ESBD_520881_1793894163011_0007577 Attachment F - Construction Services Contract Tem.pdf
PDF 559 KB Posted
- Solicitation number
- 0007577
- Issued by
- Texas
About this file
This document is a Construction Services Contract Template for the Permian Basin Beacon Roadway and Utilities Project located in Midland, Texas, issued by the Texas Facilities Commission (TFC). The project involves prime construction services for three new main roadways, associated landscaping, irrigation, lighting, and underground utilities to support future development at the Permian Basin Medical Center near North State Highway 349 and Texas State Highway 191 (Project No. 26-002-8111). The contract establishes a comprehensive framework governing the relationship between TFC and the selected contractor, with key obligations including pre-construction tasks to be completed within twenty-one days of receiving a Notice to Proceed, such as site familiarization, attendance at pre-construction conferences, and preparation of safety plans and work progress schedules. The contractor must achieve substantial completion within a timeframe specified in the accepted proposal and documented in the Notice to Proceed, with work hours restricted to Monday through Friday, 6:00 a.m. to 6:00 p.m., unless otherwise approved by TFC. The contract documents incorporate multiple exhibits including the 2025 Uniform General Conditions, 2025 Supplemental General Conditions, TFC 2018 Architectural/Engineering Guidelines, Special Conditions, Drawings, Technical Specifications, Bond Forms, Subcontracting Plans, and a Confidentiality and Non-Disclosure Agreement.
The contract sum is to be inserted upon award and shall not be exceeded without a formal Change Order executed by both parties. Payment shall be made in accordance with the Texas Government Code Chapter 2251 (Prompt Payment Act), with contractor payment to subcontractors due within ten days of TFC's payment to the contractor. Each pay application must include updated work progress schedules, compliance certifications, subcontracting plan assessments, test results, and conditional waivers from subcontractors. The contract includes liquidated damages provisions with a seven-day grace period, assessed at a rate specified in Exhibit D per calendar day for failure to achieve substantial completion. TFC expressly reserves the right to suspend work for convenience for up to thirty days with seven days' notice or for cause without notice, and to terminate the contract for cause or convenience. The contractor must comply with all applicable federal and state laws, including E-Verify employment verification, criminal background checks for all on-site personnel, equal opportunity employment requirements, and various certification obligations related to Iran sanctions, boycotts of Israel, human trafficking prohibition, and deceptive trade practices. The contract term commences upon the last signature of both parties and continues until a date to be inserted, with potential extension by mutual amendment. All deliverables, including drawings and specifications, become the property of TFC with royalty-free usage rights for future renovations and modifications.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INSTRUCTIONS TO ALL RESPONDENTS FOR RFP PR-0007577
ATTACHMENT F
CONSTRUCTION SERVICES – COMPETITIVE SEALED PROPOSAL
FOR
THE BEACON ROADWAY AND UTILITIES, MIDLAND, TEXAS
1. Respondents are required to review this Attachment F prior to submission of proposals.
2. Other than for typographical or scrivener’s errors, all exceptions to, and/or requests for modification of, this Attachment F must be submitted on time and with Respondent’s proposal.
3. TFC will not consider any exceptions and/or requests for modification submitted after the date and time for submission of proposals.
4. The following Articles, Sections and Exhibits of this Attachment F are not negotiable:
Article I Definitions Article II Description of Project & Scope of Services, Section 2.1 Article III Contract Documents Article IV Term, Suspension, and Termination.
Article V Consideration.
Article VI Acknowledgements, Covenants, and Agreements Article VII Warranties and Representations by Contractor Article VIII State Funding Article IX Copyrights and Trademarks Article X Records, Audit, Proprietary Information, and Public Disclosure Article XI Bonds and Insurance Article XII Miscellaneous Provisions
Exhibit A 2025 Uniform General Conditions Exhibit B 2025 Supplemental General Conditions| Exhibit C TFC 2018 Architectural/Engineering Guidelines, edit date
3/19/2018 Exhibit D Special Conditions Exhibit F Drawings Exhibit G Technical Specifications Exhibit H Payment and Performance Bond Forms Exhibit J Criminal Background Checks and Application Guidelines Exhibit K Approved Subcontracting Plan Exhibit L State of Texas Subcontracting Plan Form
Docusign Envelope ID: E3EC3623-2549-86A8-8069-41F1E7FD05DD
Exhibit M Prime Contractor Progress Assessment Reporting Form Exhibit N Contractor’s executed Confidentiality and Non-Disclosure
Agreement
5. The Construction Services Contract must be fully negotiated between TFC and the
Successful Respondent PRIOR TO award, whether award is made by TFC Procurement, or by the TFC Commission.
Stephen M. Foster Date TFC General Counsel
10/26/2026 | 1:42 PM CDT
ATTACHMENT F
REQUEST FOR PROPOSALS NO. PR-0007577
CONSTRUCTION SERVICES CONTRACT TEMPLATE
FOR
THE BEACON ROADWAY AND UTILITIES MIDLAND, TEXAS
THE TEXAS FACILITIES COMMISSION
AND
INSERT CONTRACTOR NAME
TFC CONTRACT NO. XX-XXX
PROJECT NO. 26-002-8111
TFC Contract No. XX-XXX Contractor Name
RFP PR-0007577
CONSTRUCTION SERVICES CONTRACT
BETWEEN
THE TEXAS FACILITIES COMMISSION
AND
INSERT CONTRACTOR NAME
The Texas Facilities Commission, a state agency located at 1711 San Jacinto Boulevard, Austin, Texas 78701 (hereinafter referred to as “TFC”), as Owner (as defined in 2025 Uniform General Conditions, Section 1.28) and Insert Contractor Name located at Insert Contractor Address (hereinafter referred to as “Contractor”), enter into the following contract for construction services (hereinafter referred to as the “Contract”) pursuant Tex. Gov’t Code §§ 2269.151-155 (Subchapter D), to be effective as of the Effective Date (as defined below).
