Entrada_Way_Plans_Final_signed.pdf

PDF 31 MB Posted

Attached to
Entrada Way Culvert Slip-Out Bank Stabilization Project
Solicitation number
E5103000
Issued by
San Mateo County, San Bernardino City, California

About this file

This is a set of construction plans and specifications for the Entrada Way Culvert Slip-Out Bank Stabilization Project prepared by the County of San Mateo Public Works Department. The project involves comprehensive creek channel realignment, bank stabilization, and roadway improvements along La Honda Creek adjacent to Entrada Way. The scope of work includes clearing and grubbing operations, installation of erosion and sediment control measures (high visibility silt fencing, wildlife exclusion fencing, and stabilized construction entrances), temporary creek diversion systems with fish exclusion netting, excavation and dewatering of isolated work areas, installation of engineered log structures (ELS) with timber pilings, placement of scour protection rock and salvaged boulders, channel realignment with low-flow channel construction, roadway pavement removal and replacement, installation of drainage infrastructure including a 24-inch storm drain pipe, retaining wall construction with soldier piling and ground anchors, and riparian restoration through live stake and container plant installations. Sealed bids are due by 2:00 p.m. on Thursday, July 23, 2026, with public bid opening immediately following. Contractors must register on the OpenGov website to access all bidding documents and are required to submit a Plan Holder's Affidavit if obtaining documents through alternative sources. Questions regarding contract documents must be submitted in writing via email to mclement@smcgov.org and wng@smcgov.org by 5:00 p.m. on July 16, 2026, with responses posted to the County's Public Works website.

The plans indicate this is a complex multi-phase construction project requiring coordination of water management, environmental controls, and in-stream work activities. All temporary water management measures are preliminary schematics subject to contractor modification and engineer approval, with the contractor bearing sole responsibility for managing surface water and groundwater and submitting a Temporary Creek Diversion System Plan prior to commencing in-water work. Construction access is restricted to property 083-051-110 on the left (east) bank with all heavy equipment requiring crane placement into the work area. The project requires coordination with qualified biologists for fish exclusion and wildlife protection measures, and engineer inspections are mandatory at multiple stages including verification of clearing and grubbing limits, root zone protection installation, excavation extents, and key log placement before construction advancement. Tree surveys were completed November 5-6, 2024, and January 8, 2025, with specific tree removal protocols and protection requirements detailed throughout the plans.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COUNTY OF SAN MATEO

CALIFORNIA

PROJECT

LOCATION

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER COVER

G01

PROJECT

LOCATION

OHW

TOP

June 26, 2026

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER CONSTRUCTION BMPS

G02

LA HONDA GUILD

CUESTA

083-370-010

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 3

McEVOY 083-370-010

VOL 10 PG 71

LA HONDA GUILD - CUESTA

083-051-150LA HONDA GUILD

CUESTA

083-051-120

Bruce 083-051-110

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 1

E N T R A D

A W A Y

6 0 ' R O W

PINGER AND FERGUSON

083-012-060

PARCEL I

2007-095388

(VOL 32 PG 87)

BUILDING

BUILDING

BUILDING

BUILDING

26105 26106

26161

26162

26177

2620526206

26208

2622026221

26222

26232

26233

26237

262412624226245 26247

26250

26254

26305

26306

2630726308 26472

2661926621

26622

2662526626 26627

26628

26636

26639

26642

26644

26650 26651

26655

26657

2665826659

26662 26663

26711

26727

26751

26773

26776

26777 26778

26779

26780

2678126783

26784

26786

2678726789

26797

26818

26819 26820

26942

27068

27120

27123 100037

100038

100039 100040 100041

100042

100130

100131 100132

100133 100134

100135100136 100137

100187

100214

100220 100223

100225

100227

100228

WATERS OF THE US

X

26124

26463264642644526446

100209

100210100211

100216

100217

OHW

OHW

OHW

OHW

O H

W

O

HW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW OHW

OHW

O H

W

OHW

O

HW

OHW

O H

W

OHW

OHW

TOP

TOP

TOP

TOP

TO

P

TOP

TO

P

TOP

TOP

TO

P

TOP

TOP

TOP

TOP

TO

P

TOP

TOP

TOP

TO

P

TOP

TOP

TO

P

TOP

TO

P

TOP

TOP

TOP

TOP

26444

150000 150001150002

150003150004

150005150006150007150008150009

150010 150011150012

150016

26378

26231

HVSF HVSF HVSF

H

VS

F

HV

SF

HVSF

HVSF

HVSF HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

HVSF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

WEF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

WEF WEF

C02

HIGH VISIBILITY SILT FENCE

(WITH WILDLIFE EXCLUSION)

SITE ACCESS FROM

ENTRADA WAY

PROJECT LIMITS

TYP

C04

TEMPORARY ROOT ZONE

PROTECTION - TYPE A

TYP

26021

26022

26457

26609 26614

26673

26676 26677

26698

26699

27035

100141 100142

100155

100207

100139

100140

27038

100138

100208100150

150017

C02

STABILIZED CONSTRUCTION

ENTRANCE

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

XCONNECT HVSF TO

FISH EXCLUSION

NETTING

SEE NOTE 1 (TYP) CONNECT HVSF TO

FISH EXCLUSION

NETTING

C04

TEMPORARY ROOT ZONE

PROTECTION - TYPE B

PROTECT IN PLACE

OVERHEAD POWER

STEEL PLATE

SEE NOTE 3

TYP

C02

WILDLIFE EXCLUSION

FENCE

K-RAIL

LEGEND

PROJECT LIMITS

HIGH VISIBILITY SILT FENCE

(WITH WILDLIFE EXCLUSION)HVSF

STAGING AND

STORAGE

TEMPORARY

CONSTRUCTION ENTRANCE

SITE ACCESS

TEMPORARY ROOT ZONE

PROTECTION -TYPE A

WILDLIFE EXCLUSION

FENCE

WEF

TEMPORARY ROOT ZONE

PROTECTION - TYPE B

STEEL PLATE

REDONDA WAY

LA HONDA GUILD

CUESTA

083-092-190 E N T R A D A W A Y

6 0 ' R O W

BUILDING

TENNIS

COURT

X X X X X X X X X X X X X X X X X

X X

X X

X X

X X

X X

X X

X

X X

X X

X X

X X

X X

X X

X X

X X

X X

EO

P

HVSF HVSF HVSF HVSF HVSF HVSF

HV

SF

H

VS

F

H

VS

F

W

EF

W

EFWEF

WEF

WEF

WEF

WEF

WEF

WEF

W

EF

W

EF

W

EF

STAGING AND STORAGE PROTECT IN PLACE

OVERHEAD POWER

C02

STABILIZED CONSTRUCTION

ENTRANCE

PROTECT IN PLACE TREE

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

020 20 40

SCALE IN FEET

C01

NOTES:

1. TERMINAL ENDS OF HIGH VISIBILITY SILT FENCE (WITH WILDLIFE EXCLUSION) SHALL BE INTEGRATED WITH FISH EXCLUSION NETS TO ENSURE A CONTINUOUS WILDLIFE EXCLUSION BARRIER ALONG THE PROJECT

LIMITS.

2. WILDLIFE EXCLUSION FENCE LIMITS SHOWN ARE APPROXIMATE AND SUBJECT TO CHANGE THROUGHOUT THE CONSTRUCTION PERIOD AND PER THE DIRECTION OF THE ENGINEER OR THE QUALIFIED BIOLOGIST.

WILDLIFE EXCLUSION FENCE SHALL CONFORM TO THE BMP BIO-3 REQUIREMENTS OF SAN MATEO

COUNTY'S ROUTINE MAINTENANCE PROGRAM.

3. STEEL PLATE(S) TO BE PLACED OVER EXISTING ROADSIDE DRAINAGE DITCH AS PART OF STABILIZED

CONSTRUCTION ENTRANCE TO PROTECT IN PLACE AND MAINTAIN ITS FUNCTION.

4. CONTRACTOR SHALL BE RESPONSIBLE FOR DEVELOPING AND IMPLEMENTING A TRAFFIC CONTROL PLAN FOR ALL PHASES OF CONSTRUCTION. ORANGE ADVISORY SIGNS SHALL BE ADDED AT EASTERN AND WESTERN EDGES OF THE PROJECT LIMITS ALONG ENTRADA WAY WITH EXACT LOCATIONS DETERMINED WITH THE COUNTY IN THE TRAFFIC CONTROL PLAN. CONTRACTOR SHALL MAINTAIN A MINIMUM 11 FOOT

WIDE TRAVEL LANE OPEN DURING CONSTRUCTION.

5. RIGHT OF ENTRY AREAS EXTEND BEYOND THE CONSTRUCTION ENTRANCE AND SHALL NECESSARILY COVER THE ENTIRE PORTION OF THE PROJECT LIMITS THAT OCCUR OUTSIDE OF COUNTY RIGHT OF WAY.

TESC PLAN

MATCHLINE THIS SHEET

MATCHLINE THIS SHEET

K-RAIL

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER TESC DETAILS

C02

ISOMETRIC

(STEEL POSTS AND TRENCH SHOWN)

SPLICE DETAIL

SEE NOTE 3

SEE NOTE 3

SHEET FLOW

(TYPICAL)

PROTECTED AREA

PROTECTED AREA

6' - 0 " M

AX. SPACING

PROTECTED AREA

GEOTEXTILE FOR HIGH VISIBILITY SILT FENCE

COLOR - ORANGE

(STEEL POSTS SHOWN)

TYPICAL HIGH VISIBILITY SILT FENCE

WITHOUT BACKUP SUPPORT

TYPICAL TRENCH INSTALLATION DETAIL

1. DURING EXCAVATION, MINIMIZE DISTURBING THE GROUND

AROUND TRENCH AS MUCH AS IS FEASIBLE, AND SMOOTH

SURFACE FOLLOWING EXCAVATION TO AVOID CONCENTRATING

FLOWS. COMPACTION MUST BE ADEQUATE TO PREVENT

UNDERCUTTING FLOWS.

2. POST SHALL ONLY BE STAKED ON THE CONSTRUCTION SIDE

FABRIC

(GEOTEXTILE)

(TYPICAL)

NOTES

1. SPLICED FENCE SECTIONS SHALL BE CLOSE ENOUGH TOGETHER

TO PREVENT SILT LADEN WATER FROM ESCAPING THROUGH THE

FENCE AT THE OVERLAP. JOINING SECTIONS SHALL NOT BE

PLACED IN LOW SPOTS OR IN SUMP LOCATIONS.

