This is a Subcontracting Plan Waiver Form (AMS-Form-001) from Brookhaven National Laboratory's Acquisition Management System. The form documents an exemption from the Small Business Subcontracting Plan requirements mandated by Public Law 95-507 for negotiated contracts exceeding $900,000 or construction contracts exceeding $2,000,000. The waiver applies to proposed Contract No. 474046 for the remanufacture of Linac Modulator Tube Types WDR8618 and WDR4CW25000A and manufacture of WDNLPT32 new tube type. The proposed contractor has certified exemption based on one of two permissible grounds: either the contract work will be performed entirely outside the United States and its territories, or no subcontracting will be conducted under the contract.

The form requires certification from the contractor, validation by the buyer or contract specialist, and approval by the Small Business Liaison Administrator. The document was approved on November 14, 2023, and printed on February 25, 2026. This waiver indicates that BSA, as the operator of Brookhaven National Laboratory under a Department of Energy contract, has determined that the Small Business Subcontracting Plan is not applicable to this procurement, contingent upon the contractor's certified exemption rationale.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROCUREMENT AND PROPERTY MANAGEMENT DIVISION

BROOKHAVEN NATIONAL LABORATORY

Managed by Brookhaven Science Associates, LLC under contract to the U.S. Department of Energy

ACQUISITION MANAGEMENT SYSTEM FORM

Form No. AMS-Form-001

Revision No. 6

APPROVED BY:

Paul Pierson 11/14/2023

PPM Manager/Date

Subcontracting Plan Waiver

Public Law 95-507 requires that all negotiated contracts in excess of $900,000 or contracts for the construction of a public facility in excess of $2,000,000, and any single action Modification, Task, or Change Order over those thresholds, have an approved Small Business Subcontracting Plan. The work covered by this Subcontracting Plan Waiver for proposed Contract No. is with in the total amount of $ AND/OR Modification, Task, or Change Order No. in the increased amount of $ . The scope of work covers .

The proposed Contractor has certified that they are exempt from submission of the Small Business Subcontracting Plan for the following reasons:

(|_|) The contract including all subcontracts there under will be performed entirely outside of the United States, its possessions or territories, the District of Columbia, and the Commonwealth of Puerto Rico.

(|_|) The Contractor has certified that subcontracting will not be conducted under this contract. Contractors’ reasons for no subcontracting opportunities required:

I hereby certify that the above statement is true, to the best of my knowledge.

Certification:

Contractor

Date:

DETERMINATION

On the basis of the above findings and pursuant to P.L. 95-507, I hereby determine that the Small Business Subcontracting Plan is not applicable to this procurement.

Validated:

Buyer / Contract Specialist / Manager

Date:

Approved:

Small Business Liaison Administrator

Date:

Date Printed 2/25/2026 1 of 1 Date Approve 11/14/2023

File details come from the government source that posted it. Updated .