Enclosure 2_Phasing Schedule_(CUI) MCASI Mod HVAC B7000_Redacted.pdf
PDF 1 MB Posted
- Solicitation number
- N4008424R1TBD
About this file
This document outlines a sources sought notice for repair and construction work at a secure access building at Marine Corps Air Station Iwakuni in Japan. The Naval Facilities Engineering Command Far East seeks potential sources to upgrade the HVAC system in Building 7000 for $10-25 million. Interested contractors should demonstrate experience modifying four-pipe hydronic systems, mechanical rooms, electrical systems, and building automation to support VAV reheat and independent temperature control. Responses are due by March 28, 2024. The work must follow construction security plans, using only U.S. companies, citizens, and persons while on site with security vetting required. The contract will be firm-fixed-price for 495 days on site from May to December 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Enclosure (4) Contractor Information Form.docx | DOCX document | |
| Enclosure 3_OTC 7000 CSPMay 2023_Signed_KTR_Redacted.pdf | ||
| Enclosure 1 Drawings(CUI)MCASI Mod HVAC B7000.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Activity ID Activity Name Original Duration
Start Finish Calendar Total Float
MCAS Iwakuni B7000 - HVAC and Simulator ModificationsMCAS Iwakuni B7000 - HVAC and Simulator Modifications 495 09-Jan-23 03-Jan-25 5 Day/Holidays 0
Option 1 - Four Pipe Hydronic System;UnconditionedAirSystemsRemovedOption 1 - Four Pipe Hydronic System; Unconditioned Air Systems Removed 495 09-Jan-23 03-Jan-25 5 Day/Holidays 0
DesignDesign 235 09-Jan-23 15-Dec-23 5 Day/Holidays 0
1240 Begin On Site Review 0 09-Jan-23 5 Day/Holidays 0
1250 Design Review On-Site 5 09-Jan-23 13-Jan-23 5 Day/Holidays 0
1320 60% Design Submittal 8 24-Jan-23 02-Feb-23 5 Day/Holidays 0
1340 60% Review Meeting 0 23-Feb-23 5 Day/Holidays 0
1350 60% Design Resubmit 17 01-Mar-23 23-Mar-23 5 Day/Holidays 0
1355 60% Resubmit Review Meeting 0 12-Apr-23 5 Day/Holidays 0
1360 100% Design Submittal 22 13-Apr-23 12-May-23 5 Day/Holidays 0
1380 100% Review Meeting 0 12-Jun-23 5 Day/Holidays 0
1400 Advanced Final Design Submittal 15 13-Jun-23 05-Jul-23 5 Day/Holidays 0
1410 Final Design Submittal 19 06-Jul-23 01-Aug-23 5 Day/Holidays 0
1420 Construction Solicitation Meeting 0 01-Aug-23 5 Day/Holidays 0
1520 Prime Contractor Award and Contract Execution 93 02-Aug-23 15-Dec-23 5 Day/Holidays 0
ConstructionConstruction 260 18-Dec-23 03-Jan-25 5 Day/Holidays 0
Phase 0 - PreconstructionPhase 0 - Preconstruction 200 18-Dec-23 03-Oct-24 5 Day/Holidays 60
1580 Contractor Notice to Proceed 0 18-Dec-23 5 Day/Holidays 0
1590 Contractor Mobilization to MCASI 20 18-Dec-23 17-Jan-24 5 Day/Holidays 240
1596 Submittals/Procurement of Materials for Red/Blue Zones 20 18-Dec-23 17-Jan-24 5 Day/Holidays 0
1598 Construction Security Plan 20 18-Dec-23 17-Jan-24 5 Day/Holidays 240
1600 Submittals for Major Equipment 25 18-Dec-23 24-Jan-24 5 Day/Holidays 25
1620 Government Review and Approval of Submittals 25 25-Jan-24 29-Feb-24 5 Day/Holidays 25
1640 Procurement of Electrical and Mechanical Equipment 150 01-Mar-24 03-Oct-24 5 Day/Holidays 25
1660 Procurement of Interior Finishes 150 01-Mar-24 03-Oct-24 5 Day/Holidays 60
1700 Kickoff Meeting with Key Subcontractors 0 18-Jan-24 5 Day/Holidays 0
Phase 1 - Mech Rooms 5-7 -Hydronic/UpstairsWorkPhase 1 - Mech Rooms 5-7 - Hydronic/Upstairs Work 80 18-Jan-24 10-May-24 5 Day/Holidays 160
2000 Selective Demolition 10 18-Jan-24 31-Jan-24 5 Day/Holidays 0
