This document outlines a federal solicitation for replacement of an HVAC system. The Federal Aviation Administration is seeking to replace the HVAC system at the Airport Surveillance Radar facility located at the Eastern Iowa Airport in Cedar Rapids, Iowa. Interested contractors must be registered in the System for Award Management by November 30, 2020 to be eligible for award. Questions regarding specifications and drawings are due by November 23, 2020, and proposals must be received by November 30, 2020. The solicitation will result in a firm-fixed-price construction contract. The contractor will be responsible for furnishing all materials, equipment, labor, insurance, and other requirements to complete the HVAC replacement as described in the specifications, drawings, and attachments.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Central Service Area
Environmental, Occupational Safety and Health (EOSH) Project Review Checklist
Rev. 05/06/2011 Page 1 of 5
PROJECT CID ASR HVAC
Replacement
JON DATE 9/6/2018
JCN 602249
Transmittal
Revised? REGION
Central DISTRICT Minneapolis
SSC Cedar Rapids
FACILITY
LOCATION
Cedar Rapids, IA FACILITY
TYPE
ASR FACILITY
ID
CID
ENGINEER
TITLE
Matthew Felix Project Engineer
EHS
Hudson Varner EOSH Coordinator
SUPERVISOR
Grant Hightower Manager
CODE AJW-2C15D CODE AJW-2C15H CODE AJW-2C15D
SIGNATURE
Issue Yes No
Action Items and Notes
If YES, always coordinate with EOSH Specialist
AIR EMISSIONS
CLEAN AIR ACT
(CAA)
Replace and/or install new emission sources such as boilers, incinerators, storage tanks, engine generators, painting booths, space heaters, equipment using CFCs or Halon, etc.
1. Review federal and state requirements for new or modified sources.
ASBESTOS Will activity potentially impact presumed or known asbestos containing materials (ACM)?
NOTE: The facility has been surveyed and does not have ACM.
1. Check Index of Asbestos and Lead Paint Surveys to see if the facility has been surveyed for asbestos. Index available from the FOPOC and ANS-500.
FEDERAL
INSECTICIDE
FUNGICIDE AND
RODENTICIDE
ACT (FIFRA)
Does the project require the application of pesticides and/or herbicides?
1. Review FAA Order 1050.17, FIFRA implementing regulations, 40 CFR Parts 152, 162, and 171 and State regulations.
CHLOROFLUORO
-CARBONS (CFC)
Is CFC containing equipment being replaced, installed or disposed? (I.e. refrigeration systems, Halon systems, HVAC systems, etc.)
NOTE: Ensure replacement of
HVAC systems with non-CFC equipment and ensure recovery and recycling of existing CFCs in accordance with Federal, State, Local, and FAA regulations.
Review FAA Order 1050.17 and
1050.18
1. Review project plans and specifications
COMPRESSED
GAS
Are compressed gasses utilized?
NOTE: All welding, cutting and brazing activities must follow ANI
SOP PROCEDURES FOR
WELDING, CUTTING AND BRAZING
1. Review Project plans, specifications and work procedures. Will welding or cutting take place?
ENVIRONMENTAL
DUE DILIGENCE
AUDIT (EDDA)
Acquire, lease and/or dispose of land property?
1. Review Project plans and specifications
Rev. 05/06/2011 Page 2 of 5
NATIONAL
ENVIRONMENTAL
POLICY ACT
(NEPA)
Does the project potentially impact the environment with respect to noise, water quality, air quality, wetlands, flora and fauna, wildlife, historic and archeological sites, endangered species & other protected areas?
1. Review Project plans and specifications.
ENERGY Install new lighting, HVAC, or environmental controls?
FLUORESCENT
LAMPS
Dispose, install or recycle fluorescent lamps?
FUEL STORAGE
TANKS
Install, remove and/or replace an underground or aboveground storage tank or piping? If the project is new construction, is an existing UST and/or piping near the project site being impacted?
1. Check Storage Tank Inventory available from the Regional FST Manager or the FOPOC or ANI Representative.
2. Review Project plans and specifications.
WASTE
MANAGEMENT
What types of waste will be generated as a result of the project?
Y N Hazardous Wastes Construction / Demolition Debris Packaging wastes and/ or recyclable materials or items.
NOTE: Ensure disposal of construction / demolition debris in accordance with Federal, State, Local, and FAA regulations.
1. Determine if the waste generated is classified as a hazardous waste by determining if it is a listed hazardous waste or if it is characteristically hazardous.
2. Review FAA Order 1050.17 (Chapter 12), 40 CFR 260- 266, 273, 279, and state hazardous waste regulations.
3. Review AC No. 150/5320-15A (Management of Airport Industrial Waste)
LEAD-ACID
BATTERIES
Disturb, store, dispose or recycle lead acid batteries?
1.
LEAD BASED
PAINT
Disturb, store, and dispose of lead paint?
NOTE: This facility has been tested and does not contain lead based paint.
1. Check Index of Lead Paint Surveys to see if sampling has been conducted.
2. If no paint sampling results available, then all impacted materials must be assumed lead containing or contaminated until sampled & tested.
LOCKOUT/
TAGOUT & HIGH
VOLTAGE
(Construction)
Are pressurized or electrical systems being impacted as part of the project construction?
NOTE: Work activities involving hazardous energy sources (i.e.
electrical) follow the LOCK
OUT/TAG OUT procedures in ANI
SOP PROCEDURES FOR
WORKING ON HAZARDOUS
ENERGY SOURCES
If yes:
1. Only utilize fully trained personal to perform electrical work and lockout/tagout procedures.
Rev. 05/06/2011 Page 3 of 5
LOCKOUT/
TAGOUT
PROCEDURE
(Post
Construction)
Will a new LOTO plan need to be developed for new equipment being installed?
NOTE: The designer/contractor will develop a site specific lockout / tag out plan for existing equipment modifications and new installation.
This plan will be based on manufacturers recommended procedures and site specific switch locations and conditions. The plan will follow the standard FAA LOTO format.
1. prepare a LOTO procedure in accordance with FAA orders and policies
2. Coordinate the LOTO procedure with the local SSC or facility contact.
ENERGIZED
ELECTRICAL
SYSTEMS
(construction)
Will the construction involve work on energized electrical systems greater than 50 volts?
1. Initiate two-person rule with first aid and CPR trained personnel.
2. Fill out and submit an energized electrical work permit prior to initiating the work.
3. Use proper PPE for arc flash hazards
ARC FLASH
HAZARD
(Post construction)
Based on the following conditions, an Arc Flash analysis is not required:
N Y The circuit is rated 240 volts or more;
The circuit is supplied by more than one transformer, and;
The transformer supplying the circuit is rated greater than 125 kVA.
1. Perform a short circuit / arc flash hazard calculation.
2. label and mark off arc flash hazards
PCBs Relocate or dispose of PCBs and/or PCB containing equipment? (Fluorescent fixture ballast's, electric transformers and equipment)
1. Check the PCB Inventory available from each FOPOC.
2. Determine if the PCB component was manufactured before 1984.
MERCURY Are Mercury Switches present that will be impacted by the work?
NOTE: Equipment may contain mercury fuses/switches. Ensure proper disposal or recycling per
Federal, State, and Local regulations.
1. Check for Mercury switches
RADIOACTIVE
SOURCES,
RADON, ETC.
Relocate or dispose Radioactive tubes, or other hazardous waste? Is there evidence or potential for elevated radon levels in construction site?
1. Determine if radon will or is an influence at the site.
SAFETY -
General
Safety issues? I.e. Clear aisle space, electrical equipment clearances, toe boards, hand rails, stair clearances, safety cages, fire protection, fire life safety, ladders, Hazard Communication (HAZCOM), first aid, accident prevention, construction safety, etc.
NOTE: Follow all OSHA regulations, NEC and FAA orders during all work activities.
1. Review FAA Orders 1050.17 & 3900.19B, and 29 CFR 1910 & 1926.
Rev. 05/06/2011 Page 4 of 5
SAFETY –
Fall Protection
Will work be conducted on elevated surfaces?
NOTE: Employee working at heights greater than four (4) feet or near an unprotected edge should use be protected by a safety net, guardrails, or personal fall arrest/restraint system. The employee/contractor should follow all OSHA regulations and FAA order 3900.63, Fall Protection
Program. The possible use of ladders or lifts are the existing fall hazards for this project.
1. Review FAA Orders 3900.63, 1050.17 & 3900.19B, and
29 CFR 1910 & 1926.
Confined Space
Will work be conducted in a confined space?
Will work be conducted in a Permit required Confined space?
1. Review FAA Orders 1050.17 & 3900.19B, and 29 CFR
Personal
Protective
Equipment (PPE)
Will any of the following be required?
Safety Glasses, Safety Shoes, Reflective Vest, Hard hat, Gloves, Disposable clothing, Respiratory Protection, Hearing Protection, Climbing Harness and Lanyard
1. Review FAA Orders 1050.17 & 3900.19A, and 29 CFR
2. Review SDS Sheets for any chemicals or materials.
Excavations and
Trenches
Will any excavations or trenches be required for the project?
NOTE: All excavations, trenches, and boring activities shall adhere to the OSHA regulations within 29
CFR 1926, Subpart P.
Runway Safety
Will the work take place in an aircraft operational area?
NOTE: Construction activities on the airport, in proximity to, or affecting aircraft operational areas or navigable airspace, shall be coordinated with the FAA, Airport
Operators, and airport users prior to initiating any construction activities.
1910 & 1926. and AC 150/5210-20 (Ground Vehicle Operations on Airports), AC No. 150/5370-2E (Operational Safety on Airports During Construction) and AC No. 150/5380-5B (debris Hazards at Civil Airports)
TRAINING Are personal required to have training to be qualified to work?
NOTE: Utilize only OSHA certified
Construction Safety, electrical safety, and LOTO trained personnel.
Rev. 05/06/2011 Page 5 of 5
WATER
CLEAN WATER
ACT (CWA) &
SAFE DRINKING
WATER ACT
(SDWA)
Does the project involve the clearing, grading, and excavation of over 5 acres; (I acre is proposed rule and is not final) impact navigable waters; utilize equipment which can discharge to storm water or wastewater systems (cooling tower discharges or boiler blow downs)? State and local regulatory authorities may impose more stringent SWDP requirements.
1. Review pollution prevention under EO 12856, EO 12873: Federal Acquisition, Recycling, and Waste Prevention.
2. Clean Water Act implementing regulations, 40 CFR Parts 110, 112, 122, 136, 400-460, and 33 CFR Part 154, FAA Order 1050.15A
WATER
Potable water testing
Does the project involve the installation of new or modification of potable water supply plumbing or fixtures? (i.e. wells, pipes, sinks, drinking fountains, etc)
CSA Engineering Services EHS Contacts
EOSH COORDINATOR (NISC)
EOSH Coordinator Hudson Varner 817-222-5279
MSP District Name Phone Fax/Cell SECM/EPS Alex Gintner 651-322-9312 651-755-0484
NISC EOSH Lance Egeland 515-974-8058 515-528-6057
| 2018-09-06T13:42:05-0500 | |
| HUDSON E VARNER |
File details come from the government source that posted it. Updated .