This is Addendum No. 3 to RFB 2024-084 from the City of Waco, Texas Purchasing Services for the Wetlands Pump Station Project, providing answers to questions about HMI interface clarifications, PLC programming, and communications requirements. The addendum specifies a bid closing time of 2:00 P.M. CST and opening time of 2:05 P.M. CST on Wednesday, December 11, 2024, with the bid opening to be conducted via Zoom Video and Dial In.
The technical clarifications specify that the HMI interface should control pump start/stop functions and display I/O status, faults, alarms, and power meter information on a single screen without menu navigation. The PLC programming must control pump operations, receive Auto signals from H/O/A switches, trigger alarms, send data to SCADA for real-time visualization, and manage pump run times and fault histories. The cellular connection, utilizing an MDS Orbit Platform with SMA connection, is intended for SCADA remote monitoring and control of equipment and processes.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Purchasing Services Post Office Box 2570
Waco, Texas 76702-2570 Phone: 254-750-8098
Fax: 254-750-8063 melaniew@wacotx.gov
CITY OF WACO www.waco-texas.com
Date: 12/02/2024
RFB No: 2024-084 Commodity: Wetlands Pump Station Project Purchasing Agent: Melanie Wade
Closing Time: 2:00 P.M. CST, Wednesday, December 11, 2024 Opening Time: 2:05 P.M. CST, Wednesday, December 11, 2024
RFB Opening Location: Via Zoom Video and Dial In
Addendum No: 3 Answers to questions
The above-mentioned RFB has been changed. Sign and return addendum to the Purchasing Office by the closing time and date with your RFB response. Returning this page signed by your authorized agent will serve to acknowledge this change. All other requirements of the invitation remain unchanged. If you have any questions, please call or stop by the Purchasing Office at the above address.
Firm:____________________________________________________________________________________
Address___________________________________________________________________________________
Signature of Person Authorized to Sign Bid:______________________________________________________________________
Signor's Name and Title (print or type):_____________________________________________________________________________
E-mail Address:____________________________________________________________________________
Date:____________________Telephone:___________________________Fax:_________________________
Questions RFB 2024-084 Wetland Pump Station Project
HMI Interface Clarifications
1. What equipment/functions should be able to be controlled from the HMI?
a. Pumps start/stop
2. What equipment/functions should NOT be able to be controlled from the HMI?
3. What data/information should be displayed on the HMI?
a. I/O status, faults and alarms
b. Voltage and information from power meter
4. What data/information should NOT be displayed on the HMI?
5. Would there be a need for multiple "screens" that would be navigated between on the HMI via a "menu" or is the intention for all functionality to be contained in one "screen" on the
HMI?
a. No need for “menu”. Single screen can display all information and have Start/Stop for two pumps
PLC Programming
6. What does the PLC programming need to be able to do? (Functional Description)
a. Control stop/start of each pump
b. Receive ‘Auto’ from pumps H/O/A to allow remote and local HMI control over pumps
c. Trigger alarms, intrusion and various pump/wetwell alarms
d. Sending data to a SCADA system for real time data visualization and historizing
e. Store/forward pump run times, fault histories, and other critical parameters
PLC Communications
7. What is the intended purpose of the cellular connection?
a. SCADA – for remote monitoring and control of equipment and processes
8. The scope only states to provide a cellular antenna. Who is providing the cellular modem and what kind of antenna connection does said modem accept?
a. Will be the MDS Orbit Platform, believe that is the antenna SMA connection.