This document outlines a sources sought notice for repair and construction work at a secure access building at Marine Corps Air Station Iwakuni in Japan. The Naval Facilities Engineering Command Far East seeks potential sources to upgrade the HVAC system in Building 7000 for $10-25 million. Interested contractors should demonstrate experience modifying four-pipe hydronic systems, mechanical rooms, electrical systems, and building automation to support VAV reheat and independent temperature control. Responses are due by March 28, 2024. The work must follow construction security plans, using only U.S. companies, citizens, and persons while on site with security vetting required. The contract will be firm-fixed-price for 495 days on site from May to December 2024.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Original Duration

Start Finish Calendar Total Float

MCAS Iwakuni B7000 - HVAC and Simulator ModificationsMCAS Iwakuni B7000 - HVAC and Simulator Modifications 495 09-Jan-23 03-Jan-25 5 Day/Holidays 0

Option 1 - Four Pipe Hydronic System;UnconditionedAirSystemsRemovedOption 1 - Four Pipe Hydronic System; Unconditioned Air Systems Removed 495 09-Jan-23 03-Jan-25 5 Day/Holidays 0

DesignDesign 235 09-Jan-23 15-Dec-23 5 Day/Holidays 0

1240 Begin On Site Review 0 09-Jan-23 5 Day/Holidays 0

1250 Design Review On-Site 5 09-Jan-23 13-Jan-23 5 Day/Holidays 0

1320 60% Design Submittal 8 24-Jan-23 02-Feb-23 5 Day/Holidays 0

1340 60% Review Meeting 0 23-Feb-23 5 Day/Holidays 0

1350 60% Design Resubmit 17 01-Mar-23 23-Mar-23 5 Day/Holidays 0

1355 60% Resubmit Review Meeting 0 12-Apr-23 5 Day/Holidays 0

1360 100% Design Submittal 22 13-Apr-23 12-May-23 5 Day/Holidays 0

1380 100% Review Meeting 0 12-Jun-23 5 Day/Holidays 0

1400 Advanced Final Design Submittal 15 13-Jun-23 05-Jul-23 5 Day/Holidays 0

1410 Final Design Submittal 19 06-Jul-23 01-Aug-23 5 Day/Holidays 0

1420 Construction Solicitation Meeting 0 01-Aug-23 5 Day/Holidays 0

1520 Prime Contractor Award and Contract Execution 93 02-Aug-23 15-Dec-23 5 Day/Holidays 0

ConstructionConstruction 260 18-Dec-23 03-Jan-25 5 Day/Holidays 0

Phase 0 - PreconstructionPhase 0 - Preconstruction 200 18-Dec-23 03-Oct-24 5 Day/Holidays 60

1580 Contractor Notice to Proceed 0 18-Dec-23 5 Day/Holidays 0

1590 Contractor Mobilization to MCASI 20 18-Dec-23 17-Jan-24 5 Day/Holidays 240

1596 Submittals/Procurement of Materials for Red/Blue Zones 20 18-Dec-23 17-Jan-24 5 Day/Holidays 0

1598 Construction Security Plan 20 18-Dec-23 17-Jan-24 5 Day/Holidays 240

1600 Submittals for Major Equipment 25 18-Dec-23 24-Jan-24 5 Day/Holidays 25

1620 Government Review and Approval of Submittals 25 25-Jan-24 29-Feb-24 5 Day/Holidays 25

1640 Procurement of Electrical and Mechanical Equipment 150 01-Mar-24 03-Oct-24 5 Day/Holidays 25

1660 Procurement of Interior Finishes 150 01-Mar-24 03-Oct-24 5 Day/Holidays 60

1700 Kickoff Meeting with Key Subcontractors 0 18-Jan-24 5 Day/Holidays 0

Phase 1 - Mech Rooms 5-7 -Hydronic/UpstairsWorkPhase 1 - Mech Rooms 5-7 - Hydronic/Upstairs Work 80 18-Jan-24 10-May-24 5 Day/Holidays 160