(WOOD POSTS SHOWN)

FASTEN GEOTEXTILE

TO POST EVERY 6" (IN.) O.C.

NOTES

1. HIGH VISIBILITY SILT FENCE (HVSF) SHALL CONFORM TO MEASURES IN

BMP BIO-3 FROM SAN MATEO COUNTY'S ROUTINE MAINTENANCE

PROGRAM.

2. HVSF SHALL MEET ALL REQUIREMENTS FOR HIGH VISIBILITY SILT

FENCE AND WILDLIFE EXCLUSION FENCE.

3. ANGLE TERMINAL END UPHILL 24" (IN) TO 48" (IN) TO PREVENT FLOW

AROUND FENCE (TYPICAL).

4. PERFORM MAINTENANCE AS NEEDED

5. SPLICES SHALL NEVER BE PLACED IN LOW SPOTS OR SUMP

LOCATIONS. IF SPLICES ARE LOCATED IN LOW OR SUMP AREAS, THE

FENCE MAY NEED TO BE REINSTALLED UNLESS THE ENGINEER

APPROVES THE INSTALLATION.

6. INSTALL SILT FENCING PARALLEL TO MAPPED CONTOUR LINES WITH

THE SUPPORTING POST ON THE PROJECT SIDE.

7. CLIMBER BARRIER FABRIC SHALL BE FOLDED AWAY FROM THE

CONSTRUCTION SIDE AND TOWARDS THE PROTECTED AREA AT AN

ANGLE REQUIRED BY QUALIFIED BIOLOGIST.

8. ESCAPE TUNNELS SHALL BE INSERTED INTO THE FENCING AT 150' OC

OR PER THE DIRECTION OF THE QUALIFIED BIOLOGIST.

9. HVSF SHALL OVERLAP FISH EXCLUSION NETTING PER SPLICE DETAIL

SHOWN WITH AN OVERLAP OF A MINIMUM OF 12 INCHES. HVSF SHALL

NOT EXTEND BELOW THE OHWM.

SCALE:

DETAIL - HIGH VISIBILITY SILT FENCE (WITH WILDLIFE EXCLUSION) 1

C01NTS

CONSTRUCTION

SIDE

FOLD AND SECURE TOP

OF GEOTEXTILE FOR

CLIMBER BARRIER

POST ~

WOOD OR STEEL

(TYPICAL)

NOTE

PROTECTED

SIDE

BACKFILL TRENCH

WITH NATIVE SOIL

6" MIN

TRENCH

DEPTH

2'

SELF-LOCKING TIE~NYLON 6/6 (MIN. GRADE),

120# MIN. TENSILE STRENGTH, UV STABILIZED

6" ON CENTER, TYPADJUST ANGLE

AS REQUIRED

FOLD AND SECURE TOP OF

GEOTEXTILE FOR CLIMBER BARRIER

42" MIN

GEOTEXTILE

12"

TYPICAL NO TRENCH INSTALLATION DETAIL

1. GEOTEXTILE SHALL BE FOLDED THEN SEALED TO THE GROUND

TO PREVENT WILDLIFE FROM ENTERING THE SITE.

2. POST SHALL ONLY BE STAKED ON THE CONSTRUCTION SIDE

CONSTRUCTION

SIDE

NOTE

PROTECTED

SIDE

SELF-LOCKING TIE~NYLON 6/6 (MIN. GRADE),

120# MIN. TENSILE STRENGTH, UV STABILIZED

6" ON CENTER, TYP

FOLD AND SECURE TOP OF

GEOTEXTILE FOR CLIMBER BARRIER

42" MIN HIGH VISIBILITY

GEOTEXTILE

COLOR - ORANGE

ADJUST ANGLE

AS REQUIRED

TEMPORARY

CONSTRUCTION

FENCE POST

TEMPORARY CONSTRUCTION FENCE SUPPORT FOR PAVEMENT

AREA. SEE TRENCH INSTALLATION FOR NON-PAVEMENT AREA.GROUND SEAL

SCALE:

DETAIL - WILDLIFE EXCLUSION FENCE 2

C01NTS

NOTES

1. FENCE SHALL CONFORM TO MEASURES IN BMP BIO-3 FROM SAN

MATEO COUNTY'S ROUTINE MAINTENANCE PROGRAM.

2. FENCE SHALL MEET ALL REQUIREMENTS FOR WILDLIFE EXCLUSION

BARRIER.

3. PERFORM MAINTENANCE AS NEEDED

4. CLIMBER BARRIER FABRIC SHALL BE FOLDED AWAY FROM THE

CONSTRUCTION SIDE AND TOWARDS THE PROTECTED AREA AT AN

ANGLE REQUIRED BY QUALIFIED BIOLOGIST.

5. ESCAPE TUNNELS SHALL BE INSERTED INTO THE FENCING AT 150' OC

OR PER THE DIRECTION OF THE QUALIFIED BIOLOGIST.

1 FT MIN

SCALE:

DETAIL - STABILIZED CONSTRUCTION ENTRANCE 3

C01NTS

50 FT MIN, TYP

EXISTING ROAD

20 FT RADIUS MIN, TYP

TYPE A ROCK

PROVIDE FULL WIDTH

OF INGRESS/EGRESS

AREA, 16 FT MINSTABILIZED CONSTRUCTION ENTRANCE NOTES:

1. CONTRACTOR SHALL BE RESPONSIBLE FOR ALL WATER POLLUTION CONTROL AND DUST CONTROL MEASURES.

STABILIZED CONSTRUCTION ENTRANCE SHALL BE CONSTRUCTED AS A TYPE 1 TEMPORARY CONSTRUCTION

ENTRANCE PER STANDARD SPECIFICATIONS OR AS APPROVED BY THE ENGINEER.

INSTALL STEEL PLATE OVER EXISTING

CONCRETE DITCH TO PROTECT IN PLACE

EXCAVATE TO MATCH

ELEVATION OF TOP OF

EXISTING PAVEMENT

TAPER ALL EDGES AT

A 1:1 SLOPE

BERM 8" HEIGHT BY 3'-0" WIDTH

LEGEND

REMOVE TREE -

TYPE A

TEMPORARY ROOT ZONE

PROTECTION - TYPE A

SITE ACCESS

CLEAR AND GRUB

CL

TEMPORARY ROOT ZONE

PROTECTION - TYPE B

REMOVE TREE -

TYPE B

CLEARING

CG

EXISTING BOULDERS

PAVEMENT REMOVAL

SITE ACCESS

K-RAIL

LA H

O

N D

A G U

ILD

C

U

ESTA

083-370-010

LA HONDA GUILD - CUESTA

083-051-150LA HONDA GUILD

CUESTA

083-051-120

Bruce 083-051-110

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 1

PINGER AND FERGUSON

083-012-060

PARCEL I

2007-095388

(VOL 32 PG 87)

26105 26106

26177

2620526206

26208

2622026221

26222

26232

26233

26237

26472

26657

26658 26659

26662 26663

26711

26773

26776

26777

26778

26779

26780

26781

26818

26819 26820

100130 100133 100134

100135 100136

100137

100187

100214

100220 100223

100225

100227

100228

WATERS OF THE US

26124

26463 26464 26445 26446

100209

100210100211

100216

100217

OHW

OHWOHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

O

HW

O

HW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

OHW OHW

O H

W

O

HW

O H

W

OHW

OHW

O H

W

OHW

OHW

OHW OHW

OHW

TOPTOP

TOP

TOP

TOPTOP

TOP

TOP

TOP

TO

P

TOP

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP TOP TOP

TOP

TOP

TOP

TOP

26444

150000

150001150002

150003 150004

150005150006 150007

150008 150009

150010

150011 150012

150016

26378

26231

C G

C G

CG

C G

C G

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

C G

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG

CG CG CG CG CG CL CL CL

C L

C L

CL

CG

CG

CG CG CG

C G

C G

CG

CGCGCGCGCGCG

CG

CG

CG

CG

CG

CG

CG

CG

CG

C G

C G

C G

C G

C G

C G

C G

C G

CG

CGCG

CG

CG

CG

CG

C G

C G

C G

CL

CL

CL

C L

CLCLCLCLCL

C L

C L

C

L CL

CL

CL

CL

CL

CL CL

CL

CL

CL

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

WEF

W

EF

W

EF

W

EF

WEFWEF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

W

EF

WEF WEF

W

EF

CLEARING AND GRUBBING

BOULDER REMOVAL

AND SALVAGE

SEE NOTE 6

BEGIN GUARDRAIL

REMOVAL

END GUARDRAIL REMOVAL

REMOVE 24" HDPE AND

SAND BAG BERMS

PROTECT IN PLACE

OVERHEAD POWER

SITE ACCESS FROM ENTRADA WAY

SEE NOTE 8

PAVEMENT REMOVAL

CONCRETE DITCH REMOVAL

CONCRETE DITCH REMOVAL

REMOVE CONCRETE

DEBRIS

CLEAR

CLEAR

26021

26022

26457

26609

26614

26673

26676

26677 26698

26699

27035

100141

100142

100155

100207

100139

100140

27038

100138

100208100150

150017

150013 150014

150015

TEMPORARY

EXCAVATION

LIMITS

SEE NOTE 10

K-RAIL

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

010 10 20

SCALE IN FEET

SITE ACCESS AND PREP

C03

NOTES:

1. TREE SURVEY PERFORMED ON NOVEMBER 5TH-6TH 2024 AND

JANUARY 8 2025. SEE TREE LISTS, SHEETS G03-G10. TREE

DIAMETER SHOWN IN INCHES MEASURED AT DIAMETER AT

BREAST HEIGHT (DBH). DRIP LINE (DRIP) DIAMETER SHOWN IN

FEET.

2. CONTRACTOR TO COORDINATE WITH THE ENGINEER A

MINIMUM OF FIVE DAYS PRIOR TO ANY GROUND DISTURBING

ACTIVITY TO ALLOW THE ENGINEER TO VERIFY AND STAKE

CLEARING AND GRUBBING, AND CLEARING LIMITS.

3. CONTRACTOR SHALL ONLY CLEAR AND MOW WITHIN STAGING

AND STORAGE AREA. NO GRUBBING SHALL BE ALLOWED

WITHIN STAGING AND STORAGE AREA.

4. EVALUATE TREE PROTECTION OPPORTUNITIES FOR TREES

ADJACENT TO CLEARING AND GRUBBING, AND CLEARING

LIMITS WITH THE LICENSED ARBORIST AND ENGINEER PRIOR

TO TREE REMOVAL ACTIVITIES. TREES NOT IDENTIFIED FOR

REMOVAL SHALL BE PROTECTED UNLESS OTHERWISE NOTED

BY THE ENGINEER.

