A/E SCOPE OF WORK

PROFESSIONAL ARCHITECTURAL/ENGINEERING SERVICES

ARGONNE UTILITIES UPGRADE (AU2) – SUBPROJECT 1

REVISION 6

JULY 19, 2021

Argonne Utilities Upgrade (AU2) – Subproject 1 Revision 6, July 19, 2021

Document No.: JMLT-259-S-T009

TABLE OF CONTENTS TABLE OF CONTENTS

1 GENERAL SCOPE

2 SAFETY, COST, AND SCHEDULE REQUIREMENTS

3 DESIGN OBJECTIVES

4 GENERAL A/E ARCHITECT-ENGINEER AND OTHER CONSULTANTS INTERFACE

5 GENERAL A/E RESPONSIBILITIES

6 SITING VERIFICATION SERVICES [BASE CONTRACT]

7 PRELIMINARY DESIGN SERVICES [CONTRACT OPTION NO. 1]

8 FINAL DESIGN SERVICES [CONTRACT OPTION NO. 2]

9 CONSTRUCTION PHASE SERVICES [CONTRACT OPTION NO. 3]

10 BUILDING INFORMATION MODELING SCOPE OF SERVICES

11 QUALITY ASSURANCE REQUIREMENTS

12 PROJECT ADMINISTRATION

13 SUPPORTING DOCUMENTS (INCLUDED HEREIN BY REFERENCE)

1 GENERAL SCOPE

1.1 Project Background: Argonne National Laboratory (Argonne) proposed a large-scale utility repair project, Argonne Utilities Upgrade (AU2) Project for Department of Energy Science Laboratory Infrastructure funding, to address numerous deficiencies associated with aging infrastructure. The AU2 Project will replace, repair, and upgrade several critical utility systems to eliminate deferred maintenance and reduce the risk of unplanned service outages, safety concerns, and other impacts to operations. This project will allow for the continued support of mission critical programmed growth, increased site resiliency, and integration of data analytics/machine learning.

The AU2 project achieved Critical Decision-0, “Approval of Mission Need” in Fiscal Year 2019, which resulted in a scope focused on the most critical repairs and investments associated with several major utility systems. Argonne hired Jacobs Engineering Group, Inc. to complete a Conceptual Design Report (CDR) for the AU2 project which included the summary of information from previous reports, studies, and new concept designs. The CDR and Preliminary Fire Protection Assessment (PFPA) are enclosed, reference section 13.

After analysis of the CDR and review with the Department of Energy (DOE), Argonne determined that the project will be designed and implemented in (2) subprojects. Subproject 1 base scope consists of new combined steam and chilled water plant and Subproject 2 encompasses new piping upgrades. This Scope of Work is for the design services associated with only Subproject 1 of the AU2 project.

The CDR analyzed (6) steam and chilled water plant alternatives. The design of the combined plant shall be based on Alternative 3B as recommended in the CDR, which is a new combined steam and chilled water plant with magnetic bearing. Reference the CDR for details on this alternative.

1.2 The Architect/Engineer (referred to hereinafter as A/E) will furnish the personnel, facilities, equipment, materials, and supplies necessary to perform Siting Verification, Preliminary Design, Final Design, and Construction Phase Services required for the implementation of AU2 - Subproject 1. The scope of AU2 - Subproject 1 is the construction of a new combined steam and chilled water plant at Argonne. The Argonne Facilities Design Guide (reference Section 13) defines the appropriate design codes for AU2 – Subproject 1.

1.3 The A/E’s services shall include all normal and customary professional services required of a qualified, professionally licensed A/E and its consultants in connection with the design, procurement, and construction phases of the project. The A/E shall furnish or provide the architectural and engineering services necessary to design the project in accordance with Argonne’s requirements as outlined herein, as well as in the CDR, PFPA and other specified supporting documents referenced in Section 13 and the CDR. The A/E agrees to prepare drawings, specifications, and other documents in which the A/E designates complete, definite, and clear assemblies and materials of construction. The A/E shall call for no result unless the A/E has furnished complete, definite, and clear drawings and specifications as to the construction results to be achieved. In particular, the A/E shall require of its consultants the level of quality recommended by industry standards.

2 SAFETY, COST, AND SCHEDULE REQUIREMENTS

2.1 Safety. The design shall endeavor to support the Lab’s safety goal of zero lost work time accidents. The design shall support safe laboratory operations by supporting compliance with Argonne’s Environment, Safety and Health policies and procedures.

2.2 Target Construction Contract Price. The construction cost range of the AU2 -

Subproject 1 is $95M to $105M. The targeted cost for purposes of design shall be $100M. Options and scope enhancements that affect the construction cost will not warrant additional compensation to the A/E.

