ESBD_484596_1769097321387_SOL_EXH_F.3_SOW.pdf

PDF 7 MB Posted

Attached to
Houston CL File Room Renovation
Solicitation number
405-26R0009376
Issued by
Harris County, Texas

About this file

This Statement of Work is issued by the Texas Department of Public Safety (TXDPS) for the remodel of the Houston Crime Lab File Room located at the Houston Regional Headquarters, Building C, 12230 West Road, Jersey Village, Texas 77065. The project involves remodeling approximately 370 square feet of existing file room space into office space, with work to include removal and installation of resilient wall base, interior painting, electrical work, and optional carpet installation as an alternate to epoxy flooring. The scope of work encompasses surface preparation, patching, repairs to match existing finishes, and compliance with all applicable building codes and ADA/TDLR-TAS regulations. Work must be performed between 8:00 a.m. and 4:30 p.m., Monday through Friday, with all work to be completed as efficiently as possible to minimize facility disruption. The contractor is required to provide a minimum one-year warranty on all installation work and deliver a complete, turnkey project as indicated in the contract documents. The contract monitor is Dinah Eghan-Wiafe, Construction Manager for the Southeast Texas Region, reachable at 346-244-3360 or Dinah.Eghan-Wiafe@dps.texas.gov.

All bidders must submit information regarding at least three similar projects completed, including project name, location, products installed, completion date, and owner's contact information. Contractors are responsible for obtaining and paying for all required permits and must conduct a pre-job damage survey with TXDPS to document existing conditions before commencing work. The contractor must provide 24-hour emergency contact information and respond to emergency situations within two hours. Materials must comply with low-emitting product standards, and all paint systems must be MPI premium grade with volatile organic compound (VOC) content limits not exceeding specified thresholds. The contractor is required to provide maintenance data, manufacturer's literature, samples, and warranty information upon project completion and must coordinate all work schedules with DPS, providing written notice 72 hours in advance of any changes to the planned work location. Substantial completion requires a comprehensive final inspection with all punch list items addressed prior to final payment.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TEXAS DEPARTMENT OF PUBLIC SAFETY - STATEMENT OF WORK

The Texas Department of Public Safety (TXDPS) is soliciting bids for the remodel of the Houston Crime Lab File Room. See the attached scope of work, drawings, and specifications for more information.

Services to Include:

1. Remodel existing file room into office space -Approx 370sf.

2. See Summary of Work and Add Alternate.

Project Location:

Houston Regional Headquarters, Building C 12230 West Road Jersey Village, Texas 77065

Department of Public Safety Contract Monitor:

Dinah Eghan-Wiafe Construction Manager Southeast Texas Region MO:

346-244-3360 Dinah.Eghan-Wiafe@dps.texas.gov

NOTE: Building contacts will be identified to the bidders for the respective locations for site visits and future access. Access times for each phase of construction must be scheduled ahead of actual work.

Table of Contents - Specification Sections Section 01 11 00 Section 01 40 00 Section 01 50 00 Section 01 73 00 Section 01 74 00 Section 09 65 13 Section 09 91 23 Section 26 05 00

Summary of Work Quality Requirements Temporary Facilities and Controls Cutting and Patching Cleaning and Waste Management Resilient Base and Accessories Interior Painting Common Work Results for Electrical

New Drawings and Photos Existing Drawings mailto:Dinah.Eghan-Wiafe@dps.texas.gov

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.01 SCOPE OF WORK

A. This section outlines the scope of work included in the project. Refer to the appropriate drawings and specification sections for further information about installation, preparation methods and components to be provided. The Contract Documents, otherwise referred to as drawings, shall serve as a part of this scope of work showing more detail on the intent of this project. The Contractor is responsible for including all means and methods necessary to complete this project and to field verify existing conditions and dimensions. In general, the work includes, but is not limited to, the following items:

1. See the New Drawings and Photos for more details on the scope of work.

2. See the Existing Drawings.

3. Patch and repair as needed. Match existing finishes unless noted otherwise.

4. Remove existing rubber wall base and install new 5" high. Match existing color.

5. Before construction DPS will remove all lose items from room unless noted otherwise.

6. Work can only be performed between B:00arn and 4:30pm Monday through Friday.

7. Ensure all applicable codes and ADA/ADAAGfTAS regulations are followed.

8. Provide a minimum one (1) year Warranty on all installation work.

9. Provide turnkey project as indicated on the drawings and as required for complete project.

ADD ALTERNATE 1

1. In lieu of epoxy flooring install carpet and metal transition. Carpet to be from Mohawk Group Colorways Expedition Digital Terrain GT341, 12" x 36" tiles (Brick Ashlar install pattern). Exact color from this group to be determined.