5. REMOVED TREES SHALL BE SALVAGED FOR REUSE AS

RACKING LOGS AND SLASH MATERIAL AND AS WOOD MULCH

PER THE SPECIAL PROVISIONS. ALL SURPLUS WOOD, WOOD

MULCH OR DEBRIS SHALL BE HAULED OFFSITE BY THE

CONTRACTOR.

6. PORTIONS OF THE BOULDERS PLACED IN THE EMBANKMENT

HAVE FAILED AND FALLEN INTO THE STREAM CHANNEL.

SALVAGE AND STOCKPILE ALL BOULDERS ONSITE FOR REUSE

AT THE DIRECTION OF THE ENGINEER, AS SHOWN ON SHEET

C07, AND PER THE SPECIAL PROVISIONS.

7. WATER MANAGEMENT FEATURES, PER APPROVAL IN THE

CONTRACTOR PRODUCED TEMPORARY CREEK DIVERSION

SYSTEM PLAN, SHALL BE INSTALLED BEFORE ANY EQUIPMENT

IS PLACED IN THE LA HONDA CREEK WORK AREA.

8. CONTRACTOR SHALL ACCESS LA HONDA CREEK AND

ADJACENT PROJECT AREA FROM PROPERTY 083-051-110 ON

THE LEFT (EAST) BANK OF THE CREEK. ALL HEAVY EQUIPMENT

SHALL BE LIFTED WITH A CRANE INTO THE LA HONDA CREEK

WORK AREA. EQUIPMENT SHALL BE STORED ABOVE OHW

OVERNIGHT IN ACCORDANCE WITH PERMITS AND

SPECIFICATIONS.

9. TREES IDENTIFIED ON THE PLANS FOR TYPE B REMOVAL

SHALL BE CUT FLUSH WITH EXISTING GROUND SURFACE,

WITH STUMP AND ROOT MASS LEFT IN PLACE. ALL OTHER

TREES DESIGNATED FOR REMOVAL SHALL BE TYPE A

REMOVAL AND SHALL BE FULLY GRUBBED, INCLUDING STUMP

AND ROOT MASS.

10. TEMPORARY EXCAVATION LIMITS FOR STRUCTURE

EXCAVATION (ELS) SHALL NOT BE EXCEEDED.

/ / / / / / / / / / / / / / / / / REMOVE ITEM

C04

TEMPORARY ROOT

ZONE PROTECTION - TYPE A

TYP

REMOVE TREE

SEE NOTE 5

TYP

C04

TEMPORARY ROOT

ZONE PROTECTION - TYPE B

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER SITE ACCESS AND PREP DETAILS

C04

HIGH VISIBILITY FENCE AS SHOWN ON PLANS.

PLACE WOOD MULCH OVER THE ROOTS OF EXISTING TREES TO

BE PRESERVED TO THE MAXIMUM EXTENT FEASIBLE, PER

ENGINEER GUIDANCE, PRIOR TO MOBILIZING LARGE

EQUIPMENT TO PROTECT ROOTS AND SUPPORT LONG-TERM

TREE HEALTH.

CRITICAL ROOTZONE

SCALE:

DETAIL - TEMPORARY ROOT ZONE PROTECTION - TYPE A 1

VARNTS

NOTES:

1. THE CONTRACTOR SHALL CONTACT THE ENGINEER TO OBSERVE AND DOCUMENT THE ROOT ZONE PROTECTION AND TREE PROTECTION FENCING WHEN THE INSTALLATION IS COMPLETE. THE ENGINEER SHALL BE NOTIFIED AT LEAST 5 WORKING DAYS PRIOR TO THE COMPLETION OF THE INSTALLATION. TEMPORARY ROOT ZONE PROTECTION INSTALLATION IS REQUIRED BEFORE ADJACENT

EARTHWORK ACTIVITIES MAY BEGIN.

2. AT THE COMPLETION OF CONSTRUCTION, THE CONTRACTOR SHALL DISTRIBUTE THE WOOD MULCH AROUND EXISTING VEGETATION AND

COVER ANY BARE SOIL.

PLACE HIGH VISIBILITY FENCE TO PROTECT THE

ROOTS OF EXISTING TREES TO BE PRESERVED

TO THE MAXIMUM EXTENT FEASIBLE.

CRITICAL ROOTZONE

SCALE:

DETAIL - TEMPORARY ROOT ZONE PROTECTION - TYPE B 2

VARNTS

NOTES:

1. THE CONTRACTOR SHALL CONTACT THE ENGINEER TO OBSERVE AND DOCUMENT THE ROOT ZONE PROTECTION AND TREE PROTECTION FENCING WHEN THE INSTALLATION IS COMPLETE. THE ENGINEER SHALL BE NOTIFIED AT LEAST 5 WORKING DAYS PRIOR TO THE COMPLETION OF THE INSTALLATION. TEMPORARY ROOT ZONE PROTECTION INSTALLATION IS REQUIRED BEFORE ADJACENT EARTHWORK

ACTIVITIES MAY BEGIN.

2. AT THE COMPLETION OF CONSTRUCTION, THE CONTRACTOR SHALL DISTRIBUTE THE WOOD MULCH AROUND EXISTING VEGETATION AND

COVER ANY BARE SOIL.

SCALE:

DETAIL - HIGH VISIBILITY FENCE 3

-NTS

ENVIRONMENTALLY

SENSITIVE AREA

BOUNDARY

PROTECTED

AREA

WORK

AREA

16 IN (TYP)

16 IN (TYP)

6 FT MAX

1.8 FT

4 FT

1 FT MIN

(DEEPER FOR

UNSTABLE SOIL) ISOMETRIC

SECTION

ELEVATION

ELEVATION

FENCE ON SLOPE

NOTES:

1. POST SHALL HAVE SUFFICIENT

STRENGTH AND DURABILITY TO

SUPPORT THE FENCE THROUGH

THE LIFE OF THE PROJECT.

SELF-LOCKING TIE - NYLON 6/6 (MIN GRADE),

50# MIN TENSILE STRENGTH, UV STABILIZED

STEEL T-BAR POST

FENCING MATERIAL

SELF-LOCKING TIE -

NYLON 6/6 (MIN GRADE),

50# MIN TENSILE

STRENGTH, UV

STABILIZED

STAPLE TOP TIE

2x2 WOOD POST

FENCING MATERIAL

HIGH DENSITY POLYETHYLENE OR

POLYPROPYLENE MESH, AND SHALL

BE UV RESISTANT, ORANGE COLOR

2×2 WOOD OR

STEEL T-BAR POST

VERTICAL POST

LA H

O

N D

A G U

ILD

C

U

ESTA

083-370-010

LA HONDA GUILD - CUESTA

083-051-150LA HONDA GUILD

CUESTA

083-051-120

Bruce 083-051-110

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 1

PINGER AND FERGUSON

083-012-060

PARCEL I

2007-095388

(VOL 32 PG 87)

26105 26106

26162

26177

2620526206

26208

2622026221

26222

26232

26233

26237

2624126242

26305

26306 26472

26622

26625 26626

26627

26628

26644

26650 26651

26655

26657

26658 26659

26662 26663

26711

26727

26751

26773

26776

26777

26778

26779

26780

26781 26783

26784

26786

2678726789

26818

26819 26820

27068

100130 100133 100134

100135 100136

100137

100187

100214

100220 100223

100225

100227

100228

WATERS OF THE US

26124

26463 26464 26445 26446

100209

100210100211

100216

100217

OHW

OHWOHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

O

HW

O

HW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

OHW OHW

O H

W

O

HW

O H

W

OHW

OHW

O H

W

OHW

OHW

OHW OHW

OHW

TOPTOP

TOP

TOP

TOPTOP

TOP

TOP

TOP

TO

P

TOP

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP TOP TOP

TOP

TOP

TOP

TOP

26444

150000

150001150002

150003 150004

150005150006 150007

150008 150009

150010

150011 150012

150016

26378

26231

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

X X

P

AC

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

010 10 20

SCALE IN FEET

FISH EXCLUSION NET

WATER MANAGEMENT PLAN

C05

ISOLATION GRAVITY

BYPASS PIPING

BAKER TANK(S)

(LOCATED ON ROADWAY)

FISH EXCLUSION NET

EXAMPLE DEWATERED

ISOLATION WORK AREA

C06

COFFERDAM,

TYP

PIPING FROM DEWATERED

ISOLATION WORK AREA.

PIPING FROM BAKER TANK(S)

EXAMPLE WORK

AREA SUMP PUMP

ENERGY DISSIPATER

EXISTING GROUND

SAND BAGS FILLED WITH

CLEAN WASHED GRAVEL

GRAVITY BYPASS PIPE

EL

EV

AT

IO

N

IN

F

EE

T

STATION

0+12 0+50

PVC, HDPE, OR OTHER

ENGINEER APPROVED

IMPERMEABLE LINER

SAND BAG FILLED WITH

CLEAN WASHED GRAVEL

COFFERDAM, TYP

WORK AREA

FLOW

TEMPORARY FLOW

BYPASS PIPE

DOWNSTREAM

ENERGY

DISSIPATOR

CHANNEL BOTTOM

1'

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER WATER MANAGEMENT DETAILS

C06

SCALE:

DETAIL - COFFERDAM AND PIPE (EXAMPLE) 1

C05NTS

GENERAL NOTES:

1. WATER MANAGEMENT MEASURES SHOWN ON PLANS ARE A PRELIMINARY SCHEMATIC REPRESENTING ANTICIPATED SITE CONDITIONS.

THE CONTRACTOR SHALL ALTER WATER MANAGEMENT MEASURES AS NEEDED OR AS DIRECTED BY THE ENGINEER. THE

CONTRACTOR IS RESPONSIBLE FOR MEETING ALL PERMIT REQUIREMENTS.

2. BEFORE STARTING ANY WORK ON THE PROJECT, THE CONTRACTOR SHALL SUBMIT, FOR ACCEPTANCE BY THE ENGINEER, A WRITTEN PROGRAM INCLUDING WATER POLLUTION CONTROL PLAN (WPCP) AND APPLICABLE PLAN DRAWINGS AND DETAILS TO CONTROL

WATER POLLUTION EFFECTIVELY DURING CONSTRUCTION OF THE PROJECT.

