Electrostatic Painting for Fayette County Pub.pdf
PDF 334 KB Posted
- Solicitation number
- PE-65615-NONST-2024-000000032
- Issued by
- Fayette County, Georgia
About this file
This document is a Request for Quote (RFQ) issued by the Fayette County Public Schools (FCPS) Purchasing Department for electrostatic painting services for student lockers at Flat Rock Middle and Whitewater Middle Schools. The purpose is to secure firm pricing to provide all materials, equipment, and labor necessary to refinish the lockers using the electrostatic painting method. Respondents must conduct a mandatory site visit by May 31, 2024 and are responsible for all preparatory work, including rust removal and locker number tag replacement. Responses are due by June 5, 2024, and the anticipated project start is in Summer 2024. The contract term is from the date of award issuance until December 31, 2024, with no option to renew.
The RFQ outlines the evaluation criteria, which include but are not limited to price, warranty, service guarantees, past performance, and delivery timelines. FCPS reserves the right to accept or reject any price escalation. Respondents must complete and submit several required forms, including a Solicitation Response Form, Reference Form, Business Capability Form, W-9, Certificate of Insurance, and E-Verify documentation. The RFQ and any resulting contract will be incorporated into the final agreement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1_ Electrostatic Painting for Fayett.pdf | ||
| AWARD Electrostatic Painting for Fayette Coun.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Fayette County Public Schools Purchasing Department
205 LaFayette Ave., Building A, Fayetteville, GA 30214
(770) 460-3535 ext 1043
Request for Quote No. 24-045-075
Georgia Procurement Registry Event No. PE-65615-NONST-2024-000000032
Electrostatic Painting for Fayette County Public Schools Objective
The Fayette County Public Schools Purchasing Department (hereinafter FCPS) invites you to participate in a request for quote (RFQ). This RFQ will consist of providing all materials and labor to refinish lockers using electrostatic painting at Flat Rock Middle and Whitewater Middle Schools, within the school district. The most responsive and responsible respondent will provide installation and demonstration upon delivery to each facility.
Responses Due
Responses to this request for quote are due no later than the date and time specified in the timeline of events either physically or electronically to the FCPS Purchasing Department located at Facilities Services, 939 Goza Road, Fayetteville, Georgia 30215. Quotes received after the specified date and time will not be considered.
Vendors are instructed to carefully read all items, conditions, terms, specifications, and attachments herein and referenced before completing their quote. Failure to comply with any requirements of the RFQ may be a cause for rejection.
Section A: Instructions to Respondents
1. Respondent Registration
1.1. Respondents are encouraged to register with the issuing agent, Jamie Marrero, by sending an email to marrero.jamie@fcboe.org after reviewing this solicitation.
Respondents who register will automatically receive an email update with additional documents such as addenda and be notified of award issuance, even if they choose not to submit a response.
mailto:marrero.jamie@fcboe.org
Electrostatic Painting for Fayette County Public Schools (RFQ 24-045-075)
2. Schedule of Events
2.1. RFQ Released: Monday, May 20, 2024
2.2. Respondent Questions Due: Friday, May 31, 2024
2.3. Addenda Issued (if applicable): Monday, June 3, 2024
2.4. Respondent Quotes Due: Before 10:00AM (EST), Wednesday, June 5, 2024
2.5. Anticipated Project Start: Summer 2024
3. Project Documents and Forms
3.1. Documents and forms required for submission as part of this RFQ can be found on the FCPS Purchasing Department website. Failure to include required submissions listed herein may result in a rejection of the response. A list of required forms is contained herein and additional submissions may be required per the specifications contained herein.
4. Response Delivery
4.1. Responses may be submitted electronically, by mail, or hand-delivered to Facilities Services, 939 Goza Road, Fayetteville, Georgia 30215, Attention:
Purchasing Department.
