Buried power and control conduit with wire/cable. Tie into spare conduit at rpm stand. (Pull wire/cable from building). Run up middle of road until trench across road to be made at joint between new and old pavement. Then run in shoulder to pedestal..

12/12/16

DRAWN BY:

DATE:

KMW

SHEET:

S - 2

SENSITIVE BUT UNCLASSIFIED (SBU) PROPERTY OF THE UNITED STATES GOVERNMENT -- FOR OFFICIAL USE ONLY. Do not remove this notice. Properly destroy documents when no longer needed.

Chateaugay LPOE Northbound Gate

Gate operator housing and 12 foot long lift gate arm. Pedestal to be set on 23 inch square concrete pad 4 inches above grade. Four concrete bollards to be installed at the corners of the pad.

Operator to be installed in the highway shoulder. Command to open gate to occur via a ground loop on south side of gate. Manual override button to be remotely operated (wired) from booth.

Backfill and patch trenches in road and shoulder to match existing

KarenMWilson Typewritten Text page 26 of 38 in SOW_-_Northbound_Gates_-_Group_1_package_1-25-17

KarenMWilson Cross-Out

KarenMWilson Callout