3. IT SHALL BE THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO MANAGE ALL SURFACE WATER AND GROUNDWATER, AND TO BYPASS ALL WATER THROUGH THE WORK AREA TO COMPLETELY ISOLATE THE WORK AREA FROM ACTIVE FLOW IN THE CREEK. THE CONTRACTOR SHALL PREPARE AND SUBMIT A TEMPORARY CREEK DIVERSION SYSTEM PLAN (TCDSP) PRIOR TO ANY IN-WATER WORK.

4. ALL TEMPORARY CREEK DIVERSION SYSTEMS EQUIPMENT SHALL BE LOCATED AND ALIGNED WITHIN THE PROJECT WORK AREA LIMITS.

5. LENGTH AND CONFIGURATION OF WORK AREA ISOLATION MEASURES NEEDED WILL VARY DEPENDING ON THE CONTRACTORS MEANS AND METHODS. CONTRACTOR SHALL DETERMINE THE NECESSARY LENGTHS NEEDED FOR THE WORK AREA AND BE RESPONSIBLE FOR DESIGNING, INSTALLING, OPERATING, MAINTAINING AND REMOVING ALL ISOLATION MEASURES.

6. CONTRACTOR SHALL CONSTRUCT WORK AREA ISOLATION MEASURES STARTING AT THE UPSTREAM END OF THE INTENDED WORK

AREA TO DIRECT WATER AWAY FROM THE WORK AREA.

7. THE ENGINEER SHALL BE NOTIFIED 24 HOURS IN ADVANCE OF ANY WATER PUMPING ACTIVITIES.

8. INSTALLATION OF ALL WATER MANAGEMENT MEASURES SHALL NOT CAUSE EXCESSIVE SEDIMENTATION, SILTATION, OR EROSION

UPSTREAM OR DOWNSTREAM OF THE PROJECT.

SCALE:

SECTION - COFFERDAM (EXAMPLE) A

C05NTS

FISH EXCLUSION NOTES:

1. PRIOR TO CONSTRUCTING AND OPERATING ANY WORK AREA ISOLATION MEASURE THE CONTRACTOR SHALL INSTALL FISH EXCLUSION

NETS AS DIRECTED BY A QUALIFIED BIOLOGIST WITHIN THE AREA TO BE ISOLATED. ALL FISH REMOVAL WORK SHALL BE COMPLETED BY A QUALIFIED FISHERIES BIOLOGIST. CONSTRUCTION WITHIN THE ISOLATED WORK AREA MAY NOT COMMENCE UNTIL ALL FISH EXCLUSION ACTIVITIES ARE COMPLETED. ALL TERMINAL ENDS OF FISH EXCLUSION NETS SHALL CONNECT TO THE TERMINAL ENDS OF HIGH VISIBILITY SILT FENCE (WITH WILDLIFE EXCLUSION). ALL TEMPORARY FISH EXCLUSION NETS INSTALLED BY THE CONTRACTOR MUST REMAIN IN PLACE DURING REMOVAL OF ISOLATION MEASURES AND OTHER TESC MEASURES. THE CONTRACTOR SHALL BE

RESPONSIBLE FOR REMOVING FISH EXCLUSION NETS.

2. FISH RELOCATION SHALL BE CONDUCTED BY COUNTY QUALIFIED FISHERIES BIOLOGISTS PRIOR TO INSTALLING THE TEMPORARY

CREEK DIVERSION SYSTEMS.

3. FISH EXCLUSION BLOCK NETS SHALL BE PROVIDED BY THE COUNTY AND INSTALLED BY THE CONTRACTOR IN CONSULTATION WITH THE QUALIFIED BIOLOGIST. BLOCK NETS SHALL BE MAINTAINED BY THE CONTRACTOR BOTH UPSTREAM AND DOWNSTREAM OF THE DIVERSION, THROUGHOUT THE PERIOD OF CONSTRUCTION. MAINTENANCE INCLUDES PERIODIC REMOVAL OF ACCUMULATED DEBRIS, AS NECESSARY TO ENSURE FUNCTION. BLOCK NETS SHALL BE REMOVED AFTER THE DIVERSION IS REMOVED AND THE IN CHANNEL

WORK AREA IS RE-WATERED.

DEWATERING NOTES:

1. WATER ENCOUNTERED DURING EXCAVATIONS AND WITHIN THE ISOLATED WORK AREAS MAY BE PUMPED AS NECESSARY TO BAKER

TANK(S), OR SIMILAR, SHOWN ON THE PLANS TO ALLOW FOR THE CONSTRUCTION OF THE ELSs AND PLACEMENT OF SCOUR PROTECTION ROCK, AND TO FACILITATE THE REMOVAL OF SEDIMENT AND TURBIDITY FROM THE WATER PER APPROVAL BY THE ENGINEER. ANY DISCHARGE OF WATER RETURNING FROM THE BAKER TANK(S), OR SIMILAR, BACK INTO LA HONDA CREEK (DUE TO DEWATERING ACTIVITIES) SHALL ADHERE TO THE WATER QUALITY REQUIREMENTS SET FORTH IN THE PROJECT PERMITS.

2. DEWATERING WATER MAY BE PUMPED TO THE BAKER TANK(S), OR SIMILAR, AND DISCHARGED THROUGH AN ENERGY DISSIPATOR, LEVEL SPREADER, FILTER SOCK, SILT BAGS, OR OTHER AS APPROVED BY THE ENGINEER. WATER DISCHARGED OR INFILTRATED

SHALL NOT CAUSE EROSION OR RESULT IN TURBIDITY IMPACTS TO LA HONDA CREEK.

3. DEWATERING WATER MAY NOT BE PUMPED DIRECTLY TO THE CREEK CHANNEL WITHOUT PRIOR WRITTEN APPROVAL FROM THE ENGINEER. WATER SHALL BE DISCHARGED IN ACCORDANCE WITH THE PLANS, SPECIFICATIONS AND PERMITS.

4. DEWATERED ISOLATION WORK AREA CONFIGURATION SHOWN IN WATER MANAGEMENT PLANS ARE TYPICAL AND MAY BE SUBJECT TO

CHANGE DEPENDING ON DRAINAGE NEEDS WITHIN THE PROJECT LIMITS.

5. ALL PUMPS USED FOR DEWATERING SHALL BE SCREENED IN ACCORDANCE WITH THE FISH SCREENING CRITERIA .

LA H

N D

A G U

ILD

C

U

ESTA

083-370-010

LA HONDA GUILD - CUESTA

083-051-150LA HONDA GUILD

CUESTA

083-051-120

Bruce 083-051-110

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 1

PINGER AND FERGUSON

083-012-060

PARCEL I

2007-095388

(VOL 32 PG 87)

26105 26106

26177

2620526206

26208

2622026221

26222

26232

26233

26472

26628 26657

26658 26659

26662 26663

26711

26727

26773

26776

26777

26778

26779

26780

26781 26783

26784

26786

2678726789

26818

26819 26820

27068

100130 100133 100134

100135 100136

100137

100187

100214

100220 100223

100225

100227

100228

WATERS OF THE US

26124

26463 26464 26445 26446

100209

100210100211

100216

100217

OHW

OHWOHW

OHW

OHW

OHW

OHW

OHW

OHW

O

H W

O

HW

O

HW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

OHW OHW

O H

W

O

HW

O H

W

OHW

OHW

O H

W

OHW

OHW

OHW OHW

OHW

TOPTOP

TOP

TOP

TOPTOP

TOP

TOP

TOP

TO

P

TOP

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP TOP TOP

TOP

TOP

TOP

TOP

26444

150000

150001150002

150003 150004

150005150006 150007

150008 150009

150010

150011 150012

150016

26378

26231

L3

L4

L2 C1

C2

L7

L5

L6

L10

L1

L8

L9

C3

ALIGNMENT DATA - CHANNEL REALIGN

L1

L2

L3

C1

C2

L4

START STA.

0+00.00

1+01.13

1+60.45

1+71.34

2+12.85

3+05.66

START COORDINATES

N: 1,943,397.34 - E: 6,045,991.46

N: 1,943,487.63 - E: 6,045,945.90

N: 1,943,546.71 - E: 6,045,940.50

N: 1,943,557.59 - E: 6,045,940.17

N: 1,943,592.41 - E: 6,045,960.31

N: 1,943,669.27 - E: 6,046,006.31

DELTA (Δ)

49° 36' 38"

52° 41' 06"

RADIUS

47.93'

100.94'

TANGENT

22.15'

49.98'

LENGTH

101.13'

59.32'

10.89'

41.50'

92.81'

45.25'

DIRECTION

N26°46'30"W

N05°13'29"W

N01°44'54"W

N03°11'50"E

ALIGNMENT DATA - NEATLINE

C3

L5

L6

L7

L8

L9

L10

L11

START STA.

0+00.00

0+09.64

0+32.65

0+55.38

0+85.45

0+96.18

1+04.68

1+12.94

START COORDINATES

N: 1,943,547.09 - E: 6,045,964.53

N: 1,943,555.83 - E: 6,045,962.18

N: 1,943,576.28 - E: 6,045,972.74

N: 1,943,593.76 - E: 6,045,987.28

N: 1,943,615.65 - E: 6,046,007.89

N: 1,943,624.93 - E: 6,046,013.27

N: 1,943,631.60 - E: 6,046,018.53

N: 1,943,632.62 - E: 6,046,026.72

DELTA (Δ)

69° 50' 43"

RADIUS

7.91'

TANGENT

5.52'

LENGTH

9.64'

23.01'

22.73'

30.07'

10.73'

8.50'

8.26'

2.85'

DIRECTION

N27°19'49"E

N39°44'13"E

N43°17'02"E

N30°04'06"E

N38°15'08"E

N82°58'00"E

S67°49'33"E

ELS TIMBER PILING TABLE

PILE #

TYPE

P2

P1

P2

P1

P1

P2

P2

P1

NORTHING

1943565.56

1943570.21

1943572.62

1943578.65

1943584.64

1943582.84

1943597.91

1943594.34

EASTING

6045985.61

6045984.12

6045999.24

6045995.57

6045999.47

6046006.29

6046009.18

6046002.53

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

010 10 20

SCALE IN FEET

A C08

SITE PLAN AND GRADING

C07

C09

CHANNEL REALIGNMENT

SOLDIER PILE WALL

SEE SHEETS S1-S5

ROADWAY IMPROVEMENTS

SEE SHEETS CD01-CD09

B C08

C11

ELS TYPE A

C12

ELS TYPE B

LIMITS OF STRUCTURE EXCAVATION (ELS)

SEE NOTE 1

NOTES:

1. SALVAGED BOULDERS SHALL BE PLACED IN DESIGNATED

LOCATIONS AND WITHIN THE ELSs AT THE DIRECTION OF

THE ENGINEER.

