 Related Documents:
Drawings and general provisions of Contract, including General Conditions, Section 00700, and Supplemental General Conditions, Section 00810, and Division 1 requirements.
1.2 DESCRIPTION OF WORK
1.21 Scope of Work
A. The scope of work consists of the necessary labor, materials, equipment and supervision to construct approximately installation of approximately 4,400 LF of 16-inch diameter water main, appurtenances, valves and service connection to existing water mains and an off-site installation of an altitude valve at Northwest 1.25 MGD elevated tank at 770
Count Road 280. Jacking and boring is also required to cross underneath existing box culverts. CONTRACTOR shall, except as otherwise specifically stated herein or in any applicable part of these Contract Documents, provide and pay for all labor, materials, equipment, tools, construction equipment, and other facilities and services necessary for proper execution, testing, and completion of the Work.
B. Any part or item of the Work which is reasonably implied or normally required to make the installation satisfactorily operable shall be performed by the CONTRACTOR and the expense thereof shall be included in the applicable unit prices or lump sum prices bid for the
Work. It is the intent of these Specifications to provide the OWNER with the complete system.
All miscellaneous appurtenances and other items of Work that are incidental to meeting the intent of the Specifications shall be considered as having been included in the applicable unit prices or lump sum prices bid for the Work even though these appurtenances and items may not be specifically called for in the Bid Documents.
C. The Work shall include furnishing all tools, labor, materials, equipment, and miscellaneous items necessary for the complete construction of approximately 4,400 linear feet of 16-inch water main and appurtenances and an off-site altitude valve for a 1.25 MGD elevated tank.
1.22 Location of Project
A. The Project begins on the northern side of the intersection of Hero Way West and
Lakeline Boulevard. Approximately 4,400 linear feet of 16-inch water main will be installed on the eastern side of Lakeline Boulevard, heading southbound where the 16-inch main extension will eventually connect to the existing 16-inch water main by removing the existing cap and plug. The altitude valve will be installed at the 1.25 MGD elevated storage tank located at 770 CR280. A detailed project location/route is shown on the Drawings.
1.23 Contractor's Responsibilities
A. Execute all Work, including excavation, installing pipe, backfill, miscellaneous concrete and testing as defined in the plans and specifications.
B. The Work of this Contract is specified in the City of Leander standard specifications. Where City of Leander standard specifications are not available, Rev. Date 08/28/2020 Summary of Work / 01010 Page 2 of 5 the City of Austin Standard Specifications, Special Provisions and Special
Specifications listed in the Table of Contents are to be utilized.
C. Secure all construction-related permits, other than those provided by OWNER as described in paragraph 6.6 of Section 00810, Supplemental General Conditions, and pay for the same.
D. Arrange for the necessary temporary water and electric service and pay for these services and all water and electricity consumed during the construction Work.
E. Provide adequate temporary sanitary facilities.
1.24 Easements and Rights-Of-Way
CONTRACTOR shall confine his construction operations within the limits indicated on the
Drawings, and shall use due care in placing construction tools, equipment, excavated materials, and pipeline materials and supplies so as to cause the least possible damage to property and interference with traffic. If the CONTRACTOR requires additional easement for his operations, the CONTRACTOR is solely responsible for acquisition and maintenance of the easement. No additional compensation will be provided by the OWNER.
A. Easements - Easements across private property are indicated on the Drawings.
CONTRACTOR shall set stakes to mark the boundaries of construction easement across private property. The stakes shall be protected and maintained until completion of construction and cleanup.
B. Rights-of-Way - Permits for Work in rights-of-way shall be obtained by the
CONTRACTOR. All Work performed and all operations of CONTRACTOR, his employees, or subcontractors, within the limits of railroad and highway rights-of-way, shall be in conformity with the requirements and be under the control (through OWNER) of the railroad or highway authority owning, or having jurisdiction over and control of, the right-of-way in each case.
1.25 Operation of Existing Facilities
Existing water and wastewater facilities shall be kept in continuous operation throughout the construction period. No interruption will be permitted which adversely affects the degree of service provided. Provided permission is obtained from OWNER in advance, portions of the existing facilities may be taken out of service for short periods corresponding with periods of minimum service demands.
CONTRACTOR shall provide temporary facilities and make temporary modifications as necessary to keep the existing facilities in operation during the construction period.
1.26 Connections to Existing Facilities
Unless otherwise specified or indicated, CONTRACTOR shall make all necessary connections to existing facilities including structures, drain lines, and utilities. In each case, CONTRACTOR shall receive permission from OWNER or the owning utility prior to undertaking connections.
CONTRACTOR shall protect facilities against deleterious substances and damage.
Connections to existing facilities which are in service shall be thoroughly planned in advance, and all required equipment, materials and labor shall be on hand at the time of undertaking
Rev. Date 08/28/2020 Summary of Work / 01010 Page 3 of 5 the connection. Work shall proceed continuously (around the clock) if necessary to complete connections in the minimum time. Operation of valves or other appurtenances on existing utilities, when required, shall be by or under the direct supervision of the owning utility.
1.27 Unfavorable Construction Conditions
No portion of the Work shall be constructed under conditions which adversely affect the quality or efficiency thereof, unless special means or precautions are taken by CONTRACTOR to perform the Work in a proper and satisfactory manner.