2000 Selective Demolition 10 18-Jan-24 31-Jan-24 5 Day/Holidays 0

2010 Extend Equipment Pads of Existing Air Handler Units 5 01-Feb-24 07-Feb-24 5 Day/Holidays 0

2020 Isolate Existing Hydronics for New Chilled Water System 5 01-Feb-24 07-Feb-24 5 Day/Holidays 0

2060 New Heating Coils in Existing Air Handling Units 5 08-Feb-24 14-Feb-24 5 Day/Holidays 0

2080 Modify Ductwork 5 08-Feb-24 14-Feb-24 5 Day/Holidays 0

2100 Modifications to Piping Headers 5 15-Feb-24 22-Feb-24 5 Day/Holidays 0

2120 New Hot Water Pumps 5 15-Feb-24 22-Feb-24 5 Day/Holidays 0

2140 New Hydronic Piping for New Hot Water System 10 15-Feb-24 29-Feb-24 5 Day/Holidays 0

2160 New 1200 Amp 208V Service for HVAC Upgrades 10 15-Feb-24 29-Feb-24 5 Day/Holidays 0

3020 Test and Balance 10 01-Mar-24 14-Mar-24 5 Day/Holidays 0

3030 Certificate of Readiness 5 15-Mar-24 22-Mar-24 5 Day/Holidays 0

3040 Commissioning - Prefunctional Checklists 5 25-Mar-24 29-Mar-24 5 Day/Holidays 0

3050 SCIF Re-Accreditation 30 01-Apr-24 10-May-24 5 Day/Holidays 160

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025

MCAS IWAKUNI, JAPAN - BUILDING 7000

MODIFY HVAC SYSTEMS

Final Design Submittal Construction Schedule

Printed on 20-Jul-23

Remaining Level of Effort

Actual Level of Effort

Actual Work

Remaining Work

Critical Remaining Work

Milestone Prime Contract #: N62742-20-D-001 Date Revision Checked Approved

02-Feb-22 60% Submittal

27-Mar-23 60% Resubmittal

12-May-23 100% Submittal

26-Jul-23 Final Design Submittal

CUI

CUI

Sirron.Vessels Text Box Enclosure 2

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Start Finish Calendar Total Float

Phase 2 - Portions ofA,C,D,E and FWingsPhase 2 - Portions of A, C, D, E and F Wings 49 01-Apr-24 07-Jun-24 5 Day/Holidays 141

2180 VAV System Hot Water Reheat Coils 20 01-Apr-24 26-Apr-24 5 Day/Holidays 0

2200 Outside Air/Exhaust Air System Mechanical and Electrical 20 29-Apr-24 24-May-24 5 Day/Holidays 0

2220 Building Control System 15 06-May-24 24-May-24 5 Day/Holidays 0

2240 Interior Finishes 24 06-May-24 07-Jun-24 5 Day/Holidays 0

2970 Test and Balance 10 06-May-24 17-May-24 5 Day/Holidays 0

2980 Certificate of Readiness 5 20-May-24 24-May-24 5 Day/Holidays 0

2990 Commissioning - Prefunctional Checklists 5 28-May-24 03-Jun-24 5 Day/Holidays 0

3010 Ready For Training 0 07-Jun-24 5 Day/Holidays 141

Phase 4 - D WingPhase 4 - D Wing 105 03-Jun-24 31-Oct-24 5 Day/Holidays 41

1860 HVAC Upgrade 30 03-Jun-24 16-Jul-24 5 Day/Holidays 41

1880 Electrical Modificaions 15 25-Jun-24 16-Jul-24 5 Day/Holidays 41

1900 Control System Modification 15 25-Jun-24 16-Jul-24 5 Day/Holidays 41

1910 HVAC Test and Balance/Commissioning 10 17-Jul-24 30-Jul-24 5 Day/Holidays 41

1920 Interior Finishes and FF&E 15 31-Jul-24 20-Aug-24 5 Day/Holidays 41

2870 Test and Balance 10 21-Aug-24 04-Sep-24 5 Day/Holidays 41

2880 Certificate of Readiness 5 05-Sep-24 11-Sep-24 5 Day/Holidays 41

2890 Commissioning - Prefunctional Checklists 5 12-Sep-24 18-Sep-24 5 Day/Holidays 41

2900 SCIF Re-Accreditation 30 19-Sep-24 31-Oct-24 5 Day/Holidays 41

2910 Ready For Training 0 31-Oct-24 5 Day/Holidays 41

Install of New AirHandlers in MehcanicalRoom forF-35 SimulatorsInstall of New Air Handlers in Mehcanical Room for F-35 Simulators 35 04-Oct-24 25-Nov-24 5 Day/Holidays 25