1.02 QUALITY CONTROL

A. Contractor is responsible for properly disposing of all trash, or construction debris associated with this project.

B. Removal shall not utilize TXDPS dumpster or equipment unless authorized by DPS.

C. TXDPS will identify an exterior staging area/ entry for use by the contractor. This temporary storage must be maintained in a neat orderly manner and restored to original condition upon completion.

D. Any container used as part of this contract is subject to inspection upon being located on DPS property.

E. Contractor shall efficiently schedule all work to ensure work will be done in as few calendar days as possible for optimum installation to meet the manufacturer's warranty requirements.

All work shall be continuous to insure the facility impact is minimal with limited disruptions.

Every effort shall be made to eliminate down time and get the DPS operations back in service as quickly and safely as possible. The exact dates will be coordinated once the bid award is made.

F. All work will be performed by qualified craft persons with a minimum of (3) three years of experience in the field. It shall be the contractor's responsibility to provide only skilled qualified workers for this project.

G. The new work shall comply with the state and local codes and ordinances.

1.03 PERFORMANCE REQUIREMENTS

A. The Work requirements of the Contract are summarized by reference to the Bidding Requirements, the Contract forms, the Conditions of the Contract, the Specification, the Drawings, and Addenda and Contract Modifications, including, but not limited to, the printed matter referenced in these requirements. It is recognized that the Work is affected or influenced by governing regulations, natural phenomenon (including weather conditions), unforeseen conditions uncovered by the Work, and other forces outside of the Contract Documents.

B. All work shall be considered new unless otherwise indicated.

C. All workmanship and materials shall be of the best construction practice. Should a conflict arise between the specification requirements and those of the referenced publications, the better quality or more stringent requirement will prevail. Specification requirements that exceed the minimum requirements of the manufacturer shall be compiled with by the Contractor.

D. The Contractor shall check and verify all dimensions, notes, conditions in the installation area on site before any construction work is started. All discrepancies shall be reported to DPS in writing. No extra charge of compensation will be allowed on account of any difference between actual measurements or dimensions supplied by TXDPS, either verbally or in written form.

E. The Contractor shall assume full responsibility for the accuracy, fit and stability of all parts of the work.

F. All labor, materials and installations must comply with the codes, rules and regulations of local, state and federal authorities having jurisdiction. Any discrepancy which exists between the requirements by the plans, specifications, said codes, rules and regulations, shall be immediately brought to the attention of DPS Facilities Department, in writing for resolution.

G. Applicable publications: Publications listed herein form a part of this Specification to the extent referenced and are indicated in the text by basic designation only. Applicable publications referenced shall be those that were issued and in use at the time of the Bid Submission.

H. The Contractor shall provide all necessary protection of existing work and newly added work.

I. The Contractor shall be responsible for adequately bracing and protecting all work during construction against damage, breakage, collapse, distortion and misalignment according to applicable codes and standards.

J. Working hours will be between 8:00 am and 4:30 pm during the week and as approved during the weekend if necessary. DPS needs to be clean and ready for work as soon as work is complete. If additional time is necessary for the specified products, schedule must be coordinated with DPS before any work begins.

K. The Contractor shall repair and restore to its original condition all work and items damaged as a result of building operations and shall leave the work completed to the true intent of the drawings and specifications and to the satisfaction of DPS.

L. Any disturbance or damage to the existing building, site or utilities resulting from either directly or indirectly from the building operations shall be promptly repaired, restored or replaced to the satisfaction of DPS at no additional cost to DPS.

M. All materials and construction to be incorporated in the work shall be in strict accordance with the latest editions of IBC and shall conform to the standards and recommendations of the various trade institutes where applicable.

N. The Contractor shall coordinate the work of any and all Sub-Contractors and also coordinate with DPS on portions of the work done by DPS employees or sub-contractors.

0. Manufacturer's Instructions:

1. Require compliance with instructions in full detail, including each step in sequence.

Do not omit preparatory steps or installation procedures unless specifically modified or exempted by the SOW.

2. Should instruction conflict with Contract Documents, request clarification from DPS Contact before proceeding.

P. Manufacturer's Certificates:

1. When required in individual specifications section, submit manufacturer's certificate, in duplicate, certifying that products meet or exceed specified requirements, executed by responsible officer.

1.04 PROJECT CONDITIONS

A. The building will be occupied and in use during construction, take necessary precautions to create as little disturbance or disruption to the building and its occupants as possible during work hours.

