Summary of Electrical Drawings for Illinois Secretary of State Chicago West Facility Boiler Replacement

This document comprises electrical drawings and specifications prepared by a licensed architect/engineer for the Illinois Secretary of State's boiler replacement project at the Chicago West facility located at 5301 W. Lexington Street, Chicago, Illinois 60644. The project involves the installation of new condensing boilers (CB-2 and CB-3) and associated electrical infrastructure, including new constant flow pumps (HWP-7 and HWP-8), control systems, and wiring modifications to existing electrical distribution panels. The electrical work includes the installation of new branch circuits, conduit runs, panelboard connections, and equipment connections in compliance with the 2019 Chicago Building Code, the 2018 Illinois Accessibility Code, and the 2018 Chicago Electrical Code. The drawings were issued for 50% review on May 9, 2025, for review on August 1, 2025, and for 75% review on August 13, 2025. All work must be performed by licensed electrical contractors and coordinated with the project architect, engineer, owner's representative, and other construction trades to ensure minimal disruption to building operations.

The specifications establish comprehensive requirements for materials, labor, and installation procedures, mandating that all electrical equipment, including panelboards and disconnects, be sourced from approved manufacturers (GE, Square D, or approved equivalents) and comply with UL, ETL, or CSA listings. Contractors are required to provide temporary lighting and power throughout construction, perform all cutting and patching of existing structures, install UL-approved firestopping compounds for raceway penetrations in fire-rated assemblies, and submit as-built drawings in AutoCAD format with three sets of hard copies upon completion. The project specifies minimum conduit sizes of 3/4 inch, copper wiring with 75-degree Celsius insulation, and branch circuit protection sized according to the Chicago Electrical Code, with specific amperage and wire gauge requirements detailed for various load configurations. Contractors must conduct thorough site inspections prior to bidding, coordinate all shutdowns with the owner's representative at least 48 hours in advance, and maintain daily debris removal and site protection throughout construction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ILLINOIS SECRETARY

OF STATE CHICAGO

WEST FACILITY

BOILER REPLACEMENT

5301 W. LEXINGTON ST.,

CHICAGO, IL 60644

SHEET NO.

DESIGN BY: RO

DRAWN BY: SMA

CHECKED BY: PBL

PROJECT NO.

ISSUE DESCRIPTION DATEREV.

ISSUED FOR 50% REVIEW 05/09/2025

I HAVE PREPARED OR CAUSED TO BE PREPARED UNDER MY DIRECT

SUPERVISION, THE ATTACHED PLANS AND SPECIFICATIONS. I STATE

THAT, TO THE BEST OF MY KNOWLEDGE AND BELIEF AND TO THE

EXTENT OF MY CONTRACTUAL OBLIGATION, THEY ARE IN

COMPLIANCE WITH THE 2019 CHICAGO BUILDING CODE

MANDATED BY THE CITY OF CHICAGO BUILDING

DEPARTMENT/CODE ENFORCEMENT AND THE ILLINOIS

ACCESSIBILITY CODE, 2018 EDITION

STATEMENT OF COMPLIANCE

SIGNED:

INDIANA REGISTRATION NO.:

DATE:

ARCHITECT/ENGINEER

623 COOPER COURT

SCHAUMBURG, IL 60173

(312) 346-8181

CITY APPROVAL STAMP BOX

N

ILLINOIS SECRETARY OF STATE

KEY PLAN

ISSUED FOR REVIEW 08/01/2025

ISSUED FOR 75% REVIEW 08/13/2025

E-000

ELECTRICAL

SPECIFICATIONS,

GENERAL NOTES, AND

SYMBOLS

CONDUIT CONCEALED IN FLOOR SLAB

WIREWAY

OR UNDERGROUND

FLEXIBLE CONDUIT CONNECTION

CONCEALED CONDUIT

RACEWAYS & WIRING

HOMERUN TO PANEL

EXPOSED CONDUIT

PHASE WIRE IN CONDUIT

GROUND WIRE IN CONDUIT

NEUTRAL WIRE IN CONDUIT

NEW WORK

TO BE REMOVED

KEY NOTE TAG

EXISTING TO REMAIN

HVAC/MECHANICAL EQUIPMENT TAG

XR

X

N

GENERAL

GROUND

TRANSFORMER

NON-MOTOR LOAD (NUMBER INDICATES kW)

CONTROL OR MISCELLANEOUS PANEL AS NOTED

POWER OR DISTRIBUTION PANELBOARD

LIGHTING OR RECEPTACLE PANELBOARD

NON-FUSED DISCONNECT SWITCH

CONTACTOR

DISCONNECT SWITCH

DISCONNECT SWITCH

FUSED DISCONNECT SWITCH

AS REQUIRED.

JUNCTION BOX

COMBINATION STARTER WITH NON-FUSED

JUNCTION BOX AND FLEXIBLE CONNECTION

MOTOR (NUMBER INDICATES HORSEPOWER)