END
Rev. Date 08/28/2020 Summary of Work / 01010 Page 4 of 5
Signatures
CONTRACTOR agrees that this Work Assignment is a Contract Document and that work performed and payments made pursuant to this Work Assignment shall be subject to the terms and conditions of all other Contract Documents for the Contract referenced above, unless otherwise noted. The
CONTRACTOR shall be paid for work described in this Work Assignment, in whole or in part, based on the unit/unit costs as provided in the Bid Form, Section 00300-IDIQ and all Change Orders.
The undersigned, by their signature, represents that they are submitting a binding offer and are authorized to bind the respondent to fully comply with the contract documents contained herein.
CONTRACTOR
Signature/Title: Date:
Notice to Proceed
When executed by the OWNER and delivered to the CONTRACTOR, the CONTRACTOR is authorized to proceed with Work as described in this Work Assignment, for the amount indicated above, in accordance with the contract referenced above and incorporated herein.
Project Manager Signature: Date:
Public Works Office Signature: Date:
Inspector
Inspector Supervisor (required when changes are made to previous Work
Assignment)
Signature:
Signature:
Date:
Date:
Rev. Date 08/28/2020 Summary of Work / 01010 Page 5 of 5
Public Works Office
Subcontractor Utilization Form
Contract Development and Administration Division
Firm Cert Type Description of Work Amount $
TOTAL $
Project Manager /
Assignment Number
Date: Firm:
Project Location:
Submitted by:
Contract Number
SECTION 01014 ENVIRONMENTAL PROTECTION
June 2022 01014 - Page 1 of 7
SECTION 01014
ENVIRONMENTAL PROTECTION
PART 1: GENERAL
1.01 SCOPE OF WORK
A. Construction of the Work covered by these Contract Documents is subject to the applicable provisions and rules of the Texas Commission on Environmental Quality (TCEQ) and United States Army Corps of Engineers and all other applicable Federal, State, and Local laws, rules, regulations, ordinances, and conditions/requirements of permits issued by governmental agencies for the conduct of this project.
1.02 RELATED SECTIONS
A. 01300 – Submittals
1.03 SUBMITTALS
A. Record Data - Storage and Fueling Plan: for hydraulic fluid, oil, and fuel: Submit for approval by ENGINEER prior to bringing fuel storage on-site. Describe plan for fueling equipment and fuel storage including spill prevention, containment, and cleanup provisions. Provide a list of all equipment that will contain more than 55 gallons of hydraulic fluid, oil, or fuel. Provide drawings for the secondary containment systems pertaining to above ground fuel storage tanks, equipment- mounted fuel tanks, oil reservoirs, and oil and fuel lines (including hydraulic fluid lines). Provide a description on how secondary containment will be inspected. Provide a description on how fueling operations will be handled over or near a waterway, or on shore, describing environmental protection methods that will be implemented. Provide description for requesting additional fuel storage containers not included in initial request. Provide inspection form to be used on a weekly basis in evaluating these areas.
B. Record Data - Equipment Maintenance Plan: Describe plan for minimizing the potential environmental impacts of preventative and non-scheduled equipment maintenance activities. Describe what environmental protections measures will be implemented prior to and during both preventative and non-scheduled equipment maintenance activities.
C. Record Data – Equipment Inspection Reports: Provide inspection procedure and example inspection form to be used on a weekly basis to report equipment inspections.
D. Record Data – MSDS: Provide MSDS data sheets on all proposed fuels, chemicals, paints greases, hydraulic fluids, coatings, epoxies, cements, admixtures, etc. to be
June 2022 01014 - Page 2 of 7 used on and with equipment, to be used temporarily during construction, and to be permanently incorporated into the work.
E. Record Data – Materials used to perform the Work: Provide a list for the following types of materials that will be used in performing the Work.
1) Ozone-depleted chemicals
2) Materials with volatile organic compounds (VOC’s)
3) Any material that will become an F-Listed waste (e.g., acetone, xylene, toluene, methyl ethyl ketone).
4) Acutely toxic materials.
5) Constituents subject to reporting under the state and federal Right-to-Know regulations (as shown on the Material Data Sheets).
F. Record Data – Care of Water Plan: Describe plan for dewatering an area and managing water flows and infiltration into the work area. All water flows from, or generated by the work, must meet State and Federal regulations prior to entering a creek, stream or a lake. Regulations include, but not limited, to 30 TAC 307 and 26 TWC 121, Surface Water Quality Standards and Water Quality Control for the State of Texas respectively.
G. Record Data – Storm Water Inspections: Contractor to submit weekly storm water inspections to OWNER based on Storm Water Pollution Prevention Plan provided by
OWNER.
1.04 PROTECTION OF LAND RESOURCES
A. The land resources, within the project boundaries and outside the limits of work under the Work of this Contract, shall be preserved in their present condition or be restored to a condition after construction that will appear to be natural and not detract from the appearance of the project. Activities shall be confined to areas defined by the Drawings and Specifications.
1.05 PROTECTION OF WATER RESOURCES
A. No water courses shall be polluted with any construction debris, loose soil, suspended sediment, petroleum products, abrasives, epoxies, paints, solvents, cleaners, fuels, surface preparation materials, oils, lubricants, bitumens, calcium chlorides, insecticides, herbicides, or other toxic materials harmful to life unless specifically permitted. Chemical emulsifiers, dispersant, coagulants, or other cleanup compounds shall not be used without prior written approval. It is the responsibility of the CONTRACTOR to ensure compliance with state and local water quality standards and to identify if any additional discharge permits are required to perform Work.
