Encl 1_Combined MAY 2026 Spill Response IDIQ.pdf

PDF 1 MB Posted

Attached to
REGIONAL RAPID SPILL RESPONSE AND PREVENTION CONTRACT AT VARIOUS U. S. NAVY, MARINE CORPS, ARMY AND AIR BASES AND FACILITIES THROUGHOUT JAPAN
Solicitation number
FY27SPILLRESPONSEJPN
Issued by

About this file

This document is a Performance Work Statement (PWS) for a Rapid Spill Response and Prevention Contract at various U.S. Navy, Marine Corps, Army, and Air Force bases and facilities throughout Japan, submitted by NAVFAC FE EV on May 20, 2026.

The contract is structured as an Indefinite Delivery Indefinite Quantity (IDIQ) performance-based contract covering seven geographic zones throughout Japan. The contractor must furnish all labor, supervision, management, tools, materials, equipment, facilities, and transportation necessary to provide environmental sampling, field-testing, and laboratory testing services at multiple installations including Commander Fleet Activities Yokosuka, Sasebo, and Okinawa; Naval Air Facility Atsugi; Yokota Air Base; Misawa Air Base; Marine Corps Air Station Iwakuni; and Marine Corps Base Camp Butler. The contract encompasses both recurring work (including annual training exercises) and non-recurring work items. Key personnel requirements include a Project Manager with at least three years of experience managing similar contracts, a Quality Manager with three years of QMS experience, and a Site Safety and Health Officer meeting EM 385-1-1 requirements. The contractor must maintain comprehensive quality management systems, accident prevention plans, safety certifications, and environmental protection procedures compliant with Federal, Host Nation, Prefectural, and local Japanese laws. Deliverables include oil and hazardous substance spill response plans, assessment reports, sampling and laboratory analysis plans, laboratory analysis reports, training exercise documentation, and after-action reports. The contract requires performance-based objectives with measurable standards and includes provisions for both anticipated work and additional services that may be ordered through task orders.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RAPID SPILL RESPONSE AND PREVENTION

CONTRACT

AT

VARIOUS U.S. NAVY, MARINE CORPS, ARMY AND AIR BASES AND

FACILITIES THROUGHOUT JAPAN

SUBMITTED BY: NAVFAC FE EV

May 20, 2026

Section C- 0100000

SECTION C: DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Project Location

1.3 Acquisition of Additional Work

1.4 Background Information

1.5 Verification of Workload and Conditions

1.6 Climate Patterns

1.7 Related Information

1.8 Navy Approach to Service Contracting

1.8.1 Partnering Philosophy

1.8.2 Contractor's Knowledge

1.8.3 Industry Best Practices

1.9 Standard Template

1.10 Navy PBSA Approach

1.11 Technical Proposal Certification

Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at various locations throughout Japan, subdivided into seven (7) zones namely Zone 1, Zone 2, Zone 3, Zone 4, Zone 5, Zone 6, and Zone 7 under an Indefinite Delivery Indefinite Quantity (IDIQ) type of a performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.

The PWS is organized into annexes. Annex 1 is "General Information".

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Not Applicable (N/A) Annex 4 N/A Annex 5 N/A Annex 6 N/A Annex 7 N/A Annex 8 N/A Annex 9 N/A Annex 10 N/A Annex 11 N/A Annex 12 N/A Annex 13 N/A Annex 14 N/A Annex 15 N/A Annex 16 N/A Annex 17 N/A Annex 18 Environmental

1.2 Project Location The work includes environmental sampling, field-testing, and laboratory testing services in support of various locations throughout Japan at various locations throughout Japan, subdivided into seven (7) zones namely Zone 1, Zone 2, Zone 3, Zone 4, Zone 5, Zone 6, and Zone 7. A list of Japan zones, regional areas and their respective locations are provided in J- 1800000-03.

1.3 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.4 Background Information For each installation information go to the following each website.

Commander Fleet Activities Yokosuka is available at:

https://cnrj.cnic.navy.mil/Installations/CFA-Yokosuka/ Commander Fleet Activities is available at:

https://cnrj.cnic.navy.mil/Installations/CFA- Sasebo/ Naval Air Facility Atsugi is available at:

https://cnrj.cnic.navy.mil/Installations/NAF- Atsugi/ Yokota Air Base is available at:

http://www.yokota.af.mil/ Misawa Air Base is available at:

http://www.misawa.af.mil/ Marine Corps Air Station Iwakuni is available at:

http://www.mcasiwakuni.marines.mil Marine Corps Base Camp Butler, Okinawa is available at:

http://www.mcbbutler.marines.mil/ Commander Fleet Activities Okinawa is available at:

http://www.cnic.navy.mil/Okinawa/index.htm Singapore Area Coordinator is available at:

https://www.cnic.navy.mil/regions/cnrj/installations/sac.html Commander Fleet Activities Chinhae is available at:

https://www.cnic.navy.mil/regions/cnfk/installations/cfa chinhae.html http://www.yokota.af.mil/ http://www.misawa.af.mil/ http://www.mcasiwakuni.marines.mil/ http://www.mcbbutler.marines.mil/ http://www.cnic.navy.mil/Okinawa/index.htm

1.5 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided. All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.6 Climate Patterns For climate patterns in Japan go to the following website:

http://www.jma.go.jp/jma/en/menu.html

1.7 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government.

Information provided in "Informational Notes" does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.8 Navy Approach to

Service Contracting

The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.

The Navy also supports the following principles:

1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.

Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.

http://www.jma.go.jp/jma/en/menu.html

1.8.2 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.

This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).

1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.

The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.

Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.

Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all firm fixed priced specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and their price must be allocated across the Exhibit Line Items.

For this PWS, the structure includes the following Annex 1, Annex 2 and Annex 18. All costs associated with management and administrative requirements for recurring and non-recurring work must be priced in each exhibit line item number ELIN.

1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are:

1) performance outcomes,

2) measurable standards,

3) consideration of incentives, and

4) performance assessment plan.

1.11 Technical Proposal

Certification The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

Section C- 0200000

0200000 – MGMT & ADMIN

0200000 – Management and Administration Table of Contents

Spec Item Title

2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Government Information Technology (IT) System

2.3.8 Directives, Instructions, and References

2.3.9 Invoicing Procedures

2.3.10 Forms

2.4 Government-Furnished Property, Materials and Services

2.4.1 Government-Furnished Facilities (GFF)

2.4.2 Government-Furnished Utilities

2.4.3 Government-Furnished Materials (GFM)

2.4.4 Government-Furnished Equipment (GFE)

2.4.5 Government-Furnished Services (GFS)

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Work Reception

2.6.2 Work Control

2.6.3 Work Schedule

2.6.4 Deliverables

2.6.5 Service Interruptions

2.6.6 NAVFAC MAXIMO

2.6.7 Quality Management System (QMS)

2.6.7.1 Quality Management (QM) Plan

2.6.7.2 Quality Inspection and Surveillance

2.6.7.3 Quality Inspection and Surveillance Report

2.6.8 Property Management Plan

2.6.9 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager (QM)

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Sensitive Unclassified Information

2.8.9 Employee Status

2.9 Contractor Safety Program

2.9.1 Accident Prevention Plan (APP)

2.9.2 Activity Hazard Analysis (AHA)

2.9.3 Safety and Occupational Health (SOH) Risk and Compliance Plans

2.9.3.1 Alcohol and Drug Abuse Prevention Plan

2.9.3.2 Chemical Hazard Communication Program

2.9.3.3 Emergency Response Plans

2.9.3.4 Fall Prevention and Protection Plan

2.9.3.5 Fire Prevention Program

2.9.3.6 Health Hazard Control Program and Hazard Communication Program

2.9.3.7 Site Sanitation Plan

2.9.4 Accident and Damage Reporting

2.9.4.1 Accident Reporting and Notification Criteria

2.9.5 Fire Protection

2.9.6 Monthly On-Site Labor Report

2.9.7 OSHA Citations and Violations

2.9.8 Safety Inspections and Monitoring

2.9.9 Safety Certification

2.9.10 Safety Apparel on Jobsites

2.9.11 Emergency Medical Treatment

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Hazardous Waste Disposal

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.3 Sustainable Procurement and Practices

2.11 Disaster Preparedness

2.12 Technical Library

2.12.1 Standard Operating Procedures (SOP) and Sampling and Analysis Plan

2.12.2 Documentation

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Notification to the Government for Work Above the Recurring Work Limitations

2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-Recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Material and Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

2.16 Performance Evaluation

0200000 - Management and Administration

2 Management and Administratio n

2.1 Definitions

and Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0700-1630, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.

2.2.1.1 Observed

Federal Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

OHS Spills can happen at any time of the day, any day of the week. The Contractor is expected to be flexible with the working hours when directed by the Government to respond to a spill.

Training will be accomplished during regular working hours.

2.2.2 Wage Determinations N/A

2.2.3 Requirements

Hierarchy Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative

2.3.1 Required Conferences

and Meetings

The Contractor shall attend administrative and coordination meetings. Prior to start of work, the contractor shall submit request for the pre-performance conference at least five working days prior to the desired conference date to the KO. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

Contractor shall attend coordination meeting at NAVFAC FE as frequent as quarterly. The frequency of the meeting shall be determined by the COR.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

N/A

2.3.3 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.

The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

Partnering should accomplish three goals:

- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.

- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.

- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.

2.3.3.1 Informal Partnering The KO shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.

The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the KO. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.

2.3.3.2 Contract

Partnering Administration

Upon award, the KO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.

Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

President/Vice President

* Project Manager

* Quality Manager Site Safety and Health Officer

2.3.4 Permits and Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, host nation, national, prefectural and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: $500,000 / ¥50,000,000 per occurrence

Automobile Liability: $200,000 / ¥20,000,000 per person, $500,000 / ¥50,000,000 per occurrence for bodily injury, $20,000 / ¥2,000,000 per occurrence for property damage

Workmen's Compensation: As required by Japanese worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000 / ¥10,000,000, except when worker's compensation may not be written by private carriers

Bodily Injury Liability: $500,000 / ¥50,000,000 Other as required by Japanese law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.

2.3.7 Government

Information Technology (IT) System

If applicable, ensure local IT system rates and policies are incorporated. U.S.

Naval Forces Japan uses the OCONUS Navy Enterprise Network (ONE-Net) IT system. More information can be found at https://www.public.navy.mil/FLTFOR/nctsfe/Pages/ONE%20NET.aspx

Information delivered to the Government via the internet shall be compatible with, and meet the requirements of ONE-Net IT system to ensure Government receipt of such information.

2.3.8 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-02. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.9 Invoicing Procedures Refer to Section G for invoicing instructions. The Contractor shall submit payment requests and receiving reports using WAWF (Wide Area WorkFlow). Refer to Invoice Form in J-0200000-04 for sample.

2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.

https://www.public.navy.mil/FLTFOR/nctsfe/Pages/ONE%20NET.aspx

2.4 Government-

Furnished Property, Materials and Services

IAW FAR 52.245-1, GOVERNMENT PROPERTY and, and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract.

2.4.1 Government-

Furnished Facilities

(GFF)

When available, the Government may provide classrooms, conference rooms, and any other Government spaces for the purpose of conducting training.

Prior coordination with the KO to reserve the training spaces is required.

2.4.2 Government-

Furnished Utilities

The Government will furnish water and electricity at existing outlets when required for the work to be performed under the contract at no cost to the Contractor. Information concerning the location of existing outlets may be secured from the KO. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all Japanese, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government, i.e. power generation equipment to facilitate operations necessary to execute the contract e.g. spill response.

2.4.3 Government-

Furnished Materials

The Government will not provide any materials for Contractor’s use.

2.4.4 Government-

Furnished

The Government will not furnish any equipment for the Contractor’s use in the performance of this contract.

2.4.5 Government-

Furnished Services

(GFS)

The Government will not provide Government Furnished Services for this contract.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Work Reception The Contractor shall establish a work reception function with the capability to receive, correspond, and respond to task orders. Work reception will be the Governments normal working hours (0700-1630).

2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and within three hours for inquiries after regular working hours.

2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO of any difficulty in scheduling work due to Government controls.

2.6.4 Deliverables Records and reports are specified in Section F and within the Directives, Instructions, and References. The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify records and reports, as directed by the KO, at no additional cost to the Government. All Contractor submittals shall be in English or may be submitted in Japanese with English translations.

Except where otherwise specified, all deliverables shall be submitted electronically in a most current version of Microsoft Office compatible format.

Deliverables shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

Deliverables shall be provided in one of the following manners: 1) Secured, encrypted email; 2) Contractor’s secured website for posting electronic copies of deliverables. Government personal access shall be limited to viewing and downloading of deliverables; or 3) Department of Defense Secure Access File Exchange (DoD SAFE).

2.6.5 Service Interruptions If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, affected tenants and customers as soon as practicable.

2.6.6 NAVFAC

MAXIMO

N/A

2.6.7 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program IAW the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.7.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit to the KO a revised QM Plan for acceptance.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Organization chart o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.7.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions.

The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the KO after termination of the contract per Section F.

2.6.7.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a summary and results of the quality inspection and surveillance events performed and assessment-driven corrective actions and process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.8 Property

Management Plan

The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Property, Materials and Services, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession.

2.6.9 System and

Equipment Replacement

N/A

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below.

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.

The key personnel shall be revised as applicable for the contract.

2.7.1.1 Project Manager (PM) The Contractor shall provide a PM and designated alternate, as applicable, who has full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be available either via telephone or electronic communication during the Government's regular working hours and after regular working hours. When the PM or alternate cannot be reached via telephone, electronic communications must be responded to within one hour during regular working hours and two hours after regular working hours.

The PM shall have at least three years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager

(QM)

The Contractor shall provide a Quality Manager or designated alternate who shall be available on-site in accordance to response times agreed upon on this contract. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

The Quality Manager shall have at least three years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager may be the same person as the SSHO.

2.7.1.3 Site Safety and Health

Officer (SSHO) The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub- paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the KO for acceptance in consultation with the Safety Office.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.

The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he possesses a Certified Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO shall not be the same person as the project manager.

2.7.1.4 Environmental/

Energy Manager

N/A

2.7.2 Employee

Requirements The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, and environmental requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures or an interpreter shall be furnished at no additional cost to the Government.

2.7.2.1 Employee

Certification and Training

The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.

2.7.2.2 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.

2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.

2.7.2.4 Identification as

Contractor Employee

Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.

2.7.2.5 Removal of

Employees

The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.

2.7.2.6 Proof of

Legal Residency

No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is submitted.

2.7.3 Service Contract

Reporting (SCR)

The Contractor shall report total dollar amount invoiced and all contractor labor hours (including sub-contractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.sam.gov.

Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year.

Contractors may direct questions to the help desk, linked at https://www.sam.gov.

2.8 Security

Requirements

The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements. The Contractor shall become acquainted with and comply with all Government regulations as posted, or as requested by the KO when required to enter a Government site. The Contractor shall ensure that all security/entrance clearances are obtained.

https://www.sam.gov/

2.8.1 Employee Listing The Contractor shall maintain a current Employee List and submit per

Section F. The list shall include, but not be limited to:

• employees’ name

• position title,

• supervisor,

• company, and

• level of security clearance and identification numbers.

2.8.2 Vehicles Vehicles shall meet all requirement of the Japanese Vehicle Code, such as safety standards, and shall carry proof of insurance and registration.

