ES7034 (AS Attach .docx
DOCX document 18 KB Posted
- Attached to
- SMDC lines for the USAF and FMS F-15 Program.
- Solicitation number
- FA821325R3015
About this file
Attachment 5 (ES7034) is a technical document detailing rework and repair procedures for nonconforming material in a federal contract. The document defines two key processes: rework (complete reprocessing to meet contract requirements) and repair (partial reprocessing to make material usable). Key procedural requirements include submitting detailed rework and repair procedures to the Government Quality Assurance Representative (QAR) for review, including descriptions of nonconformance causes and prevention measures.
The related federal contract opportunity is a solicitation by the Department of the Air Force Materiel Command for SMDC lines and explosive cord sets for the USAF and FMS F-15 Program. The procurement includes multiple NSN part numbers for various SMDC lines and explosive cord sets, with quantities ranging from 4 to 10 units per line item. The total solicitation covers 11 specific line items of specialized military equipment, with the procurement being conducted through Hill Air Force Base.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA821325R3015_______0001.pdf | ||
| FA821325R3015_______0001.pdf | ||
| SPIs Combined.pdf | ||
| CDRLs.pdf | ||
| CADPAD Item Marking Instruction - Ver 1.6.pdf | ||
| JFQR 1377-01-Various (F-15 SMDC) signed.pdf | ||
| EDLs Combined.pdf | ||
| Air Specs.docx | DOCX document | |
| Statement of Objectives.pdf | ||
| REPSHIP.pdf | ||
| ADC SOW Jan 2018.docx | DOCX document | |
| FA821325R3015.pdf | ||
| Section M.pdf | ||
| Section L.pdf | ||
| Packaging Instructions.pdf | ||
| Item Descriptions_combined.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 5
(ES7034)
REWORK AND REPAIR OF NONCONFORMING MATERIAL
Jan 2012 (version)
(a) Rework and Repair are defined as follows:
(1) Rework - The reprocessing of nonconforming material to make it conform completely to the drawings, specifications or contract requirements.
(2) Repair - The reprocessing of nonconforming material in accordance with approved written procedures and operations to reduce, but not completely eliminate, the nonconformance. The purpose of repair is to bring nonconforming material into a usable condition. Repair is distinguished from rework in that the item after repair still does not completely conform to all of the applicable drawings, specifications or contract requirements.
(b) Rework procedures along with the associated inspection procedures shall be documented by the Contractor and submitted to the Government Quality Assurance Representative (QAR) for review prior to implementation. Rework procedures are subject to the QAR's disapproval.
(c) Repair procedures shall be documented by the Contractor and submitted on a Request for Deviation/Waiver, DD Form 1694, to the Contracting Officer for review and written approval prior to implementation.
(d) Whenever the Contractor submits a repair or rework procedure for Government review, the submission shall also include a description of the cause for the nonconformances and a description of the action taken or to be taken to prevent recurrence.
(e) The rework or repair procedure shall also contain a provision for reinspection which will take precedence over the Technical Data Package requirements and shall, in addition, provide the Government assurance that the reworked or repaired items have met reprocessing requirements.
(f) Rework and repair is a supply chain flow-down requirement that applies to contractors and their suppliers, vendors or subcontractors.
(End of clause)