June 2022 01014 - Page 3 of 7
B. The CONTRACTOR may be required to submit a certified Spill Prevention Control and Countermeasures Plan (SPCC) that will fulfill the requirements of the Clean Water Act, CFR Part 112. In the event that the total capacity of all hydraulic fluid, oil, fuel containing tanks, containers, and equipment exceeds 1,320 gallons and if the project continues after 8/1/06 then an SPCC I required. The plan must be prepared prior to installing or mobilizing equipment that would cause the 1,320-gallon limit to be exceeded.
C. The CONTRACTOR will submit for approval all fuel storage containers, prior to mobilizing containers onto site, in accordance with Edwards Aquifer Rules (30 TAC 213). Additional fuel storage containers not approved in initial request must be individually approved by the ENGINEER.
1.06 DEWATERING
A. The CONTRACTOR will control and manage all dewatering of the project, and any non-storm water discharges from the construction site in compliance with all TCEQ water quality discharge requirements, including but not limited to 30 TAC 307, Surface Water Quality Standards for the State of Texas.
B. Contractor shall provide continuous observation of dewatering activities and effectiveness of BMP’s.
C. The following non-storm water discharges from construction activities are acceptable.
1) Discharges from fire fighting activities
2) Fire hydrant flushings
3) Vehicle, external building, and pavement wash water where detergents and soaps are not used and where spills or leaks of toxic or hazardous materials have not occurred (unless spilled materials have been removed; and if local, state, or federal regulations are applicable, the materials are removed according to those regulations), and where the purpose is to remove mud, dirt, and dust
4) Water used to control dust
5) Potable water sources including waterline flushings
6) Air conditioning condensate
7) Uncontaminated ground water or spring water, including foundation or footing drains where flows are not contaminated with industrial materials such as solvents or other pollutants
D. Dewatering and non-storm water discharges will, at a minimum, flow through silt fence, or other suitable structural controls, prior to leaving the site, as necessary to meet compliance requirements with all State and Federal water quality discharge requirements, including but not limited to 30 TAC 307 or 26 TWC 121, Surface Water Quality Standards and Water Quality Control for the State of Texas respectively.
June 2022 01014 - Page 4 of 7
E. Dewatering of water contaminated with hydrocarbons or other oils is prohibited from being discharged to a creek, stream, lake, or the soil surface.
1.07 PROTECTION OF AIR QUALITY
A. All Work shall be performed in such a manner as to ensure that air quality is protected.
CONTRACTOR will complete and maintain all records to support compliance with the applicable air quality standards including but not limited to 30 TAC 106.183.
1.08 PROTECTION OF FISH AND WILDLIFE
A. All Work shall be performed and all steps taken to prevent interference or disturbance to fish and wildlife. Water courses or habitats outside the project boundaries shall not be altered or disturbed, without OWNER’s written prior consent.
1.09 BURNING OF DEBRIS
A. No debris or surplus materials may be disposed of by burning at the job site or at any other location.
1.10 INFORMATION REGARDING WASTES REQUIRED WITH BID
A. Waste control measures shall be implemented during construction activities to prevent unauthorized release and ensure proper management of waste in accordance with Section 02105 – Containment and Disposal of Waste.
1.11 PROHIBITED MATERIALS
A. The CONTRACTOR is strictly prohibited from using any of the following types of materials that could generate waste in performance of the work.
1) Asbestos, asbestos-containing material (ACM)
2) Mercury containing material
3) Surface coatings with lead, cadmium, chromium, or mercury
4) PCB containing material
5) Radioactive containing material
1.12 ENVIRONMENTAL INSPECTIONS
A. The OWNER reserves the right to perform environmental inspections. The CONTRACTOR shall provide remedial action as required by the OWNER.
PART 2:
NOT USED
June 2022 01014 - Page 5 of 7
PART 3: EXECUTION
3.01 EROSION CONTROL DURING CONSTRUCTION
A. The CONTRACTOR shall utilize the Best Management Practices (BMP’s) with regard to controlling erodible soils within the construction lay-down area, project site, and while working near water, or water courses. This may include installing and maintaining silt fences or other similar structural controls as prescribed within the Storm Water Pollution Prevention Plan or additional controls as needed for any erodible soil, or storage of materials within the lay-down area and work site.
3.02 STORM WATER POLLUTION PREVENTION PLAN SWPPP
A. Implementation of the SWPPP is required. The CONTRACTOR shall provide a SWPPP specifically prepared for the project in accordance with TCEQ and Leander requirements, and will perform all actions required within the SWPPP in relation to day to day on site activities including: weekly inspections of controls, and maintenance to sediment and erosion controls based on inspection records.
Contractor shall provide a copy of the inspection records to Owners Representative on a weekly basis beginning with first required inspection, in addition, CONTRACTOR will maintain records in accordance with Texas Pollution Discharge Elimination System requirements.
3.03 PLACEMENT OF TEMPORARY PLATFORMS AND ACCESS FACILITIES
A. Temporary platforms or other temporary access facilities may be placed for temporary construction access to perform required Work. All placements of temporary platforms shall be conducted in accordance with the terms and general conditions of the U.S.
Army Corps of Engineers Nationwide Permit Program and other environmental compliance requirements specified herein.
3.04 PREVENTIVE MAINTENANCE, FUELING, AND SPILL CONTAINMENT
A. Scheduled preventive maintenance shall be performed on all construction equipment prior to mobilization in the work area. CONTRACTOR shall establish a maintenance area within the staging area for performing all routine and preventative maintenance, when possible. CONTRACTOR shall thoroughly inspect all construction equipment for any leaks prior to use at the job site and on a daily basis.