B. Supply, install, and maintain barriers, protection, warning lines, lighting, and personnel required to segregate the work area(s) from pedestrian or vehicular traffic, as well as to prevent damage to the building, its occupants, and the surrounding landscaped and paved areas. The Contractor shall observe all applicable OSHA requirements.

C. Schedule and execute work without exposing the building interior to the effects of inclement weather. Protect the building and its occupants against such risks and repair/replace work related damage to DPS's satisfaction.

1.05 PRECONSTRUCTION CONFERENCE

A. A preconstruction conference may be held with DPS Staff as required, Contractor, and involved trades to discuss all aspects of the project. The Contractor's foreman or field representative will attend this conference.

B. DPS shall reserve the right to require an alternate superintendent and/or foreman.

C. Delivery of materials and commencement of construction shall not proceed until the preconstruction conference is held unless authorized by the DPS Contract Monitor.

D. Provide a line item breakdown of construction labor and materials costs for each Specification Section included in these Contract Documents.

1.06 EMERGENCY RESPONSE

A. The Contractor shall provide DPS with after-hours (24 hour) emergency telephone numbers of the Contractor's superintendent and foreman.

B. The Contractor must respond to emergency situations or calls within two (2) hours.

1.07 SUBMITTAL$

A. Provide:

1. Manufacturer's technical data.

2. Application or installation instructions.

3. Substitution Request Form, if necessary.

B. Provide schedule of installation as part of this requirement.

C. Provide samples and manufacturer's literature for all products used on this project.

D. Provide certificates signed by the manufacturer certifying that installers comply with specified requirements.

E. All bidders shall submit information of not less than three (3) projects of similar size and complexity to include:

1. Project name and location.

2. Products installed.

3. Date of completion.

4. Owner's contact name and telephone number.

F. Provide maintenance data for O&M (Operations and Maintenance) Manuals.

G. Provide warranty information to be turned over to the Owner at Substantial Completion.

H. All submittals, samples and documentation required should be sent to DPS Contract Monitor.

1.08 SCHEDULING

A. All field work installations at the listed location shall be scheduled to facilitate continued facility usage as required by DPS.

B. Prior approval must be received from local DPS staff if scheduled project tasks may impact regular DPS facility operational schedule.

C. Proper coordination of all aspects of the work by the Contractor and any sub-trades is critical to ensure proper installation and performance of the work. The Contractor's Construction Schedule shall clearly outline the coordination between job tasks of all involved disciplines. Subject to review and acceptance by the DPS, this Schedule will be strictly adhered to by the Contractor and sub-trades.

D. DPS shall review the Contractor's Construction Schedule prior to the start of any work.

After defining the location(s) of the work progress, DPS shall arrange to control occupancy in the building to the greatest extent possible. It shall be the responsibility of the Contractor to supply DPS with written notice, 72 hours in advance, if his work location(s) for a workday is different from the schedule. The Contractor shall update his Construction Schedule weekly and submit a copy to DPS for review.

1.09 SPECIAL CONSIDERATIONS

A. Even if it is not anticipated, the contractor may be required to shut down operations during the project for an unforeseen State of Texas emergency. In this event, the contractor will be required to finish any open work, secure the site staging area, and evacuate his/her personnel as safely but as quickly as possible from the property. Notification to return to work will be issued as soon as possible from authorized DPS personnel.

B. Any Propane tanks, gas cylinders or other flammable/hazardous materials must be secured and stored in a safe industry acceptable manner when in use or when they are being stored for future use at this or any DPS facility. Storage locations and quantities are to be identified to the affected Building Manager for the duration of the contract.

C. Contractor vehicles used for transport of personnel or materials shall be locked with the emergency brake set and the ignition key removed when left unattended. Parking or storage must be located only in approved areas determined by the local building manager.

The Department of Public Safety shall not be responsible for damage by others to contract or Personal vehicles left on the project site. Any vehicle or equipment without an ignition key starter shall be rendered inoperable if left overnight. Also, any Vehicle or large equipment with a common industrial type of ignition source shall be rendered inoperable if left overnight. Security and safety of tools or equipment shall be the responsibility of the contractor during work and after regular business hours. Items such as ladders must be removed and secured prohibiting unauthorized access to the facility.

D. The facility shall not be left open by removal of any building component without prior knowledge of the DPS Building Manager. All removed openings are to be left secure with new products at the end of each work day or reasonably secured with 3/4" plywood or industry standard plugs. Temporary fillers must be cut to size and screwed securely into the opening in the event new component material need to be altered if the first attempt fails to fit an opening.