2. CONTRACTOR SHALL CONSTRUCT HAND DUG, LOW FLOW

CHANNEL THROUGHOUT THE LENGTH OF CHANNEL

REALIGNMENT PER THE DIRECTION OF THE ENGINEER.

LOW FLOW CHANNEL SHALL BE 6 INCHES IN DEPTH AND

2 FEET IN WIDTH.

3. NEATLINE SHOWN DELINEATES PAYMENT ITEM LIMIT

BETWEEN CHANNEL EXCAVATION AND STRUCTURE

EXCAVATION (ELS)

4. LIMITS OF TEMPORARY EXCAVATION ARE APPROXIMATE

AND BASED ON ASSUMED BEDROCK ELEVATION AND

1H:1V SLOPE FOR APPROXIMATE QUANTITY ESTIMATION.

ACTUAL SLOPES WILL VARY BASED ON CONTRACTOR

MEANS AND METHODS, AND CONSTRUCTION

SEQUENCING.

LEGEND

SALVAGED BOULDERS

C C

C13

ELS TYPE C

NEATLINE

NEATLINE

LIMITS OF CHANNEL EXCAVATION

TYPE L KEY LOGS

TYPE R KEY LOGS

TIMBER PILING

EL

EV

AT

IO

N

IN

F

EE

T

0+00 0+50 1+00 1+25

OHW OHW OHW OHW

EL

EV

AT

IO

N

IN

F

EE

T

0+00 0+50 1+00 1+25

OHW OHW OHW OHW

LEGEND

STRUCTURE BACKFILL (ELS)

SCOUR PROTECTION ROCK

STREAMBED SEDIMENT

VEGETATED SOIL LIFTS

RACKING LOGS AND

SLASH MATERIAL

WOOD MATERIAL AND

STRUCTURAL BACKFILL (ELS)

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

05 5 10

SCALE IN FEET

HORIZ. SCALE:

VERT. SCALE:

SECTION - ENGINEERED LOG STRUCTURE (ELS) - TYPE A A

C071"=5'

1"=5'

PROPOSED LA HONDA CREEK

CHANNEL ALIGNMENT

FOR PROFILE SEE 1/C09

APPROXIMATE

BEDROCK ELEVATION

TYP, SEE NOTE 2

SCOUR PROTECTION ROCK

PLACED FROM BEDROCK

SEE NOTE 1

STRUCTURE BACKFILL (ELS)

VEGETATED SOIL LIFTS

ELS TYPE A

EXISTING LA HONDA CREEK CHANNEL ALIGNMENT

PROPOSED GRADE

TYP

EXISTING GROUND

TYP

1EXTENT OF STRUCTURE

EXCAVATION (ELS)

ELS SECTIONS

C08

13'

DEPTH

VARIES

NOTES:

1. SCOUR PROTECTION ROCK SHALL BE PLACED FROM VARIABLE

BEDROCK DEPTH IN 12 TO15 INCH LIFTS. FOR EACH LIFT, THE

CONTRACTOR SHALL FILL VOIDS WITHIN THE SCOUR PROTECTION

ROCK BY PLACING STRUCTURE BACKFILL (ELS) MATERIAL AS DIRECTED

BY THE ENGINEER. EACH LIFT SHALL BE BUCKET COMPACTED.

CONTRACTOR SHOULD EXPECT PLACEMENT OF SCOUR PROTECTION

MIXTURE IN THE PRESENCE OF GROUNDWATER.

2. BEDROCK ELEVATIONS ARE BASED UPON PRELIMINARY GEOTECHNICAL

BORINGS IN THE ENTRADA WAY ROADWAY PRISM AND ARE

APPROXIMATE. PRIOR TO DRILLING EACH TIMBER PILE HOLE, THE

ENGINEER MUST CONFIRM THE BEDROCK ELEVATION.

3. TIMBER PILINGS FOR ELSS SHALL BE INSTALLED IN DRILLED SHAFTS A

MINIMUM OF 6 FEET DEEP INTO BEDROCK. PILES SHALL NOT BE

INSTALLED UNTIL APPROVAL OF THE ENGINEER.

4. STREAMBED SEDIMENT SHALL BE PLACED TO A DEPTH OF 2 FEET

BELOW FINISHED GRADE IN AREAS STREAMWARD OF ELSS AS SHOWN

ON PLANS.

1.5

HORIZ. SCALE:

VERT. SCALE:

SECTION - ELS TYPE B B

C071"=5'

1"=5'

PROPOSED LA HONDA CREEK

CHANNEL ALIGNMENT

FOR PROFILE SEE 1/C09

13'

SCOUR PROTECTION ROCK

PLACED FROM BEDROCK

SEE NOTE 1

STRUCTURE BACKFILL (ELS)

EXTENT OF STRUCTURE

EXCAVATION (ELS)

VEGETATED SOIL LIFTS

ELS TYPE B

RACKING LOGS AND SLASH

MATERIAL PLACEMENT ZONE

STREAMBED SEDIMENT,

SEE NOTE 4.

STREAMBED SEDIMENT,

SEE NOTE 4.

C10

C10

C09

BASE OF TIMBER PILING INSTALLED

INTO BEDROCK (TYP), SEE NOTE 3

NEATLINE

CHANNEL

EXCAVATION

PAY ITEM

LIMIT

STRUCTURE

EXCAVATION

(ELS)

PAY ITEM

LIMIT

NEATLINE

CHANNEL

EXCAVATION

PAY ITEM

LIMIT

STRUCTURE

EXCAVATION

(ELS)

PAY ITEM

LIMIT

SEE SHEET C11 FOR LOG

LAYERING PLAN

SEE SHEET C12 FOR LOG

LAYERING PLAN

WOOD MATERIAL AND STRUCTURAL

BACKFILL (ELS) ZONE

RACKING LOGS AND SLASH

MATERIAL PLACEMENT ZONE

WOOD MATERIAL AND STRUCTURAL

BACKFILL (ELS) ZONE

BASE OF TIMBER PILING INSTALLED

INTO BEDROCK (TYP), SEE NOTE 3

APPROXIMATE

BEDROCK ELEVATION

TYP, SEE NOTE 2

EL

EV

AT

IO

N

IN

F

EE

T

STATION

1+50 2+00 2+50 3+00 3+503+51

ST

A:

+6

1.

EL

: 3

.8

ST

A:

+1

8.

EL

: 3

.1

1.48%

EL

EV

AT

IO

N

IN

F

EE

T

STATION

0+00 0+50 0+95

LEGEND

STRUCTURE BACKFILL (ELS)

SCOUR PROTECTION ROCK

STREAMBED SEDIMENT

VEGETATED SOIL LIFTS

RACKING LOGS AND

SLASH MATERIAL

WOOD MATERIAL AND

STRUCTURAL BACKFILL (ELS)

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER

05 5 10

SCALE IN FEET

HORIZ. SCALE:

VERT. SCALE:

PROFILE - CHANNEL REALIGNMENT 1

C071"=10'

1"=5'

ELS AND CHANNEL REALIGNMENT SECTIONS AND PROFILE

C09

PROPOSED GRADE

EXISTING GROUND

HORIZ. SCALE:

VERT. SCALE:

SECTION - ENGINEERED LOG STRUCTURE (ELS) - TYPE C C

C071"=5'

1"=5'

STRUCTURE BACKFILL (ELS)

AND SALVAGED BOULDERS ,

SEE NOTE 1

STRUCTURE BACKFILL (ELS)

1EXTENT OF STRUCTURE

EXCAVATION (ELS)

SEE ROADWAY PLANS FOR

PROPOSED GRADING

13'

1'

VARIES

NOTES:

1. LOW FLOW CHANNEL SHALL BE HAND DUG THROUGHOUT THE ENTIRE LENGTH OF

CHANNEL REALIGNMENT 6 INCHES DEEP.

NOTES:

1. BACKFILL WITH STRUCTURE BACKFILL (ELS) MATERIAL, AS DEFINED IN THE

SPECIAL PROVISIONS, AND SALVAGED BOULDERS PER THE DIRECTION OF THE

ENGINEER TO CONSTRUCT DESIGN BANK GRADES AS SHOWN.

2. STREAMBED SEDIMENT SHALL BE PLACED TO A DEPTH OF 2 FEET BELOW FINISHED

GRADE IN AREAS STREAMWARD OF ELS AS SHOWN ON PLANS.

3. EXTEND SLASH AND RACKING APPROXIMATELY 2 FEET INTO STRUCTURE BACKFILL

(ELS) AND SALVAGED BOULDERS

SCALE:

DETAIL - CHANNEL TYPICAL SECTION (LOOKING DOWNSTREAM) 3

C08NTS

PROPOSED LA HONDA CREEK

CHANNEL ALIGNMENT

FOR PROFILE SEE B/C08

VEGETATED SOIL LIFTS

EXISTING LA HONDA CREEK

CHANNEL ALIGNMENT

PROPOSED GRADE

TYP

EXISTING GROUND

TYP

STREAMBED SEDIMENT,

SEE NOTE 2.

C10

NEATLINE

CHANNEL

EXCAVATION

PAY ITEM

LIMIT

STRUCTURE

EXCAVATION

(ELS)

PAY ITEM

LIMIT

SEE SHEET C13 FOR LOG

LAYERING PLAN

STRUCTURE BACKFILL (ELS) AND

SALVAGED BOULDERS

RACKING LOGS AND SLASH

MATERIAL PLACEMENT ZONE

WOOD MATERIAL AND STRUCTURAL

BACKFILL (ELS) ZONE

2'

12" SOIL LIFT

8' MIN

VEGETATED SOIL LIFT PREPARATION

(SEE SPECIAL PROVISIONS)

STEP 1

· OVEREXCAVATE TO PLACE COIR MATERIAL FOR VEGETATED SOIL LIFTS

· PROTECT SUBGRADE FROM FOOT TRAFFIC AND CONSTRUCTION ACTIVITIES THAT COULD CAUSE SOIL DISTURBANCE OR BANK

SETTLEMENT PRIOR TO COIR PLACEMENT

STEP 2

· PLACE OUTER WOVEN COIR FOR THE BOTTOM OF THE LIFT

· PLACE NON-WOVEN INNER COIR BLANKET

· STAKE COIR FABRIC TO NATIVE SOIL BELOW LIFT

STEP 3

· INSTALL FORM AND COIR D BLOCK TO HOLD COIR WRAP AND SOIL TO DESIGN DIMENSIONS

· PLACE 12" HIGH LAYER OF NATIVE SOIL BACKFILL MATERIAL AND COMPACT PER SPECIAL PROVISIONS WITHIN THE VEGETATED SOIL LIFTS.

· PLACE 2' IMPORTED TOPSOIL BACKFILL WITHIN THE VEGETATED SOIL LIFT AND COMPACT PER SPECIFICATIONS TO FACILITATE PLANT

INSTALLATION AND GROWTH.

STEP 4

· WRAP OUTER WOVEN COIR AND NON-WOVEN INNER COIR BLANKET AROUND VEGETATED SOIL LIFT TO ENCASE THE LIFT

STEP 5

· STAKE PER COIR MANUFACTURER'S RECOMMENDATION

BACKFILL TOP LIFT WITH IMPORTED TOPSOIL

BACKFILL FOR PLANTING AREA PREPARATION

WOOD STAKE AND ANCHOR

TRENCH FOR VEGETATED

SOIL LIFT PER

MANUFACTURER'S

RECOMMENDATIONS (TYP)

18" MIN OFFSETSIDE SLOPES,

1.5H:1V MAX

EXISTING GROUND

NON-WOVEN INNER COIR BLANKET

PER SPECIFICATIONS (TYP)

OUTER WOVEN COIR PER

SPECIFICATIONS (TYP)

STAKE VEGETATED SOIL LIFTS TO EACH

OTHER AND TO NATIVE SOILS. SEE

SPECIFICATIONS.

NATIVE SOIL BACKFILL

PROPOSED

GROUND

LIVE STAKE

PLANTING

COIR MATERIAL

ROOTBALL CENTERED ON CROSS CUT

CROSS CUT IN COIR MATERIAL TO

ACCOMMODATE ROOTBALL

COIR MATERIAL

PLANT

INSTALLATION CUT

DETAIL

IMPORTED TOPSOIL

COIR D BLOCK PER SPECIFICATIONS (TYP)

BOTTOM OF VEGETATED SOIL LIFT

RESTING ON LOG IN ELS

STRUCTURE BACKFILL (ELS)

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER ENGINEERED LOG STRUCTURE DETAILS

C10

SCALE:

DETAIL - TYPICAL VEGETATED SOIL LIFTS 1

-NTS

CHAIN, SEE CHAIN LASHING NOTES, 1-6

HORIZONTAL KEY LOG

VERTICAL TIMBER PILING

CHAIN, SEE CHAIN LASHING NOTES

HORIZONTAL KEY LOG

TOP OF VERTICAL TIMBER PILING

CHAIN, SEE CHAIN LASHING NOTES, 1-6

HORIZONTAL KEY LOG

VERTICAL TIMBER PILING

CHAIN, SEE CHAIN LASHING NOTES, 1-6

HORIZONTAL KEY LOG

TOP OF VERTICAL TIMBER PILING

CHAIN LASHING NOTES:

1. LASH HORIZONTAL LOGS TO VERTICAL TIMBER PILINGS WITH CHAIN AS SHOWN ON DETAIL AND LAYERING PLAN OR AS DIRECTED BY ENGINEER. CHAIN LASHING SYSTEM

SHALL BE PUT IN TENSION TO 1/4 OF THE CHAIN WORKING LOAD LIMIT AND BE MAINTAINED DURING CHAIN SHACKLING.

2. CHAIN LENGTH NEEDED PER LASHING WILL VARY BASED ON DIAMETER OF LOGS AT THE ACTUAL LOCATIONS THEY ARE LASHED TOGETHER.

3. CHAIN FOR LASHING SHALL BE 3/8 INCH DIAMETER GRADE 43 HIGH-TEST STAINLESS STEEL CHAIN, WITH A MINIMUM WORKING LOAD LIMIT OF 5400 LBS.

4. ALL HARDWARE USED FOR LASHING SHALL BE STAINLESS STEEL, AND CONNECTIONS SHALL BE OF THE QUANTITY AND TYPE SPECIFIED BY THE MANUFACTURER WITH A

MINIMUM WORKING LOAD LIMIT OF 4000 LBS OR AS APPROVED BY THE ENGINEER.

5. MAR OR ROUND ALL EXPOSED HARDWARE NUTS AND BOLT THREADS AFTER INSTALLATION FOR THEFT PROTECTION. ENGINEER OR OWNER SHALL APPROVE ANY COATING PRIOR TO CONTRACTOR APPLYING IT. SECURE CHAIN TO LOG AND PILING USING 6 INCH LOGGING STAPLE.

6. CONTRACTOR MAY SUBMIT ALTERNATIVE CHAIN CONNECTION SYSTEM FOR APPROVAL.

6" LOGGING STAPLE AT

FIRST CHAIN LINK

IN FULL CONTACT WITH

LOG ON BOTH SIDES

OF SHACKLE

SHACKLE

SCALE:

DETAIL - SIMPLE CHAIN LASHING 2

-NTS

SCALE:

DETAIL - SQUARE CHAIN LASHING 3

-NTS

SCALE:

DETAIL - CHAIN CONNECTION 4

-NTS

A

A

PLAN SECTION

PLAN SECTION

NOTES:

1. MINIMIZE CUTS INTO COIR MATERIAL SO THAT CUTS ARE ONLY AS WIDE AS NEEDED TO

FACILITATE PROPER PLANT INSTALLATION. PROTECT INTEGRITY OF COIR MATERIAL.

2. CUT COIR MATERIAL IN "Y" PATTERN RATHER THAN AN "X" PATTERN TO MINIMIZE

INCISIONS INTO MATERIAL.

3. PEEL BACK COIR MATERIAL TO INSTALL PLANTS.

4. REPLACE COIR MATERIAL FLAPS OVER PLANT ROOTS AND BACKFILL SOILS.

LAYER 3TIMBER PILINGS

LAYER 4

LAYER 1

LAYER 5

LAYER 2

LAYER 6

FLOW

14.5'

15'

6' 7'

RACKING LOGS AND SLASH

MATERIAL PLACEMENT ZONE

SQUARE LASHING (TYP), SEE

DETAILS 3 AND 4 ON SHEET C10

SIMPLE LASHING (TYP), SEE

DETAILS 2 AND 4 ON SHEET C10

STRUCTURE BACKFILL

(ELS) ZONE WOOD MATERIAL AND

STRUCTURAL

BACKFILL (ELS) ZONE

P2

R3 L3L2 L2

R3

L1 R3 L2

L4

L3

R4

R4

R4

L2

L2

P2

P1P1

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER ENGINEERED LOG STRUCTURE DETAILS

C11

GENERAL (TYPES A, B AND C) NOTES:

1. GENERAL STRUCTURE LOCATION AND ORIENTATION SHALL BE STAKED BY THE CONTRACTOR. FINAL STRUCTURE LOCATION

AND ORIENTATION TO BE FIELD VERIFIED BY THE ENGINEER FOLLOWING CONTRACTOR STAKING.

2. ALL TIMBER PILING LOCATIONS SHALL BE STAKED BY THE CONTRACTOR AND APPROVED BY THE ENGINEER PRIOR TO TIMBER PILING INSTALLATION. SEE SHEET C07 FOR SPECIFIC TIMBER PILING LOCATION INFORMATION.

3. PRIOR TO PLACING ANY KEY LOGS, THE CONTRACTOR SHALL OBTAIN INSPECTION APPROVAL FROM THE ENGINEER VERIFYING EXTENTS OF THE EXCAVATION. IT IS THE CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE ENGINEER FOR THE EXCAVATION INSPECTION. THE CONTRACTOR SHALL ALLOW 2 WORKING DAYS FOR THE INSPECTION TO TAKE PLACE.

4. KEY LOGS SHALL BE PLACED AT THE LOCATIONS AND ORIENTATIONS SPECIFIED ON THE PLANS OR AS DIRECTED BY THE ENGINEER. TRIM CUT ENDS OF HORIZONTAL KEY LOGS TO FIT AS REQUIRED AT THE DIRECTION OF THE ENGINEER.

5. WOOD MATERIAL CONSISTS OF RACKING LOGS AND SLASH MATERIAL.

6. ALL WOOD MATERIAL DIAMETER SHALL BE MEASURED AT BREAST HEIGHT (DBH) WITH THE EXCEPTION OF "P" PILING LOGS

WHOSE DIAMETER SHALL BE MEASURED AT THE PILE TIP END (SMALLEST DIAMETER).

ELS TYPE A NOTES:

1. CONTROL POINTS FOR ELS PLACEMENTS ARE DEFINED BASED ON TIMBER PILING LOCATION; SEE ELS TIMBER PILING TABLE ON SHEET C07.

2. KEY LOGS SHALL BE PLACED IN DIRECT CONTACT WITH TIMBER PILINGS AND SUBSEQUENT LAYER KEY LOGS;; WITH THE EXCEPTION OF L2 IN LAYER 5 UNLESS DIRECTED OTHERWISE BY THE ENGINEER. LOGS ON THE TOP THREE LAYERS SHALL BE LASHED WITH CHAIN TO EITHER

PILINGS OR KEY LOGS AS INDICATED ON THE PLANS.

3. RACKING LOG AND SLASH PLACEMENT SHALL BE COORDINATED WITH KEY LOG LAYER PLACEMENT TO ENSURE RACKING LOGS AND SLASH EXTEND THROUGH WATERWARD FACE OF STRUCTURE. LAYERS 1 THROUGH 5 SHALL HAVE 3 RACKING LOGS EACH PER LAYER INSTALLED.

SEE LAYERING PLAN AND SPECIAL PROVISIONS.

4. BACKFILL ZONE IS AN APPROXIMATION AND NOT SHOWN TO SCALE; CONTRACTOR TO BACKFILL EACH LAYER PER THE SPECIAL PROVISIONS

AND DIRECTION OF THE ENGINEER.

5. BACKFILL EACH LAYER WITH BACKFILL MATERIAL, AS DEFINED AS STRUCTURE BACKFILL (ELS) PER THE SPECIAL PROVISIONS, FLUSH TO THE TOP OF THE CURRENT LAYER PRIOR TO CONSTRUCTION THE SUBSEQUENT LAYER. COMPACT BACKFILL WITH EXCAVATOR BUCKET IN NO GREATER THAN TWO FOOT LIFTS FIILLING ALL VOIDS. SALVAGED BOULDERS WILL BE PLACED IN LOCATIONS SHOWN ON THE PLANS AND PER THE DIRECTION OF THE ENGINEER. SALVAGED BOULDER PLACEMENT WILL BE PRIORITIZED IN LOCATIONS BETWEEN THE DIFFERENT ELS

TYPES AND BETWEEN THE ELSS AND THE EXISTING GRADE.