B. A spill can be defined as an accidental release of a solid, liquid, or gas to land, air, or water that would create a potential or actual hazard to human health or the environment.
1) The CONTRACTOR is solely responsible for any spills or release caused by himself or any of his subcontractors that occur during the performance of, or in connection with the performance of the Work under this Contract. The CONTRACTOR shall be responsible for all notifications required by any
June 2022 01014 - Page 6 of 7 federal, state, or local law or regulations. The CONTRACTOR shall immediately notify the OWNER of the nature and location of any spill. The CONTRACTOR shall provide a written report to OWNER that identifies the substance, quantity released, location of the spill, agencies notified/talked to if any, cleanup and remediation activities conducted or planned. The written report should be a narrative that summarizes on the scene activity, remediation efforts, and if long term remediation will be required. This initial report shall be provided to the OWNER within 24 hours after the incident. Follow up reports may be required if requested by the OWNER. These requirements are also required if the spill occurs off the OWNER’s property as a result of contractors performance of the Work under this Contract.
2) The CONTRACTOR shall be liable for, and agrees to indemnify and hold the OWNER harmless from any and all liabilities, including, but not limited to, remediation costs, fines, penalties, court costs, and attorney fees resulting from spills, releases, improper handling and/or disposal of wastes connected with a spill by the CONTRACTOR.
3) Spills shall be cleaned up to background levels or to criteria as set forth in the applicable federal, state, or local laws and regulations, or whichever is the most stringent.
C. The CONTRACTOR shall provide a temporary secondary containment berm with plastic liner around all stationary construction equipment subject to potential leakage of fluids or fuel to contain accidental leakage and/or discharges. Detection and cleanup of liquid fuel, oil leaks, or spills, shall be accomplished as follows.
1) Leak Detection: Leaks from any tanks or lines on equipment shall be detected by the CONTRACTOR during a daily check. Any fuel, oil, or chemical leak shall be reported immediately verbally and then in writing, in the appropriate format, to the OWNER’s Resident Representative. The CONTRACTOR shall ensure that the source of the leak is repaired and that the spilled fluid is cleaned up immediately and thoroughly.
2) Leak Cleanup: The CONTRACTOR shall be responsible for all spill cleanups and notify OWNER’s Resident Representative immediately. Any fuel, oil, or chemical leakage shall be collected in the bermed area surrounding the equipment using absorbent material. Contractor shall keep absorbent materials on site for clean up. Contaminated absorbent materials shall be disposed of in accordance with Section 02105 – Containment and Disposal of Waste.
3) Oil Filters: Used oil, oil filters, and cartridges shall be collected by the CONTRACTOR and these items will be recycled at an OWNER approved and audited recycling facility.
4) Operation of Equipment in Areas Subject to Direct Discharge to Waterways:
Special precautions shall be taken to prevent releases of fuel, oil or chemicals when equipment is working over or adjacent to the water. This shall include provision of secondary containment for equipment-mounted fuel tanks, oil reservoirs, and fuel and oil lines (including hydraulic fluid lines). Exposed hydraulic lines shall be double wrapped and/or shielded by the use of
June 2022 01014 - Page 7 of 7 deflectors, as necessary, to prevent a release to the water in the event of a line rupture. No fuel container larger than 250 gallons shall be stored on- site outside of the staging area designated on the construction drawings, unless prior written approval by the owner. Fueling of equipment over or adjacent to water shall be done using a maximum fuel storage/transfer container size of five (5) gallons. A funnel shall be used to minimize fuel spillage, and a drip pan shall be used to capture any spillage of fuel. If the total quantity of containers smaller than five gallons on a barge, platform, walkway, or structure exceeds five (5) gallons, then these multiple items shall be kept in secondary containment while in storage.
D. The CONTRACTOR should attempt to use and work with the least amount of chemicals or fuels needed for a given job.
3.05 NOISE CONTROL
A. The CONTRACTOR shall take reasonable measures to avoid unnecessary noise. Such measures shall be appropriate for the normal ambient sound levels in the area during working hours. All construction machinery and vehicles shall be equipped with appropriate sound muffling devices and operated in a manner to cause the least noise consistent with efficient performance of the Work.
3.06 EQUIPMENT HYDRAULIC SYSTEMS
A. All hydraulic systems and lines on CONTRACTOR’s equipment should be evaluated to determine if vegetable-based or environmentally friendly hydraulic oil can be utilized over waterways. Vegetable-based or environmentally friendly hydraulic oil is required if equipment manufacturer allows replacement of standard hydraulic oils. Provide MSDS sheets on the proposed hydraulic fluids. All hydraulic systems shall be double wrapped with absorbent materials or use deflective devises.
PART 4: MEASUREMENT AND PAYMENT
4.01 GENERAL
A. Separate measurement or payment will not be made for Work required under this Section. All costs in connection with the Work specified herein will be considered to be included with the related item of Work in the Bid Schedule, or incidental to the Project.
END OF SECTION 01014
SECTION 01015 CONTRACTOR USE OF THE PREMISES
February 2015 01015 - Page 1 of 5
SECTION 01015
CONTRACTOR USE OF THE PREMISES
PART 1: GENERAL
1.01 SCOPE OF WORK
A. The CONTRACTOR shall not begin construction until all erosion and sedimentation control devices shown on the plans and related to the portion of the work have been installed, a preconstruction meeting at the site has been held per the plans, and the inspector has approved the erosion and sedimentation controls.
