ESBD_548091_1786380659131_Summary Bid Form Copy.xls
XLS spreadsheet 88 KB Posted
- Attached to
- Old McGregor Ground Storage Tank Improvements
- Solicitation number
- RFB2026-045
- Issued by
- Texas
About this file
This is a Summary Bid Form for the Old McGregor Ground Storage Tank Improvements project managed by the City of Waco, Texas. The project encompasses comprehensive water infrastructure improvements including demolition and removal, site improvements, ground storage tank installation, yard piping, existing tank selective rehabilitation, and electrical, instrumentation, and controls work. The bid form is structured with a base bid for Quarter 1 2027 Notice to Proceed and alternative pricing scenarios for Quarter 4 2027 Notice to Proceed. Key line items include mobilization and project incidentals (maximum 10% of total base bid), bonds and insurance (maximum 2.5% of total base bid excluding mobilization), a $100,000 owner's allowance, building Waco signage installation, stormwater pollution prevention plan implementation, trench and confined space safety plans and implementation, utility pothole coordination, private utility company coordination, and testing of improvements. The bid structure includes a base bid with three additive or deductive alternates for Quarter 1 2027 and revised pricing for Bid Alternate 4 with two additional alternates and one additive/deductive alternate for Quarter 4 2027 Notice to Proceed.
The City of Waco reserves the right to award either the Total Base Bid with any combination of Bid Alternates 1-3 based on Quarter 1 2027 Notice to Proceed or Bid Alternate 4 with any combination of Bid Alternates 5-7 based on Quarter 4 2027 Notice to Proceed, whichever option is most advantageous to the municipality. Contractors must provide revised pricing based on the applicable Notice to Proceed timeline, with Bid Alternate 4 representing the complete revised total base bid and Alternates 5 and 6 representing additional costs not inclusive of Alternate 4 or any Quarter 1 2027 pricing. Alternate 7 may be entered as either an additive amount (positive value) or deductive amount (negative value).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary Bid Form
| Summary Bid Form | |||||
| Item No. | Item Description | Quantity | Unit | Unit Price | Item Cost |
| Base Bid | |||||
| 1 | Mobilization, Permits, and Project Incidentals (Maximum 10% of Total Base Bid) | 1 | LS | ||
| 2 | Bonds and Insurance (Maximum 2.5% of Total Base Bid, Excluding Mobilization) | 1 | LS | ||
| 3 | Owner's Allowance (Allowance to be used only as authorized by the City of Waco) | 1 | LS | $100,000.00 | $100,000.00 |
| 4 | Building Waco Sign, including all signage, anchorage, installation, removal, and all material, labor, equipment, and incidentals, complete and in place | 1 | EA | ||
| 5 | Stormwater Pollution & Prevention Plan | 1 | LS | ||
| 6 | Stormwater Pollution & Prevention Plan Implementation, including all necessary material, labor, equipment, incidentals, and removal complete and in place | 1 | LS | ||
| 7 | Trench Safety Plan | 1 | LS | ||
| 8 | Trench Safety Implementation, including all material, labor, equipment, training, and incidentals, complete and in place | 1,383 | LF | ||
| 9 | Confined Space Plan | 1 | LS | ||
| 10 | Confined Space Implementation, including all material, labor, equipment, training, and incidentals, complete and in place | 1 | LS | ||
| 11 | Utility Potholes, including all necessary traffic control, traffic control plans, non-destructive potholing of the identified utility, coordination with utility provider, surveying of pothole, repair to surface, and all material, labor, equipment, and incidentals, complete and in place | 1 | LS | ||
| 12 | Coordination with Private Utility Companies, including coordination and permitting, temporary measures to protect private utilities, payment to private utility company sub-contractor to shield overhead electric lines, and all material, labor, equipment, and incidentals, complete and in place | 1 | LS | ||
| 13 | Testing of Improvements, including all testing required for acceptance of the water improvements, and all material, labor, equipment and incidentals, complete and in place | 1 | LS | ||
| 14 | Demolition and Removal (Detailed Bid Form: Bid Items 14-21) | 1 | LS | ||
| 15 | Site Improvements (Detailed Bid Form: Bid Items 22-32) | 1 | LS | ||
| 16 | Ground Storage Tank (Detailed Bid Form: Bid Item 33) | 1 | LS | ||
| 17 | Yard Piping (Detailed Bid Form: Bid Items 34 - 64) | 1 | LS | ||
| 18 | Existing 5.0 MG Ground Storage Tank Selective Rehabilitation (Detailed Bid Form: Bid Item 65) | 1 | LS | ||
| 19 | Electrical, Instrumentation, and Controls (Detailed Bid Form: Bid Item 66) | 1 | LS | ||
| Total Base Bid (Quarter 1 2027 Notice to Proceed*) | |||||
| Bid Alternates 1–3 (Quarter 1 2027 Notice to Proceed*) | |||||
| Bid amounts entered for Bid Alternates 1 and 2 shall represent additional costs and shall not include the Base Bid. Bid Alternate 3 may be additive or deductive. Enter an additive amount as a positive value and a deductive amount as a negative value. | |||||
| Additive Alternate #1 Bid (Detailed Bid Form: Bid Items 67 - 78), (Quarter 1 2027 Notice to Proceed*) | |||||
| Additive Alternate #2 Bid (Detailed Bid Form: Bid Items 79 - 90), (Quarter 1 2027 Notice to Proceed*) | |||||
| Alternate #3 Bid (Detailed Bid Form: Bid Items 91 - 96), (Quarter 1 2027 Notice to Proceed*) | |||||
| Total Base Bid Including Alternates 1–3 (Quarter 1 2027 Notice to Proceed*) | |||||
| Bid Alternates 4–7 (Quarter 4 2027 Notice to Proceed*) | |||||
| For the pricing below, the Contractor shall provide revised pricing based on a Quarter 4 2027 Notice to Proceed, as specified in Special Project Provisions Section 6. Bid Alternate #4 shall represent the complete revised Total Base Bid. Bid Alternates #5 and #6 shall represent additional costs and shall not include Bid Alternate #4 or any Quarter 1 2027 pricing. Bid Alternate #7 may be additive or deductive. Enter an additive amount as a positive value and a deductive amount as a negative value. | |||||
| Alternate #4 – Total Base Bid (Quarter 4 2027 Notice to Proceed*) | |||||
| Alternate #5 – Additive Alternate #1 (Detailed Bid Form: Bid Items 67 - 78), (Quarter 4 2027 Notice to Proceed*) | |||||
| Alternate #6 – Additive Alternate #2 (Detailed Bid Form: Bid Items 79 - 90), (Quarter 4 2027 Notice to Proceed*) | |||||
| Alternate #7 – Alternate #3 (Detailed Bid Form: Bid Items 91 - 96), (Quarter 4 2027 Notice to Proceed*) | |||||
| Total Base Bid Including Alternates #5–#7 (Quarter 4 2027 Notice to Proceed*) | |||||
| *See Special Project Provisions Section 6.2 for Notice to Proceed and early procurement requirements. | |||||
| The City reserves the right to award the Total Base Bid with any combination of Bid Alternates #1–#3 based on a Quarter 1 2027 Notice to Proceed, or Bid Alternate #4 with any combination of Bid Alternates #5–#7 based on a Quarter 4 2027 Notice to Proceed, whichever is most advantageous to the City. |