XLSX spreadsheet 24 KB Posted

Attached to
RFP for HVAC Maintenance Services in Houston, Waco, and Ft. Worth, Texas
Solicitation number
PR-0002353-A
Issued by
Harris County, Texas

About this file

This is a compensation and fees attachment for RFP PR-0002353-A from the Texas Facilities Commission (TFC) for HVAC maintenance services in Houston, Waco, and Fort Worth, Texas. The document outlines pricing requirements for three locations: the Elias Ramirez State Office Building in Houston, the Fort Worth State Office Building, and the Waco State Office Building. The services requested include quarterly and annual HVAC maintenance for equipment listed in Attachment G.

The pricing structure requires bidders to provide hourly rates for both qualified service technicians and helpers during normal hours (7:00 AM - 6:00 PM Monday through Friday) and overtime hours. Material markups are capped at 20%, while sub-contracted services and equipment rental markups are limited to 10%. All supplier and sub-contractor quotes must be provided with contractor quotes, and TFC reserves the right to request verification of invoices and receipts. The document specifies that respondents cannot modify the pricing structure or add qualifications, exceptions, or variations to their proposal, with any modifications potentially resulting in proposal rejection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Houston Attachment E - Compensation and Fees

Respondent's Name: _______________________________________________

Respondent may not add qualifications, exceptions, variations or additional items to the proposal, or otherwise modify the pricing structure of the RFP in any manner. Any such modifications will not be considered for evaluation and may be cause for rejection of the proposal, at the full and sole discretion of TFC. All materials and labor must be accounted for in the pricing submitted below. Respondent may not add additional price points after proposal opening.

HOUSTON

Base Services
BuildingBuilding NameAddressEquipmentQuarterly Maintenance PricingAnnual Maintenance Pricing
ERBElias Ramirez State Office Building5425 Polk Street
Houston, Texas 76119All inclusive list identified in Attachment G - Equipment List$ - 0$ - 0
Labor
Normal Hours* hourly rate per qualified service technician:$ - 0
Normal Hours* hourly rate per service technician helper:$ - 0
Overtime** hourly rate per qualified service technician:$ - 0
Overtime** hourly rate per service technician helper:$ - 0
Materials Mark-up
Contractor shall invoice at cost*** plusNot to exceed 20%0.0%
Sub-Contracted Services Mark-up (Radar, scanning, coring, concrete work, trenching, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Equipment Rental Mark-up (lift, scaffold, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Payment and Performance Bond (As Required)****
* Normal Hours are defined as 7:00 AM - 6:00 PM Monday through Friday
** Overtime is defined as any hours that fall outside of Normal Hours
*** All supplier and/or sub-contractor quotes/invoices need to be provided with contractor quotes.
**** TFC reserves the right to request from Contractor any invoices or receipts for verification purposes.

&"-,Bold"&16 RFP PR-0002353-A HVAC Maintenance Services in Houston, Waco, and Ft. Worth, Texas

Fort Worth Attachment E - Compensation and Fees

Respondent's Name: _______________________________________________

Respondent may not add qualifications, exceptions, variations or additional items to the proposal, or otherwise modify the pricing structure of the RFP in any manner. Any such modifications will not be considered for evaluation and may be cause for rejection of the proposal, at the full and sole discretion of TFC. All materials and labor must be accounted for in the pricing submitted below. Respondent may not add additional price points after proposal opening.

FORT WORTH

Base Services
BuildingBuilding NameAddressEquipmentQuarterly Maintenance PricingAnnual Maintenance Pricing
FTWFort Worth State Office Building1501 Circle Drive
Fort Worth, TX 76119All inclusive list identified in Attachment G - Equipment List$ - 0$ - 0
Labor
Normal Hours* hourly rate per qualified service technician:$ - 0
Normal Hours* hourly rate per service technician helper:$ - 0
Overtime** hourly rate per qualified service technician:$ - 0
Overtime** hourly rate per service technician helper:$ - 0
Materials Mark-up
Contractor shall invoice at cost*** plusNot to exceed 20%0.0%
Sub-Contracted Services Mark-up (Radar, scanning, coring, concrete work, trenching, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Equipment Rental Mark-up (lift, scaffold, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Payment and Performance Bond (As Required)****
* Normal Hours are defined as 7:00 AM - 6:00 PM Monday through Friday
** Overtime is defined as any hours that fall outside of Normal Hours
*** All supplier and/or sub-contractor quotes/invoices need to be provided with contractor quotes.
**** TFC reserves the right to request from Contractor any invoices or receipts for verification purposes.

Waco Attachment E - Compensation and Fees

Respondent's Name: _______________________________________________

Respondent may not add qualifications, exceptions, variations or additional items to the proposal, or otherwise modify the pricing structure of the RFP in any manner. Any such modifications will not be considered for evaluation and may be cause for rejection of the proposal, at the full and sole discretion of TFC. All materials and labor must be accounted for in the pricing submitted below. Respondent may not add additional price points after proposal opening.

WACO

Base Services
BuildingBuilding NameAddressEquipmentQuarterly Maintenance PricingAnnual Maintenance Pricing
WACWaco State Office Building801 Austin Avenue
Waco, Texas 76701All inclusive list identified in Attachment G - Equipment List$ - 0$ - 0
Labor
Normal Hours* hourly rate per qualified service technician:$ - 0
Normal Hours* hourly rate per service technician helper:$ - 0
Overtime** hourly rate per qualified service technician:$ - 0
Overtime** hourly rate per service technician helper:$ - 0
Materials Mark-up
Contractor shall invoice at cost*** plusNot to exceed 20%0.0%
Sub-Contracted Services Mark-up (Radar, scanning, coring, concrete work, trenching, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Equipment Rental Mark-up (lift, scaffold, etc.)
Contractor shall invoice at cost*** plusNot to exceed 10%0.0%
Payment and Performance Bond (As Required)****
* Normal Hours are defined as 7:00 AM - 6:00 PM Monday through Friday
** Overtime is defined as any hours that fall outside of Normal Hours
*** All supplier and/or sub-contractor quotes/invoices need to be provided with contractor quotes.
**** TFC reserves the right to request from Contractor any invoices or receipts for verification purposes.