I. DEFINITIONS.
1.1. Definitions. Unless specifically provided otherwise herein, all words and phrases in this Contract in initial caps shall have the meanings set out in this Section 1.1. In the event of any conflict between the definitions in the 2025 Uniform General Conditions (hereinafter referred to as “UGC”), the 2025 Supplemental General Conditions, and the Special Conditions, or in any other document that is referenced herein and incorporated for all purposes, and the definitions in this Contract, the definitions used in this Contract shall control to the extent of the conflict.
The 2025 Uniform General Conditions (hereinafter referred to as “UGC”) are incorporated herein for all purposes as Exhibit A.
The 2025 Supplemental General Conditions to the 2025 Uniform General Conditions (hereinafter referred to as the “2025 Supplemental General Conditions”) are incorporated herein for all purposes as Exhibit B.
The 2018 Architectural/Engineering Guidelines Edit Date March 19, 2018 (hereinafter referred to as the “A/E Guidelines”) Among other requirements the A/E Guidelines contain Building Information Modeling requirements for this Construction Services Contract, and are incorporated herein for all purposes as Exhibit C.
The Special Conditions, attached hereto and incorporated herein for all purposes as Exhibit D.
A/E means the architect and/or engineer with whom TFC has entered into a professional services agreement for the Project.
Application for Final Payment has the same meaning as defined in UGC, Section 1.3.
Baseline Schedule has the same meaning as defined in UGC, Section 1.6.
TFC Contract No. 27-XXX
(Rev 10-2026)
Building Information Model (“BIM”) means the computable, digital, multi-dimensional representation of the physical and functional characteristics of the Project’s facilities and their related life-cycle information in Autodesk Revit format and Autodesk Civil 3D, to be used as a repository of design and construction information for use by the Project Team during the design, bidding, Preconstruction, and construction phases of the Projects, and for TFC's use throughout the life-cycle of the facilities. Members of the Project Team are required to coordinate all efforts with respect to the BIM in accordance with the guidelines set forth in the BIM Execution Plan developed for the Project.
Building Information Model (“BIM”) Execution Plan means that certain plan prepared by the Project team with the guidelines and protocols for use by the Project Team to effectively utilize the BIM throughout the design, bidding, construction and life cycle of the Project.
CAD means AutoCAD DWG format.
Certificate of Substantial Completion means the certificate signed by the Contractor, A/E, and TFC establishing the date of Substantial Completion and identifying responsibilities for security and maintenance as set out in UGC, Paragraph 12.1.1.2.
Communication Protocol means the communication and tracking procedures to be utilized for interaction and reporting between TFC, A/E, Contractor, and its Subcontractors, including but not limited to, the use of any EPMCS, as defined herein, utilized by TFC for the Project.
Consideration means the funds and any and all other forms of valid, legal consideration as discussed in Article V of this Contract.
Construction Services means the construction and management services to be provided to TFC by Contractor as specified in Section 3.3 of the UGC and as further specified in this Contract.
Contract Documents means those documents identified in Article III of this Contract.
Deliverables means the Construction Services, which are specified to be delivered by Contractor pursuant to the terms of this Contract.
Effective Date means the date that the last signature of a party is affixed hereto.
EPMCS means electronic project management control system.
Final Inspection Deadline means the date that is thirty (30) days after the Substantial Completion Inspection, and by which date A/E must conduct a Final Inspection.
Governmental Authorities means the city, the county, any municipal utility district or similar taxing authority in which the Project is located, the State of Texas, the Federal Emergency Management Agency, the United States Army Corps of Engineers, the Environmental Protection Agency, the Texas Commission on Environmental Quality, and any other governmental or quasi-governmental agency or authority having jurisdiction over any development or construction activities on the Project or the Contractor.
Hazardous Materials means (i) any “hazardous waste” as defined by RCRA, and regulations promulgated thereunder; (ii) any “hazardous substance” as defined by CERCLA, and regulations promulgated thereunder; (iii) any toxic substance as defined under or regulated by the Toxic Substances Control Act; (iv) asbestos, polychlorinated biphenyls, radon, or explosive or radioactive materials; (v) underground and above ground storage tanks, whether empty, filled or partially filled with any substance, including without limitation any petroleum product or any other “hazardous substance”; (vi) any substance the presence of which at the Project is prohibited by any Environmental Laws; and (vii) any other substance which by any Environmental Laws requires special handling or notification of any Governmental Authority in its collection, storage, treatment, or disposal.
HUB Compliance Reporting System means the Texas Facilities Commission Historically Underutilized Business (“HUB”) online reporting system located at https://tfc.gob2g.com. The HUB Compliance Reporting System is used to maintain business records documenting compliance with the State of Texas Subcontracting Plan (“HSP”) by submission of monthly Prime Contractor Progress Assessment Reports (“PARs”). See Section 12.2., Historically Underutilized Businesses, and Section 12.3, Requirement to Utilize HUB Compliance Reporting System.
Laws and Regulations means any and all applicable laws, statutes, rules, regulations, ordinances, codes, and orders including those governing labor, equal employment opportunity, safety, and environmental protection, including but not limited to, all applicable requirements of Title III of the Americans with Disabilities Act and the Texas Architectural Barriers Act and the Texas Accessibility Standards found in Texas Government Code, Chapter 469, of any and all Governmental Authorities.
MEP Systems means mechanical, electrical, and plumbing systems.
Notice to Proceed or NTP means the written notice to be issued to Contractor by TFC, which shall inform Contractor of, among other things, the date to begin commencement of work and the date anticipated for Substantial Completion.
Open Items List means a list of work activities, punchlist items, changes, or other issues that are not expected by Owner and Contractor to be complete prior to Substantial Completion.
