Specification_072726_fluid_app_memb_air_barriers.51617.pdf

PDF 21 KB Posted

Attached to
Construction Manager as Constructor (CMc) Services for the Dwight D. Eisenhower Memorial Project Federal contract opportunity
Solicitation number
EQWPIAA-17-0016
Issued by
General Services Administration Public Buildings Service National Capital Region

About this file

New Specification Document

View the file

Other files for this federal contract opportunity

Other files attached to Construction Manager as Constructor (CMc) Services for the Dwight D. Eisenhower Memorial Project, newest first.
File Type Posted
Amendment_06.GS11P17MKC0016.060617.pdf PDF
Revised_SF1442.GS11P17MKC0016.Amendment_06.06062017.pdf PDF
Q&A.Part_3.Amendment_06.60617.pdf PDF
Bid_Speadsheet.Alternate_A.Rev_Amendment_06.6617.xlsx XLSX spreadsheet
Amendment_05.GS11P17MKC0016052617.pdf PDF
Q_and_A.Part_2.GS11P17MKC0016.5252017.pdf PDF
Spec_017700_CLOSEOUT_PROCEDURES.r2017.52517.pdf PDF
Spec_012300._ALTERNATES.r2017.52517.pdf PDF
Bid_Speadsheet.Alternate_A.revised.52517.xlsx XLSX spreadsheet
Spec.Division_1_Table_of_Contents.52517.pdf PDF
Spec_012100._ALLOWANCES.r2017.52517.pdf PDF
Amendment_04.GS11P17MKC0016.52517.pdf PDF
LBJ_visit_attendees_list_5.17.17.pdf PDF
Amendment_03.GS11P17MKC0016.051917.pdf PDF
Q_and_A.Solicitation_GS11P17MKC0016.5.16.17.pdf PDF
DOL_Wage_Rates.DC170002.Solicitation_GS11P17MKC0016.050517.pdf PDF
Bid_speadsheet.GS11P17MKC0016.5.16.17.xlsx XLSX spreadsheet
Amendment_02.GS11P17MKC0016.051617.pdf PDF
Solicitation_GS11P17MKC0016.Eisenhower_V2_2017.5.16.pdf PDF
Agreement_GS11P17MKC0016.v2.051617.pdf PDF
Amendment_01.GS-11-P-17-MK-C-0016.050217.pdf PDF
pre-proposal_attendee_list_4.25.17.pdf PDF
Bid_speadsheet_for_CMc_for_Eisenhower_-_5-2-17.xlsx XLSX spreadsheet
Division_01_Eisenhower_Memorial.r.04172017.pdf PDF
Eisenhower_Memorial_project_Pre-Proposal_Conference_Instructions.pdf PDF
Contract_Pricing_Form.GS11P17MKC0016.CMc_Project.March_22_2017.xlsx XLSX spreadsheet
Past_Performance_Questionnaire.docx DOCX document
Solicitation_GS11P17MKC0016..41017.pdf PDF
Tapestry_Development_Summary_Report.4.5.17.pdf PDF
2017-02-08_01_Eisenhower_Memorial_Spec_Vol1_Div02-22.pdf PDF
Drawings.2016.02-08.100CD_V1.pdf PDF
CMc.Agreement_GS11P17MKC0016.041017.pdf PDF
Eisenhower_Memorial_Division_01.041017.pdf PDF
GSA527-15b.pdf PDF
Reps_and_Certs.CMc.GS11P17MKC0016.Eisenhower.pdf PDF
Drawings.2016.02-08.100CD_V2.pdf PDF
GS_Form_1442.GS11P17MKC0016.Eisenhower.pdf PDF
CMc_SOW.March_22_2017.pdf PDF
2017-02-08_02_Eisenhower_Memorial_Spec_Vo2_Div23-34_&_Appendix.pdf PDF
DOL_Wage_Rates.041017.pdf PDF
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 1

DWIGHT D. EISENHOWER MEMORIAL

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

SECTION 072726 - FLUID-APPLIED MEMBRANE AIR BARRIERS (WP-3)

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes fluid-applied, vapor-permeable membrane air barriers, at the following locations and as indicated on Drawings as WP-3, including but not limited to:

1. Stone columns substrate.

2. Above grade at Information Center, Memorial columns, Memorial blocks, and overlook wall.

3. At cast-in-place concrete substrate behind stone and precast concrete cladding, including existing substrates at the sunken LBJ courtyard.