4.2. Quote openings will occur at the date and time specified at the address above.
4.2.1. No faxed or telephone responses will be accepted or considered.
4.3. Responses may be emailed to the issuing agent if meeting the following guidelines:
4.3.1. Emailed responses must be in a consistent, clear, and readable format and complete. (Adobe PDF format is preferred)
4.3.2. All response documents should be bound in one document. Multiple separate documents may result in evaluation score reductions.
5. Attachments
5.1. Any specification listed with “Must Include Attachment” should include a document within the response conforming to standards set forth.
5.2. All attachments must be marked and labeled using the following format:
Attachment #, Solicitation Reference, Respondent Name, Solicitation Title, and Number.
6. Response Format Requirements
6.1. The solicitation document has been carefully organized. All sections, specifications, requirements, and appendices are numbered; therefore responses should be organized in the same manner referencing the solicitation document when necessary.
6.2. All pages should be numbered and contain page headings or footers with the respondent's name and the solicitation title and number.
6.3. Multiple Response from the Same Respondent
6.3.1. Respondents may submit more than one response when offering multiple alternatives.
6.3.2. Responses must be separate and each should conform to all terms and conditions within the solicitation.
6.3.3. Responses must be labeled separately to easily identify differing responses from the same respondent.
Section B: Scope of Work and Specifications
7. Scope of Work
7.1. The purpose and intent of this Request for Quotation is to secure firm pricing to provide all materials, equipment, and labor necessary to refinish the student lockers at both Flat Rock Middle and Whitewater Middle Schools. This process must include the electrostatic painting of the lockers to provide a long lasting finish. The new paint color should match the existing locker color, unless otherwise modified by Mike Satterfield, Director of Facilities Services. These projects must be completed by the start of the new school year, Monday, August 5, 2024.
8. Site Visit (REQUIRED)
8.1. Site visits must be conducted by vendors planning to bid on this project.
8.1.1. Respondent must request a site visit by contacting Mike Satterfield, Director of Facilities Services, via email (satterfield.mike@fcboe.org)
8.1.2. Site visits will not be scheduled after Friday, May 31, 2024.
mailto:satterfield.mike@fcboe.org
8.1.3. If respondent does not conduct a required site visit, your company could be deemed non-responsive.
9. Technical Specifications
9.1. Respondent is responsible for all preparatory work required to refinish the lockers using the electrostatic painting method.
9.1.1. This includes the removal of rust and/or making repairs that are necessary prior to paint application.
9.1.2. Manufactures preparation specifications must be adhered to.
9.2. Respondent is responsible for completing this project without compromising the combination locks, if the existing lockers have fixed locks.
9.3. Respondent must provide pricing to replace the number tags for each locker.
9.3.1. If the respondent is able to complete the painting process without painting over the current number tags and reserving them for continued use.
9.3.1.1. Respondent must indicate if it is possible to reuse the number tags but must still provide pricing for the replacements.
9.4. Respondent will be responsible for covering all areas exposed to paint overspray.
9.4.1. Any areas or items that are not properly covered and are exposed to overspray, will be the responsibility of the respondent to clean, repair, and/or repaint.
9.4.1.1. This also applies to any paint spills or accidents.
9.5. Respondent is responsible for making sure that the work area is properly ventilated, if required.
9.6. Respondent is responsible for the removal and disposal of any job related debris.
9.6.1. Respondent is not allowed to utilize the school's waste container to dispose of these debris.
Section C: General Terms and Conditions
FCPS’s General Terms and Conditions are posted on the Purchasing Department website under the heading of Vendor Terms, Conditions, and Forms at www.fcboe.org. By submission of a response, the respondent acknowledges they have read and understood these General Terms and Conditions as well as any terms and conditions contained herein.
https://www.fcboe.org/Page/2707
Section D: Special Terms and Conditions
10. Quote Opening
10.1. Quotes will be opened at the date and time provided in the schedule of events. All results will be publicly posted on the FCSD website once an award recommendation is made.
