Camp Mabry Portables Re-Solicitation
Solicitation number
TMD27-CFMO-0046906
Issued by
Texas

About this file

This is a Pricing Schedule for the Camp Mabry Portables re-solicitation, a Texas state contract opportunity for modular facility construction and leasing services. Respondents must complete this pricing schedule as required by Section 9 of the Scope of Work. The contract involves the delivery, installation, and leasing of prefabricated modular facilities at two sites (North Site and South Site), classified under Building Construction, Prefabricated, All Types (909-25). Pricing must be provided for multiple line items including mobilization and foundation work, modular facility delivery and installation, interior fit-out and finishes, mechanical and plumbing systems, electrical and fire protection systems, IT and security infrastructure, permits and inspections, and general conditions. The contract structure includes one-time initial delivery and installation costs, a 36-month initial lease term with monthly lease rates and maintenance costs, and one-time demobilization and site restoration costs.

The pricing schedule establishes a Total Base Bid comprising three components: one-time initial delivery and installation costs, total 36-month lease costs (monthly rates multiplied by 36 months), and one-time demobilization costs. Bidders may also submit pricing for twelve bid options, including standby generators, fire sprinkler systems, acoustic enhancements, late-model-used units, lease extensions for years four and five, outright purchase options, and post-lease purchase options. Unit prices must be provided for six additional items including data drops, power feeds, acoustic partitions, doors, modular square footage, and rock excavation. Award will be based on the most responsive and responsible bidder offering the lowest Total Base Bid price, with TMD reserving the right to award all, none, or any sequence of bid alternates based on fund availability. The pricing schedule notes that award is contingent upon availability of state and/or federal funding.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pricing Schedule - Camp Mabry Portables Page 1 of 4

Attachment G.4 Pricing Schedule Camp Mabry Portables

Instructions: Respondents must complete and submit this Pricing Schedule with their Bid as required by Section 9 of the Scope of Work.

Class and Item: 909-25, Building Construction, Prefabricated, All Types.

No. Description North Site South Site Total

1 Mobilization, foundation and utility survey, as-found report (4.1)

2 Modular facility delivery, setting, tie-downs, marriage-line closure, and installation (4.2)

2A Skirting — (4.2) $ $ $

3 Interior fit-out and finishes (4.3) $ $ $

4 Acoustic privacy package — Group D/Group C (4.4)

N/A $ $

5 Mechanical and plumbing (4.5) $ $ $

6 Electrical, fire protection, life safety (4.6)

7 IT, AV, security, and low voltage (4.7) $ $ $

9 Permits, submittals, inspections, testing, commissioning, and CFMO review support

10 General conditions, supervision, insurance, overhead, and profit

Pricing Schedule - Camp Mabry Portables Page 2 of 4

No. Description North Site South Site Total

SUBTOTAL ONE-TIME INITIAL

DELIVERY AND INSTALLATION COST

11 Monthly lease rate – Initial 36-month term

$ /mo $ /mo $ /mo

12 Required Monthly maintenance and service – Initial 36-month term

$ /mo $ /mo $ /mo

Subtotal Monthly Lease Cost $ /mo $ /mo $ /mo

SUBTOTAL 36 MONTH LEASE COST $ $ $

15 Demobilization, removal, and site restoration if TMD does not exercise the Option to Purchase

SUBTOTAL ONE-TIME DEMOBILIZATION

COST

TOTAL BASE BID (To include One-Time Initial Delivery and Installation Cost, 36 Month Lease Cost & One-Time Demobilization Cost)

Bid Options (B.O.)

B.O. 1 Standby generator and/or UPS switches, or provisions for IT room

B.O. 2 Fire sprinkler system, if required $ $

B.O. 3 Electronic sound masking system (4.4.3) N/A $

B.O. 4 Additional acoustic field testing beyond the specified sample

N/A $

B.O. 5 Late-model-used units in lieu of new — credit/adjustment

N/A N/A N/A

Pricing Schedule - Camp Mabry Portables Page 3 of 4

No. Description North Site South Site Total

B.O. 6 Contractor-furnished physical cabling to private offices (Section 3.6)

B.O. 7 Stairs, ramps, landings, and accessible route —(4.1)

B.O. 8 Monthly Lease Extension (Year 4) $ /mo $ /mo $ /mo

B.O. 9 Monthly Lease Extension (Year 5) $ /mo $ /mo $ /mo

B.O. 10 Price for outright brand-new purchase $ $ $

B.O. 11 Price for outright Late-model-used units purchase

B.O. 12 Price for purchase after 36-month initial term

Provide Unit Prices (UP) for:

No. Description Units Unit Cost

UP-1 Additional Data Drops EA $

UP-2 Additional Workstation Power Feeds EA $

UP-3 Additional Acoustically Rated Partition (at STC 50) LF $

UP-4 Additional Acoustic Door Assembly EA $

UP-5 Additional Modular Square Footage SF $

UP-6 Rock Excavation CY $

* Award will be based on the most responsive, responsible Bidder and lowest price based solely on Total Base Bid. TMD will award based on best value for the state as directed by Texas Government Code § 2155.074 when awarding a Contract. Award is contingent upon the availability of State and/or Federal funding. TMD reserves the right to award all, none, or any sequence of bid alternates contingent upon the availability of funds.

N/A N/A N/A

Pricing Schedule - Camp Mabry Portables Page 4 of 4

Pricing Assumptions: Respondent shall provide any pricing amount assumptions for each Deliverable in reference to amounts and/or pricing conditions by outlining them in the table below.

No. Assumption

File details come from the government source that posted it. Updated .