B. Related Requirements:

1. Section 07 1326 – Self-Adhering Sheet Waterproofing (WP-1).

2. Section 07 1413 – Hot Fluid-Applied Rubberized Asphalt Waterproofing (WP-4).

3. Section 07 5423 – Thermoplastic Polyolefin (TPO) Roofing (WP-2).

1.3 DEFINITIONS

A. Air-Barrier Material: A primary element that provides a continuous barrier to the movement of air.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review air-barrier requirements and installation, special details, mockups, air-leakage and bond testing, air-barrier protection, and work scheduling that covers air barriers.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include manufacturer's written instructions for evaluating, preparing, and treating substrate;

technical data; and tested physical and performance properties of products.

B. LEED Submittals:

1. Product Data for Credit IEQ 4.2: For air-barrier products, documentation including printed statement of VOC content.

C. Shop Drawings: For air-barrier assemblies.

1. Show locations and extent of air barrier. Include details for substrate joints and cracks, counterflashing strips, penetrations, inside and outside corners, terminations, and tie-ins with adjoining construction.

2. Include details of interfaces with other materials that form part of air barrier.

1.6 INFORMATIONAL SUBMITTALS

A. Product Certificates: From air-barrier manufacturer, certifying compatibility of air barriers and accessory materials with Project materials that connect to or that come in contact with the barrier.

B. Product Test Reports: For each air-barrier assembly, for tests performed by a qualified testing agency.

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 2

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

1.7 QUALITY ASSURANCE

A. Installer Qualifications: An entity that employs installers and supervisors who are trained and approved by manufacturer.

B. Mockups: Install air barrier material on mockups of other sections. Refer to Section 01 1401 – Mockup Schedule.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Remove and replace liquid materials that cannot be applied within their stated shelf life.

B. Protect stored materials from direct sunlight.

1.9 FIELD CONDITIONS

A. Environmental Limitations: Apply air barrier within the range of ambient and substrate temperatures recommended by air-barrier manufacturer.

1. Protect substrates from environmental conditions that affect air-barrier performance.

2. Do not apply air barrier to a damp or wet substrate or during snow, rain, fog, or mist.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Source Limitations: Obtain primary air-barrier materials and air-barrier accessories from single source from single manufacturer.

B. VOC Content: 250 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24) and complying with VOC content limits of authorities having jurisdiction.

2.2 PERFORMANCE REQUIREMENTS

A. General: Air barrier shall be capable of performing as a continuous vapor-permeable air barrier and as a liquid-water drainage plane flashed to discharge to the exterior incidental condensation or water penetration. Air-barrier assemblies shall be capable of accommodating substrate movement and of sealing substrate expansion and control joints, construction material changes, penetrations, tie-ins to installed waterproofing, and transitions at perimeter conditions without deterioration and air leakage exceeding specified limits.

2.3 VAPOR-PERMEABLE MEMBRANE AIR-BARRIER (WP-3)

A. Fluid-Applied, Vapor-Permeable Membrane Air Barrier: synthetic polymer membrane.

1. Products: Subject to compliance with requirements, provide one of the following:

a. Synthetic Polymer Membrane:

1) Basis of Design: Grace, W. R., & Co. - Conn.; Perm-A-Barrier VPO.

2) Carlisle Coatings & Waterproofing Inc.; Barritech VP.

3) Henry Company; Air-Bloc 31.

4) PROSOCO: R-Guard MVP.

2. Physical and Performance Properties:

a. Air Permeance: Maximum 0.004 cfm/sq. ft. of surface area at 1.57-lbf/sq. ft. (0.02 L/s x

sq. m of surface area at 75-Pa) pressure difference; ASTM E 2178.

b. Vapor Permeance: Minimum 10 perms (580 ng/Pa x s x sq. m); ASTM E 96/E 96M.

c. Ultimate Elongation: Minimum 500 percent; ASTM D 412, Die C.