2.3 Additive Options. The A/E shall include 10 to 14 additive options of varying size to support incremental Construction Bid Options ranging from 90% to 110% of the targeted construction contract price. The A/E and Argonne will work together to identify specific additive/alternative items. A preliminary list of additive options with identifiers as defined in the CDR Section 3.11 include:

2.3.1 CHW-01 Building 450 Chiller Replacement;

2.3.2 CHW-02 Building 450 Ice Chiller Modification;

2.3.3 CHW-03 Building 450 Condenser Water Pump Replacement;

2.3.4 CHW-04 Building 450 Primary Chilled Water Pump Replacement;

2.3.5 CHW-05: Building 450 Filtration;

2.3.6 CHW-07a (not in CDR): Building 371 Chiller Replacement (CH4);

2.3.7 CHW-08: Building 371 Chilled Water Pump Replacement;

2.3.8 CHW-10: Building 371 Controls Upgrades;

2.3.9 CHW-15: Building 528 Filtration; and

2.3.10 CHW-16: CHW Metasys Controllers Upgrades

2.3.11 CHW-17: Smart Metering Upgrades

2.4 Schedule. This plan is tentative in nature and will be reviewed and updated periodically as the project management plan is finalized. AU2 – Subproject 1 is currently planned to be delivered as a single construction package. Based on current DOE approval/funding forecasts, it is anticipated that design will commence in May 2021.

The in-field construction phase is anticipated to last for 30 months, followed by four months for punch list work. The agreement for A/E schedule requirements should be referenced. The following table lists the schedule of deliverables and milestones:

Deliverables a ID Description Date Begin Design 11/29/2021 SC-1 Siting Confirmation Complete 04/01/2022 PD-1 50% Preliminary Design Progress Review (PDR, FPA, Drawings, Renderings) 06/10/2022 PD-1a 50% Preliminary Design Progress Cost Estimate (Estimate) 07/01/2022 PD-2 95% Preliminary Design (PDR, FPA, Drawings, Outline Specs, Renderings) 09/09/2022 PD-2a 95% Preliminary Design Cost Estimate (Estimate) 09/30/2022 PD-3 100% Preliminary Design (PDR, FPA, Drawings, Outline Specs, Renderings) 10/28/2022 Begin Final Design 10/31/2022 FD-1 50% Final Design Progress Review (FPA, Drawings, Specs, BOD, Renderings) 02/10/2023 FD-1a 50% Final Design Progress Cost Estimate (Estimate) 03/03/2023 FD-2 95% Final Design (FPA, Drawings, Specs, BOD, Renderings) 06/02/2023 FD-2a 95% Final Design Cost Estimate 06/23/2023 FD-3 100% Final Design (FPA, Drawings, Specs, BOD) – Proposal Set 07/14/2023 FD-4 100% Final Design (FPA, Drawings, Specs, BOD, BIM) – Construction Set 10/13/2023 Award Construction Contract 02/16/2024 Begin Construction Complete Construction (Beneficial Occupancy) CA-1 Record Drawings (FPA, Drawings, Specs, BOD, BIM) a PDR = Preliminary Design Report and FPA = Fire Protection Assessment.

2.4.1 At the start of the base contract work and at the start of each option’s contract work, the A/E is to provide a resource-loaded schedule of its work for Argonne’s review and approval. In addition, a schedule of values by month for the base contract and all options will be required. The schedule will be used to track cost and schedule progress using earned value measurement techniques.

3 DESIGN OBJECTIVES

3.1 The proposed combined steam and chilled water plant is to be designed as a state-of-the-art facility, enabling Argonne to meet its mission need to support scientific advancement through reliable, redundant, maintainable, and flexible utility systems.

3.2 The combined steam and chilled water plant is to be designed to provide the maximum practical flexibility to support changes in projected laboratory loads.

Argonne’s objective is for the combined plant design to provide sufficient flexibility to accommodate changes in projected site loads from future research buildings with minimal modification. One concept that illustrates the flexibility requirement includes provisions in the steam and chilled water system design to allow for expansion of the new heating and cooling systems to accommodate campus expansion.

3.3 The design of AU2 – Subproject 1 project must support compliance with DOE’s and Argonne’s environment, health, and safety requirements, both during construction and during operation. Reference Preliminary Hazard Analysis Report (PHAR) included with this Scope of Work.

3.4 Other AU2 – Subproject 1 design objectives include the following:

3.4.1 Economic Balance. The elements of the design should attain economic balance, commensurate with available funds and design objectives, between initial construction costs, building permanence, and operational maintenance costs.

3.4.2 Technical Adequacy. The elements of the design should achieve technical adequacy with respect to conventional combined utility plants.

3.4.3 Nature of Space. The design of the combined plant should comply with the requirements outlined in the Argonne Facilities Design Guide and in Section 3 of the CDR.

3.4.4 Completion on Schedule. The elements of the design should support, and not preclude, on-schedule construction of the facility.

3.4.5 Maintainability and Sustainability. The elements of the design should incorporate maintainability, energy efficiency, resiliency and environmental sustainability into the design solution. Optimal economy in operation, maintenance, and energy utilization will be sought. The design of the combined plant must comply with the Guiding Principles for Sustainable Federal Buildings requirements as detailed in Section 3.5.

3.4.6 Cleanliness. The A/E is to incorporate measures (such as special finishes, protocols for materials cleaning during construction, etc.) to achieve maximum overall cleanliness of the entire building at occupancy and during operation.

3.4.7 Environmental Considerations. The A/E shall propose measures to avoid adverse environmental effects and meet applicable national standards and Argonne guidelines. The design of AU2 – Subproject 1 must take these measures into account.