E. Contractor will be required to provide operation demonstration to the identified staff for future maintenance needs along with other information on warranty, maintenance manuals or other related details. Warranty information is subject to approval by Department of Public Safety's Legal Section. Counsel may advise as to the warranty details that are not in compliance to state law or must be changed not to violate agency policy.

1.10 DEFINITIONS

A. DPS: Texas Department of Public Safety= Owner.

B. Contractor: Primary party responsible for coordination of their own employees or their respective sub-contractor groups to complete the contract project to meet these specifications.

C. Installer/Applicator/Erector: Entity engaged by Construction Manager as an employee, Subcontractor, or Sub- subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

D. DPS Contact/Contract Monitor: Owner's primary representative for this project having authority to communicate project details and accept or deny final installation completion.

E. TDLR-TAS: Texas Department of Licensing and Regulation - Texas Accessibility Standards.

1.11 PREFERRED PRODUCTS

A. Pursuant to Texas Government Code 2155.444 and 2155.4441, when quality, availability, and price of materials are comparable, provide those produced within the following distances from the Project site (listed in order of preference): 1. Within the State of Texas and within 500 miles; 2. Within the State of Texas and greater than 500 miles; 3. Within the United States and within 500 miles; 4. Within the United States and greater than 500 miles;

5. Outside the United States and within 500 miles; 6. Outside the United States and greater than 500 miles.

1.12 CONTRACT METHOD

A. Project may be constructed under a single prime contract at the discretion of DPS.

B. Contractor may be mandated to make a scheduled site visit prior to sending in their bid proposal.

C. DPS reserves the right to revise Scope of Work. In such cases, DPS will send out an addendum with the revised scope of work.

1.13 WARRANTY

A. Installer shall furnish a single, written warranty covering 100% of the new material and labor costs protecting the owner, for a period of one (1) years from date of Substantial Completion.

B. In the event of component damage from the use of incompatible materials, or during installation any accident, mishandling, improper transportation methods or negligence on part of the Contractor or Sub-Contractor forces, the Primary Contractor shall be responsible for replacement at no cost the DPS.

C. Refer to specific sections of the specification for systems and product warranty requirements. Verify with Manufacturer of proposed systems and products that specified warranty requirements are acceptable, without exception, prior to selecting materials for use on this project.

D. Submit a full Contractor's Guarantee of the Work to be free from defect in materials and workmanship upon Substantial Completion, and prior to final payment. This Guarantee shall be for a period of one (1) years from the date of Substantial Completion, and shall be signed by a Principal of the Contractor's firm, and sealed if a corporation.

E. If requested by DPS, submit a letter from the manufacturer acknowledging that completed Work is acceptable and that warranty remains in effect.

1.14 FINAL INSPECTION AND PAYMENT

A. Inspections: DPS will conduct inspections of the project to verify work is in general compliance with the project intent, Contract Documents, and specifications prior to issuing payments to the Contractor. Inspections will be done by DPS Contract Monitor or designated representative and may be conducted at any time, prior to payments and at a minimum prior to any payments to the Contractor.

B. Final Inspection: The Contractor and the DPS Contract Monitor or designated representative shall provide a comprehensive final inspection after completion of the project. All application errors shall be addressed and final punch list items completed prior to rendering any final payments.

C. Prior to DPS final acceptance of the project and completion of receiving reports for applications for payment, the contractor shall return all security badges, issued to the contractor and sub-contractors for access to DPS facilities, to the Contract Monitor.

1.15 PERMITS

A. The Contractor will obtain and pay for any and all permits required to perform the work.

1.16 PRE-JOB DAMAGE SURVEY OF FACILITY

A. Perform a thorough pre-job survey of property and all affected and adjacent areas of the building with DPS prior to starting the work in order to document existing damage.

Damaged items identified during the survey will not be the responsibility of Contractor unless further damaged by the Contractor during execution of the project.

B. Documentation recorded during this meeting (pictures and videos) will be sent to DPS in order to review at the end of the project. It is the responsibility of the contractor to provide this documentation.

PART 2 - NOT USED

PART 3 - EXECUTION

3.01 EXAMINATION

A. Contractor shall check and verify all dimensions, notes, conditions and location of existing poles, cables or equipment in the installation area on site before any construction work starts. All discrepancies shall be reported to DPS Contact. No extra charge of compensation will be allowed on account of any difference between actual measurements and measurements or dimensions supplied by DPS, either verbally or in written form.

B. Examine substrates and conditions under which Work is to be performed. Do not commence work over unsatisfactory conditions detrimental to proper and timely execution of Work.