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 3

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

2.4 ACCESSORY MATERIALS

A. General: Accessory materials provided by or recommended by air-barrier manufacturer to produce a complete air-barrier assembly and compatible with primary air-barrier material.

B. Primer: Liquid waterborne primer recommended for substrate by air-barrier material manufacturer.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

1. Verify that substrates are sound and free of oil, grease, dirt, excess mortar, or other contaminants.

2. Verify that concrete has cured and aged for minimum time period recommended by air-barrier manufacturer.

3. Verify that concrete is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method according to ASTM D 4263.

4. Verify that masonry joints are flush and completely filled with mortar.

5. Verify that surface condition at existing substrates at the LBJ sunken courtyard are ready for air barrier installation. Correct surfaces as necessary.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 SURFACE PREPARATION

A. Clean, prepare, treat, and seal substrate according to manufacturer's written instructions. Provide clean, dust-free, and dry substrate for air-barrier application.

B. Mask off adjoining surfaces not covered by air barrier to prevent spillage and overspray affecting other construction.

C. Remove grease, oil, bitumen, form-release agents, paints, curing compounds, and other penetrating contaminants or film-forming coatings from concrete.

D. Remove fins, ridges, mortar, and other projections and fill honeycomb, aggregate pockets, holes, and other voids in concrete with substrate-patching membrane.

E. Remove excess mortar from masonry ties, shelf angles, and other obstructions.

F. At changes in substrate plane, apply sealant or termination mastic beads at sharp corners and edges to form a smooth transition from one plane to another.

G. Cover gaps in substrate plane and form a smooth transition from one substrate plane to another with stainless-steel sheet mechanically fastened to structural framing to provide continuous support for air barrier.

H. Closely examine existing substrates for compatibility of materials. Correct existing substrates as required by air barrier manufacturer.

3.3 JOINT TREATMENT

A. Concrete and Masonry: Prepare, treat, rout, and fill joints and cracks in substrate according to ASTM C 1193 and air-barrier manufacturer's written instructions. Remove dust and dirt from joints and cracks complying with ASTM D 4258 before coating surfaces.

1. Prime substrate and apply a single thickness of air-barrier manufacturer's recommended preparation coat extending a minimum of 3 inches (75 mm) along each side of joints and cracks.

Apply a double thickness of fluid air-barrier material and embed a joint reinforcing strip in preparation coat.

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 4

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

3.4 TRANSITION STRIP INSTALLATION

A. General: Install strips, transition strips, and accessory materials according to air-barrier manufacturer's written instructions to form a seal with adjacent construction and maintain a continuous air barrier.

1. Coordinate the installation of air barrier with installation of roofing membrane and base flashing to ensure continuity of air barrier with roofing membrane.

B. Apply primer to substrates at required rate and allow it to dry. Limit priming to areas that will be covered by fluid air-barrier material on same day. Reprime areas exposed for more than 24 hours.

C. Connect and seal exterior wall air-barrier material continuously to roofing-membrane air barrier, concrete below-grade structures, floor-to-floor construction, exterior glazing and window systems, glazed curtain-wall systems, storefront systems, exterior louvers, exterior door framing, and other construction used in exterior wall openings, using accessory materials.

D. At end of each working day, seal top edge of strips and transition strips to substrate with termination mastic.

E. Apply joint sealants forming part of air-barrier assembly within manufacturer's recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges.

F. Fill gaps in perimeter frame surfaces of windows, curtain walls, storefronts, and doors, and miscellaneous penetrations of air-barrier material with foam sealant.

G. Seal strips and transition strips around masonry reinforcing or ties and penetrations with termination mastic.

H. Seal exposed edges of strips at seams, cuts, penetrations, and terminations not concealed by metal counterflashings or ending in reglets with termination mastic.

I. Repair punctures, voids, and deficient lapped seams in strips and transition strips. Slit and flatten fishmouths and blisters. Patch with transition strips extending 8 inches (200 mm) beyond repaired areas in strip direction.