LOG TYPE DIAMETER (IN) LENGTH (FT) ROOTWAD TOTAL/UNIT

P1 18 (TIP) 30 NO 4

P2 18 (TIP) 35 NO 4

R3 22 20 YES 3

R4 22 15 YES 3

L1 24 20 NO 1

L2 20 20 NO 5

L3 20 25 NO 2

L4 22 30 NO 1

RACKING 8-12 15-25 VARIES 15

SLASH 30 CY

STRUCTURE LOG SCHEDULE:

SCALE:

DETAIL - ELS TYPE A LAYERING PLAN 1

C071" = 10'

TIMBER PILINGS

FLOW

10'

15'

6' 7'

LAYER 3

LAYER 4

LAYER 1

LAYER 5

LAYER 2

LAYER 6

SQUARE LASHING (TYP), SEE

DETAILS 3 AND 4 ON SHEET C10

SIMPLE LASHING (TYP), SEE

DETAILS 2 AND 4 ON SHEET C10

RACKING LOGS AND

SLASH MATERIAL

PLACEMENT ZONE

STRUCTURE BACKFILL

(ELS) ZONE

WOOD MATERIAL AND

STRUCTURAL

BACKFILL (ELS) ZONE

P2

R3 L3

L2 L2

R3

L1R3L2 L3

R4R4

R4

L2

L2

R1

P2

P1

P1

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER ENGINEERED LOG STRUCTURE DETAILS

C12

SCALE:

DETAIL - ELS TYPE B LAYERING PLAN 1

C071" = 10'

LOG TYPE DIAMETER (IN) LENGTH (FT) ROOTWAD TOTAL/UNIT

P1 18 (TIP) 30 NO 4

P2 18 (TIP) 35 NO 4

R1 22 30 YES 1

R3 22 20 YES 3

R4 22 15 YES 3

L1 24 20 NO 1

L2 20 20 NO 5

L3 20 25 NO 2

RACKING 8-12 15-25 VARIES 15

SLASH 30 CY

STRUCTURE LOG SCHEDULE:

ELS TYPE B NOTES:

1. CONTROL POINTS FOR ELS PLACEMENTS ARE DEFINED BASED ON TIMBER PILING LOCATION; SEE ELS TIMBER PILING TABLE ON SHEET C07.

2. KEY LOGS SHALL BE PLACED IN DIRECT CONTACT WITH TIMBER PILINGS AND SUBSEQUENT LAYER KEY LOGS;; WITH THE EXCEPTION OF L2 IN LAYER 5 UNLESS DIRECTED OTHERWISE BY THE ENGINEER. LOGS ON THE TOP THREE LAYERS SHALL BE LASHED WITH CHAIN TO EITHER PILINGS OR KEY LOGS AS INDICATED ON THE

PLANS.

3. RACKING LOG AND SLASH PLACEMENT SHALL BE COORDINATED WITH KEY LOG LAYER PLACEMENT TO ENSURE RACKING LOGS AND SLASH EXTEND THROUGH WATERWARD FACE OF STRUCTURE. LAYERS 1 THROUGH 5 SHALL HAVE 3 RACKING LOGS EACH PER LAYER INSTALLED. SEE LAYERING PLAN AND SPECIAL

PROVISIONS.

4. BACKFILL ZONE IS AN APPROXIMATION AND NOT SHOWN TO SCALE; CONTRACTOR TO BACKFILL EACH LAYER PER THE SPECIAL PROVISIONS AND DIRECTION OF THE

ENGINEER.

5. BACKFILL EACH LAYER WITH BACKFILL MATERIAL, AS DEFINED AS STRUCTURE BACKFILL (ELS) PER THE SPECIAL PROVISIONS, FLUSH TO THE TOP OF THE CURRENT LAYER PRIOR TO CONSTRUCTION THE SUBSEQUENT LAYER. COMPACT BACKFILL WITH EXCAVATOR BUCKET IN NO GREATER THAN TWO FOOT LIFTS FIILLING ALL VOIDS. SALVAGED BOULDERS WILL BE PLACED IN LOCATIONS SHOWN ON THE PLANS AND PER THE DIRECTION OF THE ENGINEER. SALVAGED BOULDER PLACEMENT WILL BE PRIORITIZED IN LOCATIONS BETWEEN THE DIFFERENT ELS TYPES AND BETWEEN THE ELSS AND THE EXISTING GRADE.

LAYER 3LAYER 1 LAYER 2

R3 R3

R4

RACKING LOGS AND

SLASH MATERIAL

PLACEMENT ZONE

BACKFILL ZONE

WOOD MATERIAL AND

BACKFILL ZONE

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103

RE

GIS

TE

RED PROFESSIONAL ENGINEER

STATE OF CALIFORNIAC I V I L

No. 90612

GR

ETC

HEN L. KAYSER ENGINEERED LOG STRUCTURE DETAILS

C13

SCALE:

DETAIL - ELS TYPE C LAYERING PLAN 1

C071" = 10'

LOG TYPE DIAMETER (IN) LENGTH (FT) ROOTWAD TOTAL/UNIT

R3 22 20 YES 2

R4 22 15 YES 1

RACKING 8-12 15-20 VARIES 6

STRUCTURE LOG SCHEDULE:

ELS TYPE C NOTES:

1. KEY LOGS SHALL BE INSTALLED AT THE ANGLE INDICATED IN THE STRUCTURE LOG SCHEDULE AND PER DIRECTION OF

THE ENGINEER WITH THE BUTT END OF THE LOGS (NON-ROOTWAD ENDS) TOUCHING. KEY LOGS SHALL BE PLACED AND BACKFILLED A MINIMUM OF TWO-THIRDS OF THE LOG LENGTH TO A MINIMUM LOG BURIAL DEPTH (AS MEASURED FROM

THE BUTT END OF THE LOG) AS INDICATED IN THE STRUCTURE LOG SCHEDULE.

2. RACKING LOGS AND SLASH MATERIAL NOT SHOWN IN PLAN DETAIL FOR CLARITY. RACKING LOG AND SLASH PLACEMENT SHALL BE COORDINATED WITH KEY LOG LAYER PLACEMENT TO ENSURE RACKING LOGS AND SLASH EXTEND THROUGH

WATERWARD FACE OF STRUCTURE. SEE LAYERING PLAN AND SPECIAL PROVISIONS.

3. BACKFILL ZONE IS AN APPROXIMATION AND NOT SHOWN TO SCALE; CONTRACTOR TO BACKFILL EACH LAYER PER THE

SPECIAL PROVISIONS AND DIRECTION OF THE ENGINEER.

4. BACKFILL EACH LAYER WITH BACKFILL MATERIAL, AS DEFINED AS STRUCTURE BACKFILL (ELS) AND SALVAGED BOULDERS, PER THE SPECIAL PROVISIONS. COMPACT BACKFILL WITH EXCAVATOR BUCKET IN NO GREATER THAN TWO FOOT LIFTS FILLING ALL VOIDS. SALVAGED BOULDERS WILL BE STRATEGICALLY PLACED TO CONSTRUCT DESIGN BANK GRADES AND

MINIMIZE LOCALIZED EROSION PER THE DIRECTION OF THE ENGINEER.

LAYER LOG BURIAL

SLOPE (H:V)

MINIMUM LOG

BURIAL DEPTH (FT)

1 0 9

2 10:1 7 3 6:1 8

H

W

OHW

O H

W

O

HW

OHW

OHW

OHW

O H

W

O H

W

O H

W

O H

W

OHW

O

HW

OHW

O

HW

O

HW

O H

W O

H W

O H

W O

H W

OHW

O H

W

OHW

OHW

OHW

OHW

O

HW

O

HW

OHW

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TO

P

TO

P

TO

P

TO

P TOP

TOP TOP

TO

P

TO

P

TO

P

TOP

TO

P

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

ENTRADA WAY

LA HONDA CREEK

(E) BLDG

OHW OHW

TOP TOP

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD01

ROADWAY IMPROVEMENT NOTES ABBREVIATIONS

LEGEND

LIMITS OF PAYMENT KEYNOTES

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

I m p ro v em en t

P la n .d w g, ,6

:5 :2

P

M

ROADWAY IMPROVEMENTS

LAYOUT PLAN & NOTES

OHW

OHW

OHW

OHW

O H

W

O H

W

O H

W

O H

W

O H

WO

H

W O

H W

O H

W O

H W

OHW

OHW

O H

W

TOP

TOP

TOP

TOP

TOP

TOPTOP

TOP

TO

P

TO

P

TO

P

TO

P

TO

P

TO

P

TO

P

TOP

TO

P

TOP

TO

P

ENTRADA WAY

1.0%1.6%

(2 .0

1.

8%

4.

0%

2:

1.3%

(2 .0

(2 .4

(CL STA

3+14.71)

(CL STA

2+99.85)

1+55

(E ) 3

.6

2+00

(E ) 3

.4

2+50

(E ) 3

.1

(N

) 3

.5

3+00

(E ) 3

.1

(N

) 3

.3

3+15.04

(E ) 3

.3

OHW OHW

TOP TOP

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD02

PROFILE - EDGE OF PVMT /DIKE FLOWLINE

PLAN - ENTRADA WAY (STA 1+55 TO 3+15)

NOTESLEGEND

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

I m p ro v em en t

P la n .d w g, ,6

:5 :2

P

M

ROADWAY IMPROVEMENTS

ENTRADA WAY NORTH EP - PLAN & PROFILE

TOP

7.

0+00

8.

8.

0+50

7.

0+60

OHW OHW

TOP TOP

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD03

NOTESLEGEND

PROFILE - 24-INCH SD PIPE

PLAN - 24-INCH SD PIPE

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

I m p ro v em en t

P la n .d w g, ,6

:5 :2

P

M

ROADWAY IMPROVEMENTS

ENTRADA WAY 24 INCH SD PIPE - PLAN & PROFILE

HW

OHW

O

HW

O H

W O

H W

O H

W

O H

W

O H

W O

H W

O H

W O

H W

O H

W O

H W

O H

W TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TO

P

TO

P

TO

P

LA HO

N

DA CREEK

(1.7%)

(2 .0

-2 .5

, T

YP

ENTRADA WAY

2:1 (MAX)

AB

AB

0+00

1.

0+50

7.

0+85

8.

0+00

7.

0+35

0.

0+00

6.

0+35

5.