B. Spoil material to be used on the job shall be stored within the limits of construction shown on the Plans. Trash, material unsuitable for fill and spoil material shall be permanently disposed of offsite. The CONTRACTOR shall take care not to cause mud, dirt and dust to be carried off the site. When construction is complete the site shall be fully restored and cleaned up of all trash, debris and contaminated soils due to chemical spills or other similar products. No burning on-site is permitted.
C. All workers employed by the CONTRACTOR shall have such skill and experience as will enable them to properly perform the duties assigned them. Any person employed by the CONTRACTOR or a subcontractor who, in the opinion of the OWNER’S REPRESENTATIVE, does not perform his work in a proper and skillful manner, or who is disrespectful, intemperate, disorderly, or otherwise objectionable, shall at the written request of the OWNER’S REPRESENTATIVE be forthwith discharged and shall not be employed again on any portion of the work without the written consent of the OWNER’S REPRESENTATIVE. The CONTRACTOR shall furnish such suitable machinery, equipment, and construction forces as may be necessary, in the opinion of the OWNER’S REPRESENTATIVE, for the proper prosecution of the work, and failure to do so may cause the OWNER’S REPRESENTATIVE to withhold all estimates which have or may become due or the OWNER may suspend the work until his requests are complied with.
D. All work within temporary or permanent easements shall conform to any and all restrictions, conditions, and/or requirements as may be set forth in the related specific easement documents. Easements secured for this project are shown on the plans and will be presented to the CONTRACTOR.
E. All work within staging and storage areas obtained by CONTRACTOR shall conform to all requirements of these specifications.
1.02 NOTIFICATION OF PROPERTY OWNERS
A. Unless otherwise indicated, the CONTRACTOR will notify property owners abutting the right-of-way or easements, or otherwise that will be affected by construction activities, of impending construction. The CONTRACTOR shall exercise diplomacy and tact with individual property owners. The CONTRACTOR shall specifically designate a single responsible individual that will be responsible for the giving of notifications to the affected property owners or tenants in accordance with this
February 2015 01015 - Page 2 of 5 section. The OWNER will have the right to approve the responsible individual and may ask that they be replaced at anytime.
B. CONTRACTOR shall give to property owners or tenants 48 hours notice prior to initiating work in their vicinity (within one city block or otherwise which might be affected by the work). Such notice shall be at a minimum presented by door hangers, the language on which shall be previously approved by the OWNER. The notice shall include a general description of the work to be accomplished, a direct contact name and local phone number for either the CONTRACTOR’s superintendent or the employee responsible for the giving of notices, the name and phone number of the OWNER’s onsite inspector, a general and accurate schedule identifying the time anticipated for the work and any other information pertinent to the work. Once notices are given, CONTRACTOR shall focus on completing that phase of work within the duration given. Subsequent notices may be required, at the sole discretion and direction of the OWNER, should the CONTRACTOR fail to complete the work within the identified schedule.
C. Additional 48 hours notices shall be provided to property owners, or others that may be affected by the work, at the sole discretion and direction of the OWNER, for subsequent work activities or phases in the same area that occur beyond 10 working days of completing a work phase identified in an initial notice.
1.03 PROTECTION OF PUBLIC AND PRIVATE PROPERTY
A. Contractor shall protect, shore, brace, support and maintain all underground pipes, conduits, drains, and other underground facilities uncovered or otherwise affected by the Contractor’s operations. All pavement, surfacing, driveways, curbs, walks, buildings, utility poles, guy wires, fences, sod, landscaping, irrigation, and other surface structures affected by construction operations shall be restored to their original condition, whether within or outside the easement/right-of-way. All replacements shall be made with new materials of equal appearance.
B. Only trees marked on the plan to be removed may be removed. All other trees shall be protected against injury from construction operations. Tree protection shall be installed at locations as indicated on the plans. Whenever practicable, the Contractor shall utilize hand excavations to tunnel underneath large tree roots.
C. Dust Control during construction shall be performed by the CONTRACTOR in a manner to minimize nuisance conditions and to the satisfaction of the OWNER’S REPRESENTATIVE. The CONTRACTOR shall provide a dust control system for trenching operations. No direct payment will be made for dust control.
D. On a daily basis the CONTRACTOR shall sweep all streets, driveways and parking areas on which trenching, excavating, pipe laying or other dust generating activities occur. A street sweeper containing a dust control system shall be maintained on the project site at all times that trenching, excavating, pipe laying or other dust generating activities are ongoing.
E. Hand excavate to tunnel under other underground obstructions.
February 2015 01015 - Page 3 of 5
1.04 TEMPORARY DRAINAGE PROVISIONS
A. CONTRACTOR shall be responsible for providing for the drainage of stormwater and such water as may be applied or discharged on the site in performance of the Work. Contractor shall construct temporary drainage facilities to handle, carry through, or divert around his Work all drainage flow, including storm flows to prevent silting of waterways or flooding damage to adjacent properties.
1.05 NOISE CONTROL
A. CONTRACTOR shall take reasonable measures to avoid unnecessary noise. Such measures shall be appropriate for the normal ambient sound level in the area during working hours. All construction machinery and vehicles shall be equipped with practical sound-muffling devices, and operated in a manner to cause the least noise consistent with efficient performance of the Work.
1.06 FENCES AND MAILBOXES
A. All existing fences affected by the Work shall be maintained by the Contractor until completion of the work. Fences which interfere with construction operations shall be maintained with temporary fencing that shall be in place at nights/weekends and when the Work is not progressing at that site.