CONDUIT STUB-UP AND JUNCTION BOX

COMBINATION STARTER WITH FUSED

STARTER

POWER

F

J

AMPERE

ALTERNATING CURRENT

ABOVE FINISHED FLOOR

ABOVE FINISHED GRADE

AMPERES INTERRUPTING CAPACITY

BUILDING

BREAKER

BOLTED PRESSURE SWITCH

CONDUIT

CIRCUIT BREAKER

CIRCUIT

CEILING

DIRECT CURRENT

DISCONNECT

DISCONNECT SWITCH

DOWN

DISTRIBUTION PANEL

DRAWING

EXISTING

EACH

ELECTRICAL CONTRACTOR

EXHAUST FAN

EMERGENCY LIGHTING CONTROL PANEL

EMERGENCY

ELECTRICAL METALLIC TUBING

ELECTRIC WATER COOLER

ELECTRIC WATER HEATER

FIRE ALARM

FIRE ALARM ANNUNCIATOR

FIRE ALARM CONTROL PANEL

FIRE ALARM EQUIPMENT PANEL

FIXTURE

FLOOR

FUSE

FULL VOLTAGE, NON-REVERSING

FULL VOLTAGE, REVERSING

GENERATOR

GROUND FAULT CIRCUIT INTERRUPTER

GROUND

GALVANIZED RIGID STEEL

HEATING AND AIR-CONDITIONING RATED

HAND-OFF-AUTO

HORSEPOWER

HEATER

ISOLATED GROUND

INTERMEDIATE METAL CONDUIT

JUNCTION BOX

KILOWATT

KILOVOLTAMPERES

LIGHT-EMITTING DIODE

LIGHTING CONTROL PANEL

LIGHTING PANEL

LIGHTING

MAXIMUM

MINIMUM

MANUFACTURER

MAIN LUG ONLY

MOUNTED

MOUNTING

MOTOR

NEUTRAL, NORMAL

NATIONAL ELECTRICAL CODE

NUMBER

NOT IN CONTRACT

NOT TO SCALE

OCCUPANCY SENSOR

PULLBOX

PANEL

PERCENT IMPEDENCE

PHASE

POWER PANEL

RECEPTACLE

REQUIRED

RIGID GALVANIZED STEEL

RECEPTACLE PANEL

SEPARATE CIRCUIT

SWITCH

SWITCHBOARD

TELEPHONE

TELEPHONE TERMINATION BOARD

TELEPHONE TERMINATION CABINET

TYPICAL

UNLESS OTHERWISE NOTED

UNDERWRITERS LABORATORY

VOLT

WEATHERPROOF

TRANSFORMER

A

AC

AFF

AFG

AIC

BLDG

BKR

BPS

C C/B

CCT

CLG

DC

DISC

DS

DN.

DP

DWG.

(E)

EA.

EC

EF

ELCP

EM

EMT

EWC

EWH

FA

FAA

FACP

FAEP

FIXT.

FL.

FU

FVNR

FVR

GEN

GFCI

GND

GRS

HACR

HOA

HP

HTR

IG

IMC

JB

KW

KVA

LED

LCP

LP

LTG.

MAX.

MIN.

MANUF

MLO

MTD

MTG

MTR

N

NEC

NO

NIC

NTS

OS

PBX

PNL

%Z Ø

PP

REC

REQ'D

RGS

RP

SC

SW

SWBD

TELE

TTB

TTC

TYP

U.O.N.

U.L.

V

WP

XFMR

ELECTRICAL SPECIFICATIONS AND GENERAL NOTES

1. THE CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIAL

NECESSARY FOR A COMPLETE AND FUNCTIONING ELECTRICAL

SYSTEM.

2. ALL WORKMEN PERFORMING WORK UNDER THE SCOPE OF

WORK SHALL BE LICENSED (OR CERTIFIED) SKILLED IN THEIR

RESPECTIVE TRADE.

3. ALL WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE

FOLLOWING APPLICABLE CODES AND STANDARDS:

- 2018 CHICAGO ELECTRICAL CODE

- NATIONAL ELECTRICAL SAFETY CODE (NESC)

- LAWS AND ORDINANCES OF FEDERAL & LOCAL AUTHORITIES

- OCCUPATIONAL HEALTH AND SAFETY ADMINISTRATION

(OSHA)

- UNDERWRITERS LABORATORIES (UL)

- FACTORY MUTUAL RESEARCH CORPORATION (FM)

- INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS

(IEEE)

- INSULATED CABLE ENGINEERING ASSOCIATION (ICEA)

- AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

- NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION

(NEMA)

- NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

- INTERNATIONAL ENERGY CONSERVATION CODE (IECC) 2018

4. MATERIALS AND EQUIPMENT SHALL BE LISTED AND/OR

LABELED BY U.L., E.T.L., C.S.A.

5. THE CONTRACTOR SHALL CAREFULLY EXAMINE THE

CONTRACT DOCUMENTS, VISIT THE SITE AND THOUROUGHLY

BECOME FAMILIAR WITH THE BUILDING STANDARDS AND

LOCAL CONDITIONS RELATING TO THE WORK. FAILURE TO DO

SO WILL NOT RELIEVE THE CONTRACTOR OF THE

OBLIGATIONS OF THE CONTRACT.

6. THE CONTRACTOR IS RESPONSIBLE FOR CLEAN-UP AND

REMOVAL FROM THE PREMISES OF ALL WASTE MATERIALS,

RUBBISH, WRAPPING, AND SALVAGES AS GENERATED BY THE

CONSTRUCTION.

7. CONSTRUCTION OPERATIONS SHOULD BE SCHEDULED WITH

ARCHITECT AND OWNER.

A. ALL DRILLING SHALL BE ACCOMPLISHED DURING STATED

WORKING HOURS.

B. CONTRACTOR SHALL VERIFY ALLOWED HOURS WITH

OWNER.

8. CONSTRUCTION WORK SHALL BE CONFINED TO THE SPACE

SHOWN ON THE PLANS AND ASSOCIATED INFRASTRUCTURE

SUPPORT SPACE. WORK INCLUDED UNDER THIS CONTRACT

SHALL NOT CREATE DUST, DIRT OR OTHER SUCH

INCONVENIENCES TO BUILDING ACTIVITIES.

9. THE CONSTRUCTION PROCEDURE INCLUSIVE OF MATERIAL

STORAGE, WASTE STORAGE, WORK IN PROGRESS, ETC, SHALL

NOT BLOCK HALLWAYS OR MEANS OF EGRESS OF THE

BUILDING. SHOULD IT BE NECESSARY TO OBSTRUCT A

HALLWAY OR OTHER MEANS OF EGRESS, AN ALTERNATE

CONSTRUCTION SCHEDULE SHALL BE INCLUDED AS PART OF

THE BASE BID AND NOT CONSIDERED AS AN EXTRA SERVICE.

