This is a Performance Work Statement (PWS) for a five-year Blanket Purchase Agreement (BPA) to provide comprehensive maintenance and repair services for emergency electrical generators and automatic transfer switches (ATS) at Hoover Dam and associated Bureau of Reclamation (BOR) facilities in Boulder City, Nevada, and Arizona.
The contractor must provide all personnel, supervision, labor, tools, materials, equipment, and supplies necessary to inspect, maintain, troubleshoot, and repair six generators ranging from 10 kW to 1,250 kW capacity, manufactured by Himoinsa, Onan, Kato Lite, Kohler, and Cummins. Services shall be performed Monday through Friday, 7:00 a.m. to 3:00 p.m., with emergency work outside normal hours as required. The contractor must respond to emergency calls within 8 hours and be on-site within 24 hours, with non-emergency repairs targeted for completion within two business days of notification. All repairs exceeding $500 require prior written approval from the Contracting Officer or Contracting Officer's Representative. Service requirements include Level I Quarterly Inspections covering belts, cooling systems, fuel systems, batteries, and ATS components, and Level II Annual Inspections that include air filter replacement, coolant and fuel analysis, oil and battery testing, and 60-minute load bank tests at 80% capacity. The contractor must maintain detailed service records on-site, provide inspection and repair reports within specified timeframes (5 business days for inspections, 3 business days for repairs), and implement a Quality Control Plan requiring COR approval before contract payments commence. Personnel performing inspections and repairs must hold EGSA Electrical Generator Systems Technician Certification or equivalent. All work must comply with NEC, OSHA, NFPA 70B/70E, ASME, ANSI standards, and Reclamation Safety and Health Standards. The contract excludes full generator replacements, major engine overhauls, alternator repairs beyond standard preventive maintenance, emission upgrades, and enclosure repairs not caused by the contractor.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HOOVER DAM EMERGENCY GENERATOR
MAINTENANCE AND REPAIR SERVICES
PERFORMANCE WORK STATEMENT (PWS)
1.0 GENERAL
1.01 INTRODUCTION
The Bureau of Reclamation (BOR), Lower Colorado Region, requires comprehensive generator and automatic transfer switch (ATS) maintenance and repair services for Hoover Dam facilities. This PWS outlines a five-year Blanket Purchase Agreement (BPA) to support preventative maintenance (PM), emergency services, and repair of electrical generator systems. All generator inspections, services, and repairs shall be performed Monday through Friday, excluding Federal holidays. Tasks shall be performed during the day between 7:00 a.m.
and 3:00 p.m. Hoover Dam hours of operation are Monday through Friday, 6:00 a.m. to 4:30 p.m. Note: If generator inspections, services, or repairs require interruption of electrical services, the inspections, services, or repairs shall be accomplished after normal duty hours or on the weekend. This shall be specified in the task order.
This Performance Work Statement (PWS) set forth requirements for generator and ATS inspections, services, and repairs at the BOR’s Hoover Dam Bolder City Nevada.
1.02 SCOPE OF WORK
The Contractor shall provide all personnel, supervision, labor, subcontractors, tools, materials, equipment, and supplies necessary to inspect, maintain, and repair electrical power generators and ATS units, in accordance with manufacturer instructions and all applicable regulations. The Contractor shall provide customer service, inspections, services, quality control and all other services as listed herein. The Contractor shall determine how work is to be performed, how much labor is needed to perform the tasks, what methods will be used to complete the job, and which supplies, materials, and equipment are needed. These performance-based specifications express the Government’s requirements in the form of General Work Quality Standards (GWQS) (see Section 2.10). GWQSs are provided as the Government’s best gauge of the minimum quality standards to be met. The results of the work performed under this contract will conform to the GWQS. The Government expects that these minimum standards will be met or exceeded during generator and ATS inspection and service processes.
1.03 PERIOD OF PERFORMANCE
The period of performance for this BPA is five (5) years from date of award. Specific tasks will be issued through BPA Calls.