OHW OHW

TOP TOP

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD04

PROFILE - (E) VALLEY GUTTER FLOW LINE & PIPE OUTFALL SECTION A-A - PIPE OUTFALL SECTION B-B - PIPE OUTFALL

PLAN - 3' X 4' DRAIN INLET AND PIPE OUTFALL

LEGEND NOTES

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

I m p ro v em en t

P la n .d w g, ,6

:5 :2

P

M

ROADWAY IMPROVEMENTS

24 INCH SD PIPE OUTFALL - PLAN & PROFILE

H

W O

H W

OHW

O H

W

O

HW

OHW

OHW

OHW

O H

W

O H

W

O H

W

O H

W

OHW

O

HW

O

HW

O

HW

O H

W O

H W

O H

W O

H W

OHW

O H

W

OHW

OHW

OHW

OHW

O

HW

O

HW

OHW

O H

W O

H W

TO

P

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TO

P

TO

P

TO

P

TO

P TOP

TOP TOP

TO

P

TO

P

TO

P

TOP

TO

P

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TO

P

TO

P

C

CD

06 D CD

06 E

CD

ENTRADA WAY

LA HONDA CREEK

LA

H

O N

DA

R

O

AD

(E) BLDG

CCD06

DCD06

ECD06

ENTRADA WAY

F

CD

F

CD

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD05

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

I m p ro v em en t

P la n .d w g, ,6

:5 :2

P

M

ROADWAY IMPROVEMENTS

ROAD SECTION KEY PLAN

OHW OHW OHW

0+00

8.

0+50

9.

1.

OHW OHW

0+00

8.

0+50

9.

1.

OHW

0+00

8.

0+50

0.

7.

0+00

8.

0+39

8.

7.

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD06

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

R o ad w ay

P ro fi le

S ec ti o n s.

d w g, ,1

:3 :2

P

M

ROADWAY IMPROVEMENTS

ROAD SECTIONS

IC LIV

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD07

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

C D

D

E T

A

IL

S .d w g, ,1

:3 :2

P

M

DETAILS

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD08

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

C D

D

E T

A

IL

S .d w g, ,1

:3 :2

P

C 66905

D N ONSH

A

N

SSEFORPDERETSIGER RE

EN

IG

NE

LANOI

STATE FO

AINROFILAC

D.

U

UA T

CO

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103

CD09

p sm c e n g o n ca ll\ t as k o rd er s\ t o en tr ad a sl ip o u t\ t ec h n ic al c ad d es ig n b id d o cu m en ts s h ee t fi le s\

C D

D

E T

A

IL

S .d w g, ,1

:3 :2

P

UN

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103RETAINING WALL GENERAL PLAN

S1

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103RETAINING WALL GENERAL NOTES

S2

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103RETAINING WALL DETAILS No. 1

S3

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103RETAINING WALL DETAILS No. 2

S4

TY

OF SAN MATEO

P U

B L I C W O R

K S

1/5103RETAINING WALL GROUND ANCHORS

S5

LEGEND

LOWER RIPARIAN

UPPER RIPARIAN

ELS LIVE STAKE PLANTING

NATIVE EROSION CONTROL

SEEDING AREA

LA H

O

N D

A G U

ILD

C

U

ESTA

083-370-010

LA HONDA GUILD - CUESTA

083-051-150LA HONDA GUILD

CUESTA

083-051-120

Bruce 083-051-110

SUBDIVISION NO. 1

CUESTA LA HONDA

(17-RSM-PG056)

Block 1

26105 26106

26177

2620526206

26208

2622026221

26222

26232

26233

26237

26472

26657

26658 26659

26662 26663

26711

26773

26776

26777

26780

100130 100133 100134

100135 100136

100137

100187

100214

100220 100223

100225

100227

100228

WATERS OF THE US

26124

26463 26464 26445 26446

100209

100210100211

100216

100217

OHW

OHWOHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

O

HW

O

HW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

OHW

O H

W

OHW OHW

O H

W

O

HW

O H

W

OHW

OHW

O H

W

OHW

OHW

OHW OHW

OHW

TOPTOP

TOP

TOP

TOPTOP

TOP

TOP

TOP

TO

P

TOP

TO

P

TO

P

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TOP

TOP

TOP

TOP

TO

P

TOP

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP

TOP

TO

P

TO

P

TOP

TOP TOP TOP

TOP

TOP

TOP

TOP

26444

150000

150001150002

150003 150004

150005150006 150007

150008 150009

150010

150011 150012

150016

26378

26231

REDONDA WAY

LA HONDA GUILD

CUESTA

083-092-190 E N T R A D A W A Y

6 0 ' R O W

BUILDING

TENNIS

COURT

X X X X X X X X X X X X X X X X X

X X

X X

X X

X X

X X

X X

X

X X

X X

X X

X X

X X

X X

X X

X X

X X

EO

P

CO

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103LIC

EN

SE

D LA

NDSCAPE ARCHITECT

STATE OF CA LIFORNIA

KA

TH

RY

N S

UZANNE FORESTER NO. 7047Signature

Renewal Date

Date

9/30/2026

010 10 20

SCALE IN FEET

PLANTING PLAN

L01

1. ENGINEER SHALL APPROVE GRADING PRIOR TO PLANT INSTALLATION.

2. PLANTING AND SEEDING SHALL OCCUR WITHIN TWO WEEKS AFTER GRADING IS APPROVED.

3. ALL PLANTS SHALL CONFORM TO THE STANDARDS OF THE CURRENT EDITION OF AMERICAN

STANDARD FOR NURSERY STOCK AS APPROVED BY THE AMERICAN STANDARDS INSTITUTE

(z60.01-2014).

4. ALL NURSERY STOCK SHALL BE TESTED AND CERTIFIED FREE OF PHYTOPHTHORA RAMORUM

A MINIMUM OF 30 DAYS PRIOR TO DELIVERY AND INSTALLATION ON SITE.

5. PLANT SUBSTITUTIONS ARE SUBJECT TO APPROVAL BY THE ENGINEER.

6. PLANTS SHALL BE TAGGED OR MARKED FOR IDENTIFICATION UPON DELIVERY.

7. THE ENGINEER SHALL INSPECT ALL PLANT MATERIAL UPON DELIVERY. ALL PLANTS WITH

DAMAGED ROOTS, LEADERS, OR BRANCHES SHALL BE REJECTED. NO ROOT-BOUND

CONTAINER STOCK SHALL BE ACCEPTED.

8. KEEP PLANTS SHADED UNTIL THE TIME OF PLANTING. DO NOT LET THE PLANT MATERIAL SIT

IN THE SUN OR DRY OUT BEFORE PLANTING.

9. THE ENGINEER SHALL APPROVE SAMPLE PLANT LAYOUT PRIOR TO PLANTING.

10. ENGINEER SHALL REVIEW SAMPLE INSTALLATIONS OF EACH PLANT MATERIAL TYPE TO

VERIFY INSTALLATION OCCURS ACCORDING TO PLANS.

11. LOW GROWING SPECIES THAT WILL MAINTAIN A MINIMUM 15-FOOT CLEARANCE SHALL BE

INSTALLED WITHIN 20 HORIZONTAL FEET OF ALL POWER LINES.

12. THOROUGHLY WATER ALL PLANTED AREAS IMMEDIATELY AFTER PLANTING.

13. APPLY 3" OF WOOD MULCH TO ALL PLANTING AREAS ABOVE THE APPROXIMATE 2 YEAR

FLOOD ELEVATION.

14. NATIVE EROSION CONTROL SEEDING AREAS SHALL BE HYDROSEEDED WITH NATIVE EROSION

CONTROL SEED MIX USING A TWO-PASS APPROACH.

15. NATIVE EROSION CONTROL SEEDING AREAS WILL INCLUDE ADDITIONAL NATIVE TREES,

SHRUBS, AND GROUNDCOVER PLANTINGS COORDINATED WITH PROPERTY OWNERS. WILL

OCCUR UNDER A SEPARATE CONTRACT.

GENERAL NOTES

MATCHLINE THIS SHEET

MATCHLINE THIS SHEET

020 20 40

SCALE IN FEET

LOWER RIPARIAN ZONE EXTENDING

TO THE 2-YEAR FLOOD ELEVATION

LOWER RIPARIAN ZONE BEGINS AT THE

APPROXIMATE LOCATION OF THE

ORDINARY HIGH WATER MARK

LOWER RIPARIAN ZONE EXTENDING

TO THE 2-YEAR FLOOD ELEVATION

ELS LIVE STAKE

PLANTING

NATIVE EROSION

CONTROL SEEDING

NATIVE EROSION CONTROL SEEDING

AROUND NEW STONE APRON

SEE NOTE #15

NATIVE EROSION

CONTROL SEEDING AREA

NO VEGETATION INSTALLATION

IS TO OCCUR ON SLOPES

ADJACENT TO THE STREAM

BANK.

SEE NOTE #15

6/22/2026

UN

TY OF SAN MATEO

P U

B L I C W O R

K S

1/5103LIC

EN

SE

D LA

NDSCAPE ARCHITECT

STATE OF CA LIFORNIA

KA

TH

RY

N S

UZANNE FORESTER NO. 7047Signature

Renewal Date

Date

9/30/2026

PLANTING SCHEDULE AND DETAILS

L02

FINISHED GROUND PLANT AT SAME LEVEL AS

GROWN IN CONTAINER

PLANTING HOLE/

EXCAVATION 3X

GREATER THAN

ROOTBALL OR

CONTAINER WIDTH

3" THICK LAYER WOOD MULCH, KEEP

AWAY FROM TRUNK OF PLANT

EXCAVATE SOIL FOR PLANTING TO DIMENSIONS

SHOWN. FIRM SOIL AROUND ROOTBALL AND WATER

TO SETTLE. DO NOT LEAVE AIR POCKETS. DO NOT

DAMAGE ROOTS DURING PLANTING OPERATIONS

REMOVE CONTAINER PRIOR TO PLANTING.

DURING PLANTING OPERATIONS GENTLY LOOSEN

AND SPREAD ROOTS AT BOTTOM OF ROOTBALL

EXISTING GROUND

MAX

LIVE STAKE NOTES:

1. LIVE STAKES SHALL BE HARVESTED WITHIN 50 MILES OF THE PROJECT SITE.

2. ALL LIVE STAKES SHALL BE SINGLE-STEMMED AND STRAIGHT, WITH NO MAJOR CROOKS OR BENDS. PRUNING SHALL ONLY OCCUR AT THE ENDS OF THE

MATERIAL.

3. STAKES SHALL HAVE A BASAL DIAMETER OF 3/4" TO 1 1/2" AND BE AT LEAST 4 FEET IN LENGTH.

4. SOAK THE BASAL END OF ALL WILLOW…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .