Enclosure A - Draft Contract.pdf

PDF 150 KB Posted

Attached to
Construction Manager as Advisor Federal contract opportunity
Solicitation number
459544
Issued by
Department of Energy Office of Science

About this file

This is a draft contract between Brookhaven Science Associates, LLC (BSA) and a future contractor for Construction Manager as Advisor (CMa) Pre-Construction Support Services for the Electron-Ion Collider (EIC) Infrastructure Project at Brookhaven National Laboratory. The contract period of performance runs through September 30, 2025, with a firm fixed price to be determined (amount shown as XXXX US Dollars).

The scope includes eight key deliverables with specific timelines: review and estimate of long lead items (4 weeks after award), cost estimates for 90% and 100% detailed design (4 weeks each after submittal), constructability reviews of 90% and 100% detailed design (4 weeks each), review of project commissioning plan (2 weeks after submittal), and comprehensive cost & resource-loaded construction schedules at both 90% and 100% design stages (6 weeks each). The contract incorporates BSA's General Terms and Conditions for Non-Commercial Services and Supplemental Terms for Contractors working on-site at BNL. Kevin Kirkendall serves as BSA's Contractual Representative, and electronic invoice submission is preferred via apinvoices@bnl.gov.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Buyer Amount Contract Number

Kevin Kirkendall TBD 459544

BROOKHAVEN NATIONAL LABORATORY

Brookhaven Science Associates

P.O. Box 5000

UPTON, L.I., N.Y. 11973-5000

Name and Address of Contractor

CONTRACT

This Contract (the "Contract") is between the party named above (the "Contractor"), and

Brookhaven Science Associates, LLC. ("BSA"), the latter acting under a Prime Contract with the

United States of America (the "Government") represented by the United States Department of

Energy ("DOE”).

I. SCOPE OF WORK

All work shall be conducted in strict accordance with Attachment (A) Statement of Work entitled “Statement of Work for the Electron-Ion Collider (EIC) Infrastructure Project

Construction Manager as Advisor (CMa) Pre-Construction Support Services” Doc. No.

EIC-IFD-SOW-003, Rev 01, Dated February 4, 2025.

A. Reports/Deliverables: The Contractor shall provide the following deliverable(s) to and as directed by BSA’s Technical Representative:

Key Deliverables Milestone Schedule

No. Deliverable Completion Date

1 Review and estimate of Long Lead items Four (4) weeks after contract award

2 Cost Estimate of 90% Detailed Design Four (4) weeks after receipt of 90%

Detailed Design submittal

3 Constructability Review of the 90% Detailed Design Four (4) weeks after receipt of 90%

Detailed Design submittal

4 Review of Project Commissioning Plan Two (2) weeks after Commissioning Plan submittal

5 Comprehensive Cost- & Resource-Loaded

Construction Schedule

Six (6) weeks after receipt of 90% Detailed

Design submittal

6 Cost Estimate of 100% Detailed Design Four (4) weeks after receipt of 100%

Detailed Design submittal

7 Constructability Review of the 100% Detailed

Design

Four (4) weeks after receipt of 100%

Detailed Design submittal

8 Final Comprehensive Cost- & Resource-Loaded

Construction Schedule

Six (6) weeks after receipt of 100%

Detailed Design submittal

II. PERIOD OF PERFORMANCE:

This Contract shall be effective as of the date executed by BSA provided that the Contractor executes the Contract without exception or alteration. It shall remain in effect through

9/30/2025.

III. FIRM FIXED PRICE AND PAYMENT

A. Firm Fixed Price: In full consideration of the Contractor's performance hereunder

BSA shall pay the Contractor the firm fixed price of XXXX US Dollars ($0.00).

The said sum shall constitute full compensation for all services and materials furnished hereunder.

B. Payment: Payment will be made upon receipt and approval of properly certified invoices. Payment will be in accordance with the following milestone payment schedule:

Cumulative

Milestone Amount Amount

Total $.00 $.00

Payment terms are Net TBD.

Invoices shall be directed to BSA’s Accounts Payable Section via electronic or regular mail.

Electronic invoice submittal is preferred by BSA. The Contractor shall make every effort to have systems in place that allow for electronic invoice transmittal.

Invoices shall be submitted in PDF format, via e-mail, to apinvoices@bnl.gov.

Hard copy invoices, in duplicate, shall be directed to BSA's Accounts Payable

Section, Contracts Division, Bldg. No. 400d.

The Contractor shall indicate the final invoice by clearly marking such invoice as

"FINAL". A copy of the final invoice must be submitted to BSA’s Contractual

Representative.

IV. AUTHORIZED REPRESENTATIVES

A. BSA’s Technical Representative: ____________ of the __________, located in

Building __________ is BSA's Technical Representative, hereunder. (He/She) shall act as liaison between BSA and the Contractor in technical matters only.

(He/She) can be reached at __________(phone), ___________(e-mail).

B. BSA’s Contractual Representative: Kevin Kirkendall, telephone no. 631-344-

4605, kkirkenda@bnl.gov, is BSA's Contractual Representative. Any change or modification in the terms and conditions of this contract shall require the written approval of BSA's Procurement and Property Management Division’s Manager, or his designee.

C. Contractor’s Technical Representative: ________ is the Contractor’s authorized Technical Representative, hereunder. (He/She) shall act as point of contact between BSA and the Contractor in technical matters only. (He/She) can be reached at ________(phone), _____(e-mail).

D. Contractor’s Contractual Representative: ______________is the Contractor’s authorized Contractual Representative, hereunder. (He/She) shall act as liaison between BSA and the Contractor. (He/She) can be reached at _______(phone), ____________(e-mail).

V. ADDITIONAL TERMS

The provisions of Brookhaven Science Associates, LLC General Terms and Conditions for Non-Commercial Services, Rev 22.0 Sept 2022, are incorporated herein and made a part hereof.

The provisions of Brookhaven Science Associates, LLC Supplemental Terms and

Conditions for Work by Contractors on Site at Brookhaven National Laboratory, Rev

22.0 Sept 2022 are incorporated herein and made a part hereof.

This Contract is issued pursuant to Brookhaven Science Associates General and/or

Supplemental terms and conditions listed above which are incorporated herein by reference. The complete text of these terms and conditions can be viewed via the internet at: PPM | Terms and Conditions (bnl.gov). Should the Contractor have any questions and/or not have access to these terms and conditions, contact the buyer or contracts specialist immediately.

The following documents attached hereto and made a part hereof, contain additional provisions of this contract:

Attachment A: Statement of Work, Doc. No. EIC-IFD-SOW-013, Rev 02, Dated June 12, 2024

Attachment B: BNL-QA-101

This Contract does not bind nor purport to bind the Government of the United States.

ACCEPTED:

CONTRACTOR BROOKHAVENSCIENCE

ASSOCIATES, LLC.

By: By:

Name: Name:

Title: Title:

Date: Date:

Should you accept this Contract without exception or alteration, one copy of the Contract executed by both parties shall be returned to BSA's Contractual Representative. Should you take any exceptions or attempt to alter the Contract https://www.bnl.gov/ppm/terms-and-conditions.php in any manner, BSA's execution thereof shall be null and void. Should you wish to take exception(s)/alteration(s), you shall notify BSA's Contractual Representative. BSA will consider the requested exception(s)/alteration(s) and notify you accordingly. No Contract shall exist unless and until such differences are resolved.