The document is a comprehensive set of construction plans and technical specifications for the Dane County EMS-EOC Facility Fiber Connection Project in Wisconsin. The project involves installing a fiber optic cable network connecting the Emergency Medical Services-Emergency Operations Center (EMS-EOC) facility, involving multiple handhole installations, fiber optic cable routing, and splice connections across various locations including McKee Road, King James Way, and near the Military Ridge State Trail. The project requires furnishing and installing 12-fiber optic termination panels, multiple Type V handholes, non-metallic conduits, and fiber optic cables with varying fiber counts (12-CT, 24-CT, 96-CT, and 144-CT) using bored installation methods.

The construction plans detail precise technical specifications for fiber optic infrastructure, including specific requirements for splice enclosures, handhole types, and cable routing. The project appears to be funded through Dane County and involves connecting existing conduit and handhole infrastructure with new fiber optic cable segments. Contractors are explicitly instructed to keep all equipment off private property and to perform splicing operations only between 12:00 AM and 6:00 AM. The project involves multiple existing utility connections and requires careful coordination with local traffic engineering and utility locate services, with specific notification protocols for work within city right-of-way and near existing underground structures.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY

D

M

M

M

Fitchburg

Monona

Verona

Hills

VERONA

9 4 5

L.

Wingra

Madison

17 16

PD

MS

MC

PD

MM

MM

77 79

258 260

Lake Monona

TR

A

IL

TRA

IL

Sugar R.

Ba dg er M ill Cr

Nine

K ee na ns

Springs

CAPITAL

Title Typical Sections and Details Estimate of Quantities Miscellaneous Quantities Right of Way Plat Plan and Profile Standard Detail Drawings Sign Plates Structure Plans Computer Earthwork Data Cross Sections

ORDER OF SHEETS

LAYOUT

SCALE

CORPORATE LIMITS

PROPERTY LINE

LOT LINE

EXISTING RIGHT OF WAY

SLOPE INTERCEPT

COMBUSTIBLE FLUIDS

POWER POLE

TELEPHONE POLE

ORIGINAL GROUND

MARSH OR ROCK PROFILE

UTILITY PEDESTAL

GAS

ELECTRIC

G

E

T

PROPOSED OR NEW R/W LINE

CAUTION

WOODED OR SHRUB AREA

MARSH AREA

EXISTING CULVERT

PROPOSED CULVERT

(Box or Pipe)

CULVERT (Profile View)

CONVENTIONAL SYMBOLS

ROCK

(To be noted as such)

SS

W

SANSANITARY SEWER

STORM SEWER

WATER

COUNTY:

PLOT NAME : H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\TITLE - GENERAL NOTES - PLAN SHEETS.DWGFILE NAME : 2/27/2023 10:52 AMPLOT DATE : PLOT BY : QAMAR AL DIK

FOFIBER OPTIC

UTILITIESREFERENCE LINE

GRADE LINE

PROFILE

TELEPHONE

SPECIAL DITCH LABELLIMITED HIGHWAY EASEMENT

TOTAL SHEETS = 6

GRADE ELEVATION 95

.3

PLAN

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

Section No.

300'EB'

COORDINATES ON THIS PLAN ARE REFERENCED TO THE WISCONSIN

COUNTY COORDINATE SYSTEM, DANE COUNTY.

PROJECT LOCATION

EMS-EOC FACILITY FIBER CONNECTION

DANE COUNTY

2.0 MI.

E

DANE

WISDOT/CADDS SHEET 42

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\TITLE - GENERAL NOTES - PLAN SHEETS.DWGFILE NAME : 2/27/2023 10:52 AMPLOT DATE : PLOT BY : QAMAR AL DIK

PROJECT: EMS-EOC FACILITY FIBER CONNECTION

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

GENERAL NOTES

LAYOUT NAME - General Notes

DIGGERS HOTLINE

Dial or (800)242-8511 www.DiggersHotline.com

COMMUNICATIONS

THESE PLANS AND THE ASSOCIATED SPECIAL PROVISIONS REFLECT CONDITIONS KNOWN DURING THE DEVELOPMENT OF THE PLANS AND SPECIAL PROVISIONS. THE CONTRACTOR IS FULLY RESPONSIBLE FOR THE APPLICATION OF ALL WORK SHOWN IN THE PLANS TO THE ACTUAL PHYSICAL FIELD CONDITIONS IN ORDER TO PROVIDE A COMPLETE AND ACCEPTED PROJECT. IN THE EVENT THAT ACTUAL PHYSICAL FIELD CONDITIONS AFFECT OR PREVENT THE APPLICATION OR PROGRESSION OF ANY WORK SHOWN IN THE PLANS OR SPECIAL PROVISIONS, THE CONTRACTOR SHALL NOTIFY THE ENGINEER IMMEDIATELY, PRIOR TO ANY FURTHER

WORK BEING PERFORMED.

ANY CHANGES TO THE WORK SHOWN IN THE PLANS SHALL BE APPROVED IN WRITING BY THE ENGINEER PRIOR TO THE WORK

BEING PERFORMED.