10.2. Quote openings are open to the public.
10.3. Quotes must be marked with the RFQ number.
10.4. Electronically delivered quotes will utilize the timestamp generated on the email.
10.5. Quotes must conform to the guidelines listed herein.
10.6. Quotes received late will be marked “non-responsive” and may not be considered at the sole discretion of the FCPS Purchasing Department.
11. Questions
11.1. All questions concerning this solicitation must be submitted in writing by email to the issuing agent.
11.2. No questions other than written will be accepted and only answers provided via addenda shall be binding.
12. Award Oversight
12.1. The awarded respondent will report to Mike Satterfield, Director of Facilities Services, or their designee.
13. Cooperative Purchasing
13.1. This solicitation allows for other Fayette County, Georgia government entities, including local municipalities, to purchase from the awarded contract at the same prices quoted during the effective term pending an agreement between the awarded respondent(s) and the third party.
14. Quote Evaluations
14.1. According to the Fayette County Board of Education policy, DJE “lowest price alone will not be the sole determining criteria in the selection process”.
14.2. Factors that may be used in evaluating responses may include but are not limited to, the following: price/cost, warranty, service guarantees or past performance, costs of ownership analysis, business capabilities analysis, delivery schedules and methods, and product-specific manufacturer/quality standards.
14.3. Respondents may inquire as to specific evaluation methods and may request in writing an explanation of evaluation methods used to determine an award. See General Terms and Conditions regarding award protests.
15. Cost Escalation/Price Change
15.1. The Purchasing Department recognizes that independent market factors may result or necessitate the need for price changes. Through the submission of a quote, the respondent agrees to the following:
15.2. All price increases must be based upon product cost ONLY, and documentation of the price increase is required.
15.3. Quote prices must be held firm for the term of the solicitation or December 31st of the issuing year, after which an escalator can be invoked.
15.4. The awarded respondent must provide the FCPS Purchasing Department written notification at a minimum of 30 days before a price escalation change.
15.5. Single changes of no more than 10% are allowed. There are exceptions only when market conditions dictate a revised escalator for a particular commodity.
15.6. FCPS reserves the right to accept or reject any price escalation. A rejection of a price escalation may result in the termination of any agreement, contract, purchase order, or other agreement without fault or obligation.
16. Installation
16.1. Installation and application process must be within the Manufacturers specifications as well as the work scope outlined in solicitation.
17. Quantities
17.1. Projects listed within this solicitation are not guaranteed. Purchase orders and/or contracts will be issued for specific projects, as needed, for the term duration.
Fayette County Public Schools anticipates that these projects will be completed.
But, the approval will be determined by the available budget allotment.
18. Term
18.1. The term of this RFQ and resulting agreement is from the date of resulting award issuance until December 31, 2024, with no option to renew.
18.2. Per the General Terms & Conditions, should the Fayette County Board of Education fail to appropriate funding for each fiscal year beginning July 1st, this solicitation and resulting contract or purchase orders will be canceled with no-fault or obligation beyond products or services already received and properly invoiced.
18.2.1. FCPS may notify the awarded bidder in writing thirty (30) days prior to cancellation for non-appropriation.
19. Required Forms
19.1. The forms listed below are required for submission and included as attachments.
They may also be located on FCPS’s Purchasing Department website at www.fcboe.org.
19.1.1. Solicitation Response Form
19.1.2. Reference Form
19.1.3. Business Capability Form
19.1.4. W-9 Document
19.1.5. Certificate of Insurance (Meeting the minimum requirements listed in FCPS General Terms and Conditions)
19.1.6. E-Verify Documentation
19.2. Failure to include any form may result in a reduction in evaluation scoring or the submitted quote being declared non-responsive at the sole discretion of the FCPS Purchasing Department.