2010 Extend Equipment Pads of Existing Air Handler Units 5 01-Feb-24 07-Feb-24 5 Day/Holidays 0
2020 Isolate Existing Hydronics for New Chilled Water System 5 01-Feb-24 07-Feb-24 5 Day/Holidays 0
2060 New Heating Coils in Existing Air Handling Units 5 08-Feb-24 14-Feb-24 5 Day/Holidays 0
2080 Modify Ductwork 5 08-Feb-24 14-Feb-24 5 Day/Holidays 0
2100 Modifications to Piping Headers 5 15-Feb-24 22-Feb-24 5 Day/Holidays 0
2120 New Hot Water Pumps 5 15-Feb-24 22-Feb-24 5 Day/Holidays 0
2140 New Hydronic Piping for New Hot Water System 10 15-Feb-24 29-Feb-24 5 Day/Holidays 0
2160 New 1200 Amp 208V Service for HVAC Upgrades 10 15-Feb-24 29-Feb-24 5 Day/Holidays 0
3020 Test and Balance 10 01-Mar-24 14-Mar-24 5 Day/Holidays 0
3030 Certificate of Readiness 5 15-Mar-24 22-Mar-24 5 Day/Holidays 0
3040 Commissioning - Prefunctional Checklists 5 25-Mar-24 29-Mar-24 5 Day/Holidays 0
3050 SCIF Re-Accreditation 30 01-Apr-24 10-May-24 5 Day/Holidays 160
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025
MCAS IWAKUNI, JAPAN - BUILDING 7000
MODIFY HVAC SYSTEMS
Final Design Submittal Construction Schedule
Printed on 20-Jul-23
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone Prime Contract #: N62742-20-D-001 Date Revision Checked Approved
02-Feb-22 60% Submittal
27-Mar-23 60% Resubmittal
12-May-23 100% Submittal
26-Jul-23 Final Design Submittal
CUI
CUI
Sirron.Vessels Text Box Enclosure 2
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Start Finish Calendar Total Float
Phase 2 - Portions ofA,C,D,E and FWingsPhase 2 - Portions of A, C, D, E and F Wings 49 01-Apr-24 07-Jun-24 5 Day/Holidays 141
2180 VAV System Hot Water Reheat Coils 20 01-Apr-24 26-Apr-24 5 Day/Holidays 0
2200 Outside Air/Exhaust Air System Mechanical and Electrical 20 29-Apr-24 24-May-24 5 Day/Holidays 0
2220 Building Control System 15 06-May-24 24-May-24 5 Day/Holidays 0
2240 Interior Finishes 24 06-May-24 07-Jun-24 5 Day/Holidays 0
2970 Test and Balance 10 06-May-24 17-May-24 5 Day/Holidays 0
2980 Certificate of Readiness 5 20-May-24 24-May-24 5 Day/Holidays 0
2990 Commissioning - Prefunctional Checklists 5 28-May-24 03-Jun-24 5 Day/Holidays 0
3010 Ready For Training 0 07-Jun-24 5 Day/Holidays 141
Phase 4 - D WingPhase 4 - D Wing 105 03-Jun-24 31-Oct-24 5 Day/Holidays 41
1860 HVAC Upgrade 30 03-Jun-24 16-Jul-24 5 Day/Holidays 41
1880 Electrical Modificaions 15 25-Jun-24 16-Jul-24 5 Day/Holidays 41
1900 Control System Modification 15 25-Jun-24 16-Jul-24 5 Day/Holidays 41
1910 HVAC Test and Balance/Commissioning 10 17-Jul-24 30-Jul-24 5 Day/Holidays 41
1920 Interior Finishes and FF&E 15 31-Jul-24 20-Aug-24 5 Day/Holidays 41
2870 Test and Balance 10 21-Aug-24 04-Sep-24 5 Day/Holidays 41
2880 Certificate of Readiness 5 05-Sep-24 11-Sep-24 5 Day/Holidays 41
2890 Commissioning - Prefunctional Checklists 5 12-Sep-24 18-Sep-24 5 Day/Holidays 41
2900 SCIF Re-Accreditation 30 19-Sep-24 31-Oct-24 5 Day/Holidays 41
2910 Ready For Training 0 31-Oct-24 5 Day/Holidays 41
Install of New AirHandlers in MehcanicalRoom forF-35 SimulatorsInstall of New Air Handlers in Mehcanical Room for F-35 Simulators 35 04-Oct-24 25-Nov-24 5 Day/Holidays 25
2075 Install New Air Handlers in Mech Room for F-35 Simulators 35 04-Oct-24 25-Nov-24 5 Day/Holidays 25
Phase 5 - C WingPhase 5 - C Wing 105 03-Jun-24 31-Oct-24 5 Day/Holidays 41
2370 Protect C-Wing Simulators 10 03-Jun-24 14-Jun-24 5 Day/Holidays 41
2380 VAV System Hot Water Reheat Coils 15 17-Jun-24 09-Jul-24 5 Day/Holidays 41
2400 Electrical Modification 15 17-Jun-24 09-Jul-24 5 Day/Holidays 41