10. THE CONTRACTOR SHALL PROVIDE TEMPORARY LIGHTING,

POWER AND WIRING FOR THE PERFORMANCE OF ALL TRADES,

FOR THE ENTIRE PERIOD OF THE CONSTRUCTION AND SHALL

REMOVE ALL TEMPORARY WIRING AT THE COMPLETION OF

CONSTRUCTION.

11. EXCEPT AS NOTED OTHERWISE, ALL WORK REQUIRED FOR

THE INSTALLATIONS AS SHOWN ON DRAWINGS INCLUDING

LABOR, EQUIPMENT AND MATERIALS SHALL BE IN STRICT

COMPLIANCE WITH ALL APPLICABLE CODES.

12. IF DAMAGE OCCURS TO THE SURFACES AND FINISHES WHICH

ARE TO REMAIN DURING DEMOLITION OR ANY STAGE OF

WORK, IT SHALL BE REPAIRED AND RESTORED BY THE

CONTRACTOR AT HIS EXPENSE TO ITS ORIGINAL CONDITION.

13. THE CONTRACTOR SHALL NOTIFY THE OWNER/ARCHITECT OF

ANY MATERIALS OR APPARATUS BELIEVED TO BE

INADEQUATE, UNSUITABLE, IN VIOLATION OF LAWS,

ORDINANCES, RULES OR REGULATIONS OF AUTHORITIES

HAVING JURISDICTION.

14. NOTIFY ENGINEER AND OWNER OF CONFLICTS BETWEEN

DRAWINGS, SPECIFICATIONS, AND FIELD CONDITIONS BEFORE

SUBMITTAL OF PROPOSAL.

15. THE CONTRACTOR SHALL PROVIDE LIGHTING AND POWER IN

LOCATIONS ILLUSTRATED ON THE PLANS WITH CIRCUITRY AS

INDICATED.

16. ALL MATERIALS AND EQUIPMENT SHALL BE ERECTED,

INSTALLED, CONNECTED, CLEANED, ADJUSTED, TESTED,

CONDITIONED AND PLACED IN SERVICE IN ACCORDANCE WITH

THE MANUFACTURER'S DIRECTIONS AND RECOMMENDATIONS,

UNLESS OTHERWISE SPECIFIED ON THE PLANS.

17. ALL CUTTING, DRILLING AND PATCHING OF MASONRY, STEEL

OR IRON WORK BELONGING TO THE BUILDING MUST BE DONE

BY THIS CONTRACTOR IN ORDER THAT THE WORK MAY BE

PROPERLY INSTALLED, BUT UNDER NO CONDITIONS SHALL

ANY STRUCTURAL MEMBER BE CUT, EXCEPT AT THE

DIRECTION OF THE ARCHITECT/ENGINEER.

18. ALL PENETRATIONS THROUGH NON-FIRE RATED

CONSTRUCTION SHALL BE SLEEVED, SEALED AND PATCHED

TO MATCH EXISTING SURFACES.

19. REFER TO DRAWINGS FOR EXACT LOCATIONS AND MOUNTING

HEIGHTS OF ELECTRICAL EQUIPMENT AND WIRING DEVICES.

20. PROVIDE "AS-BUILT" DRAWINGS AND SUBMIT FOR APPROVAL

TO THE ARCHITECT/ENGINEER. AS-BUILTS SHALL BE

SUBMITTED ON AUTOCAD DISC AND (3) SETS OF FULL SIZE

HARD COPIES.

21. ALL MATERIAL, EQUIPMENT, WIRING DEVICES, ETC. SHALL BE

NEW, UNLESS SPECIFICALLY INDICATED AS EXISTING TO BE

REUSED.

A. ALL NEW RECEPTACLES SHALL BE PROVIDED AS INDICATED

ON PLANS AS NEMA 5-20R UNLESS INDICATED OTHERWISE.

B. ALL NEW SWITCHES SHALL BE PROVIDED AS INDICATED ON

PLANS.

22. MINIMUM CONDUIT SIZE SHALL BE 3/4".

23. ALL WIRES SHALL BE COPPER, 75°C, 600V INSULATION,

STRANDED TYPE, UNLESS OTHERWISE NOTED.

A. FOR INTERIOR DRY LOCATIONS TYPE THWN

THERMOPLASTIC 600 VOLT INSULATED COPPER CONDUCTORS

SHALL BE USED.

B. FOR EXTERIOR WET LOCATIONS TYPE XHHW

POLYETHYLENE 600 VOLT INSULATED COPPER CONDUCTOR

SHALL BE USED.

C. WIRE SMALLER THAN #10 AWG MAY BE SOLID OR

STRANDED, WIRE #10 AWG AND LARGER SHALL BE STRANDED.

D. NO WIRE SMALLER THAN #12 AWG SHALL BE USED FOR

POWER, LIGHTING OR BRANCH CIRCUIT WIRING.

24. IN SUSPENDED CEILINGS, SUPPORT CONDUIT AND JUNCTION

BOXES DIRECTLY FROM THE STRUCTURAL SLAB, DECK, OR

FRAMING PROVIDED FOR THAT PURPOSE. BRANCH CIRCUIT

CONDUITS SHALL NOT BE CLIPPED TO THE CEILING SUPPORT

WIRES, SPLINE OR MECHANICAL DUCTS, PIPES, ETC.

25. ALL HANGERS, CLAMPS, FITTINGS AND RODS SHALL BE

MALLEABLE STEEL AND EITHER U.L., NEMA OR ANSI

APPROVED. ALL HANGERS, CLAMPS, FITTINGS AND RODS

SHALL BE HOT-DIPPED GALVANIZED STEEL WHERE SUBJECT

TO CORROSION.

26. NUMBERED CIRCUITS ARE SHOWN FOR THE CONVENIENCE OF

DESIGN ONLY. DESIGN INTENT MUST BE FOLLOWED

THROUGHOUT, INDICATE THE ACTUAL CIRCUIT NUMBERS

USED ON THE "AS-BUILT" DRAWINGS. EMERGENCY PANEL

CIRCUIT NUMBERS MAY VARY. ACTUAL FIELD CONDITIONS

SHALL BE VERIFIED.

27. BRANCH CIRCUIT WIRING:

A. BRANCH CIRCUIT HOMERUNS SHALL HAVE DEDICATED

PHASE, NEUTRAL AND EQUIPMENT GROUND CONDUCTORS

FOR EACH LINE TO NEUTRAL CIRCUIT. WHERE HOMERUN

EXCEEDS 100 LINEAR FEET, CONDUCTOR SIZE SHALL BE

INCREASED ONE WIRE GAUGE, UON.

B. BRANCH CIRCUIT WIRING SHALL BE AS FOLLOWS FOR 3

PHASE LOADS, WITH ASSOCIATED BRANCH CIRCUIT

PROTECTION, UON.

20A-3#12AWG + #12AWG GROUND IN 3/4"C

30A-3#10AWG + #10AWG GROUND IN 3/4"C

40A-3#8AWG + #10AWG GROUND IN 3/4"C

50A-3#8AWG + #10AWG GROUND IN 3/4"C

60A-3#6AWG + #10AWG GROUND IN 3/4"C

28. ALL ELECTRICAL DISTRIBUTION EQUIPMENT I.E.

PANELBOARDS, DISCONNECTS, TRANSFORMERS, MOTOR

STARTERS, ETC. SHALL BE OF ONE MANUFACTURER.

APPROVED MANUFACTURERS: GE, SQUARE"D", OR APPROVED

EQUAL.

29. ALL INSTALLATIONS SHALL HAVE EQUIPMENT GROUNDING

CONDUCTORS SIZED IN ACCORDANCE WITH ARTICLE 250 OF

THE CHICAGO ELECTRICAL CODE.

30. ALL ELECTRICAL DRAWINGS ARE TO BE READ IN

CONJUNCTION WITH THE ENTIRE PROJECT SPECIFICATIONS

AND ALL OTHER TRADE DRAWINGS RELATED TO THE

PERFORMANCE OF THE ENTIRE SCOPE OF WORK.

31. BECOME THOROUGHLY FAMILIAR WITH THE PROJECT

SPECIFICATIONS PRIOR TO COMMENCING ANY WORK. THE

PROJECT SPECIFICATIONS AND DRAWINGS FORM THE BASIS

OF THE CONTRACT REQUIREMENTS AND INCLUDE THE TYPE

AND GRADE OF MATERIALS TO BE USED, EQUIPMENT TO BE

FURNISHED, THE MANNER BY WHICH TO BE INSTALLED AND

WHERE TO BE LOCATED.

32. CHECK CAREFULLY ALL CONSTRUCTION DRAWINGS AND

SPECIFICATIONS THAT ARE PART OF THIS PROJECT TO

ENSURE THAT NO FIXTURE, OUTLET, CONTROL OR POWER

WIRING IS OMITTED. CONSULT ALL TRADES FURNISHING

EQUIPMENT AND OBTAIN FROM THEM ALL DATA. IN SOME

CASES, EQUIPMENT, FIXTURES AND DEVICES ARE SHOWN

ONLY. ASCERTAIN AND PROVIDE THE WIRING AND CONTROL

STATIONS REQUIRED FOR THE PROPER OPERATION OF

BUILDING EQUIPMENT. NO EXTRA CHARGES WILL BE

ACCEPTED BY OWNER AFTER BIDDING FOR SUCH EQUIPMENT

AND LABOR.

33. EQUIPMENT LABELS AND INSTRUCTIONS REGARDING THE

APPLICATION AND INSTALLATION OF THE LISTED EQUIPMENT

SHALL BE FOLLOWED TO ENSURE THAT THE EQUIPMENT IS

BEING USED IN ACCORDANCE WITH THE MANUFACTURER'S

LISTING INSTRUCTIONS. THE TEMPERATURE RATING AND LUG

SIZES OF THE EQUIPMENT TERMINATIONS MUST BE

CAREFULLY COORDINATED WITH THE SPECIFIED CONDUCTOR

AMPACITY TO PREVENT OVERHEATING AND PREMATURE

FAILURE.^p

34. CONDUIT RUNS SHOWN ON DRAWINGS ARE DIAGRAMMATIC.

ALL CONDUITS SHALL RUN CONCEALED, EXCEPT IN

EQUIPMENT ROOMS.

35. COORDINATE LOCATION OF ALL ELECTRICAL & DATA OUTLETS

WITH MILLWORK AND ARCHITECTS PRIOR TO ROUGH-IN.

36. ELECTRICAL CONTRACTOR SHALL VISIT SITE AND BECOME

FAMILIAR WITH ALL ASPECTS AND REQUIREMENTS FOR THIS

PROJECT.

37. USE CAUTION IN WORK AS ACTUAL CONDITIONS MAY VARY

FROM ORIGINAL DOCUMENTS AS WELL AS OBTAINED IN BRIEF

OBSERVATIONS FROM A/E SITE VISITS. ALL CONDITIONS SHALL

BE DETERMINED IN FIELD BY CONTRACTOR. DO NOT

DISCONNECT ANY POWER, ALARM AND COMMUNICATION

WIRING WITHOUT CONSULTATION AND APPROVAL OF OWNER.

38. BRING ALL QUESTIONS TO THE OWNER FOR DIRECTIONS

BEFORE PROCEEDING WITH WORK. FIELD COORDINATION IS

ESSENTIAL.

39. ALL RECEPTACLES, DATA OUTLETS, LIGHT SWITCHES, FIRE

ALARM SYSTEM, ETC. IN THE SCOPE OF THIS PROJECT SHALL

BE NEW & LABELED WITH PROPER I.D. TAGS, UON.

40. PROVIDE ALL ADDITIONAL HARDWARE FOR FIXTURE

MOUNTING AS REQUIRED, AT NO EXTRA COST. FOR DRYWALL

CEILING, ADDITIONAL FLANGES MAY BE REQUIRED. CHECK

ARCHITECTURAL DRAWINGS FOR PLASTER/DRYWALL CEILING.

41. COORDINATE WITH ARCHITECTURAL DRAWINGS AND CEILING

CONTRACTOR FOR EXACT LIGHTING FIXTURE LOCATIONS.

42. UPON COMPLETION OF THE JOB, THE CONTRACTOR SHALL

SUBMIT A CERTIFICATE OF INSPECTION AND A CERTIFICATE

OF SUBSTANTIAL COMPLETION.

43. E.C. SHALL PROVIDE UL APPROVED FIRESTOPPING

COMPOUNDS SUCH AS "3M" FIRESEAL SYSTEMS OR

APPROVED EQUAL FOR ALL RACEWAY PENETRATIONS IN FIRE

RATED WALLS AND FLOORS. VERIFY FIRE RATING CONDITIONS

AND LOCATIONS PRIOR TO FINAL BIDS. ALL OPEN CONDUIT

SLEEVE PENETRATIONS SHALL BE FIRESEALED AFTER CABLES

ARE COMPLETELY INSTALLED . SEALING METHODS SHALL BE

PROVIDED, SUBJECT TO APPROVAL OF CABLE CONTRACTOR.

44. IDENTIFY ALL RECEPTACLES AND SWITCHES WITH THEIR

RESPECTIVE CIRCUIT NO'S AND PANEL DESIGNATIONS FROM

WHICH THEY ARE FED.

45. RACEWAYS SHALL BE USED FOR THEIR INTENDED PURPOSE.

COMMUNICATION CABLES OR WIRES SHALL NOT BE STRAPPED

, TAPED, OR ATTACHED BY ANY MEANS TO EXTERIOR OF ANY

CONDUIT OR RACEWAY AS A MEANS OF SUPPORT.

ELECTRICAL INSTALLATION NOTES :

1. CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD

VERIFICATION OF ALL DIMENSIONS, SIZES, SYSTEM

VOLTAGES, QUANTITIES AND EXTENT OF WORK.

2. THIS CONTRACTOR IS ADVISED TO CONSULT WITH THE

CONSTRUCTION MANAGER PRIOR TO BID SUBMITTAL FOR

PHASE OPERATION AND SCHEDULING OF THE WORK.

3. CONTRACTORS SHALL REFER TO THE ARCHITECTURAL,

STRUCTURAL, MECHANICAL AND ELECTRICAL DRAWINGS

AND SPECIFICATIONS FOR COORDINATION AND EXTENT OF

THE WORK OF THE VARIOUS TRADES.

4. WHERE THE WORK OF ONE TRADE WILL INTERFACE WITH

THE WORK OF OTHER TRADES, ALL TRADES SHALL ASSIST

IN WORKING OUT SPACE CONDITIONS, MAKE

SATISFACTORY ADJUSTMENTS AND PREPARE AND REVISE

COORDINATED SHOP DRAWINGS.

5. WITH THE APPROVAL OF THE ARCHITECT/ENGINEER, AND

WITHOUT ADDITIONAL COST TO THE OWNER, MAKE MINOR

MODIFICATIONS IN THE WORK, INCLUDING REROUTING AS

REQUIRED BY INTERFERENCES WITH STRUCTURAL,

GENERAL WORK OF OTHER TRADES OR FOR PROPER

EXECUTION OF THE WORK.

6. WORK INSTALLED BEFORE COORDINATING WITH OTHER

TRADES SO AS TO CAUSE INTERFERENCE WITH THE WORK

OF SUCH OTHER TRADES SHALL BE CHANGED TO CORRECT

SUCH CONDITION WITHOUT ADDITIONAL COST TO THE

OWNER.

7. TEMPORARY SERVICES SHALL BE PROVIDED WHEN

REQUIRED.

8. THE CONTRACTORS SHALL MAKE ALL NECESSARY

PROVISIONS TO PURSUE THEIR WORK IN A MANNER WHICH

WILL ASSURE THAT THE OPERATION OF THE EXISTING

BUILDINGS IS MINIMALLY IMPAIRED. THIS SHALL INCLUDE,

BUT NOT BE LIMITED TO, DELIVERY OF SUPPLIES,

TEMPORARY UTILITY CONNECTIONS, ETC.

9. CUTTING AND PATCHING FOR ELECTRICAL WORK SHALL BE

PERFORMED BY THE CONTRACTOR UNLESS NOTED

OTHERWISE.

10. SEAL ALL PENETRATIONS USING UL APPROVED FIRE

STOPPING COMPOUND.

11. ABANDONED CIRCUITS SHALL BE REMOVED TO A PANEL OR

TERMINATED IN A CODE COMPLIANT BOX.

MANUAL STARTERM

AutoCAD SHX Text %%uABBREVIATIONS

AutoCAD SHX Text %%uSYMBOLS

AutoCAD SHX Text T

ILLINOIS SECRETARY

OF STATE CHICAGO

WEST FACILITY

BOILER REPLACEMENT

5301 W. LEXINGTON ST.,

CHICAGO, IL 60644

SHEET NO.

DESIGN BY: RO

DRAWN BY: SMA

CHECKED BY: PBL

PROJECT NO.

ISSUE DESCRIPTION DATEREV.

ISSUED FOR 50% REVIEW 05/09/2025

I HAVE PREPARED OR CAUSED TO BE PREPARED UNDER MY DIRECT

SUPERVISION, THE ATTACHED PLANS AND SPECIFICATIONS. I STATE

THAT, TO THE BEST OF MY KNOWLEDGE AND BELIEF AND TO THE

EXTENT OF MY CONTRACTUAL OBLIGATION, THEY ARE IN

COMPLIANCE WITH THE 2019 CHICAGO BUILDING CODE

MANDATED BY THE CITY OF CHICAGO BUILDING

DEPARTMENT/CODE ENFORCEMENT AND THE ILLINOIS

ACCESSIBILITY CODE, 2018 EDITION

STATEMENT OF COMPLIANCE

SIGNED:

INDIANA REGISTRATION NO.:

DATE:

ARCHITECT/ENGINEER

623 COOPER COURT

SCHAUMBURG, IL 60173

(312) 346-8181

CITY APPROVAL STAMP BOX

ILLINOIS SECRETARY OF STATE

ISSUED FOR REVIEW 08/01/2025

ISSUED FOR 75% REVIEW 08/13/2025

E-101

PANEL SCHEDULES

PANEL: DP-1

NEW OR EXISTING: EXISTING VOLTAGE/PHASE : 208Y/120 V NEUTRAL BUS: 100%

LOCATION : ELECTR. ROOM BUS AMPS : 600A GROUND BUS: 100%

MOUNTING : SURFACE MAIN BREAKER : 600A ISO. GRND. BUS: NONE

ENCLOSURE: NEMA 1 FED FROM : FULLY RATED AIC: 10,000

ENTRANCE: BOTTOM SUB-FEED TO : SPD: NONE

LOAD DESCRIPTION LOAD

TYPE NOTE

VOLT-AMPS

CKT BKR/

POLE A B C BKR/

POLE CKT

VOLT-AMPS

NOTE LOAD

TYPE LOAD DESCRIPTION

A B C A B C

PP-2

P 1 1

100/3

100/3

2 1 L

LP-7AP 1 3 - * - 4 1 L

P 1 5 - - * 6 1 L

LP-4

L 1 7

100/3

100/3

8 1

L LP-2L 1 9 - * - 10 1

L 1 11 - - * 12 1

LP-5A

L 1 13

60/3

100/3

14 1

L LP-5BL 1 15 - * - 16 1

L 1 17 - - * 18 1

LP-7

L 1 19

100/3

100/3

20 1 L

LP-6L 1 21 - * - 22 1 L

L 1 23 - - * 24 1 L

Spare S

1 25

100/3

100/3

26 1 P

PP-11 27 - * - 28 1 P

1 29 - - * 30 1 P

Boiler Wireway E

1 31

30/3

60/3

32 1 S

Spare1 33 - * - 34 1 S 1 35 - - * 36 1 S

HWP-8 (1HP) (NOTE 3)

M 1 553 37

15/3

15/3

38 553 1 M

HWP-7 (1HP) (NOTE 3)M 1 553 39 - * - 40 553 1 M

M 1 553 41 - - * 42 553 1 M

BREAKER NOTES CONNECTED PHASE LOADS Type Description Connected Demand Type Code

1) Thermal Magnetic TOTAL ØA = 1,106 VA Lighting (L) = 0 0 L

2) Shunt trip TOTAL ØB = 1,106 VA Receptacles (R)= 0 0 R

3) Lock-out device TOTAL ØC = 1,106 VA Motors (M)= 3318 2157 M

4) GFEP Electric Heating (H) = 0 0 H

5) GFIC Equipment (E) = 0 0 E

6) AFCI (Dedicated Neutral Required) Panels (P) = 0 0 P

7) Aux Switches Spare (S) = 0 0 S

8) HACR Space (X) = 0 0 X

9) Existing Breaker Total VA = 3,318 2157

10) Dedicated Neutral Required Total Added Amps = 9.2 6.0

PANEL: DP-2

NEW OR EXISTING: EXISTING VOLTAGE/PHASE : 208Y/120 V NEUTRAL BUS: 100%

LOCATION : ELECTR. ROOM BUS AMPS : 600A GROUND BUS: 100%

MOUNTING : SURFACE MAIN BREAKER : 600A ISO. GRND. BUS: NONE

ENCLOSURE: NEMA 1 FED FROM : XFMR #2 FULLY RATED AIC: 10,000

ENTRANCE: BOTTOM SUB-FEED TO : SPD: NONE

LOAD DESCRIPTION LOAD

TYPE NOTE

VOLT-AMPS

CKT BKR/

POLE A B C BKR/

POLE CKT

VOLT-AMPS

NOTE LOAD

TYPE LOAD DESCRIPTION

A B C A B C

LP-4A

L 1 1

100/3

100/3

2 1 L

LP-5L 1 3 - * - 4 1 L

L 1 5 - - * 6 1 L

LP-3

L 1 7

100/3

100/3

8 1

L LP-1L 1 9 - * - 10 1

L 1 11 - - * 12 1

TVSS E

1 13

60/3

100/3 14 1 L

LP-81 15 - * - 16 1 L

1 17 - - * 18 1 L

P-1 E 1 19

20/3

20/3 20 1 E

P-21 21 - * - 22 1 E 1 23 - - * 24 1 E

P-3

E 1 25

20/3

20/3

26 1 E

P-4E 1 27 - * - 28 1 E E 1 29 - - * 30 1 E

P-5

E 1 31

20/3

20/3

32 1 E

Sump PumpE 1 33 - * - 34 1 E E 1 35 - - * 36 1 E

Water Heater E 1 37 20/1 * - - 20/3

38 1 E Cond. Boiler Pumpcontrol E 1 39 20/1 - * - 40 1 E

Cond. Boiler 120V E 1 41 20/1 - - * 42 1 E

BREAKER NOTES CONNECTED PHASE LOADS Type Description Connected Demand Type Code

1) Thermal Magnetic TOTAL ØA = 0 VA Lighting (L) = 0 0 L

2) Shunt trip TOTAL ØB = 0 VA Receptacles (R)= 0 0 R

3) Lock-out device TOTAL ØC = 0 VA Motors (M)= 0 0 M

4) GFEP Electric Heating (H) = 0 0 H

5) GFIC Equipment (E) = 0 0 E

6) AFCI (Dedicated Neutral Required) Panels (P) = 0 0 P

7) Aux Switches Spare (S) = 0 0 S

8) HACR Space (X) = 0 0 X

9) Existing Breaker Total VA = 0 0

10) Dedicated Neutral Required Total Added Amps = 0.0 0.0

PANEL: PP-1

NEW OR EXISTING: NEW VOLTAGE/PHASE : 208Y/120 V NEUTRAL BUS: 100%

LOCATION : ELECTR. ROOM BUS AMPS : 100A GROUND BUS: 100%

MOUNTING : SURFACE MAIN BREAKER : 100A ISO. GRND. BUS: NONE

ENCLOSURE: NEMA 1 FED FROM : XFMR #2 FULLY RATED AIC: 10,000

ENTRANCE: BOTTOM SUB-FEED TO : SPD: NONE

LOAD DESCRIPTION LOAD

TYPE NOTE

VOLT-AMPS

CKT BKR/

POLE A B C BKR/

POLE CKT

VOLT-AMPS

NOTE LOAD

TYPE LOAD DESCRIPTION

A B C A B C

WMS HAND DRYER E 1 1 20/1 * - - 20/1 2 1 E WMS HAND DRYER

WMS HAND DRYER E 1 3 20/1 - * - 20/1 4 1 E WMS HAND DRYER

WMS HAND DRYER E 1 5 20/1 - - * 20/1 6 1 E FIAG

WMS HAND DRYER E 1 7 20/1 * - - 20/1 8 1 S SPARE

GEN. E 1 9 20/1 - * - 20/1 10 1 S SPARE

GEN. E 1 11 20/1 - - * 20/1 12 1 S SPARE

ELEV. RM. LTS L 1 13 20/1 * - - 20/1 14 1 S SPARE

ELEV. RM. OUTLET R 1 15 20/1 - * - 20/1 16 1 S SPARE

SPARE S 1 17 20/1 - - * 20/1 18 1 E 24V AUTOMATED

SPARE S 1 19 20/1 * - - 30/1 20 1,800 1 E BOILER CB-2 (NOTE 4)

ELEV. PIT SUMP PUMP E 1 21 20/1 - * - 30/1 22 1,800 1 E BOILER CB-3 (NOTE 4)

ELEV. PIT LIGHT L 1 23 15/1 - - * 20/1 24 1 S SPARE

MAIN PRINCIPAL

P 1 25 100/3

P 1 27 - * -

P 1 29 - - *

BREAKER NOTES CONNECTED PHASE LOADS Type Description Connected Demand Type Code

1) Thermal Magnetic TOTAL ØA = 1,800 VA Lighting (L) = 0 0 L

2) Shunt trip TOTAL ØB = 1,800 VA Receptacles (R)= 0 0 R

3) Lock-out device TOTAL ØC = 0 VA Motors (M)= 0 0 M

4) GFEP Electric Heating (H) = 0 0 H

5) GFIC Equipment (E) = 3600 2340 E

6) AFCI (Dedicated Neutral Required) Panels (P) = 0 0 P

7) Aux Switches Spare (S) = 0 0 S

8) HACR Space (X) = 0 0 X

9) Existing Breaker Total VA = 3,600 2340

10) Dedicated Neutral Required Total Added Amps = 10.0 6.5

NOTES:

1. FOR ELECTRICAL GENERAL NOTES, ABBREVIATIONS AND

SYMBOLS SEE DWG. E-000.

2. ALL BRANCH CIRCUIT WIRING SHALL BE SIZED IN ACCORDANCE

WITH THE CURRENT CHICAGO ELECTRICAL CODE.

3. CONTRACTOR SHALL FURNISH AND INSTALL CIRCUIT BREAKER

TO MATCH WITH EXISTING INSTALLATION. FIELD VERIFY EXISTING

INSTALLATION PRIOR TO ORDERING.

4. RE-USE EXISTING CIRCUIT BREAKERS TO FEED BOILERS CB-2

AND CB-3.

NOTE:

ELECTRICAL PANELS AND CIRCUIT BREAKERS

ARE EXISTING UNLESS OTHERWISE NOTED

AIR SEPARATOR

EXISTING BOILER

CONDENSING

BOILER

CB-1

BOILER

B07

ELECTRICAL ROOM

4 5 6 6.1

BOILER ROOM

VESTIBULE

PUMP-XX

PUMP-XX

PUMP-XX

PUMP-XX

(ABOVE)

EXISTING

PANEL DP-1

EXISTING

PANEL DP-2

EXISTING

TRANSFORMER 1

EXISTING

TVSS

EXISTING

PANEL PP-1

EXISTING

TRANSFORMER 2

EXISTING C/T

CABINET AND METER

EXISTING

MDP

(NOTE 9)

C

D

E

ILLINOIS SECRETARY

OF STATE CHICAGO

WEST FACILITY

BOILER REPLACEMENT

5301 W. LEXINGTON ST.,

CHICAGO, IL 60644

SHEET NO.

DESIGN BY: RO

DRAWN BY: SMA

CHECKED BY: PBL

PROJECT NO.

ISSUE DESCRIPTION DATEREV.

ISSUED FOR 50% REVIEW 05/09/2025

I HAVE PREPARED OR CAUSED TO BE PREPARED UNDER MY DIRECT

SUPERVISION, THE ATTACHED PLANS AND SPECIFICATIONS. I STATE

THAT, TO THE BEST OF MY KNOWLEDGE AND BELIEF AND TO THE

EXTENT OF MY CONTRACTUAL OBLIGATION, THEY ARE IN

COMPLIANCE WITH THE 2019 CHICAGO BUILDING CODE

MANDATED BY THE CITY OF CHICAGO BUILDING

DEPARTMENT/CODE ENFORCEMENT AND THE ILLINOIS

ACCESSIBILITY CODE, 2018 EDITION

STATEMENT OF COMPLIANCE

SIGNED:

INDIANA REGISTRATION NO.:

DATE:

ARCHITECT/ENGINEER

623 COOPER COURT

SCHAUMBURG, IL 60173

(312) 346-8181

CITY APPROVAL STAMP BOX

N

ILLINOIS SECRETARY OF STATE

KEY PLAN

ISSUED FOR REVIEW 08/01/2025

ISSUED FOR 75% REVIEW 08/13/2025

E-200D

POWER PLAN DEMO

Boiler Room - Electrical Plan Demo 1/2" = 1'-0"

NORTH

0 5' 10'

NOTES:

1. COORDINATE ALL WORK WITH OWNER.

2. EXISTING SYSTEMS SHOWN ARE BASED ON VISUAL INSPECTION &

AS-BUILT DRAWINGS. THESE DRAWINGS MAY NOT REFLECT THE ACTUAL

CONDITIONS. THE CONTRACTOR SHALL INSPECT THE SITE AND EXAMINE

THE WORK BEFORE EXECUTION OF ANY WORK.

3. COORDINATE AND OBTAIN WRITTEN PERMISSION FOR SHUTDOWNS OF

ELECTRICAL POWER FROM THE OWNER'S REPRESENTATIVE AT LEAST

FORTY-EIGHT (48) HOURS PRIOR TO SHUTDOWN.

4. REMOVE ALL DEBRIS DAILY FROM SITE AND DISPOSE OF ALL MATERIAL

IN A LEGAL AND RESPONSIBLE MANNER.

5. PROTECT INSTALLED WORK. DAMAGE TO EXISTING INSTALLATION FROM

CONSTRUCTION ACTIVITIES SHALL BE REMEDIED AT THE CONTRACTOR'S

EXPENSE.

6. SEAL AND FILL ANY OPENING AFTER REMOVING EQUIPMENT.

7. RE-SUPPORT ELECTRICAL EQUIPMENT AFTER DEMOLITION, IF REQUIRED.

8. CONDUIT AND WIRING REMOVED DURING DEMOLITION SHALL BE

DISPOSED OF BY THE CONTRACTOR

9. DE-TERMINATE POWER AND CONTROL CABLES TO THE EXISTING BOILER.

PUMP-HWP-3 (EXISTING)

PUMP-SPARE (EXISTING)

PUMP-HWP-1 (EXISTING)

PUMP-HWP-5

(EXISTING)

(ABOVE)

ELECTRICAL ROOM

4 5 6 6.1

C

D

E

BOILER ROOM

VESTIBULE

EXISTING

AIR

SEPARATOR

EXISTING

CONDENSING

BOILER

CB-1

EXISTING

BOILER

B07

CONDENSING

BOILER

CB-2

EXISTING

HOT

WATER

BOILER

HWB-1

CONSTANT

FLOW

PUMP

HWP-7

CONSTANT

FLOW

PUMP

HWP-8

EXISTING

PANEL DP-1

EXISTING

PANEL DP-2

EXISTING

TRANSFORMER 1

EXISTING

TVSS

EXISTING

PANEL PP-1

EXISTING

TRANSFORMER 2

EXISTING C/T

CABINET AND METER

EXISTING

MDP

PROPOSED BOILER 1

CONDENSING

BOILER

CB-3

EXISTING

CONSTANT

FLOW

PUMP HWP-6

(NOTE 3)F

MS-7

2#10, 1#10 GND, 3/4"C

TO PP-1

CKT: 20

4#14, IN 3/4"C

3#12, 1#12 GND, 3/4"C

2#10, 1#10 GND, 3/4"C

TO PP-1

CKT: 22

(NOTE 3)F

MS-8

3#12, 1#12 GND, 3/4"C

TO DP-1

CKT: 38,40,42

TO DP-1

CKT: 37,39,41

4#14, IN 3/4"C

E-200

POWER PLAN

ILLINOIS SECRETARY

OF STATE CHICAGO

WEST FACILITY

BOILER REPLACEMENT

5301 W. LEXINGTON ST.,

CHICAGO, IL 60644

SHEET NO.

DESIGN BY: RO

DRAWN BY: SMA

CHECKED BY: PBL

PROJECT NO.

ISSUE DESCRIPTION DATEREV.

ISSUED FOR 50% REVIEW 05/09/2025

I HAVE PREPARED OR CAUSED TO BE PREPARED UNDER MY DIRECT

SUPERVISION, THE ATTACHED PLANS AND SPECIFICATIONS. I STATE

THAT, TO THE BEST OF MY KNOWLEDGE AND BELIEF AND TO THE

EXTENT OF MY CONTRACTUAL OBLIGATION, THEY ARE IN

COMPLIANCE WITH THE 2019 CHICAGO BUILDING CODE

MANDATED BY THE CITY OF CHICAGO BUILDING

DEPARTMENT/CODE ENFORCEMENT AND THE ILLINOIS

ACCESSIBILITY CODE, 2018 EDITION

STATEMENT OF COMPLIANCE

SIGNED:

INDIANA REGISTRATION NO.:

DATE:

ARCHITECT/ENGINEER

623 COOPER COURT

SCHAUMBURG, IL 60173

(312) 346-8181

CITY APPROVAL STAMP BOX

N

ILLINOIS SECRETARY OF STATE

KEY PLAN

ISSUED FOR REVIEW 08/01/2025

ISSUED FOR 75% REVIEW 08/13/2025

Boiler Room - Electrical Plan 1/2" = 1'-0"

NORTH

0 5' 10'

NOTES:

1. FOR ELECTRICAL SPECIFICATIONS, GENERAL NOTES, AND

SYMBOLS SEE DRAWING E-000.

2. FOR PANEL SCHEDULE SEE DRAWING E-001.

3. PROVIDE AND INSTALL, NEMA 1, 250V, 3P FUSIBLE

DISCONNECT.

4. ALL ELECTRICAL EQUIPMENT SHALL BE INSTALLED IN

ACCORDANCE WITH MANUFACTURERS' RECOMMENDATIONS.

5. PROVIDE PROPER WORKING SPACE IN FRONT OF THE

ELECTRICAL PANELS.

AutoCAD SHX Text 14'-0"

AutoCAD SHX Text 14'-0"

E-000 Specifications, General Notes and Symbols-Layout1
Layout1
E-101 Panel Schedule-Layout1
Layout1
E-200D Power Plan-Demo-Layout1
Layout1
E-200 Power Plan-Layout1
Layout1

File details come from the government source that posted it. Updated .