This document is an Engineer's Opinion of Probable Cost (EOPC) for the City of Texico Brown Well project, dated 4/8/2025, prepared by DBS&A (a Geo-Logic Company). The draft design cost estimate outlines a comprehensive infrastructure upgrade involving the demolition of an existing CMU building and the construction of a new well facility. The project includes installing a pre-fabricated FRP building, implementing a gas chlorination system, replacing electrical infrastructure, and making necessary piping and electrical connections. The scope of work encompasses nine distinct construction items, with quantities specified as lump sum (LS) or square feet (SF) as appropriate.
The total estimated construction cost is $220,409, which includes a construction subtotal of $178,600, a 15% contingency of $26,790, and New Mexico Gross Receipts Tax (NMGRT) of $15,019 at 7.3125%. Major cost components include $13,250 for mobilization and demobilization, $30,000 for a new pre-fabricated building, $51,000 for the gas chlorination system, and $49,350 for electrical infrastructure. The project appears to be a municipal infrastructure improvement focused on upgrading water treatment and well facility capabilities, with careful consideration given to technical specifications and potential additional costs through the contingency and tax allocations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of Texico Date: 4/8/2025
Texico Brown Well Prepared by: NA
Engineer's Opinion of Probable Cost: Draft Design Checked by: KH Item No. Item Description QTY Unit Unit Price
Extended Price
Construction Cost 1 Mobilization and demobilization 1 LS 13,250$ 13,250$
2 Demolition of existing CMU building, including concrete and foundation, CIP 1 LS 12,000$ 12,000$
3 Remove existing plumbing, electrical, and mechanical inside well building, coordinate with City on disposal, CIP 1 LS 6,000$ 6,000$
4 Pre-fabricated FRP Building (6'x6'), including heating and ventilation, pre drawings, CIP 1 LS 30,000$ 30,000$
5 Concrete foundation for new building, per drawings, CIP 77 SF 64$ 5,000$
Gas chlorination system, including two cylinder tanks, scale, monitoring sensors, outputs & alarms, pump, analyzer, piping, and all appurtenances, CIP
1 LS 51,000$ 51,000$
7 SCH 80 PVC piping and connections to existing manifold, CIP 1 LS 2,000$ 2,000$
Electrical including 100A/3P disconnect, TVSS, MPZ, pump starter, 75 LF of circuiting for chlorination system, unistrut rack, and 125 LF of service conduit and conductors, CIP
1 LS 49,350$ 49,350$
9 Electric company to disconnect existing service and reconnect new service 1 Allow 10,000$ 10,000$
Construction Subtotal 178,600$ Contingency 15% 26,790$
NMGRT 7.3125% 15,019$
Total Construction Cost 220,409$
4/8/2025 S:\Projects\DB25.1018_Curry_County_Texico_Brown_Well\Engineering\Cost Estimates\EOPC_Texico Brown Well_Draft Design