Person means an individual, firm, partnership, corporation, association, and any other legally recognized entity.
Post-Final Inspection Punchlist means the punchlist of items that TFC will deliver to Contractor that sets out any part of the work that was not corrected or completed in accordance with the Contract Documents as of the Final Inspection.
https://tfc.gob2g.com/
Post-Final Inspection Punchlist Deadline means the date that is a fixed number of days after the date of the Final Inspection, and by which date A/E shall deliver any Post-Final Inspection Punchlist to Contractor.
Pre-Construction Tasks means the mobilization and pre-construction services to be provided to TFC as part of the pre-construction phase of the Project as described in Article II below.
Pre-Construction Tasks Deadline means the date that is twenty-one (21) days after delivery of a Notice to Proceed, and by which date Contractor shall complete all Pre-Construction Tasks.
Pre-Final Inspection Punchlist means the list of final punchlist items as defined in UGC, Paragraph 12.1.1.2 that TFC will deliver to Contractor along with a Certificate of Substantial Completion.
Pre-Final Inspection Punchlist Deadline means the date that is a fixed number of days after the date of the Substantial Completion Inspection, and by which date A/E shall deliver a Pre-Final Inspection Punchlist to Contractor.
Project means as stated in Section 2.1 below and includes each component design/construction package that may be prescribed by TFC.
Project Manager means the individual designated by Contractor, and who must be approved by TFC, as the contact person with specific authority to properly supervise and direct the duties and responsibilities of Contractor, on behalf of Contractor, pursuant to the terms and conditions of this Contract, and who shall have decision-making authority to bind Contractor with respect to the Construction Services and the Project.
Punchlist means, except as may be specifically provided otherwise below, a list of items of work to be finished, remaining work to be performed, or work that does not meet quality or quantity requirements as required in the Contract Documents.
RFI Response means a written clarification, instruction, and/or interpretation, including, but not necessarily limited to, an architect’s supplemental instructions issued in response to an RFI, which response must be consistent with the intent of the Construction Documents.
Scope of Services means the Construction Services as set out in Section 2.2 below.
Shop Drawings means all drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the work.
Site means lands or areas indicated in the Contract Documents as being furnished by TFC upon which the work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by TFC which are designated for the use of the Contractor.
Subcontract means any agreement between Contractor and a Subcontractor.
Subcontractor means a Person, including a supplier that enters into an agreement with Contractor to perform any part of the Construction Services.
Substantial Completion has the same meaning as defined in UGC, Section 1.44.
Substantial Completion Inspection means the inspection requested by Contractor as set forth in UGC, Subsection 12.1.1 of the Project, or a designated portion thereof, that is sufficiently complete in accordance with the Contract so as to be operational and fit for the use intended.
Substantial Completion Inspection Deadline means the date that is a fixed number of days after proper written notification is delivered to TFC and A/E by Contractor that Contractor has fully satisfied the requirements of UGC, Subsection 12.1.1, and by which A/E must conduct a Substantial Completion Inspection.
TFC Project Manager means the individual designated by TFC as the Owner’s designated representative with the direct responsibility to properly supervise the design and construction of the Project and the services being provided pursuant to this Contract on behalf of TFC, including, but not limited to: (i) serving as the point of contact between TFC, Using Agency (if any), and A/E; and (ii) supervising TFC’s review and approval of the Construction Services.
1.1.40.
Work means, in addition to those items set forth in UGC Section 1.48, the provision of all, labor, materials, supplies, and equipment that are required of the Contractor to manage, implement, and fully construct or demolish the Project in accordance with the requirements of this Contract and the Contract Documents. The Work includes the Pre-Construction and Construction Services described in Article II and all additional work required by any Change Orders, and any other work reasonably inferable from the Contract Documents. The term “reasonably inferable” includes the understanding of the Parties that some minor details of the Work may not be shown on the Drawings or included in the Specifications, but they are included in the Work if they are usual and customary components of the Work for a project of the type depicted in the Contract Documents and they are needed to produce a complete and useable facility.
Work Progress Schedule means the schedule prepared and maintained in accordance with the Critical Path Method and the requirements of the Special Conditions, and the UGC, for design and construction of the Project, reflecting the Contractor’s actual progress of the construction or demolition of the Work and the scheduled activities and current plans for completing the Work.
The Work Progress Schedule may subsequently be modified by mutual agreement between TFC and Contractor to reflect any refinement in its requirements.
Using Agency has the same meaning as defined in Texas Government Code, Section 2166.001(10).
II. DESCRIPTION OF PROJECT & SCOPE OF SERVICES.
2.1. Description of Project. The project for which Contractor agrees to provide Construction Services is as defined in Article II (hereinafter referred to as the “Project”) is generally described as prime construction services for the Permian Basin Beacon Roadway and Utilities, Midland Texas Project No. 26-002-8111. The Project includes construction of three (3) new main roadways, associated landscaping, irrigation, lighting and underground utilities to support future development. The work location is at the Permian Basin Medical Center, North State Highway 349 and Texas State Highway 191.
2.2. Scope of Services. Contractor agrees to timely deliver the Construction Services described in this Contract. In the event of any material conflict between the duties and responsibilities of Contractor as set out in the 2025 UGC, the 2025 Supplemental General Conditions, and the Special Conditions, or in any other Contract Documents, and as set out in this Contract, the duties and responsibilities set out in this Contract shall control to the extent of any such material conflict.
2.2.1. Pre-Construction Phase. Upon receipt of a Notice to Proceed, Contractor shall commence, and as soon as reasonably practicable, but in no event later than the Pre- Construction Tasks Deadline, timely complete the following Pre-Construction Tasks for the Project.
