This is an Engineer's Estimate document for the City of Gallup, New Mexico, in partnership with the US Department of Commerce Economic Development Administration (EDA), detailing the Carbon Coal Road and McKinley County Industrial Park Waterline Project. The project consists of two lots involving the installation of approximately 2,395 linear feet of 12-inch CL350 ductile iron pipe on Carbon Coal Road and 540 linear feet of 8-inch CL350 ductile iron pipe on Industrial Park Road, both buried at minimum depths of 5 feet and 4 feet respectively. Associated work includes the installation of gate valves, air release valves, fire hydrant assemblies, waterline tie-ins, fittings, rock excavation, and temporary traffic control. Sealed bids must be submitted electronically by 2:00 pm local time on January 5, 2026, with a question submission deadline of December 16, 2025 at 5:00 pm. The contractor must commence work within the timeframe specified in the Notice to Proceed and complete the entire project within 90 calendar days, with a one-year performance and materials warranty period following substantial completion.

The Engineer's Estimate establishes a total project cost of $834,458.63, with Lot 1 (Carbon Coal Road) subtotaled at $613,350.00 and Lot 2 (Industrial Park Road) subtotaled at $158,850.00, including New Mexico Gross Receipts Tax at 8.0625%. The project is funded by the US Department of Commerce EDA under grant 08-79-05634. Bidders must submit a bid bond equal to five percent of the bid sum, and upon contract award, provide performance and payment bonds each in 100 percent of the contract amount. The procurement offers preferences to New Mexico resident contractors and New Mexico resident veteran contractors certified by the State Department of Taxation and Revenue. All contractors and subcontractors must be registered with the New Mexico Labor and Industrial Division for public works projects exceeding $60,000 and must comply with prevailing wage requirements per the Public Works Minimum Wage Act. Subcontractors exceeding $5,000 must be listed with the bid, and those exceeding $125,000 must furnish separate performance bonds. Liquidated damages are assessed at $500 per calendar day for failure to meet the 90-day completion deadline. The contractor is responsible for all costs related to traffic control, storm water pollution prevention, construction staking, independent material testing, insurance coverage, and waste disposal.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UNIT

ITEM DESCRIPTION PRICE AMOUNT

2410 LF $160.00 $385,600.00

1 LS $25,000.00 $25,000.00

2 EA $12,000.00 $24,000.00

1 EA $35,000.00 $35,000.00

1 EA $9,000.00 $9,000.00

3 EA $10,000.00 $30,000.00

2 EA $1,500.00 $3,000.00

400 LBS $30.00 $12,000.00

425 CY $150.00 $63,750.00

10 1 LS $10,000.00 $10,000.00

11 $25,000.00 $25,000.00

LOT 1 SUBTOTAL: $613,350.00

For Tie-In "A" to existing 24-inch waterline including up to 25' of new 24-inch CL350 D.I.P., fittings as required, sleeves, but not valves as detailed complete and in place for the Lump Sum Price of:

ENGINEER'S ESTIMATE

CARBON COAL ROAD McKINLEY COUNTY

INDUSTRIAL PARK WATERLINE PROJECT

CITY OF GALLUP, NEW MEXICO

FORMAL BID NO.

SEPTEMBER 2025

Lot 1: Carbon Coal Road Waterline

ESTIMATED

QUANTITY

For installation of new 12-inch CL350 D.I.P. waterline with fittings, buried at a minimum depth of 5 feet, complete in place for the Unit Price per Linear Foot of:

For the installation of AWWA C509 12-inch resilent wedge gate valve (MJxMJ) and valve box complete and in place for the Unit Price per Each of:

For the installation of AWWA C515 24-inch resilent wedge horizontal gate valve (MJxMJ) with bypass and valve box complete and in place for the Unit Price per Each of:

For the installation of Type "1" air release valve (1" size) station with bollards complete and in place for the Unit Price per Each of:

For the installation of 12-inch AWWA C153 MJ cap coupling on new waterline complete and in place for the Unit Price per Each of:

For the installation of additional unidentified fittings, horizontal and vertical not shown on project drawings complete and in place for the Unit Price per Pound of Fitting of:

For installation of fire hydrant assembly including 12"x6" tee, valve, fittings, concrete and 6-inch CL 350 DIP waterline (restrained) complete and in place for Unit Price per Each:

For rock excavation and disposal in accordance with rock excavation detail and pay width complete and in place for the Unit Price per Cubic Yard of:

For implementing and maintaining temporary Traffic Control Plan for the Lump Sum Price of:

For material testing by an independent lab (soil, concrete, base course and PMBP). This amount is for totaling bid.

Actual amount is to be paid by approbed invoice. ALLOWANCE

EE 1

540 LF $135.00 $72,900.00

2 EA $8,000.00 $16,000.00

2 EA $9,000.00 $18,000.00

1 EA $10,000.00 $10,000.00

1 EA $8,500.00 $8,500.00

1 EA $15,000.00 $15,000.00

1 EA $1,200.00 $1,200.00

150 LBS $30.00 $4,500.00

9 125 CY $150.00 $18,750.00

10 1 LS $10,000.00 $10,000.00

ESTIMATED

For installation of new 8-inch CL350 D.I.P. waterline with fittings, buried at a minimum depth of 4 feet, complete in place for the Unit Price per Linear Foot of:

For the installation of AWWA C509 8-inch resilent wedge gate valve (MJxMJ) and valve box complete and in place for the Unit Price per Each of:

For installation of fire hydrant assembly including 8"x6" tee, valve, fittings, concrete and 6-inch CL 350 DIP waterline (restrained) complete and in place for Unit Price per Each:

For the installation of Type "1" air release valve (1" size) station complete and in place for the Unit Price per Each of:

For high pressure water service meter including up to 20’ of 6” D.I.P. waterline, 10’ of 1” of 3/4" Type K copper line, 1” tapped 6” cap, fittings, valves, specials, connection to customer service lines, and appurtenances as required complete and in place for the Unit Price per Each of:

For fire line with detector check valve including up to 20’ of 4” D.I.P. waterline, post indicator, detector check valve, Type “C” manhole, fittings, valves, and appurtenances as required complete and in place for the Unit Price per Each of:

For implementing and maintaining temporary Traffic Control Plan for the Lump Sum Price of:

QUANTITY

For the installation of 8-inch AWWA C153 MJ cap coupling on new waterline complete and in place for the Unit Price per Each of:

For the installation of additional unidentified fittings, horizontal and vertical not shown on project drawings complete and in place for the Unit Price per Pound of Fitting of:

For rock excavation and disposal in accordance with rock excavation detail and pay width complete and in place for the Unit Price per Cubic Yard of:

Lot 2: Industrial Park Road Waterline

EE 2

$7,500.00 $7,500.00

LOT 2 SUBTOTAL: $158,850.00

LOT 1 SUBTOTAL: $613,350.00

LOT 2 SUBTOTAL: $158,850.00

LOT 1 & 2 SUBTOTAL: $772,200.00

NMGRT @ 8.0625%: $62,258.63

PROJECT TOTAL: $834,458.63

QUANTITY

For material testing by an independent lab (soil, concrete, base course and PMBP). This amount is for totaling bid.

Actual amount is to be paid by approbed invoice. ALLOWANCE

Lot 2: Industrial Park Road Waterline