C. Do not proceed with Work until unsatisfactory conditions have been corrected.

D. Commencement of installation constitutes acceptance of conditions and cost of any corrective measures are the responsibility of the Contractor.

E. The Contractor is responsible for notifying the DPS Contact should there be a discovery of asbestos during the demolition process. In such cases, Work will cease until there is a resolution and permission from DPS Contract Monitor to commence work.

F. Ensure preparatory works are correctly done prior to main work.

END OF SUMMARY OF WORK

SECTION 01 40 00 • QUALITY REQUIREMENTS

1.01 SUMMARY

A. This Section includes administrative and procedural requirements for quality assurance and quality control.

B. Requirements for Contractor to provide quality-assurance and -control services required by TXDPS Contract Monitor or authorities having jurisdiction are not limited by provisions of this Section.

C. See specific specification sections for testing and inspection requirements.

1.02 DEFINITIONS

A. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

B. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements.

C. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

D. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.

E. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

F. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

G. Testing Agency: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.

H. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.

I. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.

1.03 CONFLICT/NG REQUIREMENTS

A. If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to TXDPS Contract Monitor for a decision before proceeding.

B. The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to TXDPS Contract Monitor for a decision before proceeding.

1.04 SUBMITTALS

A. If required and for TXDPS's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.

1.05 QUALITY ASSURANCE

A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required;

individual Specification Sections specify additional requirements.

B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.

C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

E. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1. Requirement for specialists shall not supersede building codes and regulations governing the

Work.

F. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.

1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910. 7.

2. NVLAP: A testing agency accredited according to NIST's National Voluntary Laboratory

Accreditation Program.

G. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

1.06 QUALITY CONTROL

A. Inspections are Contractor's responsibility. Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.

a. Contractor shall not employ same entity engaged by TXDPS, unless agreed to in writing by

TXDPS.

2. Notify testing agencies at least 24 hours in advance of time when Work that requires testing or inspecting will be performed.

3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.

4. Testing and inspecting requested by Contractor and not required by the Contract Documents are

Contractor's responsibility.

5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing to the TXDPS Contract Monitor.

C. Retesting/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced Work that failed to comply with the Contract Documents.

D. Testing Agency Responsibilities: Cooperate with TXDPS Contract Monitor and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1. Notify TXDPS Contract Monitor and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.

3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the Work.

6. Do not perform any duties of Contractor.

E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1. Access to the Work.

2. Incidental labor and facilities necessary to facilitate tests and inspections.

F. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

PART 2 - PRODUCTS - Not applicable.

PART 3 - EXECUTION

3.01 REPAIR AND PROTECTION

A. On completion of testing, inspecting, and similar services, repair damaged construction and restore substrates and finishes.

1. Provide materials and comply with installation requirements specified in other Specification

Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

B. Protect construction exposed by or for quality-control service activities.

C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION

SECTION 01 50 00 - TEMPORARY FACILITIES AND CONTROLS

1.01 SUMMARY

A. This Section contains instructions and requirements for the provision and utilization of temporary facilities to protect DPS's property, the site, and construction materials, and for daily maintenance and cleanup of the site during the project.

1.02 CONTRACTOR'S USE OF EXISTING FACILITIES

A. Limit use of the premises to the work indicated, so as to allow for the DPS's uninterrupted occupancy and use. Confine operations to the areas indicated under the Contract. Conformance to the regulations set forth by the DPS regarding use of existing facilities is mandatory.

B. DPS will assist in controlling occupancy. Contractor shall provide and place portable barricades, as coordinated with DPS, under work areas inside the building.

C. Take precautions necessary and provide equipment, materials and labor to adequately protect previous construction, the building, its contents and occupants, and surrounding landscaped areas from damage due to construction as well as from inclement weather during construction.

D. Clean exterior areas affected by the construction on a daily basis. Do not allow construction debris, waste materials, tools, excess packaging materials or other construction related materials to accumulate on the exterior grounds and pavements.

1.03 UTILITIES

A. Electrical service will be provided to the Contractor free of charge by the DPS. Use shall be limited to construction hours only.

B. Water for construction purposes will be provided to the Contractor free of charge by DPS. Use shall be limited to construction hours only.

C. All other utilities required will be provided by the Contractor.

D. Plumbing, heating, and electrical work, including reinstallation of equipment and other work to be performed by the Contractor, shall be carried out without interference to the building's normal operation. Where work requires interruption of service, the Contractor shall make advance arrangements with DPS for dealing with such interruption.

E. Ensure proper and safe operation and maintenance of utility systems within the construction limits, whether these are supplied by DPS's distribution system or otherwise, until the work is accepted by DPS. Maintain and operate appurtenances within the construction area that serve the distribution system, subject to periodic inspection by DPS's operating personnel. Inspection by any representative or personnel of DPS shall not relieve the Contractor of his responsibilities in connection with operation and maintenance of these facilities and equipment.

1.04 ACCESS

A. Do not interfere with normal building operations. Coordinate activities with DPS and building occupants.

1.05 BARRIERS

A. Install temporary fencing, warning lines, barriers and guards, as required, to segregate the construction areas from adjacent operational facilities, occupants and the public. Provide guard lights on barriers and lighting as necessary to prevent vandalism of work and storage areas. DPS is not responsible for Contractor's losses due to damage or theft by vandals.

1.06 TEMPORARY PROTECTION

A. Provide warning signs to reroute personnel around areas of dangerous work. Place warning barriers at work area perimeters and openings.

B. Avoid traffic on completed work areas. Coordinate work to prevent this situation. Should temporary access be required, provide temporary substrate protection for trafficked areas.

C. Protect materials scheduled to be reused from damage by placing them in labeled containers or wrappings stored in a weathertight trailer.

D. Provide temporary protection during all phases of the project.

1.07 ROOFTOP PROTECTION - NOT USED

1.08 DEBRIS REMOVAL

A. DPS shall designate refuse container locations. These areas shall be sectioned off with proper warning lines.

B. Supply adequate receptacles for waste, debris and rubbish. One receptacle will be allowed on site at a time, and must be immediately removed from the site when full. Clean the project area daily and prior to moving the receptacle to another location on the site. Locations shall be as permitted by the DPS. Disposal shall be off-site in a legal dump authorized to accept construction demolition solid wastes.

1.09 WEATHER PROTECTION -NOT USED

1.10 VOLATILE MATERIALS

A. The Contractor is reminded that adhesives, solvents, etc., are highly volatile and flammable materials. Take precautions and closely follow the Specification requirements for fire protection on site during construction.

1.11 FIRE PROTECTION

A. Should cutting, burning or welding be necessary, provide a fire watch during operations and for four hours minimum after completion of the operations.

B. Do not use open flames near adhesives, caulks or cleaning solvents as they will readily ignite.

Rags soaked with cleaning solvent shall not be discarded in the dumpsters, but shall be stored in a separate metal receptacle and removed from the site daily.

C. Comply with local fire codes and obtain permits necessary from the local fire department. Provide a copy to DPS. Provide recently tested, fully charged fire extinguishers around the storage area, rubbish receptacle and two fire extinguishers within 50 feet of the Work.

1.12 NOT USED

1.13 CLEAN-UP

A. Clean and restore the work areas to original condition prior to the construction.

B. Debris, dust and dirt shall be swept completely clean. Those items soiled or stained from the work shall be cleaned and refinished.

C. Electrical fixtures damaged by the construction shall be replaced with an equal in shape, color, manufacturer, and capacity at no added expense to the DPS.

D. Remove completely temporary protection materials and facilities from the site upon completion of the work and demobilization of the project.

E. Restore streets, drives, curbs, sidewalks, landscaping and existing improvements disturbed by the construction operations to their condition at the start of the work.

1.14 NOTIFICATION

A. Notify the DPS's Representative at least 72 hours in advance of the desire to extend, connect, disconnect, turn on or off HVAC, steam, electric, water or other service from the DPS's supply systems. The actual operation shall be witnessed by authorized representatives of the DPS.

Plumbing, heating and electrical work, including installation of equipment and any other work to be performed by the Contractor, shall be carried out without interference with the DPS's normal operation. Where work requires interruption of a service, make advance arrangements with the DPS for dealing with such interruption.

1.15 VEHICLES

A. Acceptable areas for the locations of the Contractor's vehicles shall be as designated by the DPS. No other areas may be utilized without the DPS's permission.

SECTION 017300-CUTTING AND PATCHING

1.1 SUMMARY

A. Provisions as established in the General Requirements of the Scope of Work.

1.2 SUBMITTALS

A. Submit written request in advance of cutting or alteration, which affects:

1. Structural integrity of any element of the Project.

2. Integrity of weather-exposed or moisture-resistant element.

3. Efficiency, maintenance, or safety of any operational element.

4. Visual qualities of sight-exposed elements.

5. Work of Owner or separate contractor.

B. Include in request:

1. Identification of Project.

2. Location and description of affected work.

3. Necessity for cutting or alteration.

4. Description of proposed work, and products to be used.

5. Alternatives to cutting and patching.

6. Effect on work of Owner or separate contractor.

7. Written permission of affected separate contractor.

8. Date and timework will be executed.

1.3 PAYMENT FOR COSTS

A. Costs resulting from ill-timed or defective work, or work not conforming to Contract Documents, including costs for additional services of other consultants shall be borne by the party responsible for ill-timed, rejected or non-conforming Work.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Products: Those required for original installation.

PART 3 - EXECUTION

3.1 GENERAL

A. Execute cutting, fitting, and patching including excavation and fill, to complete the Work, and to:

1. Fit the several parts together, to integrate with other work.

2. Uncover work to install ill-timed work.

3. Remove and replace defective and non-conforming work.

4. Remove samples of installed work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical work.

3.2 INSPECTION

A. Inspect existing conditions, including elements subject to damage or movement during cutting and patching.

B. After uncovering, inspect conditions affecting performance of work.

C. Beginning of cutting or patching means acceptance of existing conditions.

3.3 PREPARA T/ON

A. Provide temporary supports to assure structural integrity of su"oundings; devices and methods to protect other portions of the Project from damage.

B. Provide protection from elements for areas, which may be exposed by uncovering work;

maintain excavations free of water.

3.4 CUTTING AND PATCHING

A. Execute cutting, fitting, and patching (including excavation and fill) to complete work.

B. Fit products together, to integrate with other work.

C. Uncover work to install ill-timed work.

D. Remove and replace defective or non-forming work.

E. Remove samples of installed work for testing when requested.

F. Provide openings in the work for penetration of mechanical and electrical work.

3.5 PERFORMANCE

A. Execute work by methods to avoid damage to other work, and which will provide proper surfaces to receive patching and finishing.

B. Employ original installer to perform cutting and patching for weather-exposed and moisture-resistant elements and sight-exposed surfaces.

C. Cut rigid materials using masonry saw or core drill. Pneumatic tools are not allowed without prior approval.

D. Restore work with new products in accordance with requirements of the Contract Documents.

E. Fit work tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces.

F. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for an assembly, refinish entire unit.

SECTION 01 74 00 - CLEANING AND WASTE MANAGEMENT

1.1 SUMMARY

A. Provisions as established in the General Requirements of the Scope of Work.

B. Section Includes:

1. Cleaning during construction.

2. Final cleaning of project and related site work.

1.2 CLEANING DURING CONSTRUCTION

A. Control accumulation of waste materials and rubbish; dispose of off-site daily.

B. Keep site and construction areas clean on a daily basis.

C. Maintain areas free of dust and other contaminants during finishing operations.

1.3 FINAL CLEANING

A. Execute cleaning prior to inspection for Substantial Completion of the Work.

PART 2 - PRODUCTS

2.1 CLEANING MATERIALS

A. Use materials which will not create hazards to health or property, and which will not damage surfaces.

B. Use only materials and methods recommended by manufacturer of material being cleaned.

PART 3 - EXECUTION

3.1 CLEANING

A. In addition to removal of debris and cleaning specified in other sections, clean exposed-to-view surfaces.

B. Remove waste, foreign matter, and debris from access ways.

C. Maintain cleaning until Final Completion.

D. Final Cleaning: In addition to cleaning during construction, prior to Substantial Completion provide the following:

1. Remove temporary protection and labels not required to remain.

2. Remove waste, debris, and surplus materials from site daily. Clean grounds; remove stains, spills, and foreign substances from paved areas and sweep clean. Rake clean other exterior surfaces.

SECTION 09 65 13 - RESILIENT BASE AND ACCESSORIES

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions apply to this Section.

1.02 SUMMARY

A. Section Includes:

1. Resilient base.

2. Resilient molding accessories.

1.03 SUBMITTALS

A. Product Data: For each type of product.

B. Samples: For each exposed product and for each color and texture specified, not less than 12 inches long.

1.04 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Furnish not less than 10 linear feet for every 500 linear feet or fraction thereof, of each type, color, pattern, and size of resilient product installed.

1.05 DELIVERY, STORAGE, AND HANDLING

A. Store resilient products and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50 degrees For more than 90 degrees F.

1.06 FIELD CONDITIONS

A. Maintain ambient temperatures within range recommended by manufacturer, but not less than 70 degrees F or more than 95 degrees F, in spaces to receive resilient products during the following time periods:

1. 48 hours before installation.

2. During installation.

3. 48 hours after installation.