2.2.1.1. Consult with staff of TFC, any representatives of Using
Agency, and A/E as may be directed by TFC, and become thoroughly familiar with: (i) the Site;
and (ii) any and all relevant and existing Site and facilities studies.
2.2.1.2. Attend a pre-construction conference between TFC, A/E, and any other representatives as deemed appropriate by TFC, before any work at the Site is commenced, at such time and location as may be determined by TFC. The Communication Protocol, initial Work Progress Schedule, procedures for handling Shop Drawings and other submittals, processing Pay Applications, maintaining required records, designation of Project Manager, and any other subject as may be determined by TFC to be appropriate, shall be the subject of said conference.
2.2.1.3. Reaffirm the assignment and identity of Project Manager.
2.2.1.4. If requested by TFC, assign appropriate Contractor staff to receive instruction regarding the use of EPMCS to be utilized by TFC.
2.2.1.5. Prepare for A/E’s review and TFC’s review and acceptance, a procurement schedule for items that must be ordered well in advance of commencement of construction.
2.2.1.6. Timely expedite and coordinate the ordering and delivery of products and materials that must be ordered well in advance of commencement of construction.
2.2.1.7. Prepare a safety plan as specified in UGC, Section 7.1, and deliver same to A/E and TFC for review.
2.2.1.8. Designate a qualified and experienced safety representative at the Site whose duties and responsibilities shall be, at a minimum, the prevention of accidents and the maintenance and supervision of said safety plan.
2.2.1.9. Prepare, deliver, and periodically update as specified herein, the initial Work Progress Schedule.
2.2.1.9.1. When acceptable to TFC, this initial Work
Progress Schedule shall become the Baseline Schedule for comparison to actual conditions throughout the Contract duration.
2.2.1.9.2. Update the Work Progress Schedule as per the
provisions of UGC, Subsection 9.3.2 and as defined in UGC Section 1.49. All updated Work Progress Schedules shall include: (i) the components of the work; (ii) times of commencement and completion required of each Subcontractor; (iii) ordering and delivery of products, including those that must be ordered well in advance of construction; (iv) a clear delineation of the critical path; and (v) the occupancy requirements of TFC.
2.2.1.9.3. On a monthly basis, or as otherwise agreed in
writing by TFC, submit written progress reports to TFC and A/E, showing percentages of completion and other information required by TFC.
2.2.2. Construction Phase. Contractor shall timely deliver to TFC the
Construction Services for the Project as follows.
2.2.2.1. Direct all RFIs to A/E.
2.2.2.2. Adhere to the Work Progress Schedule established in
accordance with the terms and conditions of this Contract, as it may be amended from time to time.
2.2.2.3. Except as otherwise required for the safety or protection of persons or the work or property at the Site or adjacent thereto, and except as otherwise may be stated in the Contract Documents, all work at the Site shall be performed during the following days and times, to wit: Monday through Friday, from 6:00 a.m. until 6:00 p.m. Contractor shall not permit the performance of work on any other day or time without TFC’s prior written consent, which consent shall not be unreasonably withheld.
2.2.2.4. All requests for clarification of information provided in the
Contract Documents or for direction concerning information necessary in order to perform the work must be directed to A/E via an RFI.
2.2.2.5. On a monthly basis, or as otherwise agreed in writing by TFC, submit written progress reports to TFC and A/E, reporting Contractor’s assessment of percentages of completion and other information required by TFC.
2.2.2.6. Unless and until instructed otherwise in writing by TFC, prepare a daily log containing: (i) a record for each day’s weather; (ii) a statement of which days since the previous monthly report are claimed by Contractor to be subject to Force Majeure portions of the work in progress; (iii) number of workers on site; (iv) identification of all equipment on site; (v) problems that might affect progress of the work; and (vi) all accidents, injuries, and any other information that may be requested by TFC from time-to-time, and upload said daily log into EMPCS as directed by TFC, by the end of each next business day.
2.2.2.7. During the progress of the work, keep the Site and other areas free from accumulations of waste materials, rubbish, and other debris. Removal and disposal of such waste materials, rubbish, and other debris must be in compliance with all applicable Laws and Regulations.
2.2.2.8. Plan for and develop the schedule to accommodate necessary inspections and testing of electrical systems. Contractor is strictly prohibited from (i) de-energizing or otherwise deactivating; or (ii) energizing or otherwise activating, any electrical systems or equipment at the Site without a minimum of twenty-four (24) hour advance notice to, and written approval of, TFC. Any provisions in the Contract Documents to the contrary notwithstanding, TFC reserves the right to deny and/or revoke Contractor’s authority to energize or otherwise activate any electrical systems or equipment at the Site. Contractor will not be entitled to receive additional compensation for any such denial or revocation.
2.2.2.9. Prior to Substantial Completion of the work, clean the Site and the work and make it ready for utilization by TFC. At the Substantial Completion of the work, store and secure all tools, appliances, construction equipment and machinery, and surplus materials necessary to allow for beneficial occupancy by the end user, and shall restore all property not designated for alteration by the Contract Documents to original condition.
2.2.2.10. Confine all construction operations within the limits of construction indicated on the Drawings or otherwise agreed to in writing by TFC, and use due care in placing construction tools, equipment, materials, and supplies so as to cause the least possible damage to property and interference with traffic. If additional easements for its operations are needed, Contractor is solely responsible for acquisition and maintenance of the easement.
2.2.2.11. All materials and equipment shall be stored, applied, installed, connected, erected, protected, used, cleaned, and conditioned in accordance with instructions of the applicable supplier, except as otherwise may be provided in the Contract Documents.
2.2.2.12. In order for an Application for Final Payment to be considered complete and subject to review and approval, submit to TFC a Final Payment Punchlist in such form as prescribed by TFC, jointly executed by Contractor, TFC, and A/E. No approval of an
Application for Final Payment is valid and enforceable unless and until the foregoing requirement is fully satisfied.
2.2.2.13. Achieve substantial completion within the period of time specified in the proposal as accepted by TFC, and which shall be stated in the NTP. In the event the Project is to be constructed in phases, each phase must be constructed within the period of time specified in the respective proposals, and which shall be stated in the respective NTP.
2.2.2.13.1. At such time that Contractor considers the entire work or a portion thereof Substantially Complete, notify TFC and A/E in writing that said work will be ready for a Substantial Completion Inspection on a specific date.
2.2.2.13.1.1. Include with the foregoing
notice a Punchlist that sets out, among other things that may be requested by TFC and/or A/E, the following: (i) a list of those portions of the work that are to be the subject of the Substantial Completion Inspection; and (ii) the Open Items List, which must include the date for scheduled completion and/or correction for each item of work contained therein.
2.2.2.13.1.2. The delivery of the foregoing
notice by Contractor shall constitute Contractor’s certification that it has, in fact, inspected each and every portion of the work that is to be the subject of the Substantial Completion Inspection and that they are completed in conformity with the Contract Documents.
2.2.2.13.2. No later than ten (10) days prior to the date of
the Substantial Completion Inspection, deliver to A/E a copy of Contractor’s marked-up Record Documents and a preliminary copy of each instructional manual, maintenance and operating manual, parts catalog, wiring diagrams, spare parts, specified written warranties, and like publications or parts for all installed equipment, systems, and like items as described in the Contract Documents for the work that is the subject of the Substantial Completion Inspection.
2.2.2.13.3. Subject to the provisions of UGC, Subsection
12.1.1, and no later than the Substantial Completion Inspection Deadline, A/E shall conduct a Substantial Completion Inspection while accompanied by the TFC Project Manager to determine whether said portion of the work has achieved Substantial Completion.
2.2.2.13.3.1. In the event A/E determines
that the work, or any portion thereof, has not been performed or completed in accordance with the Contract Documents, and no later than the Pre-Final Inspection Punchlist Deadline, A/E shall prepare and deliver to Contractor a Pre-Final Inspection Punchlist with a copy to TFC.
2.2.2.13.3.2. In the event any fees, and/or
other direct and/or consequential damages are charged to, or incurred by, TFC by reason of Contractor’s failure to timely correct and/or complete the items that are the subject of the Substantial Completion Inspection, Contractor shall be liable to TFC for such fees and/or damages for which TFC may issue a Unilateral Change Order and deduct those costs from the Final Payment.
2.2.2.13.4 Contractor shall achieve substantial completion
within [Insert] calendar days after issuance of the NTP.
2.2.2.14. Subject to the provisions of UGC, Subsection 12.1.2, and no later than the Final Inspection Deadline, and prior to requesting a Final Inspection, complete and/or correct all work specified in the Pre-Final Punchlist.
2.2.2.14.1. Issuance of a Certificate of Substantial
Completion is a condition precedent to Contractor’s right to issue notice that the work will be ready for Final Inspection.
2.2.2.14.2. By requesting a Final Inspection, Contractor
thereby certifies that it has, in fact, inspected each and every portion of the work that is set out in the Pre-Final Punchlist, and that they are completed in conformity with the Contract Documents.
2.2.2.14.3. No later than the Final Inspection Deadline, A/E
shall conduct a Final Inspection, while accompanied by the TFC Project Manager, to determine whether all of the items set out in the Pre-Final Punchlist have been fully completed in accordance with the Contract Documents.
2.2.2.14.4. In the event A/E determines that any of the Pre-
Final Inspection Punchlist items have not been corrected or completed in accordance with the Contract Documents, A/E shall prepare and deliver to Contractor, no later than the Post-Final Inspection Punchlist Deadline, a Post-Final Inspection Punchlist with a copy to TFC.
2.2.2.14.5. No later than ten (10) days after receipt of the
Post-Final Inspection Punchlist, and prior to submitting a request for Final Payment, Contractor must complete and/or correct all work specified in the Post-Final Inspection Punchlist.
2.2.2.14.6. In the event any fees and/or other consequential
damages are charged to, or incurred by, TFC by reason of Contractor’s failure to timely correct and/or complete the items that are the subject of the Final Inspection, Contractor shall be liable to TFC for such fees and/or damages.
2.2.2.14.7. At final completion, Contractor shall remove all
tools, appliances, construction equipment and machinery, and surplus materials from the Site.
2.2.2.15. In order for an Application for Final Payment to be considered complete and subject to review and approval, Contractor must deliver to TFC:
2.2.2.15.1. a fully completed and executed Final Payment
Checklist in such form as is prescribed by TFC;
2.2.2.15.2. all test reports; and
2.2.2.15.3. all Close-out Documents.
2.2.2.16. No approval of an Application for Final Payment is valid and enforceable unless and until the foregoing requirements are fully satisfied.
2.2.2.17. Issuance of a Certificate of Final Completion is a condition precedent to Contractor’s right to receive Final Payment.
2.2.3. Contractor Services During All Phases. Contractor shall timely deliver to TFC the following services, as applicable, during all phases for which Contractor is obligated to provide Construction Services.
2.2.3.1. Participate with A/E in all explanatory presentations as may be requested by TFC.
2.2.3.2. Critically review and closely scrutinize all documents submitted by all Subcontractors, suppliers, and all other third-parties.
2.2.3.3. Thoroughly review and closely scrutinize the performance, constructability, schedules, and costs of all of its Subcontractors and suppliers.
2.2.3.4. Critically review and evaluate Subcontractor’s proposed means, methods, schedule, and costs as relevant to each Subcontractor’s discipline.
2.2.3.5. Maintain work progress and products consistent with the schedules.
2.2.3.6. Promptly communicate with pertinent parties, including topics regarding information needs and responses to needs of other parties.
2.2.3.7. Actively participate in all meetings and/or teleconferences to bring the full measure of Contractor’s collective experience, expertise and recommendations to the Project as it pertains to the overall Project or to a specific discipline including, but not limited to, matters concerning the proposed site use and improvements, selection of materials, and building systems and equipment.
2.2.3.8. Ensure that each Subcontractor includes thorough examinations of all documents they author, for accuracy, intended completeness, and constructability as their standard of care for the Project.
2.2.3.9. Ensure that its Project Manager, and any other representative of
Contractor whose presence is requested by TFC, attend all meetings and participate in all conference calls that are scheduled by TFC or A/E.
2.2.3.10. Cooperate with any commissioning agent that may be engaged by TFC.
2.2.4. TFC Approvals. Any provisions in this Contract to the contrary notwithstanding, all consents and/or approvals by TFC shall be in its sole and absolute discretion, and must be in writing.
2.2.4.1. No changes to (i) the scope of the Construction Services; or (ii) the Consideration, shall be valid or enforceable unless evidenced by a fully executed written amendment to this Contract.
2.2.4.2. To the extent that TFC approval is required to authorize incurring any costs, such approval must be acquired prior to incurring any such costs.
2.2.4.3. Contractor is not authorized to commence providing any
Construction Services to TFC or any Using Agency with respect to the Project unless and until an appropriate Notice to Proceed is delivered by TFC.
2.2.4.4. TFC, including by and through the TFC Project Manager, reserves the right, if deemed appropriate by TFC in its sole discretion, to extend any of the deadlines set out in this Contract.
2.2.4.5. TFC hereby reserves the right, if deemed appropriate by TFC in its sole discretion, to conduct reviews of inspections during the course of design and construction of the Project. However, Contractor shall not be relieved of any of its obligations arising pursuant to this Contract.
2.2.4.6. No inspections of the Project conducted by TFC or A/E during the course of construction, either singularly or in the aggregate, shall reduce the level or extent of Contractor’s responsibilities arising pursuant to this Contract. Neither the approval and/or final acceptance of the Project or any Deliverables, the payment of any Pay Application, or the issuance of any Certificates of Final or Substantial Completion by TFC shall constitute, nor be deemed, a release of Contractor’s obligation to perform and timely deliver the Construction Services in a manner consistent with (i) that degree of care and skill ordinarily exercised by members of the same profession currently practicing under similar circumstances; and (ii) as required by the Contract Documents.
III. CONTRACT DOCUMENTS.
3.1. Contract Documents. In performing its Construction Services for the Project, Contractor shall be bound by, and comply with, the following Contract Documents.
3.1.1. UGC. The UGC, Exhibit A.
3.1.2. Supplemental General Conditions. The 2025 Supplemental General
Conditions, Exhibit B.
3.1.3. A/E Guidelines. The A/E Guidelines, Exhibit C.
3.1.3. Special Conditions. The Special Conditions to the UGC, Exhibit D.
3.1.4. Contractor’s Proposal Response to RFP. Any additional services or provisions depicted in Contractor’s Proposal Response submitted in response to RFP No. 0007480 (collectively, the “RFP”), a copy of which Response is incorporated herein for all purposes as Exhibit E, to the extent any warranties, representations, and/or promises of additional services are made therein, and only to that extent.
3.1.5. Drawings. The Drawings prepared under TFC Contract No. 26-057 by
Parkhill, Smith & Cooper, dba Parkhill, and any approved revisions thereto are incorporated herein by reference as Exhibit F. In TFC’s sole discretion, Exhibit F may be provided by an encryption method satisfactory to TFC such as EPCMS or by any other method TFC determines necessary to assure their confidentiality. Drawings may also include existing conditions drawings required for the work. All Drawings subject to this subsection 3.1.5 are confidential and subject to the confidentiality provisions in Section 10.4 as well as Exhibit N, Contractor’s executed Confidentiality and Non-Disclosure Agreement as incorporated below at 10.4.1.
3.1.6. Specifications. The Specifications dated September 2026, prepared under
TFC Contract No. 26-057 by Parkhill, Smith & Cooper, dba Parkhill, and any approved revisions thereto, incorporated herein by reference as Exhibit G. In TFC’s sole discretion, Exhibit G may be provided by an encryption method satisfactory to TFC or by any other method TFC determines necessary to assure their confidentiality. All Specifications subject to this subsection 3.1.6 are confidential and subject to the confidentiality provisions in Section 10.4 as well as Exhibit N, Contractor’s executed Confidentiality and Non-Disclosure Agreement as incorporated below at 10.4.1.
IV. TERM, SUSPENSION, AND TERMINATION.
4.1. Contract Term. This Contract shall be effective as of the date of the last party to sign and shall terminate on [Insert], unless extended by the parties by amendment to this Contract or terminated earlier, as provided below.
4.2. Suspension of Work.
4.2.1. For Cause. TFC may suspend all or any part of the work, for cause, without prior notice, as more specifically provided in UGC, Section 14.1.
4.2.2. For Convenience. TFC may suspend all or any part of the work for the convenience of TFC for a period of up to thirty (30) days, without breach of this Contract, upon seven (7) days written notice, as more specifically provided in UGC, Section 14.2.
4.2.2.1. Upon receipt of a Notice of Suspension pursuant to this subsection, Contractor shall, subject to the provisions of UGC, Section 14.2, immediately stop all work.