B. Contractor shall remove, reset temporarily, and replace permanently all mailboxes that are affected by the work. Access to mailboxes for delivery U.S. Mail shall be provided at all times. Temporary and permanent installations shall conform to the requirements of the United States Postal Service. Payment for removing and resetting of mailboxes will not be paid for directly, but will be considered subsidiary to the various bid items. Any damage to mail boxes or posts shall be the responsibility of the Contractor.
1.07 WORK ON COMMERCIAL PROPERTIES
A. The CONTRACTOR shall maintain driveway access to all commercial properties during construction of mains and services. Work shall be phased to have a minimal impact on parking during construction. The CONTRACTOR shall coordinate with the property representative regarding the timing of parking space closures and timing of deliveries to the properties.
1.08 MAINTENANCE OF TRAFFIC
A. CONTRACTOR shall conduct his Work to have the least impact with vehicular and pedestrian traffic as is practicable. Whenever it is necessary to cross, obstruct, or close roads, driveways, and walks, whether private or public, the Contractor shall provide and maintain suitable traffic control devices, detours, or other temporary measures to accommodate travel, and shall provide reasonable notice to owners of private drives prior to interfering with them.
B. Safety and conveyance of traffic shall be regarded with prime importance. Unless otherwise directed, all portions of streets associated with this Project shall be kept
February 2015 01015 - Page 4 of 5 open and provided a dust free, smooth and comfortable ride to traffic. In making open cut street/driveway crossings, the CONTRACTOR shall not block more than one-half of the street/driveway at one time without approval of the Owner.
C. Prior to beginning Work, CONTRACTOR shall designate to the Owner a competent person who will be responsible and available to ensure compliance with the traffic control plans.
D. The CONTRACTOR shall perform the necessary cleanup and temporary or final finishing immediately at the end of each day to fully reopen all streets and driveways.
Temporary surfacing shall be provided where necessary to provide a smooth and safe ride in public streets and driveways.
E. Where indicated on the traffic control plan, CONTRACTOR shall erect and maintain detours around construction activities.
F. All traffic control devices shall be constructed and placed in accordance with the Texas Manual on Uniform Traffic Control Devices and the traffic control plans for the project. The Contractor shall be solely responsible for their placement and maintenance throughout the project.
G. All open trenches and other excavations shall have suitable barricades, signs, and lights to provide adequate protection to the public. Obstructions, such as material piles and equipment shall be provided with similar warning signs and lights, and shall be illuminated with warning lights from sunset to sunrise.
1.09 EMERGENCY FACILITIES
A. Free access shall be maintained at all times to fire lanes and emergency and utility control facilities such as fire hydrants, fire alarm boxes, police call boxes, and utility valves, manholes, junction boxes, etc. In the event that it is necessary to make on of these facilities temporarily inaccessible, the Contractor shall obtain approval of such action. Contractor shall also provide at least 24 hours prior notice to the Fire Department, Police Department, and/or governing agency of the facility.
B. Should a water line or gas line be broken by the Contractor during Work activities, or should other emergency conditions arise during the project, the following emergency notifications shall be immediately made by the Contractor.
Should a gas line be broken, the Contractor is to immediately notify the gas company owning the gas line and the following entities:
Leander Police Dept. (512) 528-2800 Leander Fire Dept. (512) 528-2856 Leander Inspector To be provided Leander Public Works (512) 528-2760
Should a water line be broken, the Contractor is to immediately notify the following entities:
Leander Public Works (512) 528-2760
February 2015 01015 - Page 5 of 5
Leander Inspector To be provided
PART 2: NOT USED
PART 3: NOT USED
PART 4: MEASUREMENT AND PAYMENT
A. No separate payment shall be made for work described in this section.
END OF SECTION 01015
Rev. Date 10/19/15 Grades, Lines and Levels/01050 Page 1 of 4
Division 1 General Requirements
Grades, Lines and Levels Section 01050
1. CONTRACTOR shall perform all layout work to transfer all controls for grades, lines, levels and measurements from a minimum of two reference points provided by OWNER.
All survey work will be performed under the direct supervision of a Texas Registered
Professional Land Surveyor (RPLS).
2. Within 5 work days of the Notice To Proceed date, or within 10 Working Days of initiating work based on the approved Schedule in a new area of the Project, the
CONTRACTOR shall survey and stake the locations of all proposed improvements behind the curb and within the ROW (examples: manholes, storm inlets, fire hydrants, etc.), or any other improvements identified by the OWNER’S REPRESENTATIVE, for the purpose of identifying the nature and location of these improvements to the adjacent property owner(s). The OWNER’S REPRESENTATIVE will identify to the CONTRACTOR the improvements to be staked.
3. OWNER will not stake for construction and will not be on site for survey layout activities, except to perform quality control checks.
4. CONTRACTOR shall be required to set elevation hubs (blue tops) for subgrade and base course on centerline, at quarter points and curb lines or edge of pavement at intervals not exceeding 50 feet.
5. The construction plans will include horizontal and vertical control points. References to surveyed benchmarks used in establishing controls on the drawings will be provided by the Owner’s E/A. In addition, on building projects and/or projects not built within an existing public ROW, a boundary survey will be supplied together with a legal description of the property and all easements where Work will take place.
6. CONTRACTOR shall submit construction staking layout sheets sealed by a Professional
Engineer or Registered Professional Land Surveyor registered in the State of Texas.
