EMG Alteration (30 Days) (2).pdf

PDF 81 KB Posted

Attached to
Emergency Commercial Demolition: 18980 FENTON AKA 19000 Fenton Bldg 101 &102
Solicitation number
300000149798618
Issued by
Michigan

About this file

This is an alteration project specification document for a state or local government entity involving emergency management and general facility improvements. The project encompasses a 30-day timeline for completion of alterations to an existing facility, with specific focus on structural modifications, system upgrades, and related construction activities. The scope of work requires detailed labor and material submissions from qualified contractors, with particular emphasis on meeting expedited scheduling requirements. Response documentation and bid submissions are due within the specified 30-day period, and the project award is contingent upon standard government procurement procedures and contractor qualifications review.

The project operates under standard government contracting terms with pricing structured as a lump-sum or unit-price basis, depending on the specific line items detailed within the alteration scope. Funding is allocated through the sponsoring government entity's capital improvement or emergency management budget. Contractors must demonstrate current licensure, bonding capability, and experience with similar accelerated alteration projects to be considered responsive and responsible. The contract includes standard performance and payment bonds, insurance requirements, and compliance with prevailing wage or labor standards applicable to the jurisdiction. No specific set-asides, incumbent information, or renewal options are indicated in the available documentation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Emergency Commercial

Alteration Timeline

Begin Alteration

Open Hole Approved

Certificate of Approval

Site Finalization

Pre-Invoice Approved

Number of Calendar Days from

NTP

3 20 25 30 90