3.5 Sustainability Requirements. The design of AU2 – Subproject 1 must comply with the

Guiding Principles requirements. Argonne is a federal facility, and as such, this project is required to comply with Executive Order 13834, Efficient Federal Operations, dated May 17, 2018; DOE O 436.1, Departmental Sustainability, dated May, 2, 2011; and the Council on Environmental Quality Guiding Principles for Sustainable Federal Buildings and Associated Instructions, dated February 2016. The project is required to achieve a level of energy efficiency that is 30% or better than the current American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE) 90.1 standard, as well meet other sustainable building requirements outlined in Guiding Principles. As a result, the A/E is expected to utilize energy-efficient, sustainable design and construction principles to achieve the Guiding Principles. Reference the Guiding Principles checklist (2016 Guiding Principles Checklist for New Construction and Modernization v2.0) included in the CDR Appendix G for details pertaining to the AU2 project. The project will not pursue LEED certification.

3.5.1 Decarbonization – In response to recent federal decarbonization goals, the AU2 project must consider incorporating decarbonization strategies. The A/E shall work with the Argonne team to consider a minimum of three (3) decarbonization strategies.

Additionally, the A/E shall ensure that the project design is flexible and supports Argonne’s ability to institute future decarbonization efforts post-project, including emerging technologies.

3.6 An additional design objective not discussed in the CDR includes the design & construction of utilities for the existing Combined Heat and Power (CHP) Building (Building 109) so that it can operate independently from the existing Boiler House (Building 108). These new utilities could come from the new combined plant as needed, or any other source that the A/E may identify. CHP system needs identified thus far include:

3.6.1 Steam – The steam line will need to be rerouted and connected back into the two steam headers past the Boiler House. It is currently connected inside the Boiler House.

3.6.2 Condensate – The condensate return system does not go directly to the CHP but it does feed the feedwater system in the Boiler House that does go to the CHP.

3.6.3 Feedwater – The feedwater will need to be routed from the new steam plant to the

CHP.

3.6.4 Boiler and Turbine Controls – The CHP process control system is pulled into the

Boiler House manned centralized control room. The CHP process controls will need to be pulled into the new steam plant.

3.6.5 Blowdown – The CHP blowdown goes to the Boiler House. This will need to be routed into the new steam plant from the CHP.

3.6.6 Air – Air compressors are utilized from the Boiler House to drive equipment in the

CHP. An air line will need to be run from the new steam plant to the CHP.

3.6.7 Domestic Water – Domestic water is used in the CHP for a janitor’s closet and at hose stations to allow washing the floor. A new source of water would need to be run from the new plant to the CHP.

3.6.8 Fire Protection – Fire Protection water is domestic water that is fed into the fire protection system of piping and is currently supplied from the Boiler House to the

CHP.

3.6.9 Fire Protection/PA System – The CHP is covered under the Boiler House Fire Dept fire detection system and Argonne PA announcement system. This would need to come from the new steam plant.

3.6.10 Electric – The CHP will need electrical feeds to run its equipment. Once the CHP is online it can feed the Boiler House electrically if needed. The throw-over transformer may need to be replaced in CHP. Also, the Boiler House diesel generator is used for black start capability of either plant.

3.6.11 Argonne Intranet – There is an Argonne intranet cabinet located in the CHP that may connect to whole system through Boiler House.

3.6.12 A preference for a Connecting Corridor/Hallway – The CHP and Boiler House have the above listed system connected through a corridor/hallway between the two buildings. The new steam plant ideally would require a similar corridor/hallway to carry these systems and allow Utilities Ops personnel to perform required walkdowns between the two plants. This will also allow for quick response to alarming equipment because operators will not need to go outside and possibly encounter slippery conditions during bad weather.

3.7 Other requirements are listed in the CDR and PFPA.

4 GENERAL A/E ARCHITECT-ENGINEER AND OTHER CONSULTANTS

INTERFACE

4.1 Project Team Cooperation. It is Argonne's expectation that all parties will cooperate to achieve a successful outcome. The A/E, Construction Manager (CM), Argonne, Commissioning Agent, and other contractor(s)/consultant(s) shall work as a team to achieve successful completion of the project. Each team member shall communicate with all other team members to assure overall coordination, cooperation, and efficiency. Each team member shall cooperate fully and coordinate fully with each other team member in order to achieve project development in an expeditious and economical manner.

4.1.1 Commissioning will be an integral part of the design and construction effort.

Argonne will procure under separate contract the services of an independent commissioning agent. The A/E shall coordinate his efforts to support the commissioning agent through all phases of the project.

4.1.2 Independent Material Inspection and Testing will also be an integral part of the design and construction effort. Argonne will procure, under separate contract, the services of a materials inspection / testing company (soil, compaction, concrete, steel, and welding). A copy of the testing reports will be given to the A/E who will be required to evaluate any non-conformances.

4.2 Argonne will provide construction management services for the design and construction phases of this project. This service will be performed by Argonne personnel, outside consultants retained by Argonne, or a combination thereof.

4.3 The tasks to be performed by the CM during the design and construction phases of the project may consist of any of the services described below:

4.3.1 The design-phase services will include, but are not limited to, review of design documents for constructability, completeness, and consistency;

development of schedules and independent cost estimates;

recommendation of alternative solutions when design details affect construction feasibility, cost, or schedules; and assistance during construction bidding and contract award.

4.3.2 The construction-phase services to be performed by the CM will include, but are not limited to, planning and oversight; schedule and cost control support;

inspection of construction contractors’ work; submittal tracking; and punch list management.

4.4 Several of the tasks mentioned above will require close interaction between the A/E and

CM. Certain tasks for which the CM is responsible will require input from the A/E and vice versa. Therefore, for the orderly operation of this relationship, each party will be held fully accountable for the quality and timeliness of their respective inputs. Any outstanding difference of opinion will be promptly brought to the attention of the Argonne Project Manager for resolution.

4.5 The CM and/or consultants will review design documents for constructability, completeness, consistency, and the economics of materials and systems. This review will be carried out on behalf of Argonne, and the comments will be directed to the Argonne Project Manager.

5 GENERAL A/E RESPONSIBILITIES

5.1 The completed design shall be clear, definite, comprehensive, and developed to appropriate scales of detail so as to be conducive to narrow-range equipment and construction bidding. The A/E is responsible for producing a complete set of drawings, design narrative/analysis, calculations, sample boards, and specifications in accordance with professional standard practices and Argonne requirements identified in this Agreement.

5.2 Safety. A/E employees performing field work (e.g., inspections) on the Argonne site will perform such work in compliance with Argonne Environment, Safety and Health requirements. The A/E will be required to prepare a Job Safety Analysis for Argonne’s review and approval covering its field work. Any A/E employees who will perform field work will be required to complete an Argonne safety orientation. Those A/E employees performing field work may also be required by Argonne to attend other safety training for specific hazards encountered during the work.

5.3 The A/E is responsible for designing the project to meet the program requirements in accordance with all contract terms and conditions.

5.3.1 The A/E shall prepare estimates of the construction contract price at various times during the design process that are sufficient to ensure that the design remains within Argonne’s construction contract price limit as the design is developed. The estimates are required to comply with GAO requirements as outlined in the GAO Cost Estimating and Assessment Guide, included as a supporting document. The A/E shall maintain a current cost table throughout the design and provide the status on a monthly basis to the Project Manager to ensure that cost targets are maintained. At a minimum, the A/E shall prepare and submit construction contract price estimates at the following design milestones:

5.3.1.1 50% Preliminary Design Progress Cost Estimate (PD-1a)

5.3.1.2 95% Preliminary Design Cost Estimate (PD-2a)

5.3.1.3 50% Final Design Progress Cost Estimate (FD-1a)

5.3.1.4 95% Final Design Cost Estimate (FD-2a)

5.3.2 The AU2 funding profile may create the need for a “speed limit” to be placed on the general construction contractor at certain points during construction.

Working with the Argonne team to obtain the latest funding information, the A/E’s cost estimate should consider AU2 funding limitations and any construction schedule inefficiencies that may result from a lack of available funding. The A/E should consider ideas to help mitigate these schedule inefficiencies for discussion with Argonne.

5.3.3 For each design milestone estimate, the A/E shall coordinate with the CM as necessary to reconcile the A/E’s and CM’s respective estimates to ensure accuracy and agreement. The A/E is required to participate positively in the reconciliation of estimated construction contract prices with the CM’s estimator.

5.3.4 If the reconciled construction contract price estimate at a design milestone exceeds Argonne’s estimated construction contract price limit, the A/E shall identify and incorporate the changes necessary to bring the design into compliance. The design must remain in compliance with the scope described herein. No review of the A/E’s recommended changes by Argonne shall relieve the A/E of its contractual responsibility to design AU2 - Subproject 1 within the estimated construction contract price limit. No reliance on the CM’s estimate information shall relieve the A/E of its contractual responsibility to design AU2 — Subproject 1 within the estimated construction contract price limit.

5.3.5 If the reconciled construction contract price estimate at 95% Preliminary Design

(PD-2a) exceeds Argonne’s estimated construction contract price limit, the A/E shall not proceed with the next design phase (Final Design) until it has identified and received Argonne concurrence on reasonable changes necessary to bring the design into compliance.

5.3.6 In the event that the A/E does not agree with the accuracy of the CM’s estimate or is unable to reconcile the CM’s estimate with its own, the A/E shall meet with the CM’s estimator and attempt to resolve the outstanding issues. If the A/E is unable to resolve its differences with the CM’s estimate, Argonne will determine whether the estimate submitted by the CM or the estimate submitted by the A/E shall be utilized for purposes of evaluating the A/E's potential obligation to modify the design to bring the design within Argonne's estimated construction contract price limit. Argonne's decision in this regard shall be final.

5.3.7 Additionally, in the event that the A/E and CM are unable to reconcile their cost estimates and that such inability to reconcile the cost estimates is resulting, in the opinion of Argonne, in a materially adverse impact on either the design or construction schedule, Argonne shall determine whether the estimate prepared by the CM or the A/E shall be utilized for purposes of evaluation of the A/E's potential obligation to modify the design to bring the design within Argonne's estimated construction contract price limit. Argonne's decision in this regard shall be final.

5.4 The A/E will be required to comply with relevant portions of DOE Order 413.3B, “Program and Project Management for the Acquisition of Capital Assets” (Reference Section 13).

5.5 The A/E’s services shall consist of the design and specification of materials and assemblies:

• Building and site infrastructure survey, coordination and existing condition verification;

• Modifications and reconfiguration of existing buildings, systems and site features;

• Architectural systems;

• Structural systems;

• Geotechnical consultant

• Fire protection and life safety;

• Civil systems (including necessary campus utilities, extensions, and street improvements);

• Mechanical systems (heating, cooling, ventilation, plumbing, fire protection, temperature control systems, utilities metering, campus and building mechanical utilities, campus mechanical utilities coordination, campus and building automation network);

• Electrical systems (including standard and special voltage systems, security and/or life safety systems, electrical metering, and campus electrical utilities);

• Built-in equipment (including storage racks, built-in casework, and other fixed items);

• Graphics and signage;

• Furniture, fixtures & equipment (including work station equipment/desks, conference tables, seating, open office partitions, etc.);

• Lighting;

• Landscaping;

• Interior design and finishes;

• Code Analysis;

• Audio Visual Systems

• Building security

• Information technology and communications, including building automation systems;

• Cost estimating;

• Sustainability compliance (Guiding Principles)

• Environmental, safety and health compliance

5.6 The A/E is responsible for confirming that all design documents are coordinated at each phase of the design process and prior to completion of the Final Design phase so that all interfaces between system components and equipment are clearly shown in design drawings and are cohesive, without exception.

5.7 The project will utilize a web-based project management control system (PMCS). The system will include the ability to track project information, such as requests for information, and submittals, and provide various formatted reports as required by Argonne. The web-based PMCS shall be Prolog Manager (by Meridian) or a similar tool.

Subsequent to award of the contract, the A/E will be provided with a manual describing required levels of participation in the elements of the PMCS to be used to support the project. At a minimum, the PMCS will be used as the basis for the project’s Request for Information (RFI) and Submittal processes.

5.7.1 The A/E shall participate in project processes, such as Design Reviews, in accordance with project-specific procedures by Argonne.

5.8 Construction Field Observation and Inspection

5.8.1 The A/E shall provide an A/E Project Representative, to visit the construction site for not less than one eight-hour day per week throughout the duration of construction, who shall be approved by Argonne and shall not be removed prior to final completion of the project, except for reasonable cause, unless approved or requested by Argonne. This Project Representative will attend regular weekly progress meetings. The Project Representative shall be resident in the Chicago metropolitan area and shall maintain an office in the Chicago metropolitan area throughout the course of the project.

5.9 Interior Design/Wayfinding

5.9.1 The A/E shall provide Interior Design and Wayfinding services for the proposed facility. Interior design shall consist of all essential and non- essential or code required Furniture, Fixtures and Equipment (e.g. specialty finishes or features, office systems, conference room(s) furniture, break room furniture, etc.)

5.10 Audio Visual Equipment

5.10.1 Argonne will select the audio/video (A/V) components, but the A/E will design and specify the infrastructure associated with the A/V components and typically installed by the construction contractor: “in-wall” systems including electrical, data, and mountings.

5.11 Building Information Modeling Requirements. Building Information Modeling; “BIM” is defined as the process and virtual model of the building using software such as REVIT or equivalent for object-based design, 3D coordination of technical disciplines, interactive detection of clashes, and improved communication in the interest of providing improved design, construction, and life-cycle durability and operability of the facility. The A/E shall utilize BIM software, processes and methodology for all disciplines throughout the design process. A coordinated or integrated model is required to coordinate clashes and interferences. BIM requirements are detailed in Section 10 of this Scope of Work.

5.12 Energy Modeling. Energy modeling software (CDS Trace700, latest version) shall be utilized to demonstrate building energy performance meets the above stated requirements. Provide final model results in both pdf and native files to Argonne.

6 SITING VERIFICATION SERVICES [BASE CONTRACT]

6.1 Scope. During the Conceptual Design phase, multiple locations were studied for the combined steam and chilled water plant and evaluated with Argonne personnel. The analysis and the selected area for the combined plant is documented in Section 3.5 of the CDR. In addition, reference site map below created by Argonne that identifies potential sites in more detail. During the Siting Verification stage, the A/E shall finalize the selected location as required to move on the Preliminary Design Phase.

6.2 As part of this phase, the A/E shall determine and document any demolition of support buildings or utility structures and site reconfiguration that may be required to accommodate the selected plant location. The extent of demolition and/or reconfiguration scope will impact Argonne’s final decision for the plant location. A Space Analysis and Programming Document (SAP) that focuses on the “100 Area” of Argonne was compiled in 2017 as part of a Physical Plant Consolidation and Modernization (PPCM) Project, reference Section 13.

This study includes information on existing buildings located at the selected area for the combined plant and a list of buildings that are proposed to be demolished. In addition to the buildings listed in this study, Buildings 145 and 146 are currently being considered to be demolished. The map included above takes into consideration the buildings to be demolished.

6.3 Siting verification shall include sample geotechnical soil borings to confirm acceptable soil qualities and CCDD testing to support confirming that future construction spoils can be disposed of at an off-site landfill. Geotechnical consultant services and testing shall be included in the A/E’s scope.

6.4 The expected deliverables for this phase are as follows:

• Finalized siting plan that the Preliminary Design will be based on;

• Narrative and conceptual drawings documenting the demolition and site modification required for the new combined plant; and

• Geotechnical report with soil borings test result.

7 PRELIMINARY DESIGN SERVICES [CONTRACT OPTION NO. 1]

7.1 In Preliminary Design (PD), the design will be defined in greater detail, and drawings for the approved project concept will be expanded with more detailed information, together with additional required drawings. Also, descriptive information that has been further refined and more detailed outline specifications will be developed that will serve as the firm basis to proceed toward final design. The A/E shall use the CDR, PFPA and finalized siting plan as the requirements for preliminary design. The AE shall also incorporate requirements from the CDR supporting documents and the CDR internal review comments and responses referenced in section 13.

7.2 The A/E will conduct preliminary design activities, including but not limited to the following:

7.2.1 Preparing engineering calculations and conducting computer modeling to size the building’s utilities and systems. The various technical components and conventional building systems shall be reviewed and calculations performed so that preliminary sizing can be performed on the required floor space for the systems’ components (e.g., framing and floor members, supply and return air ducts, air handling systems and ratings, piping runs, conduits, cables, transformers, and switchgear).

7.2.2 Fully evaluating and formalizing the scope from the conceptual design into a feasible and workable preliminary design.

7.2.3 Completing a survey of the selected site.

7.2.4 Preparing drawings that are appropriately detailed for Preliminary Design.

Drawings of all building elements, systems, site, utilities, and other elements will be developed in sufficient depth and detail so that the drawings clearly illustrate all items; drawings may be single-line and shall, at a minimum, consist of a title sheet with abbreviations/symbols, Argonne location plan, site plan, civil, landscaping, architectural, interior finishes and colors, structural, HVAC, plumbing, fire protection, electrical, special systems, materials, schematics, schedules, diagrams, and necessary elevations and cross sections.

7.2.5 Completing code analyses to identify and address security, safety hazards, risks, life safety, and fire protection.

7.2.6 Ensuring that provisions are made for the disabled and for future flexibility of the combined plant’s functionality.

Preparing an outline specification to provide sufficient statements and details to illustrate the principal materials to be used.

7.2.7 Preparing a preliminary design-level cost estimate with quantities and unit costs for each intended type of material, equipment item, and system to verify and monitor compliance to the project budget.

7.2.8 The A/E is to provide assistance to the CM in preparing independent cost estimates and schedules. This assistance includes providing preliminary design information to the CM for the development of preliminary estimates of construction labor, equipment, and material quantities; and identify long-lead procurement or other potential labor or material supply problems and more accurate project cost estimates.

7.2.9 Providing input to the CM as required for the CM’s development of a preliminary construction schedule (utilizing the Critical Path Method).

7.2.10 Providing specifications and drawings for identified long-lead procurement items.

7.3 The A/E will prepare the Preliminary Design Report (PDR) for the facility that will incorporate the following.

7.3.1 An Executive Summary including project overview, program, and scope.

7.3.2 A General Project Description section including functional area program, criteria, basis, and justification for various design elements, systems, and approaches.

7.3.3 A Site Analysis section including project location, campus context, landscape, and parking.

7.3.4 A Basis of Design section including codes, standards, guidelines, occupancy, special uses, fire protection systems, means of egress, demolition/sequence of construction, site/civil, sustainability, structural, architectural, mechanical, electrical, plumbing, fire protection, utilities, and security systems.

7.3.5 An Assessments section that addresses safety and health, quality, and environmental considerations and conventional issues associated with facilities. These considerations and issues may include issues concerning air, water, land, impacts of various possible pollutants, quantities, sources, release points, measures proposed to avoid adverse impacts, methods of controlling and treating discharged effluents and pollutants, and compliance with U.S. Environmental Protection Agency (EPA) and Illinois Environmental Protection Agency (IEPA) requirements, energy modeling, and life cycle analysis. Additionally, this section will address security, safety hazards and risks, life safety and fire protection analysis, and provisions for the disabled.

7.3.6 A Value Engineering section that addresses any value engineering issues that were considered and analyzed, including life-cycle costing studies and calculations, and the reasons and justification for their disposition.

7.3.7 An Energy Analysis section that includes energy modeling. Energy modeling software (CDS Trace700, latest version) shall be utilized to demonstrate building energy performance meets the above stated requirements. Provide final model results in both pdf and native files to Argonne.

7.3.8 A Sustainability section describing the projects approach to meeting the key elements of Guiding Principles that must be incorporated at preliminary design to ensure compliance. At a minimum this would include energy efficiency, water efficiency and resilience. The section should be supported with a completed Guiding Principles checklist included in the CDR consistent with the 2016 Guiding Principles Checklist for New Construction and Modernization v2.0 that reflects the projects approach for meeting the requirements.

7.3.9 An Appendices section that includes miscellaneous items such as:

Acronyms and Abbreviations, geotechnical surveys, environmental surveys, and any other relevant studies or reference materials. Also included in this section shall be an updated version of Guiding Principles checklist consistent with the 2016 Guiding Principles Checklist for New Construction and Modernization v2.0 and a crosswalk that identifies specification sections that satisfy the applicable guiding principles requirements.

7.4 Outline Specifications providing sufficient statements and details to illustrate the principal materials to be used.

7.5 Preliminary Cost Estimate with quantities and unit costs for each intended material, equipment item, and system.

7.6 Fire Protection Assessment (FPA) to identify potential fire hazards and a set of fire hazard controls. The FPA shall represent the project’s compliance with the guidelines of DOE O 420.1C – Facility Safety, (reference Section 13) and it shall be an updated version of the PFPA submitted with the CDR. The FPA will serve as one basis for the final design of facility-related hazard control strategies.

7.6.1 The FPA is to be prepared by a qualified professional. The A/E shall ensure that a full, independent review of the FPA is performed by a qualified professional. “Independent” is herein defined as a review by a person not directly involved in the preparation of the FPA. (The reviewer can be an employee of the same preparing firm.) Comments and findings of the review shall be resolved and incorporated prior to issuance of the FPA to Argonne.

The FPA shall be signed by the responsible preparer and independent reviewer to indicate concurrence. The FPA shall be formally approved and signed by the manager overseeing its preparation and by the A/E Project Manager.

7.7 Scoping: The A/E is required to include in its design a number of additive option scope items. These items shall support Argonne’s goal of soliciting overall competitive construction proposals that reflect the estimated price scope and incremental additive option items that will allow Argonne to award a construction contract scope ranging from 90% to 110% of the target construction contract price by utilizing the designed additive options. This approach is necessary to meet DOE requirements for designed-in project scope contingency management. The A/E and Argonne will work together to identify selected additive/alternative items. A preliminary list is provided in Section 2.

7.8 Design Reviews. The A/E will provide design documents and make oral presentations to an Argonne Design Review Committee at Preliminary Design completion levels and will incorporate all review recommendations in the design documents as agreed with Argonne. The PD documents are an integral part of Argonne’s CD-2 submittal and presentation to the DOE and subsequent approval for Final Design. Argonne will request the Argonne Preliminary Design comments to be incorporated into revised Preliminary Design documents to be resubmitted to Argonne in PD-4, the Revised Preliminary Design deliverable. The A/E will provide three-dimensional (3D) computerized renderings of key views of the project for Argonne’s. The renderings may be produced with “non-photorealistic” 3D rendering modeling software such as SketchUp or equivalent.

7.8.1 Project Progress Review. The A/E shall issue design progress documents and make presentations to the ANL Project Team at the 50% Preliminary Design (PD-1) completion level. A Design Review Meeting will be scheduled to occur within 5 to 7 Business days from the submittal date. The review period will be limited to 10 working days. Argonne will provide formal review comments to the A/E within 5 working days after completion of the review period. The A/E shall provide formal responses to all review comments and issue to the ANL Project Manager no later than 15 working days after the completion of the review period.

7.8.2 Argonne Design Reviews. The A/E shall provide design documents to

Argonne at the 95% Preliminary Design completion level. 95% Preliminary Design (PD-2) Review recommendations are to be incorporated into the 100% Preliminary Design (PD-3) documents. Design Review Meetings will be scheduled to occur within 5 to 7 Business days from the submittal dates.

The review period will be limited to 10 working days. Argonne will provide formal review comments to the A/E within 5 working days after completion of the review period. The A/E shall provide formal responses to all review comments and issue to the ANL Project Manager no later than 15 working days after the completion of the review period.

7.9 Owner-Architect Design Progress Meetings. During Preliminary Design, the A/E shall attend and lead Owner-Architect Design Progress Meetings on a weekly basis. At a minimum, the meeting shall be attended by the A/E Project Manager and Technical Lead. The purpose of the meeting is for the A/E to provide design progress updates.

The A/E will track issues and action items based on design discipline. The A/E will create technical committees based on discipline and assign a lead for each committee.

Argonne will designate a corresponding technical leader to enhance dialogue between the two parties. The A/E will maintain a master list of tracking items that are distributed at least 2 days ahead of each Owner-Architect Design Progress Meeting. Based on the list of open tracking items, the Owner will ensure key Owner project stakeholders are available when relevant topics warrant their attendance and participation so that timely direction can be provided to the A/E.

7.10 Critical Decision Support: The A/E will provide needed technical support to the AU2 – Subproject 1 Project Team to prepare for the Critical Decision 2 (CD-2), Directors Project Review (DPR) and Independent Project Review (IPR). Support includes (1) full day of attendance at each by A/E PM, mechanical lead and electrical lead to answer questions and provide technical information prior to and during reviews. Support includes preparing graphical materials to display facility floor plans and site layouts.

7.11 Independent Cost Review Support: The A/E will provide needed technical support to the AU2 – Subproject 1 Project Team to prepare for the CD-2 Independent Cost Review (ICR). Support includes (2) full days of attendance by A/E PM and lead cost estimator to answer questions and provide technical information prior to and during reviews. Support includes preparing graphical materials to display facility floor plans and site layouts.

7.12 Design to Cost/Budget: From the more detailed drawings and information developed, more accurate cost estimates and project schedules will be developed independently by both the A/E and the CM. This activity may reveal the need, at this stage of design, for revisions in scope or project features to keep the project within authorized funding and/or the need for early procurement of long-lead equipment to keep the project on schedule. Any necessary revisions in scope, project features, materials, and finishes that are required to stay within budget shall be made by the A/E at no cost to Argonne.

7.13 Value Engineering Workshop: The A/E will fully participate in a Value Engineering (VE) workshop to be conducted subsequent to Preliminary Design. The A/E will assist the VE effort by initially presenting a summary of each major element of the design to the VE team at the beginning of the VE effort. The A/E will then answer any questions of the VE team to clarify design intent. The A/E will also attend the out-brief presentation of the VE team to learn their recommendations and to make use of the opportunity to ask any questions. Argonne will then discuss the VE recommendations with the A/E to determine what VE recommendations to include in the actual VE design revisions.

7.14 Drawing Standards: The A/E PD drawings (excluding site, schedules, and code compliance drawings) shall be drawn at a minimum scale of 1/8-inch per foot and shall comply with Argonne drafting standards (reference FMS-PROC-108 Drafting Standards). Sections and elevations shall be provided as required to confirm that building floor-to-floor heights are optimized. A minimum of four (4) sections shall be provided for the MEP drawings to verify space adequacy and to ensure coordination of all utilities and services. The A/E shall, as part of the design activity, specify layers within the building elevation for each utility, including but not limited to electrical conduit, HVAC ductwork, heating and cooling piping, process piping, and telecommunications cable trays. The A/E shall also provide elevations and profiles of all utilities.

7.15 Calculations: Prior to the conclusion of PD, the A/E shall provide to Argonne for review a complete set of engineering calculations, including but not limited to:

7.15.1 Site drainage,

7.15.2 Structural analysis and design,

7.15.3 Heating and cooling analysis,

7.15.4 Plumbing calculations (for interior and site storm and wastewater levels), and

7.15.5 Lightning protection.

7.16 Preliminary Design Document Submissions. The A/E shall submit the following to

Argonne within two (2) working days of the date of issuance:

7.16.1 50% PD (PD-1):

7.16.1.1 One (1) size E (34” x 44”).

7.16.1.2 Ten (10) size C (17” x 22”) print copies.

7.16.1.3 Three (3) bound copies of all calculations.

7.16.1.4 Five (5) bound copies of all specifications.

7.16.1.5 Five (5) bound copies of the BOD.

7.16.1.6 Five (5) bound copies of Cost Estimate (PD-1a).

7.16.1.7 Electronic copies of all design deliverables posted to project Box site.

7.16.2 95% PD (PD-2):

7.16.2.1 One (1) size E (34” x 44”).

7.16.2.2 Ten (10) size C (17” x 22”) print copies.

7.16.2.3 Three (3) bound copies of all calculations.

7.16.2.4 Five (5) bound copies of all specifications.

7.16.2.5 Five (5) bound copies of the BOD.

7.16.2.6 Five (5) bound copies of Cost Estimate (PD-2a).

7.16.2.7 Electronic copies of all design deliverables posted to project Box site.

7.16.3 100% PD (PD-3):

7.16.3.1 One (1) size E (34” x 44”).

7.16.3.2 Ten (10) size C (17” x 22”) print copies.

7.16.3.3 Three (3) bound copies of all calculations.

7.16.3.4 Five (5) bound copies of all specifications.

7.16.3.5 Five (5) bound copies of the BOD.

7.16.3.6 Electronic copies of all design deliverables posted to project Box site.

8 FINAL DESIGN SERVICES [CONTRACT OPTION NO. 2]

8.1 The Final Design will be prepared utilizing the Preliminary Design reference documents and results from the Program Verification Phase. The A/E’s work during this phase will also include support of Argonne’s construction and equipment procurement based on the Final Design.

8.2 Final Design includes the following:

8.2.1 Resolution of any open Preliminary Design Argonne review comments.

8.2.2 Preparation of a Basis of Design (BOD) for the facility, including a narrative summary report that incorporates the following:

8.2.2.1 An Executive Summary including project overview, program, and scope.

8.2.2.2 A General Project Description section including functional area program, criteria, basis, and justification for various design elements, systems, and approaches.

8.2.2.3 A Site Analysis section including project location, campus context, landscape, and parking.

8.2.2.4 A Basis of Design section including codes, standards, guidelines, occupancy, special uses, fire protection systems, means of egress, demolition/sequence of construction, site/civil, sustainability, structural, architectural, mechanical, electrical, plumbing, fire protection, utilities, and security systems.

8.2.2.5 An Assessments section that addresses safety and health, quality, and environmental considerations and conventional issues associated with facilities. These considerations and issues may include issues concerning air, water, land, impacts of various possible pollutants, quantities, sources, release points, measures proposed to avoid adverse impacts, methods of controlling and treating discharged effluents and pollutants, and compliance with U.S. Environmental Protection Agency (EPA) and Illinois Environmental Protection Agency (IEPA) requirements, energy modeling, and life cycle analysis.

Additionally, this section will address security, safety hazards and risks, life safety and fire protection analysis, and provisions for the disabled.

8.2.2.6 A Value Engineering section that addresses any value engineering issues that were considered and analyzed, including life-cycle costing studies and calculations, and the reasons and justification for their disposition.

8.2.2.7 An Energy Analysis section that includes energy modeling. Energy modeling software (CDS Trace700, latest version) shall be utilized to demonstrate building energy performance meets the above stated requirements. Provide final model results in both pdf and native files to Argonne.

8.2.2.8 A Sustainability section describing the projects approach to meeting the key elements of Guiding Principles that must be incorporated at preliminary design to ensure compliance. At a minimum this would include energy efficiency, water efficiency and resilience. The section should be supported with a completed Guiding Principles checklist included in the CDR consistent with the 2016 Guiding Principles Checklist for New Construction and Modernization v2.0 that reflects the projects approach for meeting the requirements.

8.2.2.9 An Appendices section that includes miscellaneous items such as:

Acronyms and Abbreviations, geotechnical surveys, environmental surveys, and any other relevant studies or reference materials. Also included in this section shall be an updated version of Guiding Principles checklist consistent with the 2016 Guiding Principles Checklist for New Construction and…