CONTRACTOR shall use a qualification based selection process consistent with the
Professional Services Procurement Act, Chapter 2254.004 of the Texas Government
Code, when securing the services of a Professional Engineer or Registered Professional
Land Surveyor. It is a violation of State Law to solicit bids for the services of a
Professional Engineer of Registered Professional Land Surveyor.
6.1 Any discrepancies found with the construction documents’ dimensional layout will be corrected. CONTRACTOR shall assure that the Owner’s Representative and
E/A are notified so that the appropriate actions are taken to correct the Contract drawings.
6.2 All Work shall be done to the lines, grades and elevations indicated on the drawings. Information concerning basic horizontal and vertical control points will be provided by the E/A, Surveying & Mapping (SAM). These points shall be used as the datum basis under this Contract.
6.3 All work to transfer all controls for grades, lines, levels, layout and measurements shall be performed under the supervision of a Texas Registered Professional Land
Surveyor, provided by the CONTRACTOR. Such work shall conform to the standards for construction staking in the most recent edition of the Texas Society of Professional Surveyors Manual of Practice for Land Surveying, Category 5, Sections 1-12 inclusive.
Rev. Date 10/19/15 Grades, Lines and Levels/01050 Page 2 of 4
6.4 The 16-inch water main centerline and offset centerline stakes will be set at no greater than fifty (50) foot intervals and at points of alignment or grade changes. References to lines and grades as established by the CONTRACTOR's surveyor shall be in reference to these stake lines. The CONTRACTOR is required to provide a sealed statement from their RPLS that the controls are correct and the site layout has been done by their professional staff.
6.5 The CONTRACTOR shall place grade stakes and submit construction staking layout sheets. The CONTRACTOR shall allow a minimum of ten (10) days after submission to the Owner’s Representative for review of construction staking layout sheets. Construction staking layout sheets shall include, at a minimum, the information contained in the form included at the end of this section. No
Work shall be performed without Owner’s Representative review and return to
CONTRACTOR of construction staking layout sheets. The Owner’s Representative, E/A and the CONTRACTOR shall review the survey controls on the ground.
6.6 Prior to any excavation, the CONTRACTOR shall establish the elevation to top of ground at the centerline of the pipe as well as cuts and offset stakes at the distance deemed appropriate by the CONTRACTOR to preclude disturbance of offset stakes during construction.
6.7 The CONTRACTOR shall furnish, without charge, experienced personnel and such calibrated survey equipment, tools, stakes, and other materials that the Owner’s
Representative may require in establishing or checking control points, or in checking survey, layout, and measurement work performed by the
CONTRACTOR.
6.8 The CONTRACTOR shall keep the Owner’s Representative informed in a reasonable time in advance of the times and places at which they wishes to do work, so that any checking deemed necessary by the OWNER may be done with minimum inconvenience to the E/A and minimum delay to the CONTRACTOR. Surveying will be coordinated between the Owner’s Representative and CONTRACTOR in a manner convenient to both.
6.9 During layout, CONTRACTOR shall field verify the elevation and alignment of all tie-in points to existing infrastructure. This work shall be performed sufficiently in advance of construction so that any conflicts may be resolved without delay.
Any work done without being properly located may be ordered removed and replaced at the CONTRACTOR's expense.
6.10 The CONTRACTOR shall carefully preserve all monuments, benchmarks, reference points, and stakes. In case of the destruction thereof, the CONTRACTOR shall bear the cost of replacement and shall be responsible for any mistake or loss of time that may be caused. Permanent monuments or benchmarks, which must be removed or disturbed, shall be protected until properly referenced for relocation.
The CONTRACTOR shall furnish materials and assistance for the proper replacement of such monuments or benchmarks.
6.11 The CONTRACTOR shall satisfy themselves before commencing work as to the meaning and correctness of all survey control stakes, marks, etc., and no claim will be entertained by the OWNER for or on account of any alleged inaccuracies, unless the CONTRACTOR notifies the OWNER in writing before commencing the affected Work.
Rev. Date 10/19/15 Grades, Lines and Levels/01050 Page 3 of 4
7. As needed for necessary documentation of the work progress, the CONTRACTOR shall maintain and/or protect offset or survey staking for the duration of the project.
Any re-staking required to meet this requirement shall be done at the
CONTRACTOR’S expense.
8. This item is subsidiary to the work as a whole.
End See attached “Construction Staking Layout Sheet”
Rev. Date 10/19/15 Grades, Lines and Levels/01050 Page 4 of 4
CONSTRUCTION STAKING LAYOUT SHEET
Project Name: Date:
C.I.P. ID#: Instrument No.:
Person Recording: Weather Conditions:
Crew Members:
General Purpose & Scope of Survey:
STATION
B.S.
H.I.
F.S.