THE LOCATIONS OF EXISTING AND PROPOSED UTILITY INSTALLATIONS SHOWN ON THE PLANS ARE APPROXIMATE. THERE MAY BE

OTHER UTILITY INSTALLATIONS WITHIN THE PROJECT AREA THAT ARE NOT SHOWN.

THE CONTRACTOR SHALL NOTIFY DIGGERS HOTLINE AND AFFECTED UTILITIES PRIOR TO THE START OF WORK. ANY UTILITY WHICH

IS NOT A MEMBER OF THE DIGGERS HOTLINE MUST BE CONTACTED SEPARATELY.

ALL EXISTING UNDERGROUND AND ABOVE GROUND STRUCTURES AND FACILITIES WITHIN THE SCOPE OF THIS PROJECT MAY NOT BE SHOWN IN THE PLANS. THE CONTRACTOR IS FULLY RESPONSIBLE FOR LOCATING ALL UNDERGROUND AND ABOVE GROUND

STRUCTURES AND FACILITIES.

TYPICAL EQUIPMENT FOR THIS WORK INCLUDES A PICKUP TRUCK, MINI EXCAVATOR, CONDUIT PLOW, BORING MACHINE, AND A

FIBER SPLICING TRAILER.

NOTIFY THE ENGINEER (PRIMARY 608-298-5402, SECONDARY 763-452-4730) AT LEAST TWO WEEKS PRIOR TO STAKING ANY

DEVICE LOCATIONS.

NOTIFY THE ENGINEER (PRIMARY 608-298-5402, SECONDARY 763-452-4730) AT LEAST FORTY-EIGHT HOURS PRIOR TO

PENETRATING BUILDINGS.

NOTIFY THE ENGINEER (PRIMARY 608-298-5403, SECONDARY 763-452-4730) AT LEAST FORTY-EIGHT HOURS IN ADVANCE OF ANY WORK ON CITY OF MADISON OWNED OR MAINTAINED FACILITIES TO ARRANGE FOR AN INSPECTOR TO BE PRESENT DURING ALL SUCH WORK. WORK SHALL NOT COMMENCE UNTIL THE CITY TRAFFIC ENGINEERING INSPECTOR IS PRESENT.

CALL CHAD VEINOT (714-745-4064) AT THE CITY OF MADISON TRAFFIC ENGINEERING SHOP AT LEAST TWENTY-FOUR HOURS IN

ADVANCE OF WORK WITHIN THE CITY OF MADISON RIGHT-OF-WAY.

HAND DIG TRENCHES NEAR EXISTING CONDUITS AND CABLES. VERIFY DEPTHS OF EXISTING CONDUITS AND CABLES PRIOR TO

CROSSING BY DIRECTIONAL BORE.

ALL CABLE PULLING AND SPLICING OPERATIONS SHALL OCCUR AT ACCESS POINTS (HANDHOLES, COMMUNICATION VAULTS, ETC.)

SHOWN IN THE PLANS.

ALL SPLICING OPERATIONS SHALL OCCUR BETWEEN THE HOURS OF 12:00AM AND 6:00AM.

WETLANDS, WATERWAYS, AND OTHER ENVIRONMENTALLY SENSITIVE AREAS SHALL BE PROTECTED AT ALL TIMES. DO NOT STORE

EQUIPMENT OR MATERIALS NEAR THESE SITES UNLESS APPROVED BY THE ENGINEER.

NO TREES OR SHRUBS ARE TO BE REMOVED WITHOUT APPROVAL OF THE ENGINEER.

AREAS WITHIN THE RIGHT-OF-WAY DISTURBED DUE TO CONSTRUCTION OPERATIONS ARE TO BE RESTORED TO THE ORIGINAL CONDITION WITH TOPSOIL, FERTILIZER, SEED, AND MULCH. NO PAYMENT WILL BE MADE FOR RESTORING AREAS DISTURBED DUE

TO CONSTRUCTION OPERATIONS.

DANE COUNTY

SAM OLSON

OLSON@COUNTYOFDANE.COM

608-283-2970

210 MARTIN LUTHER KING JR BLVD

MADISON, WI 53703

SRF CONSULTING GROUP

RACHEL BURNHAM

608-298-5402

RBURNHAM@SRFCONSULTING.COM

JACOB FOLKERINGA

763-452-4730

JFOLKERINGA@SRFCONSULTING.COM

6720 FRANK LLOYD WRIGHT AVENUE, SUITE 100

MIDDLETON, WI 53562

STANDARD ABBREVIATIONS

EX ----- EXISTING

FO ----- FIBER OPTIC

HH ----- HANDHOLE

QP ----- QUANTITY POINT

SM ----- SINGLE MODE

LEGEND

DESCRIPTION SYMBOL

HANDHOLE -----------------------------------

CONDUIT -------------------------------------

QUANTITY POINT ---------------------------

GENERAL NOTES

PLOT SCALE : 1 IN:1000 FT

WISDOT/CADDS SHEET 44

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\PO.DWGFILE NAME : 2/27/2023 10:53 AMPLOT DATE : PLOT BY : QAMAR AL DIK

PROJECT: EMS-EOC FACILITY FIBER CONNECTION

PLOT NAME :

SHEET PROJECT OVERVIEW

LAYOUT NAME - Project Overview

EMS-EOC FACILITY

MCKEE RD

MILITARY RIDGE STATE TRAIL

US 18

S S

EM

IN

O

LE

H W

Y

US 14

PROJECT LOCATION

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\TYPE V HH.DWGFILE NAME : 2/27/2023 10:53 AMPLOT DATE : PLOT BY : QAMAR AL DIK

PROJECT: EMS-EOC FACILITY FIBER CONNECTION

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION DETAIL

LAYOUT NAME - Type V HH

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\TYPE V HH.DWGFILE NAME : 4/26/2023 9:23 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: EMS-EOC FACILITY FIBER CONNECTION

PLOT NAME :

SHEET

PLOT SCALE : Custom

COMMUNICATION SCHEMATICS

LAYOUT NAME - CS

U .S

. H

IG

HW

AY

EMC-EOC

FACILITY

FURNISH & INSTALL:

FIBER OPTIC TERMINATION/PATCH PANEL

12-FIBER OPTIC TERMINATION

FURNISH & INSTALL:

TYPE V HANDHOLE

FURNISH & INSTALL:

TYPE V HANDHOLE

EXISTING:

HANDHOLE

FURNISH & INSTALL:

NON-METALLIC CONDUIT 3-INCH (BORED)

FIBER OPTIC CABLE 12-CT

EXISTING:

CONDUIT

FIBER OPTIC CABLE 144-CT

EXISTING:

CONDUIT

FIBER OPTIC CABLE 144-CT

EXISTING:

CONDUIT

FURNISH & INSTALL:

FIBER OPTIC CABLE 12-CT

SEE NOTE 1

FURNISH & INSTALL:

NON-METALLIC CONDUIT 3-INCH (BORED)

FIBER OPTIC CABLE 12-CT

MCKEE RD

KING JAMES WAY

KAPEC RD

M

ILI

TA

RY

R

ID

GE

ST

AT

E

TR

AI

L

VE

RO

N A

RD

MCKEE RD

EXISTING:

VII HANDHOLE

FIBER OPTIC SPLICE ENCLOSURE

FURNISH & INSTALL:

4-FIBER OPTIC SPLICE

EXISTING:

HANDHOLE

FIBER OPTIC SPLICE ENCLOSURE

FURNISH & INSTALL:

4-FIBER OPTIC SPLICE

EXISTING:

CONDUIT

FURNISH & INSTALL:

FIBER OPTIC CABLE 24-CT

EXISTING:

TYPE VII HANDHOLE

FURNISH & INSTALL:

FIBER OPTIC SPLICE ENCLOSURE

4-FIBER OPTIC SPLICE

EXISTING:

TYPE I HANDHOLE

EXISTING:

TYPE I HANDHOLE

EXISTING:

TYPE I HANDHOLE

EXISTING:

CONDUIT

FIBER OPTIC CABLE 144-CT

EXISTING:

CONDUIT

FURNISH & INSTALL:

FIBER OPTIC CABLE 12-CT

EXISTING:

CONDUIT

FIBER OPTIC CABLE 96-CT

EXISTING:

CONDUIT

FIBER OPTIC CABLE 96-CT

EXISTING:

CONDUIT

FIBER OPTIC CABLE 144-CT

EXISTING:

TYPE I HANDHOLE

EXISTING:

HANDHOLE

FURNISH & INSTALL:

NON-METALLIC CONDUIT 3-INCH

FIBER OPTIC CABLE 12-CT

FURNISH & INSTALL:

NON-METALLIC CONDUIT 3-INCH (BORED)

FIBER OPTIC CABLE 12-CT

NOTE 1: CONTRACTORS SHALL KEEP ALL

EQUIPMENT OFF PRIVATE PROPERTY

FURNISH & INSTALL:

TYPE V HANDHOLE

SA

N

SA

N

SAN SAN

WISDOT/CADDS SHEET 44

ECOUNTY: DANE

H:\PROJECTS\12000\12598\CAD_BIM\SHEETSPLAN\EMS-EOC FACILITY (KING JAMES WAY)\CONSTRUCTION DETAIL PLAN SHEET.DWGFILE NAME : 4/26/2023 11:02 AMPLOT DATE : PLOT BY : BRENT BOKEMPER

PROJECT: EMS-EOC FACILITY FIBER CONNECTION

PLOT NAME :

SHEET

PLOT SCALE : 1 IN:100 FT

CONSTRUCTION PLANS

LAYOUT NAME - Construction Plans

GG

G

G

E E

Sheets and Views
1 Title
2 General Notes
3 PO - Project Overview
4 Type V HH - Type V HH
5 Type V HH - CS
6 Construction Detail Plan Sheet - Construction Plans

File details come from the government source that posted it. Updated .