4.3. Termination.
4.3.1. For Cause. Upon written notice to Contractor and its surety, TFC may, without prejudice to any right or remedy, terminate this Contract and take possession of the Site and of all materials, equipment, tools, construction equipment, and machinery thereon owned by Contractor under any of the following circumstances, each one of which shall be considered a material breach of this Contract:
4.3.1.1. the failure or refusal, except during complete or partial suspensions of work authorized under the Contract, to supply enough properly skilled workmen or proper materials;
4.3.1.2. a violation, whether discovered or asserted before or after the
Effective Date, of any Laws and/or Regulations of any Governing Authority;
4.3.1.3. the failure of Contractor to timely deliver the services set out herein or timely complete the Project in accordance with the Contract Documents;
4.3.1.4. the failure to timely remedy defective work;
4.3.1.5. the failure to pay Subcontractors, laborers, and material suppliers pursuant to Tex. Gov’t Code, Chapter 2251;
4.3.1.6. the endangerment of the safety of employees, Subcontractors, or any other members of the public or of the work;
4.3.1.7. the failure to timely obtain and deliver, or maintain any required bonds or any required proof of insurance, pursuant to the Contract Documents;
4.3.1.8. the falsity of any material statement, warranty or representation when given or made by Contractor to TFC or A/E, whether in this Contract, in Contractor’s response to the RFP, or otherwise, or any such statement, warranty or representation becoming materially false at any time during the term of this Contract, or any fraud committed by Contractor or its members, officers, agents, or principals in connection with the procurement of this Contract or the delivery of the Construction Services;
4.3.1.9. Contractor (i) makes an assignment for the benefit of creditors;
(ii) files a voluntary proceeding seeking protection from creditors under any bankruptcy or other law; (iii) is the subject of an involuntary proceeding under any bankruptcy or other similar law and such proceeding is not dismissed within sixty (60) days; or (iv) makes any admission of its inability to pay its debts generally as they become due;
4.3.1.10. the appointment of a trustee, receiver, or liquidator for
Contractor;
4.3.1.11. the use of or otherwise incorporating an item of material or equipment into the Project that is not specified by the Drawings or Specifications, or otherwise approved pursuant to the procedures set out in the Requirements for Substitutions and Equivalents;
4.3.1.12. the failure to timely comply with any other requirements of the
Contract Documents; and
4.3.1.13. upon receipt of a Notice of Termination pursuant to this subsection, Contractor shall immediately stop all work, and shall continue to cease work activities, unless and until TFC and Contractor agree on the method and means of satisfying UGC, Subsection 14.3.4.
4.3.2. For Convenience. TFC may terminate this Contract for any reason and at any time during the performance of the work as more particularly provided in UGC, Section 14.5.
4.3.2.1. Upon receipt of a Notice of Termination pursuant to this subsection, Contractor shall immediately: (i) stop all work; and (ii) comply with the provisions of UGC, Subsection 14.5.2.
V. CONSIDERATION.
5.1. Contract Sum. The Contract Sum shall not exceed the sum of [Insert Text] and No/100 Dollars $[Insert Numerical Amount].
5.2. Contract Amendment. Any amendment to the Contract Sum must be submitted to TFC for review and, if approved, must be evidenced by a Change Order issued by TFC in order to be valid and enforceable. No work under a Change Order modifying the Contract Sum may commence until the Change Order is executed by the parties.
5.2.1 Change Orders. Contractor’s claims for amendment to the contract sum and Owner’s orders for changes in the Work shall be executed and documented as a Change Order in accordance with Article 11 of the UGC subject to the 2025 Supplemental General Conditions. A change order executed in accordance with the requirements of the 2025 Uniform General Conditions (UGC) and as defined in UGC Definition 1.9 is a written modification to this agreement.
5.3. Payment of the Contract Sum. The Contract Sum shall be paid in accordance with Article 10 of the UGC, subject to the 2025 Supplemental General Conditions or Special Conditions or as provided below.
5.3.1. Initial Pay Application. At least twenty-one (21) days prior to the submission of the initial Pay Application, the Schedule of Values must be submitted and approved by TFC, as per UGC, Subsection 10.1.1.
5.3.2. Subsequent Pay Applications. In addition to the requirements of UGC, Article 10, each Pay Application must also include the following additional documentation.
5.3.2.1. Contractor shall certify that, among other things, it is in full compliance with UGC, Section 2.2.
5.3.2.2. An updated Work Progress Schedule, including the executive summary and all required schedule reports, including any time Change Orders, as per UGC, Paragraphs 8.3.1.3 and 10.2.1.2.
5.3.2.3. A Subcontracting Plan Prime Contractor Assessment Report form Rev Date 5/26 (“PAR”) monthly compliance report complying with UGC, Paragraphs
4.3.5.1 and 10.2.1.3.
5.3.2.4. All test results and reports from all Subcontractors and/or otherwise under Contractor’s possession or subject to Contractor’s control.
5.3.2.5. A duly executed Conditional Waiver & Release on Progress
Payment from each Subcontractor that complies with Tex. Prop. Code § 53.284(b).
5.3.2.6. Any other information or documentation as may be requested by TFC.
5.3.3 Payment Application Certifications. Each submission of a Payment Application shall also constitute Contractor’s certification that:
5.3.3.1. Contractor has updated all expired insurance policies as required by UGC, Section 5.2;
5.3.3.2. Contractor has updated the Record Documents, as per UGC, Subsection 6.2.3;
5.3.3.3. Contractor has updated the Submittal Register, as per UGC, Paragraph 8.3.1.2; and
5.3.3.4. the sums contained in the Payment Application that represent amounts owed to Subcontractors and/or suppliers are, in fact, due and owing to said Subcontractors and/or suppliers, without any deductions or offsets.
5.3.4. Prompt Payment. All payments shall be governed as follows.
5.3.4.1. Contractor shall be paid in accordance with Chapter 2251 of the Texas Government Code, also known as the “Prompt Payment Act” and the provisions set out in Article 10 of the UGC, subject to Special Conditions, Exhibit D.
5.3.4.2. For all services rendered, Contractor’s payment to
Subcontractors is due within ten (10) days after receipt of payment from TFC and, when appropriate, in the sole discretion of TFC, TFC may issue joint checks to Contractor and Subcontractor(s).