1.04 LOCATIONS AND EQUIPMENT
All services shall be performed at Hoover Dam and associated BOR facilities, the following generators are included:
# Location Engine kW Manufacturer Model
1 NV SRF Building C10TE1D 287 Himoinsa HFW-290-T6
2 NV Visitor Center Cummins KTA50-G3 1250 Onan 1250DFLC75207L
3 NV Lower Portal Rd VH4D1 10 Kato Lite L10FJW4
4 NV Gantry Crane Cummins 6BT-5.9 80 Kohler 80ROZ271
5 AZ Portable Unit 4B3.9-G2 35 Onan DGBB-5006900
6 AZ Gantry Crane Cummins 6BT-5.9 80 Kohler 80ROZ271
2.0 EXECUTION
2.01 CONTRACTOR RESPONSIBILITIES
i. Schedule, coordinate, and execute inspections, tests and repairs with approval from the Hoover Dam electrical group Forman (Power Systems).
ii. Initial inspection on this BPA will be (Level II Annual inspection).
iii. Ensure compliance with NEC, OSHA, NFPA 70B/70E, ASME, ANSI, and other applicable codes.
iv. Provide documentation of technician certification equivalent to (EGSA Electrical Generator Systems Technician Certification) for personnel who are to perform inspections, tests and repairs.
v. Provide service jackets maintaining detailed service records and repairs to be kept on site (Hoover Dam Electrical Office) for each emergency generator and ATS.
vi. Provide written reports for all services performed.
vii. Respond to emergency calls per Section 2.03
2.02 SERVICE REQUIREMENTS
Level I Quarterly Inspection:
Performed by qualified personnel and includes:
i. Belts, Cooling System, Exhaust System
ii. Oil levels, Engine Crankcase, Air Filters
iii. Fuel system and storage tank
iv. Governor, Control Panel, Gauges
v. Battery and starting system, Generator protective devices
vi. Operational checks: Oil pressure, voltage, frequency, leaks
vii. ATS: Inspect in accordance with manufacturer requirements, repair as necessary.
Level II Annual Inspection:
Performed by qualified personnel and includes:
i. Replace air filters, analyze coolant (Correct any deficiencies)
ii. Replace fuel filters as needed, test fuel (Clean or Replace) as test results require.
iii. Test and if required from test results change oil and filters.
iv. Test batteries and charging system, replace as required.
v. ATS: Inspect in accordance with manufacturer requirements, repair as necessary.
vi. Conduct load bank test to 80% rated load capacity of the unit for 60 minutes. (Mobile load bank provided by contractor) The load tests must be scheduled with the Hoover Dam Electrical shop Forman (Power Systems).
2.03 REPAIRS AND EMERGENCY SERVICES
Scheduled Repairs:
i. Non-emergency repairs shall be completed with the optimal goal of two business days from notification.
ii. No repairs exceeding $500 shall be performed without prior approval via BPA Call.
iii. A detailed inspection and repair report is required within 3 business days of service.
Emergency Repairs:
i. Contractor must respond to notification within 8 hours
ii. On-site within 24 hours
iii. Work shall begin within 24 hours; priority will be assigned by the Government if multiple emergencies occur.
2.04 DELIVERABLES
The Contractor shall submit the following:
i. Inspection Reports (Quarterly and Annual): Within 5 business days.
ii. Repair Reports: Within 3 business days of task completion.
iii. Equipment Deficiency Checklist: Submitted with each inspection report.
iv. Service Log: Cumulative maintenance history provided annually.
v. All reports shall be submitted in PDF format via email to the Contracting Officer (CO) and the designated Technical Point of Contact (POC).
2.05 QUALITY ASSURANCE
The Government will conduct quality assurance in accordance with Section 2.06, Work Performance Analysis.