B. After installation and until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer, but not less than 55 degrees F or more than 95 degrees F.

C. Install resilient products after other finishing operations, including painting, have been completed.

PART 2-PRODUCTS

2.01 PERFORMANCE REQUIREMENTS

A. Low-Emitting Materials: Flooring system shall comply with the testing and product requirements of the California Department of Public Health's "Standard Method for the

Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

2.02 THERMOSET-RUBBER BASE RB-1

A. Product Standard: ASTM F 1861, Type TS (rubber, vulcanized thermoset), Group I (solid, homogeneous).

1. Style and Location:

a. Style B, Cove.

b. Thickness: 0.125 inch.

c. Height: 4" High unless otherwise noted.

d. Lengths: Coils in manufacturer's standard length.

e. Outside Corners: Job formed

f. Inside Corners: Job formed

g. Color: Roppe Brown, #110

2.03 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, Portland cement based or blended hydraulic-cement-based formulation provided or approved by resilient product manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by resilient-product manufacturer for resilient products and substrate conditions indicated.

1. Adhesives shall have a voe content of 50 g/L or less.

PART 3-EXECUTION

3.01 EXAMINATION

A. Examine substrates, with Installer resent, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

1. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of resilient products.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

1. Installation of resilient products indicates acceptance of surfaces and conditions.

3.02 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

C. Fill cracks, holes, and depressions in substrates with trowel-able leveling and patching compound; remove bumps and ridges to produce a uniform and smooth substrate.

D. Do not install resilient products until they are the same temperature as the space where they are to be installed.

1. At least 48 hours in advance of installation, move resilient products and installation materials into spaces where they will be installed.

E. Immediately before installation, sweep and vacuum clean substrates to be covered by resilient products.

3.03 RESILIENT BASE INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient base.

B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.

C. Install resilient base in lengths as long as practical without gaps at seams and with tops of adjacent pieces aligned.

D. Adhere the resilient base tightly to the substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.

E. Do not stretch resilient base during installation.

F. On masonry surfaces or other similar irregular substrates, fill voids along top edge of resilient base with manufacturer's recommended adhesive filler material.

G. Preformed Corners: Install preformed comers before installing straight pieces.

H. Job-Formed Comers:

1. Outside Corners: Use straight pieces of maximum lengths possible and form with returns not less than 24 inches in length.

a. Form without producing discoloration (whitening} at bends.

2. Inside Comers: Use straight pieces of maximum lengths possible and form with returns not less than 24 inches in length.

a. Miter comers to minimize open joints.

3.04 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protecting resilient products.

B. Perform the following operations immediately after completing resilient-product installation:

1. Remove adhesive and other blemishes from exposed surfaces.

C. Protect resilient products from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period.

D. Cover resilient products subject to wear and foot traffic until Substantial Completion.

SECTION 09 91 23 - INTERIOR PAINTING

1.01 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.02 SUMMARY

A. Section includes surface preparation and the application of paint and repainting systems on the following interior substrates:

1 . Concrete.

2. Concrete masonry units (CMU).

3. Steel.

4. Galvanized metal.

5. Wood.

6. Gypsum board.

7. Natural stone.

B. Related Requirements:

1. Division 01 Sections for waste management and disposal.

2. Division 05 Sections for shop priming of metal substrates with primers specified in this Section.

3. Division 06 Sections for shop priming carpentry with primers specified in this

Section.

4. Division 06 Sections for surface preparation and the application of wood stains and transparent finishes for interior architectural woodwork and other interior wood substrates.

5. Division 09 Section "Exterior Painting" for surface preparation and the application of paint systems on exterior substrates.

1.03 DEFINITIONS

A. Gloss Level 1: Not more than 5 units at 60 degrees and 10 units at 85 degrees, according to ASTM D 523.

B. Gloss Level 2: Not more than 10 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.

C. Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.

D. Gloss Level 4: 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D 523.

E. Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523.

F. Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523.

G. Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523.

1.04 ACTION SUBMITTALS

A. Product Data: For each type of product. Include preparation requirements and application instructions.

B. Samples for Verification: For each type of paint system and in each color and gloss of topcoat.

1. Submit Samples on rigid backing, 8 inches square.

2. Step coats on Samples to show each coat required for system.

3. Label each coat of each Sample.

4. Label each Sample for location and application area.

C. Product List: For each product indicated, include the following:

1. Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules.

2. Printout of current "MPI Approved Products List" for each product category specified in Part 2, with the proposed product highlighted.

3. voe content.

1.05 MAINTENANCE…

This is the start of the file's text. The full file is on GovTribe.