5.4. Liquidated Damages. The Contractor acknowledges and agrees that time is of the essence in completing the Work required hereunder, that the Contractor’s failure to meet the deadlines set forth in this Contract shall be a material breach of the Contract, and that TFC will incur substantial damages due to any failure by the Contractor to achieve Substantial Completion on or before the required date(s). If the Contractor fails to achieve Substantial Completion of the Work by the date(s) set forth in Section 6.6, as such date(s) may be modified in accordance with the terms of the Contract Documents, the Contractor shall pay TFC liquidated damages, and not as a penalty, in the amount as defined in Exhibit D per calendar day until Substantial Completion of the Work is achieved. If the Contractor fails to achieve Substantial Completion of certain construction milestones(s) by the date(s) set forth in Section 6.6, as such date(s) may be modified in accordance with the terms of the Contract, the Contractor shall pay TFC liquidated damages, and not as a penalty or forfeiture, in the amount as defined in Exhibit D calendar day until Substantial Completion of such construction milestone is achieved. There shall be a seven (7) calendar day grace period applied to the dates for Substantial Completion of the Work and each construction milestone before such liquidated damages are assessed.
5.4.1. TFC may deduct any liquidated damages from any amounts due the Contractor, and/or TFC may require the Contractor to pay any liquidated damages, within ten (10) days after TFC’s request should the available contract funds be insufficient to cover the liquidated damages assessed against the Contractor. If liquidated damages are actually recovered by TFC, the above-stated liquidated damages provided for herein shall be TFC’s exclusive damages remedy for the Contractor’s unexcused failure to achieve Substantial Completion of the Work or Substantial Completion of any construction milestone, but such damages shall in no way limit TFC’s other rights (e.g., termination) under the Contract or TFC’s entitlement to damages for any other injury, damage or loss, other than for delay to achieving Substantial Completion of the Work or Substantial Completion of certain construction milestone (s), for which the Contractor may be responsible pursuant to the terms of this Contract or Applicable Law.
5.4.2. In determining the amount(s) of liquidated damages set forth in Exhibit D, TFC has carefully considered the following categories of damages and has thoughtfully determined such amount(s) accordingly: increased financing charges, cost of relocation of personnel to alternative space, costs for managing an extended schedule, costs for the AE’s extended involvement, costs of storage of TFC-provided FF&E, lease extension costs, and other numerous damages. Further, the Contractor acknowledges and agrees that as of the date this Contract is executed (i) the amount of damages TFC will incur due to the Contractor’s failure to achieve Substantial Completion of the Work or Substantial Completion of certain construction milestone(s) as required by this Contract are impossible or difficult to estimate, (ii) the liquidated damages set forth in Exhibit D are a reasonable pre-estimate of damages that TFC will incur as a result of a delay in achieving Substantial Completion of the Work or Substantial Completion of certain construction milestone(s) as required by this Contract, (iii) that the consequential damages contemplated at the time of this Contract are uncertain and difficult to determine with exactness, and (iv) that the liquidated damages set forth in Exhibit C are not out of all proportion to the probable loss.
5.4.3. This Section 5.5 survives the termination of the Contract. In the event this liquidated damage provision is held to be unenforceable or void (except when the holding is the result of a challenge by TFC), TFC shall be allowed to recover actual damages (both direct and consequential damages) caused by the Contractor's failure to achieve the applicable Contract Time requirements.
VI. ACKNOWLEDGEMENTS, COVENANTS, AND AGREEMENTS.
6.1. Acknowledgements, Covenants, and Agreements of TFC. TFC acknowledges, covenants, and agrees as follows.
6.1.1. TFC Deliverables to Contractor. TFC shall have provided Contractor with a copy of, or reasonable access to, the following information and documentation regarding the Project:
6.1.1.1. the UGC;
6.1.1.2. the 2025 Supplemental General Conditions;
6.1.1.3. any Special Conditions;
6.1.1.4. sample copies of the following:
6.1.1.4.1. contract forms; and
6.1.1.4.2. Payment and Performance bond forms, Exhibit
H, attached hereto and incorporated herein for all purposes ;
6.1.1.5. bidding information and instructions;
6.1.1.6. minimum wage rates;
6.1.1.7. the PAR; and
6.1.1.8. the communication protocol, which includes the communication and tracking procedure to be utilized for interaction and reporting for the Project.
6.1.2. TFC Services to Contractor. TFC shall timely provide, or cause to be provided, to Contractor the following services for the Project.
6.1.2.1. Assuming satisfactory completion of all criminal background checks, assist Contractor in obtaining such access to the Project Site as is reasonably necessary to enable Contractor to provide the Construction Services.
6.1.2.2. Designate the TFC Project Manager who will manage the construction of the Project and the services being provided pursuant to this Contract and the other Contract Documents.
6.1.2.3. Provide intermediate reviews of the work product of Contractor as necessary to allow Contractor to proceed with delivery of the Construction Services in a timely manner.
6.2. Acknowledgements, Covenants, and Agreements of Contractor. Contractor acknowledges, covenants, and agrees as follows.
6.2.1. Timely Delivery of Conforming Services. Contractor will, subject to Force Majeure events, as defined in Article XII below, timely provide the Construction Services and construct the Project in conformity with, and as specified in, this Contract, the UGC, the 2025 Supplemental General Conditions, any Special Conditions, and the other Construction Documents.
6.2.2. Risk of Loss. Contractor shall bear all losses, if any, resulting on account of the amount and character of the work, or because the conditions under which the work must be done are different from what were estimated or anticipated by Contractor, or because of weather, floods, elements or other causes.
6.2.3. Limitation of Authority. Contractor agrees that the TFC Project Manager shall not have…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .