This is a Proposed Performance Schedule for the Camp Mabry Portables project, a Texas state and local contract opportunity. The project involves the delivery and installation of portable units at Camp Mabry, with multiple phases requiring coordination between the respondent and the client. Key milestones include an Award/Notice to Proceed by December 28, 2026, followed by an as-found foundation survey and report, unit ordering and fabrication release, CFMO layout reviews, conditions issuance, unit delivery and installation, MEP and low-voltage rough-in completion, and acoustic field testing. The critical deadline for CFMO occupancy approval is April 16, 2027, with separate target dates for North and South units. Owner move-in is scheduled to occur after TMD acceptance.

The schedule requires respondents to complete and submit the Proposed Performance Schedule as part of their bid response, as mandated by Section 8 of the Scope of Work. No pricing terms, set-asides, incumbent information, or funding sources are identified in this document, which serves solely to establish the timeline and performance expectations for project completion and delivery.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Proposed Performance Schedule - Camp Mabry Portables

Attachment G.7 Proposed Performance Schedule Camp Mabry Portables

Instructions: Respondents must complete and submit this Proposed Performance Schedule with their Bid as required by Section 8 of the Scope of Work.

Milestone Target date North South

Award / Notice to Proceed 12/7 NLT 12/28/2026 — —

As-found foundation survey and report

Units ordered/released for fabrication

CFMO layout reviews complete

THC conditions issued

Units delivered and set

MEP and low-voltage rough-in complete

Acoustic field testing complete —

CFMO occupancy approval No later than 04/16/2027

04/16/2027 04/16/2027

Owner move-in After TMD acceptance After acceptance

After acceptance