19.3. This request for quote, any addenda, and the awarded quote will be incorporated into any resulting contract and/or purchase order.
https://www.fcboe.org/Page/2707
Cost Proposal
Flat Rock Middle School Project (325 Jenkins Road, Tyrone, Georgia 30290)
Locker Quantity: _____________
Total Cost to Refinish Lockers using Electrostatic Painting Process: $__________________
Total Cost to Replace Number Tags on all Lockers: $________________
Total Project Cost Combined (including materials, equipment, and labor): $_________________
Whitewater Middle School Project (1533 GA-85, Fayetteville, Georgia 30215)
Locker Quantity: _____________
Total Cost to Refinish Lockers using Electrostatic Painting Process: $__________________
Total Cost to Replace Number Tags on all Lockers: $________________
Total Project Cost Combined (including materials, equipment, and labor): $_________________
Total Cost of Flat Rock and Whitewater Middle Schools Projects Combined:
Company Name Date
Printed Name Signature
Respondent Information Form
Place this form on top of your response.
Electrostatic Painting for Fayette County Public Schools (RFQ 24-045-075)
Company Name:
Point of Contact:
Street Address:
City:
State:
Zip Code:
Telephone:
Email:
Website:
Authority to Act
The undersigned states that he/she has the requisite authority to act on behalf of his/her employer in these matters and has offered to provide the products/services in accordance with the terms and conditions herein.
Terms, Conditions, and Specifications
Through the submission of response and signature below, the respondent verifies that their solution, if applicable, complies fully, or complies with an exception, to all stated general and special terms, conditions, and specifications. See the FCPS General Terms and Conditions for further information and directions on notating exceptions to stated specifications.
Addenda
Through the submission of response and signature below the respondent verifies that they have read and understood any addenda issued for this solicitation if issued.
Signature: _____________________________________ Date: _______________________
Business Capability and Respondent Qualification Questionnaire
Please answer all questions fully. Additional pages for responses must be clearly marked to identify the respondent’s name and solicitation number.
1) How long has your company been in business?
2) What was your annual gross revenue in 2023?
3) Please indicate current contracts in hand similar to the scope of this project and attach a separate document indicating the name, telephone, and email of each owner/controlling firm; and the status and completion date of each. (Must Include Attachment).
4) Does your company have experience in public school services? List all public school projects completed in Georgia since 2015.
5) Has your company ever completed a project more than one month behind schedule? If so, please identify the project and explain the circumstances. (If applicable, must include an attachment.)
6) Has your company ever failed to complete any work awarded to it? If so, please explain.
(If applicable, must include an attachment.)
7) Has your company ever defaulted on a contract? If so, please explain. (If applicable, must include an attachment.)
8) Please indicate your company’s bonding capacity.
9) Please indicate your company’s insurance carrier.
10) Please indicate whether any insurance claim has been made against or by your company in the past seven (7) years, the circumstances surrounding such claims, and the outcome.
(If applicable, must include an attachment.)
11) Please indicate whether any legal claim, administrative hearings and/or procedings has been made against your company in the past seven (7) years (including starte and federal Department of Labor as well as OSHA), the circumstances surrounding such claims, and the adjudicated outcome. (If applicable, must include an attachment.)
12) Please list bank reference:
13)Has your company ever had a bankruptcy petition, arbitration demand, or lien filed against it in the previous seven (7) years? If so, please explain. (If applicable, must include an attachment.)
14)Has your company, any principal officers, or project managers had any criminal investigations or proceedings brought against them in the previous ten (10) years? If so, please explain. (If applicable, must include an attachment.)
15) Please attach a separate list of all employees who will be assigned to work on the project described herein and include any professional licenses or certifications they hold. (Must Include Attachment)
The respondent attests that the information included as attachments and responses are true and accurate as of the date of submission. Respondent also agrees by submission to allow Fayette County Public Schools to review or investigate any response contained herein. Respondent may be required to submit recent financial statements/reports and should indicate any objection herein. Failure to indicate or answer questions may deem the proposal non-responsive.
Notarized
Reference Form
Requested Information Response
Reference Name
Contact for Reference
Street Address
City, State, Zip
Phone Number
Requested Information Response
Reference Name
Contact for Reference
Street Address
City, State, Zip
Phone Number
Requested Information Response
Reference Name
Contact for Reference
Street Address
City, State, Zip
Phone Number
FAYETTE COUNTY PUBLIC SCHOOLS - PURCHASING DEPARTMENT
GEORGIA SECURITY & IMMIGRATION COMPLIANCE ACT FORM
GEORGIA SECURITY AND IMMIGRATION COMPLIANCE ACT OF 2006, AS AMENDED BY
THE ILLEGAL IMMIGRATION REFORM ACT OF 2011, OCGA 13-10-90, ET SEQ.
TO ALL PROSPECTIVE CONTRACTORS:
If you are providing services to Fayette County Public Schools, this completed document, as well as the applicable Georgia Security and Immigration Compliance forms and affidavits referenced herein must be completed, signed, notarized and submitted with your bid, proposal or contract.
Fayette County Public Schools shall comply with the Georgia Security and Immigration Compliance Act, as amended, O.C.G.A.,~13-10-90 et seq. In order to ensure compliance with the Immigration Reform and Control Act of 1986 (IRCA,P.L.99-603 and the Georgia Security and Immigration Compliance Act of 2006, as amended by the Illegal Immigration Reform Act of 2011,O.C.G.A ~ 13-10-90 et seq. (collectively the “Act”) the contractor (“Contractor”) MUST INITIAL the statement applicable to Contractor below:
INITIAL ONLY ONE CHOICE BELOW
____ (Initial here) Contractor represents and warrants that Contractor has registered at https://e-verify.uscis.gov/enroll/ to verify information of all new employees in order to comply with the Act; Is authorized to use and uses the federal authorization program; and will continue to use the authorization program throughout the contract period. Contractor further represents, warrants and agrees that it shall execute and return any and all affidavits required by the Act and the rules and regulations issued by the Georgia Department of Labor as set forth at Rule 300-10-1-01 et.seq. In accordance with the terms thereof; (Complete and submit the Contractor Affidavit and Agreement); OR
____ (Initial here) Contractor represents and warrants that it has no employees and does not intend to hire employees to perform contractual services, and that Contractor has therefore provided a U.S. state-issued Driver’s license or ID card in lieu of an affidavit and that such license or ID card was issued by a State that verifies lawful Immigration status before issuing the license or ID card. If my status changes I will, before hiring any employees, immediately notify the School District in writing and provide all affidavits required under the Act; OR
____ (Initial here) Contractor represents and warrants that it does not physically perform any service within the State of Georgia as defined in the Act and thus does not have to comply with foregoing Georgia law; OR
_____(Initial here) Contractor is a foreign company and therefore not required to provide the affidavit as required by the Act. The Contractor must comply with any other laws required to perform services in the United States, including but not limited to having an appropriate visa.
USE OF SUBCONTRACTOR(S) and COMPLIANCE AS ABOVE
___(Initial here) Contractor will not employ or contract with any subcontractor in connection with a covered contract unless the subcontractor is registered, Is authorized to use, and uses the Federal Work Authorization Program and provides Contractor with all affidavits required by the Act and the rules and regulations issued by the Georgia Department of labor as set forth at Rule 300-10-01 et seq.
____(Initial here) Contractor covenants and agrees that, if Contractor employs or contracts with any Subcontractor in connection with the covered contract under the Act and DOL Rule 300-10-1-02, then in such event Contractor will secure from each subcontractor at the time of the subcontract, the subcontractor’s name and address, the employer identification number/taxpayer identification number applicable to the subcontractor; the date the authorization to use the Federal Work Authorization Program was granted to subcontractor; the subcontractor’s attestation of the subcontractor’s compliance with the Act and Georgia Department of Labor Rule 300-10-1-.2.; and the subcontractor’s agreement not to contract with subcontractors unless the subcontractor is registered, authorized to use, and uses the Federal Work Authorization Program; and provides subcontractor with all affidavits required by the Act and the rules and regulations issued by the Georgia Department of Labor as set forth at Rule 300-10-1-01 et seq. (Complete and submit the Subcontractor Affidavit and Agreement)
_____(Initial here) Contractor agrees to provide Fayette County Public Schools with all affidavits of compliance as required by the Act and Georgia Department of Labor Rule 300-10-1-02, 300-10-1-03, 300-10-1-07 and 300-10-1-08 within five (5) business days of its receipt of any such documents.
Company Name: _____________________________________________________________
SIGNATURE: __________________________________________________________________
DATE: __________________________________________
CONTRACTOR AFFIDAVIT PROVIDED PURSUANT TO O.C.G.A. § 13-10-91(b)(2)
(Rev. 4/18/2019)
By executing this affidavit, the undersigned contractor verifies its compliance with O.C.G.A. § 13-10-91 stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services under a contract with Fayette County Public Schools, has registered with, is authorized to use, and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned contractor covenants that it will continue to use the federal work authorization program throughout the contract period, that the undersigned contractor will contract for the physical performance of services in the performance of such contract only with subcontractors who present an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b), and that the contractor shall forward any subcontractor’s affidavit to the School District within five (5) days of its receipt of the same.
Contractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:
EEV User Identification Number (4 to 6 Digit Number)
Date of Authorization
Contractor/Company
Email Address
Telephone Number
Name of Project
Project Number
Name of Public Employer
I hereby declare under penalty of perjury that the foregoing is true and correct.
Executed on , 20 in (city), (state).
Signature of Authorized Officer or Agent
Printed Name of Authorized Officer or Agent Title of Authorized Officer or Agent
NOTARY INFORMATION
Sworn to before me this day of , 20 .
Notary Public Signature
My Commission Expires: ____________________________
SUBCONTRACTOR AFFIDAVIT PURSUANT TO O.C.G.A. § 13-10-91(b)(3)
(Rev. 4/18/2019)
By executing this affidavit, the undersigned subcontractor verifies its compliance with O.C.G.A. § 13-10-91 stating affirmatively that the individual, firm or corporation which is engaged in the physical performance of services under a contract with ___________________, which has a contract with Fayette County Public Schools, has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the undersigned subcontractor covenants that it will continue to use the federal work authorization program throughout the contract period, that the undersigned subcontractor will contract for the physical performance of services in the performance of such contract only with sub-subcontractors who present an affidavit to the subcontractor with the information required by O.C.G.A. § 13-10-91(b), and that the subcontractor shall forward any sub-subcontractors affidavit to the contractor and School District within five (5) days of its receipt of the same.
Subcontractor hereby attests that its federal work authorization user identification number and date of authorization are as follows:
EEV User Identification Number (4 to 6 Digit Number)
Date of Authorization
Subcontractor/Company
Email Address
Telephone Number
Name of Project
Project Number
Name of Public Employer
I hereby declare under penalty of perjury that the foregoing is true and correct.
Executed on , 20 in (city), (state).
Signature of Authorized Officer or Agent
Printed Name of Authorized Officer or Agent Title of Authorized Officer or Agent
NOTARY INFORMATION
Sworn to before me this day of , 20 .
Notary Public Signature
My Commission Expires: ____________________________
| Electrostatic Painting for Fayette County Public Schools (RFQ 24-045-075) |
| Respondent Information Form_ RFQ 24-045-075 |
| Copy of Business Capability and Respondent Qualification Form |
| Reference Form_ RFQ 24-045-075 |
| E-Verify Compliance Form & Affidavit_ RFQ 24-045-075 |
File details come from the government source that posted it. Updated .