2.06 QUALITY CONTROL
i. The Contractor shall implement a Quality Control Plan (QCP) to ensure all work meets or exceeds standards. The Government reserves the right to inspect any service for compliance.
ii. The Contractor shall establish and maintain a complete Quality Control Plan (QCP) to ensure the requirements of the contract are provided as specified. Contractor Submittals, one copy of the Contractor’s QCP shall be provided to the COR for approval not later than the post-award conference. A revised copy of the QCP shall also be provided to the COR for approval as changes occur. No payments shall be made under the contract until the initial QCP is approved by the Government. The plan shall include, as a minimum, the following:
iii. A self-inspection system covering all the services listed in Section 2.02. It must specify the areas to be inspected and repairs on both a scheduled or unscheduled basis, how often inspections will be accomplished, and the title of the individual(s) who will perform the inspections. The Contractor shall establish methods for identifying and preventing defects in the quality of service/maintenance performed before the level of performance becomes unacceptable.
iv. The Contractor shall maintain onsite records of all inspections, services, and generator malfunctions and all associated repairs. These records shall be made available to the Government upon request during the term of the contract.
2.07 DEFINITIONS AND ACRONYMS
2.07(A) Definitions Acceptable Quality Level (AQL): The maximum percentage defective or the maximum number of defects that can be considered satisfactory on the average. It is the allowable leeway from a standard before the Government will reject the specific service. An AQL does not imply that the Contractor may knowingly perform in an unsatisfactory way.
Maintenance Noncompliance: Those actions lacking and/or not taken by the Contractor to ensure that the standards and requirements of the contract are met (i.e., not in conformity with contract requirements).
Contract Discrepancy Report (CDR): A report initiated by the Government, which the Contractor is required to complete, whenever performance is unsatisfactory. The CDR requires the Contractor to explain in writing why performance was unsatisfactory, how performance will be returned to satisfactory levels, and the corrective action that will be taken to prevent recurrence.
Customer Complaint Inspection: Unscheduled surveillance of Contractor’s work prompted by the agency (BOR) receiving the service. The COR may receive customer complaints about the Contractor’s performance or quality of service. The COR may review the alleged unsatisfactory performance, verify the contract requirement and provide the Contractor notification of deficiencies, if applicable.
Defect: Each instance of non-compliance with a contract requirement. A defect may be caused by either non-performance or poor performance. Each defect is subject to deductions from the Contractor’s payment if the defect is not corrected in a timely manner as stated in paragraph 9.3.
Spot: A temporarily discolored, marked, soiled area or stain caused by a foreign substance presently or previously on the surface.
Green Initiative: The green initiative covers many facets such as: generating inspection checklists electronically instead of paper, using environmentally safe cleaners, promoting energy-efficiency, etc.
Inspection: Surveillance of the entire Contractor’s work on scheduled and random bases.
Safety Data Sheet (SDS): A document that chemical manufacturers supply with their products to describe the chemical’s general properties, its hazards, and how to safely use, handle and store the product.
Paragraph: For this contract, all occurrences within the contract text of the term “paragraph” shall be understood to include the stated or referenced paragraph and all levels of subparagraphs below the stated or referenced paragraph.
Quality Assurance (QA): Those actions taken by the Government to determine that the services received meet the contract requirements. QA evaluators are Government employees responsible for checking Contractor performance. Quality Control (QC): Those actions taken by the Contractor to ensure that the standards and requirements of the contract are met.
2.07(B) Acronyms Acronym Meaning ANSI = American National Standards Institute AQL = Acceptable Quality Level CDR = Contract Discrepancy Report CO = Contracting Officer COR = Contracting Officer’s Representative CR = Contractor’s Representative GWQS = General Work Quality Standards NEC = National Electric Code NFPA = National Fire Protection Agency PRS = Performance Requirement Summary PWS = Performance Work Statement RSHS = Reclamation Safety & Health Standards QA = Quality Assurance QAE = Quality Assurance Evaluators QASP = Quality Assurance Surveillance Plan QC = Quality Control SDS = Safety Data Sheet TE = Technical Exhibit
2.08 ACCEPTANCE CRITERIA
Work will be accepted if:
i. All tasks conform to manufacturer and code standards
ii. Reports are complete, accurate, and submitted timely
iii. No repeat deficiencies or failures are noted
2.09 SAFETY
i. The Contractor shall not require any Contractor employee in the performance of this contract to work under conditions which are unsanitary, hazardous, or dangerous to the Contractor employee’s health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.), as amended, and the most current version of Reclamation Safety and Health Standards (RSHS), published by the Bureau of Reclamation.
ii. The Contractor shall comply with all applicable safety and occupational health requirements set forth in 29 CFR 1910, Occupational Safety and Health Association (OSHA) General Industry Standards and with the RSHS. In the case of a conflict between 29 CFR 1910, OSHA’s General Industry Standards, 29 CFR 1926, OSHA Construction Industry Regulations, and the RSHS, the more stringent requirements apply. If the Contractor fails or refuses to promptly comply with safety requirements, the CO may issue an order stopping all or part of the work until satisfactory corrective action has been taken.
iii. The Bureau of Reclamation Regional Safety Office will review the Contractor’s “Safety Program” for compliance with the RSHS. Job Hazard Analysis (JHA) submitted for approval must be site-specific and follow guidelines set forth in the RSHS. Both Safety Plan and JHAs must be submitted for approval at least two (2) weeks prior to the start of work.
iv. Reclamation’s objective is to eliminate or minimize exposure to hazards. The primary tool Reclamation uses to do this is the hierarchy of controls, which prioritizes hazard controls in order from most effective to least effective. The hazard controls in the hierarchy are: • elimination, • substitution, • engineering controls, • administrative controls, and • PPE.
Since PPE is the least effective method of hazard control and mitigates the least amount of risk, it must be used in conjunction with other, more effective means of hazard control whenever feasible. All other means of controlling a hazard must be considered and determined infeasible before PPE is selected as the sole primary hazard control.
v. All Reclamation-owned, -controlled, or -occupied facilities and construction sites shall implement Facilities Instructions, Standards, and Techniques (FIST) Volume 1-1, Hazardous Energy Control Program.
vi. The Contractor shall ensure that employees observe safe work practices in accordance with the RSHS and as appropriate for the character of the services performed. The COR will evaluate the public demeanor and ability of the Contractor’s employees to safely perform the work. If the COR determines a Contractor’s employee is unacceptable by reason of inadequate public demeanor or by reason of physical or mental impairment, the COR will contact the CO, who will then request the Contractor or CR remove the employee and provide an adequate substitute. The CR shall provide the substitute within 4 hours of such request.
vii. Reporting Emergencies, Injuries and Illnesses: The Contractor shall call the appropriate emergency services to report incidents such as criminal acts, fires, or medical emergencies. The Contractor shall call the COR immediately to report such incidents as bomb threats, chemical spills, or suspicious packages. The COR will then provide instructions on whether any action should be taken. Regional Office policies and phone numbers may be updated periodically. The Government will provide a copy of all updated policies and phone numbers to the Contractor as necessary. The Contractor shall investigate and report accidents, injuries, or illnesses in accordance with RSHS.
2.10 GENERAL WORK QUALITY STANDARDS (GWQS)
The COR (and alternate COR, if appointed) will be designated in writing at the time of contract award. The COR will inspect work quality and bring any deficiencies to the Contractor’s attention. The Contractor shall remedy such deficiencies within 8 business hours.
The Contractor shall accomplish the specific inspection, service, generator troubleshooting and repair tasks for all the equipment listed in this PWS in accordance with the specific tasks as described below. The Contractor shall designate a person to coordinate with the COR regarding all aspects of these tasks. The Contractor shall provide all management, planning, supervision, administration, equipment, supplies and personnel necessary to ensure the tasks outlined below are performed in a manner that will maintain the full functionality of all BOR electrical power generators.
All generator inspection, service, repair tasks shall be accomplished to meet the requirements of this PWS. The Contractor shall maintain each electrical power generator to the standards established in this contract.
2.10(A) Reporting to BOR
The Contractor or its designated generator repair technician shall report to building 1200, Building and Grounds Maintenance, once he or she has arrived on BOR property.
The technician will meet with the Foreman, Pete Gonzales (702-575-0041, pgonzales@usbr.gov); if he is unavailable, contact the maintenance help desk at 702- 293-8345 or sha-lcr-maintenance@usbr.gov. The Foreman or BOR’s COR will provide a list of generator symptoms to the Contractor’s Representative/generator technician, if the information is known.
2.10(B) Specific Tasks
The Contractor shall follow the manufacturer's recommendation for inspecting, servicing, troubleshooting, and repairing generators. The Contractor shall not make repairs where cost exceeds $500 without written approval from the COR or CO. The Contractor shall notify the COR or CO if the cost of the repair shall be greater than $500. The Contractor shall provide a detailed report of all actions taken to repair the generator to include parts and a cost breakout. The report shall also contain the technician’s name, date, generator location, generator manufacturer and model number; a copy of the report will be provided to the COR or CO within five (5) business days of the repair being completed. The Contractor shall certify that all repairs have been made and that the generator has been returned into service. The Contractor shall also provide copies of all inspections and services, which shall be provided to the COR or CO.
The Contractor shall implement comprehensive inspection, testing preventive maintenance, and repair programs incorporating the manufacturer’s instructions, and complying with the current version of NEC (requirements for generators and standby power systems), OSHA, NFPA 70B/70E, ASME, ANSI, as well as all Federal, State, and county codes and regulations.
At a minimum, the inspection, testing, preventive maintenance, and repair program shall include the following:
a. Periodic inspections, testing and preventive maintenance frequency and schedule
b. Written comprehensive maintenance procedures and schedule incorporating the manufacturer’s instructions to define the tasks and skills required.
c. Qualifications of personnel performing the task.
d. Tools and instruments to perform the work.
e. Inspection and testing checklist including equipment history and record of dates of service, conditions found, maintenance performed, and changes made.
f. Equipment condition assessment before and after maintenance and testing.
g. Supply of spare parts to perform required maintenance.
h. Housekeeping essential for prevention of fires or explosions.
2.11 SECURITY
Contractor shall coordinate access and security requirements with the Technical POC (Escort Required). Vehicle parking at the tail bay requires parking pass obtained from SRF.
2.12 BPA CALL PROCESS
i. All tasks shall be initiated by a written BPA Call
ii. Calls will define scope, location, pricing (T&M or Fixed Price), and deliverables
iii. No work may commence without an authorized BPA Call
2.13 EXCLUSIONS
The following are not included in this contract:
i. Full generator replacements
ii. Major engine overhauls or catastrophic failures
iii. Alternator repairs beyond standard PM
iv. Emission upgrades, fuel tank removal, or control system reprogramming
v. Enclosure repairs (except those caused by contractor)
2.14 POINTS OF CONTACT
i. Contracting Officer: [To be filled in upon award]
ii. Technical Representative: [To be assigned]
Required Submittals
RSN Submittals Required Reference
Paragraph or clause
Number or set to mail to*
Due date or delivery date
CO COR
001 Insurance FAR 52.228-5
1 0 Within 15 calendar days after award
002 Quality Control Plan 2.06 (ii) 1 1 Post-award conference
003 Safety Program 2.09 (iii) Post-award conference
004 Contractor’s
Representative Information
1 1 Post-award conference
005 Generator Inspection Report/ Form
2.04 (i) 1 1 Post-award conference
(initial) and updated during performance of the contract as necessary.
006 Generator Repair Report/Form 2.04 (ii) 1 1 Due to the COR/CO five business days after repairs are complete