3.5 FLUID AIR-BARRIER MEMBRANE INSTALLATION

A. General: Apply fluid air-barrier material to form a seal with strips and transition strips and to achieve a continuous air barrier according to air-barrier manufacturer's written instructions. Apply fluid air-barrier material within manufacturer's recommended application temperature ranges.

1. Apply primer to substrates at required rate and allow it to dry.

2. Limit priming to areas that will be covered by fluid air-barrier material on same day. Reprime areas exposed for more than 24 hours.

B. Membrane Air Barriers: Apply a continuous unbroken air-barrier membrane to substrates according to the following thickness. Apply air-barrier membrane in full contact around protrusions such as masonry ties.

1. Vapor-Permeable Membrane Air Barrier: Total dry film thickness as recommended in writing by manufacturer to meet performance requirements, but not less than 40-mil (1.0-mm) dry film thickness, applied in one coat.

C. Apply strip and transition strip a minimum of 1 inch (25 mm) onto cured air-barrier material or strip and transition strip over cured air-barrier material overlapping 3 inches (75 mm) onto each surface according to air-barrier manufacturer's written instructions.

D. Do not cover air barrier until it has been tested and inspected by Contractor's testing agency.

E. Correct deficiencies in or remove air barrier that does not comply with requirements; repair substrates and reapply air-barrier components.

3.6 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 5

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

B. Inspections: Air-barrier materials, accessories, and installation are subject to inspection for compliance with requirements. Inspections may include the following:

1. Continuity of air-barrier system has been achieved throughout the areas that receive coating with no gaps or holes.

2. Continuous structural support of air-barrier system has been provided.

3. Masonry and concrete surfaces and existing surfaces at LBJ Building are smooth, clean, and free of cavities, protrusions, and mortar droppings.

4. Site conditions for application temperature and dryness of substrates have been maintained.

5. Maximum exposure time of materials to UV deterioration has not been exceeded.

6. Surfaces have been primed, if applicable.

7. Laps in strips and transition strips have complied with minimum requirements and have been shingled in the correct direction (or mastic has been applied on exposed edges), with no fishmouths.

8. Termination mastic has been applied on cut edges.

9. Strips and transition strips have been firmly adhered to substrate.

10. Compatible materials have been used.

11. Transitions at changes in direction and structural support at gaps have been provided.

12. Connections between assemblies (air-barrier and sealants) have complied with requirements for cleanliness, surface preparation and priming, structural support, integrity, and continuity of seal.

13. All penetrations have been sealed.

C. Tests: As determined by Contractor’s testing agency from among the following tests:

1. Adhesion Testing: Air-barrier assemblies will be tested for minimum air-barrier adhesion of 10 lbf/sq. in. (70 kPa) according to ASTM C 836 for each 600 sq. ft. (56 sq. m) of installed air barrier or part thereof.

D. Air barriers will be considered defective if they do not pass tests and inspections.

1. Apply additional air-barrier material, according to manufacturer's written instructions, where inspection results indicate insufficient thickness.

2. Remove and replace deficient air-barrier components for retesting as specified above.

E. Repair damage to air barriers caused by testing; follow manufacturer's written instructions.

3.7 CLEANING AND PROTECTION

A. Protect air-barrier system from damage during application and remainder of construction period, according to manufacturer's written instructions.

1. Protect air barrier from exposure to UV light and harmful weather exposure as required by manufacturer. If exposed to these conditions for more than 30 days, remove and replace air barrier or install additional, full-thickness, air-barrier application after repairing and preparing the overexposed membrane according to air-barrier manufacturer's written instructions.

2. Protect air barrier from contact with incompatible materials and sealants not approved by air-barrier manufacturer.

B. Clean spills, stains, and soiling from construction that would be exposed in the completed work using cleaning agents and procedures recommended by manufacturer of affected construction.

C. Remove masking materials after installation.

END OF SECTION 072726

FLUID-APPLIED MEMBRANE AIR BARRIERS 072726 - 6

Contract No. GS-11P-12-MK-C-0005

100% Construction Documents February 8, 2016

THIS PAGE LEFT BLANK INTENTIONALLY