2075 Install New Air Handlers in Mech Room for F-35 Simulators 35 04-Oct-24 25-Nov-24 5 Day/Holidays 25

Phase 5 - C WingPhase 5 - C Wing 105 03-Jun-24 31-Oct-24 5 Day/Holidays 41

2370 Protect C-Wing Simulators 10 03-Jun-24 14-Jun-24 5 Day/Holidays 41

2380 VAV System Hot Water Reheat Coils 15 17-Jun-24 09-Jul-24 5 Day/Holidays 41

2400 Electrical Modification 15 17-Jun-24 09-Jul-24 5 Day/Holidays 41

2420 Outside Air/Exhaust Air System Mechanical and Electrical 12 10-Jul-24 25-Jul-24 5 Day/Holidays 41

2440 Building Control System 12 10-Jul-24 25-Jul-24 5 Day/Holidays 41

2460 Interior Finishes 18 26-Jul-24 20-Aug-24 5 Day/Holidays 41

2462 Test and Balance 10 21-Aug-24 04-Sep-24 5 Day/Holidays 41

2465 Certificate of Readiness 5 05-Sep-24 11-Sep-24 5 Day/Holidays 41

2468 Commissioning - Prefunctional Checklists 5 12-Sep-24 18-Sep-24 5 Day/Holidays 41

2478 SCIF Re-Accreditation 30 19-Sep-24 31-Oct-24 5 Day/Holidays 41

2488 Ready For Training 0 31-Oct-24 5 Day/Holidays 41

Phase 6 - G WingPhase 6 - G Wing 97 03-Jun-24 21-Oct-24 5 Day/Holidays 49

2560 VAV System Hot Water Reheat Coils 10 03-Jun-24 14-Jun-24 5 Day/Holidays 49

2580 Outside Air/Exhaust Air System Mechanical and Electrical 15 17-Jun-24 09-Jul-24 5 Day/Holidays 49

2600 Building Control System 12 10-Jul-24 25-Jul-24 5 Day/Holidays 49

2620 Interior Finishes 10 26-Jul-24 08-Aug-24 5 Day/Holidays 49

2625 Test and Balance 10 09-Aug-24 22-Aug-24 5 Day/Holidays 49

2630 Certificate of Readiness 5 23-Aug-24 29-Aug-24 5 Day/Holidays 49

2650 Commissioning - Prefunctional Checklists 5 30-Aug-24 06-Sep-24 5 Day/Holidays 49

2660 SCIF Re-Accreditation 30 09-Sep-24 21-Oct-24 5 Day/Holidays 49

2670 Ready for Training 0 21-Oct-24 5 Day/Holidays 49

Phase 3 - B WingPhase 3 - B Wing 120 04-Jun-24 25-Nov-24 5 Day/Holidays 0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025

MCAS IWAKUNI, JAPAN - BUILDING 7000

MODIFY HVAC SYSTEMS

Final Design Submittal Construction Schedule

Printed on 20-Jul-23

CUI

CUI

Sirron.Vessels Text Box Enclosure 2

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Text Box Secure Space

Sirron.Vessels Text Box Secure Space

Sirron.Vessels Text Box Secure Space

Sirron.Vessels Text Box Secure Space

Sirron.Vessels Text Box Secure Space

Sirron.Vessels Text Box Secure Space

Start Finish Calendar Total Float

2260 VAV System Hot Water Reheat Coils 25 04-Jun-24 10-Jul-24 5 Day/Holidays 0

2280 Outside Air/Exhaust Air System Mechanical and Electrical 25 11-Jul-24 14-Aug-24 5 Day/Holidays 0

2300 Building Control System 25 11-Jul-24 14-Aug-24 5 Day/Holidays 0

2320 Interior Finishes 30 15-Aug-24 26-Sep-24 5 Day/Holidays 0

2920 Test and Balance 10 13-Sep-24 26-Sep-24 5 Day/Holidays 0

2930 Certificate of Readiness 5 27-Sep-24 03-Oct-24 5 Day/Holidays 0

2940 Commissioning - Prefunctional Checklists 5 04-Oct-24 10-Oct-24 5 Day/Holidays 0

2950 SCIF Re-Accreditation 30 11-Oct-24 25-Nov-24 5 Day/Holidays 0

2960 Ready For Training 0 25-Nov-24 5 Day/Holidays 0

Phase 7 - ProjectCloseoutPhase 7 - Project Closeout 25 25-Nov-24 03-Jan-25 5 Day/Holidays 0

2760 Substantial Completion 0 25-Nov-24 5 Day/Holidays 0

2780 Punch List 20 26-Nov-24 26-Dec-24 5 Day/Holidays 0

2800 As-Built Drawings 10 12-Dec-24 26-Dec-24 5 Day/Holidays 0

2820 Commissioning / Owner Training 10 12-Dec-24 26-Dec-24 5 Day/Holidays 0

2840 Final Cleanup/Demobilization 15 12-Dec-24 03-Jan-25 5 Day/Holidays 0

2860 Project Finish 0 03-Jan-25 5 Day/Holidays 0

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecJan 2023 2024 2025

MCAS IWAKUNI, JAPAN - BUILDING 7000

MODIFY HVAC SYSTEMS

Final Design Submittal Construction Schedule

Printed on 20-Jul-23

CUI

CUI

Sirron.Vessels Text Box Enclosure 2

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Sirron.Vessels Rectangle

Enclosure 2_Phasing Schedule_(CUI) MCASI Mod HVAC B7000
Enclosure 2A_Phasing Schedule_(CUI) MCASI Mod HVAC B7000
Enclosure 2B_Phasing Schedule_(CUI) MCASI Mod HVAC B7000

File details come from the government source that posted it. Updated .