The Contractor’s vehicles operated on Government property shall be maintained in good repair.

2.8.3 Passes and Badges The Contractor shall prior to the start of the contract, submit the names of personnel to be utilized during the contract term to the KO and shall include the following for each person:

Name Date of Birth Place of Birth Height Weight Citizenship Permanent and Present Address Job Title

After receipt of the names and obtaining of security clearances, the cognizant Pass & ID office will issue a Contractor’s pass and/or badge to each person on the list. No personnel will be permitted on the site without a valid pass and/ or badge. When within the confines of U.S. Government controlled premises, personnel shall have their passes and/or badges immediately available and shall produce them for identification purposes when requested by security authority.

Passes and/or badges shall be presented when entering or departing the base.

When an employee leaves the Contractor’s service, the employee’s pass and/or badges issued to Contractor employees shall not negate the requirement for employee identification.

2.8.4 Access to Installation All Contractor personnel principal to immediate spill response services shall obtain access to installations in the listed zones through enrollment and registration into the Defense Biometric Identification System (DBIDS).

The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.

2.8.4.1 DBIDS Program DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.

The Government performs background screening and credentialing.

Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

2.8.4.2 DBIDS Credentials Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved.

The SECNAV 5512/1 form and additional information about DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html.

The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.

The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:

(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.

2.8.5 Access to Buildings The Contractor shall monitor and control access into restricted areas under their responsibility, allowing only those individuals who have been properly cleared into restricted areas or other controlled access areas. The Contractor shall comply with security requirements, plus those imposed by the installation Commander at all times. Personnel with access to special areas will have the appropriate screening and/or security clearance, and personnel requiring routine access to restricted areas will wear special badges authorizing access for those areas. Contractor personnel shall not enter restricted or controlled areas or installation facilities unless specifically authorized in performance of their duties. The Contractor shall secure all buildings and facilities entered during non-duty hours and will secure all building and facilities under the Contractor’s cognizance at the end of each work day or shift period.

2.8.6 Access Arrangements The Contractor shall make all arrangements through the appropriate office necessary to obtain access to buildings, facilities and other work areas, and when necessary, arrange for them to be opened and closed by the controlling authority. The Government may issue keys to the Contractor. The Contractor shall use due diligence and be responsible for compromised security systems to include replacement costs that result from its action or inaction

2.8.6.1 Escort Arrangement

for Secured Areas

The Contractor shall make arrangements for Government escort into secured areas requiring escort. The KO will provide information on applicable buildings, spaces and the appropriate point of contact.

The Contractor may experience delays while waiting for escorts. The Government estimates the wait period can be up to 15 minutes. The Contractor shall notify the Government Performance Assessment Representative (PAR) and appropriate point of contract if an escort is not available after 15 minutes and access to accomplish the work is denied.

Unscheduled requirements, e.g., trouble calls, may require a longer wait for an escort.

2.8.7 Security Clearances N//A

https://www.cnic.navy.mil/om/dbids.html

2.8.8 Access to Sensitive

Unclassified Information

N/A

2.8.9 Employee Status The Contractor shall notify the KO of any changes to any employee’s status to include, but not limited to, termination, convictions/arrests, adverse actions taken on the job for any reason or any other documented misbehavior that may affect, or have the potential to affect, security standing in terms of access to federal facilities or IT systems.

2.9 Contractor Safety

Program

The Contractor shall develop and implement a Safety Program detailing how the Contractor plans, staffs, performs, and controls all safety practices while delivering best value services to the Government without any accidents or mishaps. The Contractor’s safety program shall comply with all safety standards identified in the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, UFC 3-560-01 Operation and Maintenance Electrical Safety, and Public Law 91-596, Occupational Safety and Health Act.

Any reference to “USACE" facilities, property, or equipment specified in EM 385-1-1 should be interpreted as Government facilities, property, and equipment.

2.9.1 Accident Prevention

Plan (APP)

The Contractor shall develop and implement a site…