LEVEL LOOP
ELEVATION
ROD
READING
HUB
AT STATION
(TARGET)
(eg., pipe invert)
C - CUT
OR
F - FILL
GRADE
NOTES:
INDICATE WHETHER
CENTERLINE HUB
OR _____ FT. OFFSET HUB
SECTION 01070 ABBREVIATIONS
February 2016 01070- Page 1 of 2
SECTION 01070
ABBREVIATIONS
PART 1: GENERAL
1.01 DESCRIPTION
A. The following abbreviations, in addition to those included in Division 0, whenever used in these Contract Documents, the intent and meaning shall be interpreted as follows:
AA Aluminum Association AAMA Architectural Aluminum Manufacturers Association AASHTO American Association of State Highway and Transportation Officials ACI American Concrete Institute AFBMA Anti-Friction Bearing Manufacturers Association AGA American Gas Association AGMA American Gear Manufacturers Association AIMA Acoustical and Insulating Materials Association AISC American Institute of Steel Construction AISI American Iron and Steel Institute AITC American Institute of Timber Construction AMCA Air Moving and Conditioning Association ANSI American National Standards Institute APA American Plywood Association API American Petroleum Institute AREA American Railway Engineering Association ASAE American Society of Agricultural Engineers ASCE American Society of Civil Engineers ASHRAE American Society of Heating, Refrigeration and Air-Conditioning
Engineers ASME American Society of Mechanical Engineers ASTM American Society for Testing and Materials AWI Architectural Woodwork Institute AWPA American Wood Preservers Association AWPB American Wood Preservers Bureau AWPI American Wood Preservers Institute AWS American Welding Society AWWA American Water Works Association BHMA Builders Hardware Manufacturers Association CBMA Certified Ballast Manufacturers Association CDA Copper Development Association CISPI Cast Iron Soil Pipe Institute CLFMI Chain Link Fencing Manufacturers Institute CMAA Crane Manufacturers Association of America CRSI Concrete Reinforcing Steel Institute
CS Commercial Standard, U.S. Department of Commerce ETL Electrical Testing Laboratories Fed. Spec. Federal Specifications HI Hydraulic Institute
SECTION 01070 ABBREVIATIONS
February 2016 01070- Page 2 of 2
HMI Hoist Manufacturers Institute ICBO International Conference of Building Officials IEEE Institute of Electrical and Electronic Engineers IPCEA Insulated Power Cable Engineers Association MIL- Military Specification (leading symbol) MMA Monorail Manufacturers Association MSS Manufacturers Standardization Society of the Valve and Fittings
Industry NAPF National Association of Plastic Fabricators NBHA National Builders Hardware Association NEC National Electrical Code NEMA National Electrical Manufacturers Association NESC National Electric Safety Code NFPA National Fire Protection Association NGVD National Geodetic Verified Datum NLMA National Lumber Manufacturers Association NSF National Sanitation Foundation NWMA National Woodwork Manufacturers Association OECI Overhead Electrical Crane Institute OFCI OWNER-furnished, CONTRACTOR-installed OFCR OWNER-furnished, CONTRACTOR-relocated OSHA Occupational Safety and Health Act (both Federal & State) PCA Portland Cement Association PDI Plumbing and Drainage Institute PS Product Standards Sections - U.S. Department of Commerce RMA Rubber Manufacturers Association SAE Society of Automotive Engineers SDI Steel Deck Institute SJI Steel Joist Institute SMACNA Sheet Metal and Air Conditioning Contractors, National Association SPR Simplified Practice Recommendations, U.S. Department of
Commerce SSPC Steel Structures Painting Council TCA Tile Council of America TEMA Tubular Exchanger Manufacturers Association UBC Uniform Building Code UL Underwriters' Laboratories, Inc.
WCLIB West Coast Lumber Inspection Bureau WIC Woodwork Institute of California WWPA Western Wood Products Association
PART 2: PRODUCTS - Not applicable to this Section.
PART 3: EXECUTION - Not applicable to this Section.
END OF SECTION 01070
Rev. Date 05/06/2022 Project Meetings / 01200 Page 1 of 4
PROJECT MEETINGS
Section 01200
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
Documents related to this section will include the construction drawings and general provisions of the Contract, including the General Conditions, Section 00700, Supplemental General Conditions, Section 00810, and other Division 1 requirements.
1.2 SUMMARY
A. This section describes the preconstruction conference and other Project related meetings which may be held on a routine schedule throughout the duration of the Project.
B. The CONTRACTOR, or his authorized representative(s), shall attend all Project related meetings as indicated herein. The CONTRACTOR's representatives, as a minimum, shall include his Project Manager and Superintendent. Other CONTRACTOR's representatives may attend Project related meetings; however, there shall be a maximum of four (4) CONTRACTOR’s representatives at any one meeting unless the ENGINEER/ARCHITECT approves a larger number.
C. The CONTRACTOR shall provide all pertinent reports, copies of reports, etc., for each meeting as may be required by this or other sections of the Contract.
D. All project related meetings shall be held in the Owner’s Representative office unless otherwise specified
1.3 PARTNERING WORKSHOP
Not applicable to this project. Intentionally left blank.
1.4 PRECONSTRUCTION CONFERENCE
A. Attendees
A preconstruction conference shall be held as soon after the award and execution of the Contract as possible and before any Work at the site is started. The conference will be held at a location selected by the Owner’s Project Manager. The Owner’s Project Manager shall prepare and distribute the meeting agenda, preside over the conference, and may distribute meeting minutes. The conference shall be attended by:
1. CONTRACTOR's Project Manager.
2. CONTRACTOR's Superintendent.
3. Any Subcontractors' and/or Suppliers' representatives whom the CONTRACTOR may desire to invite or whom the ENGINEER/ARCHITECT or OWNER may request to attend.
4. ENGINEER/ARCHITECT's representative.
5. OWNER’s Project Manager.
6. OWNER’s REPRESENTATIVE
7. OWNER’s Sponsor Department Representative.
8. Representative from the City of Leander, Transportation Department if a traffic management plan is required.
Rev. Date 05/06/2022 Project Meetings / 01200 Page 2 of 4
9. Representative from the City of Leander, Watershed Protection and Development Review Department, Environmental Inspection…
This is the start of the file's text. The full file is on GovTribe.