Emergency Purchase Final Cost and Term v.25.1 8.27.24~6.pdf

PDF 1 MB Posted

Attached to
Emergency final costs for Sinnissippi Dam stop logs purchase
Solicitation number
26-422DNR-DIREC-B-51885
Issued by
Washington County, Illinois

About this file

This is an Emergency Purchase Final Cost and Term report from the State of Illinois Chief Procurement Office for General Services, documenting the completion of an emergency procurement by the Illinois Department of Natural Resources, Office of Water Resources. The project involved the purchase of four additional stop logs for placement upstream of Gate 3 at Sinnissippi Dam in Rock Falls, Illinois. The stop logs were required to halt water flow through the gate, enabling IDNR to maintain the upstream pool elevation at the required level until the gate could be examined and a permanent repair completed. The contract was awarded to Orsolini Welding Fabricators, located at 3034 W Carroll Ave., Chicago, Illinois, with IDNR's office based at One Natural Resources Way, Springfield, Illinois. The final contract term was established through June 18, 2025.

The final total cost of supplies and services was $191,390.00. The emergency purchase was documented under Reference #26-422DNR-DIREC-B-51885 and was certified by Lisa Bulinski, Executive II, on April 7, 2026, when the final costs and term were reported to the Chief Procurement Office and the Auditor General as required for emergency contract documentation.

View the file

Other files

File Type Posted
Emergency Purchase Statement v.25.2 signed~1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EMERGENCY PURCHASE FINAL COST AND TERM

Page 1 of 1State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost and Term v.25.1

Zip: 61071State:ILCity:ChicagoAddress: 3034 W Carroll Ave.

Vendor: Orsolini Welding Fabricators

Zip: 62702State: ILCity:SpringfieldAddress: One Natural Resources Way

Division: Office of Water ResourcesAgency: Illinois Department of Natural Resources

Final Costs and Term Reference #: 26-422DNR-DIREC-B-51885

Final total cost of supplies and services: $191,390.00 Final total term of contract: 06/18/2025

Title: Executive II Date: 4/7/2026

Printed Name: Lisa Bulinski Agency Signature:

I am reporting the final costs and term for the referenced emergency contract to the CPO and the Auditor General.

Page of

EMERGENCY PURCHASE FINAL COST AND TERM

State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost and Term v.25.1

EMERGENCY PURCHASE FINAL COST AND TERM

Page of State of Illinois Chief Procurement Office for General Services Emergency Purchase Final Cost and Term v.25.1 Final Costs and Term I am reporting the final costs and term for the referenced emergency contract to the CPO and the Auditor General.

11.0.0.20130303.1.892433.887364

PageCount:
CurrentPage:
VendorZip: 61071
VendorState: IL
VendorCity: Chicago
VendorAddress: 3034 W Carroll Ave.
Vendor: Orsolini Welding Fabricators
AgencyZip: 62702
AgencyState: IL
AgencyCity: Springfield
AgencyAddress: One Natural Resources Way
AgencyDivision: Office of Water Resources
AgencyUniversity: Illinois Department of Natural Resources
CurrentMasterPage:
MasterPageCount:
ReferenceNumber: 26-422DNR-DIREC-B-51885
FinalTotalCost: $191,390.00
FinalTotalTerm: 06/18/2025
TitleField: Executive II
Date: 4/7/2026
PrintedName: Lisa Bulinski
AuthorizedSignature: