Mt. Carmel WTP Pump Equipment Purchase
Solicitation number
RFB2024-081
Issued by
Loving County, Texas

About this file

This is Addendum No. 2 for RFB No. 2024-081 issued by the City of Waco, Texas for the Mt. Carmel Water Treatment Plant Pump Equipment Purchase. The addendum provides answers to bidder questions and revisions to contract documents and technical specifications. Key dates remain unchanged with a closing time of 2:00 P.M. CST and opening time of 2:05 P.M. CST on Tuesday, December 17, 2024, via Zoom video and dial-in. The addendum clarifies that Flowserve 28 EKL-2 pump is acceptable in place of the discontinued 25ENL-3 model, and adds Sulzer as an approved manufacturer alongside Fairbanks Nijhuis Pentair, Flowserve, and Peerless Pump. Site visits will not be permitted as Mt. Carmel WTP is a secure facility.

The addendum makes several technical specification changes, including setting the minimum bowl efficiency requirement at 82% (reduced from 84%) and eliminating consideration of "or equal" substitutions. SIMFLO pumps were deemed unacceptable due to NPSH3 concerns. The addendum specifies that MCC1 and MCC2 will be new equipment purchased under this contract, and no further pump suppliers will be considered after the December 5, 2024 deadline for plan holder questions. Manufacturers must demonstrate compliance with specifications per Section 43 24 26.15 during the submittal phase.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Purchasing Services Post Office Box 2570

Waco, Texas 76702-2570 Phone: 254-750-8098

Fax: 254-750-8063 melaniew@wacotx.gov

CITY OF WACO www.waco-texas.com

Date: 12/10/2024

RFB No: 2024-081 Commodity: Mt. Carmel WTP Pump Equipment Purchase Purchasing Agent: Melanie Wade

Closing Time: 2:00 P.M. CST, Tuesday, December 17, 2024 Opening Time: 2:05 P.M. CST, Tuesday, December 17, 2024

RFB Opening Location: Via Zoom Video and Dial In

Addendum No: 2

1. Answers to questions.

2. Revisions to contract documents and technical specifications.

The above-mentioned RFB has been changed. Sign and return addendum to the Purchasing Office by the closing time and date with your RFB response. Returning this page signed by your authorized agent will serve to acknowledge this change. All other requirements of the invitation remain unchanged. If you have any questions, please call or stop by the Purchasing Office at the above address.

Firm:____________________________________________________________________________________

Address___________________________________________________________________________________

Signature of Person Authorized to Sign Bid:______________________________________________________________________

Signor's Name and Title (print or type):_____________________________________________________________________________

E-mail Address:____________________________________________________________________________

Date:____________________Telephone:___________________________Fax:_________________________ mailto:melaniew@wacotx.gov file://NETAPP/HOMES/JodyC/0%20Purchasing/Utilities/2014/RFB%202014-012%20Generator%20Rebuild/www.waco-texas.com

Addendum No 2 Page 1 of 2

CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS

CITY OF WACO

MOUNT CARMEL WATER TREATMENT PLANT

PUMP EQUIPMENT PURCHASE

RFB: 2024-081

ADDENDUM NO. 2

Date Issued: December 09, 2024

Prepared by Chetan Soni, PE 103240

CDM Smith Inc Texas Registration No. F-3043

Bidders on this project are hereby notified that this addendum shall be attached to and made a part of the above named Contract Documents and Technical Specifications, dated November 14, 2024.

The following items are issued to add to, modify, and clarify the Contract Documents and Technical

Specifications and Drawings. These items shall have full force and effect as the Contract Documents and

Technical Specifications, and cost involved shall be included in bid prices. Bids to be submitted on the specific bid date shall conform to the additions and revisions listed herein.

Acknowledge receipt of this addendum by designating receipt of the addendum on the first page of the Bid

Proposal. Failure to do so may subject bidder to disqualification.

RESPONSES TO QUESTIONS RECEIVED:

1. Would a Flowserve 28EKL-2 stage pump be approved in place of the listed Flowserve 25ENL-3 stage pump? Unfortunately, the 25ENL model has been discontinued.

Response: Flowserve 28 EKL-2 is acceptable. Manufacturer shall still demonstrate that they meet the specified requirements per Section 43 24 26.15.

2. Will you allow bids from other pump manufacturers whom meet the specification?

Response: See response to question 3 in Addendum No. 1.

3. Is there any way to take a site visit?

Response: Site visits will not be allowed.

4. Can photos be provided of the nomenclature where MCC1 is to be added?

Response: MCC1 will be new equipment purchased under this Contract.

5. Can photos be provided of the nomenclature where MCC2 is to be added?

Response: MCC2 will be new equipment purchased under this Contract.

6. Can SIMFLO be considered an approved manufacturer for this project?

Response: SIMFLO is not acceptable due to NPSH3 concerns.

Response: Mt. Carmel WTP is a secure facility, and the City will not be permitting site visits for this project.

Addendum No 2 Page 2 of 2

7. Will you consider Sulzer pump for this bid? Sulzer has several pump stations in the area and is able to service these pumps locally. Please let me know if you have any questions or need any clarifications.

Response: Sulzer is acceptable. Manufacturer shall still demonstrate during submittal phase that they meet the specified requirements per Section 43 24 26.15

8. Is it necessary to submit for your approval in case we consider using another manufacturer for this pump? What would be the time limit for this approval if so?

Response: No further pump suppliers will be considered after the deadline for plan holder questions, or December 5, 2024. See response to question 3 in Addendum No. 1.

9. Could you clarify what are the mandatory certifications that the pump in question must have?

Response: Refer to Section 43 24 26.15 Para 1.4 regarding certifications.

REVISIONS TO CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS

SECTION 432426.15 – VERTICAL TURBINE SHORT-SET PUMPS

a) Page 432426.15-2.1 B: Delete the part of the sentence “Any consideration for “or equal” or substitute will be allowed only during the bid phase.” and replace with the following sentence “No substitutions/equals allowed.”

b) Page 432426.15 -2.1.B.1.: Delete the model numbers, such that the paragraph reads

“1. Fairbanks Nijhuis Pentair”

c) Page 432426.15 -2.1.B.2.: Delete the model number, such that the paragraph reads

“2. Flowserve”

d) Page 432426.15 -2.1.B.3.: Delete the model number, such that the paragraph reads

“3. Peerless Pump”

e) Page 432426.15 -2.1.B.: Add the following paragraph:

“4. Sulzer.”

f) Page 432426.15 -2.2.D.13.: Change “84” to “82”, such that the paragraph reads

“13. Bowl Efficiency at First Design Point: 82 percent minimum.”

REVISIONS TO DRAWINGS

N/A

END OF ADDENDUM NO. 2

Closing Time: 2:00 P.M. CST, Tuesday, December 17, 2024