2420 Outside Air/Exhaust Air System Mechanical and Electrical 12 10-Jul-24 25-Jul-24 5 Day/Holidays 41
2440 Building Control System 12 10-Jul-24 25-Jul-24 5 Day/Holidays 41
2460 Interior Finishes 18 26-Jul-24 20-Aug-24 5 Day/Holidays 41
2462 Test and Balance 10 21-Aug-24 04-Sep-24 5 Day/Holidays 41
2465 Certificate of Readiness 5 05-Sep-24 11-Sep-24 5 Day/Holidays 41
2468 Commissioning - Prefunctional Checklists 5 12-Sep-24 18-Sep-24 5 Day/Holidays 41
2478 SCIF Re-Accreditation 30 19-Sep-24 31-Oct-24 5 Day/Holidays 41
2488 Ready For Training 0 31-Oct-24 5 Day/Holidays 41
Phase 6 - G WingPhase 6 - G Wing 97 03-Jun-24 21-Oct-24 5 Day/Holidays 49
2560 VAV System Hot Water Reheat Coils 10 03-Jun-24 14-Jun-24 5 Day/Holidays 49
2580 Outside Air/Exhaust Air System Mechanical and Electrical 15 17-Jun-24 09-Jul-24 5 Day/Holidays 49
2600 Building Control System 12 10-Jul-24 25-Jul-24 5 Day/Holidays 49
2620 Interior Finishes 10 26-Jul-24 08-Aug-24 5 Day/Holidays 49
2625 Test and Balance 10 09-Aug-24 22-Aug-24 5 Day/Holidays 49
2630 Certificate of Readiness 5 23-Aug-24 29-Aug-24 5 Day/Holidays 49
2650 Commissioning - Prefunctional Checklists 5 30-Aug-24 06-Sep-24 5 Day/Holidays 49
2660 SCIF Re-Accreditation 30 09-Sep-24 21-Oct-24 5 Day/Holidays 49
2670 Ready for Training 0 21-Oct-24 5 Day/Holidays 49
Phase 3 - B WingPhase 3 - B Wing 120 04-Jun-24 25-Nov-24 5 Day/Holidays 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025
MCAS IWAKUNI, JAPAN - BUILDING 7000
MODIFY HVAC SYSTEMS
Final Design Submittal Construction Schedule
Printed on 20-Jul-23
CUI
CUI
Sirron.Vessels Text Box Enclosure 2
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Text Box Secure Space
Sirron.Vessels Text Box Secure Space
Sirron.Vessels Text Box Secure Space
Sirron.Vessels Text Box Secure Space
Sirron.Vessels Text Box Secure Space
Sirron.Vessels Text Box Secure Space
Start Finish Calendar Total Float
2260 VAV System Hot Water Reheat Coils 25 04-Jun-24 10-Jul-24 5 Day/Holidays 0
2280 Outside Air/Exhaust Air System Mechanical and Electrical 25 11-Jul-24 14-Aug-24 5 Day/Holidays 0
2300 Building Control System 25 11-Jul-24 14-Aug-24 5 Day/Holidays 0
2320 Interior Finishes 30 15-Aug-24 26-Sep-24 5 Day/Holidays 0
2920 Test and Balance 10 13-Sep-24 26-Sep-24 5 Day/Holidays 0
2930 Certificate of Readiness 5 27-Sep-24 03-Oct-24 5 Day/Holidays 0
2940 Commissioning - Prefunctional Checklists 5 04-Oct-24 10-Oct-24 5 Day/Holidays 0
2950 SCIF Re-Accreditation 30 11-Oct-24 25-Nov-24 5 Day/Holidays 0
2960 Ready For Training 0 25-Nov-24 5 Day/Holidays 0
Phase 7 - ProjectCloseoutPhase 7 - Project Closeout 25 25-Nov-24 03-Jan-25 5 Day/Holidays 0
2760 Substantial Completion 0 25-Nov-24 5 Day/Holidays 0
2780 Punch List 20 26-Nov-24 26-Dec-24 5 Day/Holidays 0
2800 As-Built Drawings 10 12-Dec-24 26-Dec-24 5 Day/Holidays 0
2820 Commissioning / Owner Training 10 12-Dec-24 26-Dec-24 5 Day/Holidays 0
2840 Final Cleanup/Demobilization 15 12-Dec-24 03-Jan-25 5 Day/Holidays 0
2860 Project Finish 0 03-Jan-25 5 Day/Holidays 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025
MCAS IWAKUNI, JAPAN - BUILDING 7000
MODIFY HVAC SYSTEMS
Final Design Submittal Construction Schedule
Printed on 20-Jul-23
CUI
CUI
Sirron.Vessels Text Box Enclosure 2
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
Sirron.Vessels Rectangle
| Enclosure 2_Phasing Schedule_(CUI) MCASI Mod HVAC B7000 |
| Enclosure 2A_Phasing Schedule_(CUI) MCASI Mod HVAC B7000 |
| Enclosure 2B_Phasing Schedule_(CUI) MCASI Mod HVAC B7000 |
File details come from the government source that posted it. Updated .